Task Name Duration Start Finish

The document outlines a schedule for upgrading the fire protection system at an existing power plant in Salalah, Oman. It involves installing a new fire water pump performance test facility over 24.5 days from October 15th to November 8th 2017. The work is divided into multiple teams installing piping, valves, and headers for 5 electric pumps, with tasks including isolating lines, cutting, welding, painting, and fixing supports. Testing of the fire pump performance is scheduled for November 7-8 after installation is completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views

Task Name Duration Start Finish

The document outlines a schedule for upgrading the fire protection system at an existing power plant in Salalah, Oman. It involves installing a new fire water pump performance test facility over 24.5 days from October 15th to November 8th 2017. The work is divided into multiple teams installing piping, valves, and headers for 5 electric pumps, with tasks including isolating lines, cutting, welding, painting, and fixing supports. Testing of the fire pump performance is scheduled for November 7-8 after installation is completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

Task Name Duration Start Finish

SALALAH II IPP EXISTING POWER PLANT - FIRE PROTECTION SYSTEM UPGRADE 3 days? Oct 15 '17 Oct 17 '17
PART C: FIRE WATER PUMP PERFORMANCE TEST FACILITY 24.5 days? Oct 15 '17 Nov 8 '17
Installation 24.5 days? Oct 15 '17 Nov 8 '17
Site Mobilization 3 days Oct 15 '17 Oct 17 '17
Pump - 1 (Electric Pump - 1) - Team A 12.25 days Oct 15 '17 Oct 26 '17
Test piping line 12.25 days Oct 15 '17 Oct 26 '17
Isolating & Draining of water 1 day Oct 15 '17 Oct 15 '17
Measuring & Cutting (On Existing line) 1 day Oct 15 '17 Oct 15 '17
Cleaning and Edge prepartion 1 day Oct 15 '17 Oct 15 '17
Welding & Fabricating 3 days Oct 15 '17 Oct 18 '17
Painting 1 day Oct 18 '17 Oct 19 '17
Support fabrication 2 days Oct 15 '17 Oct 16 '17
Support Installation 1 day Oct 19 '17 Oct 21 '17
Valve Fixing 1 day Oct 21 '17 Oct 22 '17
Pipe Header Fabrication 2 days Oct 22 '17 Oct 23 '17
Pipe Header Fixing 1 day Oct 24 '17 Oct 24 '17
Pump - 2 (Electric Pump - 2) Team B 10 days Oct 15 '17 Oct 24 '17
Test piping line 10 days Oct 15 '17 Oct 24 '17
Isolating & Draining of water 1 day Oct 15 '17 Oct 15 '17
Measuring & Cutting (On Existing line) 1 day Oct 15 '17 Oct 15 '17
Cleaning and Edge prepartion 1 day Oct 15 '17 Oct 15 '17
Welding & Fabricating 3 days Oct 16 '17 Oct 18 '17
Painting 1 day Oct 19 '17 Oct 19 '17
Support fabrication 2 days Oct 15 '17 Oct 16 '17
Support Installation 1 day Oct 21 '17 Oct 21 '17
Valve Fixing 1 day Oct 22 '17 Oct 22 '17
Pipe Header Fabrication 2 days Oct 22 '17 Oct 23 '17
Pipe Header Fixing 1 day Oct 24 '17 Oct 24 '17
Return to Tank Test Pipe Line 7.75 days Oct 25 '17 Nov 1 '17
Tank-1 - Team A 7 days Oct 25 '17 Nov 1 '17
Vertical Pipe Fabrication 2 days Oct 25 '17 Oct 26 '17
Vertical Pipe Welding 3 days Oct 26 '17 Oct 30 '17
Painting 1 day Oct 30 '17 Oct 31 '17
Supporting Fixing 2 days Oct 26 '17 Oct 29 '17
Painting 1 day Oct 30 '17 Oct 31 '17
Vertical Pipe Fixing 1 day Oct 31 '17 Nov 1 '17
Tank-2 - Team B 7.63 days Oct 25 '17 Nov 1 '17
Vertical Pipe Fabrication 2 days Oct 25 '17 Oct 26 '17
Vertical Pipe Welding 3 days Oct 28 '17 Oct 30 '17
Painting 1 day Oct 31 '17 Oct 31 '17
Supporting Fixing 2 days Oct 28 '17 Oct 29 '17
Painting 1 day Oct 31 '17 Oct 31 '17
Vertical Pipe Fixing 1 day Nov 1 '17 Nov 1 '17
Pump - 3 5.5 days Nov 2 '17 Nov 7 '17
PRV & Test piping line - Team A 5 days Nov 2 '17 Nov 7 '17
Isolating & Draining of water 1 day Nov 2 '17 Nov 2 '17
Measuring & Cutting (On Existing line) 1 day Nov 2 '17 Nov 2 '17
Cleaning and Edge prepartion 1 day Nov 2 '17 Nov 2 '17
Welding & Fabricating 2 days Nov 2 '17 Nov 5 '17
Painting 1 day Nov 5 '17 Nov 6 '17
Support fabrication 1 day Nov 2 '17 Nov 4 '17
Support Installation 1 day Nov 4 '17 Nov 5 '17
Valve Fixing 1 day Nov 5 '17 Nov 6 '17
Pipe Header Fabrication 2 days Nov 2 '17 Nov 4 '17
Pipe Header Fixing 1 day Nov 6 '17 Nov 7 '17
Pump - 4 5.5 days Nov 2 '17 Nov 7 '17
PRV & Test piping line - Team B 5.5 days Nov 2 '17 Nov 7 '17
Isolating & Draining of water 1 day Nov 2 '17 Nov 2 '17
Measuring & Cutting (On Existing line) 1 day Nov 2 '17 Nov 2 '17
Cleaning and Edge prepartion 1 day Nov 2 '17 Nov 2 '17
Welding & Fabricating 2 days Nov 4 '17 Nov 5 '17
Painting 1 day Nov 6 '17 Nov 6 '17
Support fabrication 1 day Nov 4 '17 Nov 4 '17
Support Installation 1 day Nov 5 '17 Nov 5 '17
Valve Fixing 1 day Nov 6 '17 Nov 6 '17
Pipe Header Fabrication 2 days Nov 2 '17 Nov 4 '17
Pipe Header Fixing 1 day Nov 7 '17 Nov 7 '17
Pump - 5 5.5 days Nov 2 '17 Nov 7 '17
PRV & Test piping line - Team C 5.5 days Nov 2 '17 Nov 7 '17
Isolating & Draining of water 1 day Nov 2 '17 Nov 2 '17
Measuring & Cutting (On Existing line) 1 day Nov 2 '17 Nov 2 '17
Cleaning and Edge prepartion 1 day Nov 2 '17 Nov 2 '17
Welding & Fabricating 2 days Nov 4 '17 Nov 5 '17
Painting 1 day Nov 6 '17 Nov 6 '17
Support fabrication 1 day Nov 4 '17 Nov 4 '17
Support Installation 1 day Nov 5 '17 Nov 5 '17
Valve Fixing 1 day Nov 6 '17 Nov 6 '17
Pipe Header Fabrication 2 days Nov 2 '17 Nov 4 '17
Pipe Header Fixing 1 day Nov 7 '17 Nov 7 '17
Testing the Fire pump performance 1 day? Nov 7 '17 Nov 8 '17