A1 A2
AP1 AP2
FORMATION
LEVEL-617.055
2
FOUNDING
LEVEL-603.384
FOUNDING
LEVEL-597.978
FOUNDING
LEVEL-592.184
L.B.L. 590.000
A1 AP1 AP2 A2
1 2 D/S
EXISTING BRIDGE
SHIMLA MATAUR
1
U/S
HALF BOTTOM 2 HALF TOP
PLAN
Scale: Project: Drawing Title: Intercontinental Consultants & Technocrats Pvt Ltd, Rev. No. Date Description Checked By
AS Consultancy Services for Preparation of Feasibility and Detailed Project GENERAL ARRANGEMENT DRAWING A - 8, Green Park, New Delhi - 110016
Ph : 40863000, Fax 26855252 REVISIONS
NATIONAL HIGHWAYS SHOWN Report for upgradation to 4 lane of Shimla to Mataur Section (Km. FOR MAJOR BRIDGE AT CH. 202+565
Drawing No. Rev.
AUTHORITY OF INDIA 0.000 to Km. 223.700) of NH-88 in the State of Himachal Pradesh (EXISTING CH. 212+350) NHAI/NH-88/SHIMLA/MATAUR/MJB/202+565/R0
through BOT/Hybrid Annuity/EPC mode (BANER KHAD) Prepared by Designed by Checked by Approved by R0