Karda Kos 2014
Karda Kos 2014
a r t i c l e i n f o a b s t r a c t
Article history: This paper addresses the problem of developing an optimal bidding strategy for a strategic producer
Received 29 April 2013 in a transmission-constrained day-ahead electricity market. The optimal bidding strategy is formulated
Received in revised form as a bi-level optimization problem, where the rst level represents the producer prot maximization
23 September 2013
and the second level represents the ISO market clearing. The transmission network is incorporated into
Accepted 23 December 2013
the ISO problem under two different approaches based on the Nodal and PTDF formulation, respec-
Available online 22 January 2014
tively. The bi-level problem is converted to a mathematical program with equilibrium constraints
(MPEC) which, in turn, is transformed into a mixed-integer linear programming (MILP) model using
Keywords:
Electricity market
the KarushKuhnTucker (KKT) optimality conditions and the strong duality theory. Test results on the
Mathematical program with equilibrium IEEE 24-bus and 118-bus systems show that the PTDF formulation of the transmission constraints is
constraints (MPEC) computationally far more efcient than the Nodal formulation.
Mixed-integer linear program (MILP) 2013 Elsevier B.V. All rights reserved.
Optimal bidding strategies
Transmission network
0378-7796/$ see front matter 2013 Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.epsr.2013.12.014
142 E.G. Kardakos et al. / Electric Power Systems Research 109 (2014) 141149
results. An MPEC model that uses the same BE approach for the dis- An MPEC problem is formulated and solved for the determina-
cretization of the offer quantities and prices taking also into account tion of the optimal offering strategy of a strategic producer over
the effect of the transmission network on the producer strategic a 24-h scheduling horizon. A detailed unit commitment modeling
behavior is analyzed in [15]. In both works [14,15], the proposed in the strategic producer prot maximization (rst-level) prob-
models were also formulated for single-period time intervals only. lem is used, in contrast to [17] that takes into account only the
Moreover, the proposed binary expansion methodology failed to capacity and the ramping limits of the generating units. In addi-
converge when tested to large test systems due to computational tion, the transmission network is effectively incorporated into the
issues. ISO (second-level) problem. The proposed MPEC model is effec-
The transmission network is also taken into account in [16], tively transformed into an MILP model, which is solved using a
where the proposed model is based on the bi-level programming commercial MILP solver.
and a primal-dual interior point method (PDIPM) is developed for A PTDF modeling of the transmission network constraints is pro-
the solution of the ISO market clearing problem, which included posed and compared to the respective Nodal formulation used
a DC power ow. In addition, sensitivity functions are developed in [17]. Although PTDF modeling has been extensively used for
from linear programming for the modeling of the producers the formulation and solution of the standard unit commitment
payoffs with respect to bidding strategies to solve the bi-level problem solved by the ISO in pool-type day-ahead electricity mar-
problem. In this model, a single-period modeling is used, ignoring kets in order to clear the market [31], it is the rst time that
the inter-temporal and unit commitment constraints. In addition, this transmission modeling is used for the formulation of the
E.G. Kardakos et al. / Electric Power Systems Research 109 (2014) 141149 143
producer optimal bidding strategy problem as an MPEC problem (a) Nodal formulation
in transmission-constrained electricity markets.
A theoretical analysis along with extensive simulations in two qift Ldt
different real test systems show that the PTDF formulation is far i n , f F i dn
more efcient than the Nodal formulation, especially when the
size of the system and the number of the congested branches = Bnm (nt mt ) : nt n N, t T (6)
increase. In addition, the ability of the producer to take advantage mn
of the strategic position of his generating units in the network to
his own benet is properly demonstrated. max
Flnm max
Bnm (nt mt ) Flnm n N, m n , t T (7)
2. Mathematical formulation
Flmax Anr qift Ldt
The optimal bidding strategy of a strategic producer (henceforth,
Producer) is mathematically formulated as a bi-level optimiza- nN in , f F i dn
tion problem, where the rst level represents the producer prot
Flmax : min , max L, t T (11)
maximization problem and the second level represents the ISO t t
market clearing problem. The transmission network is included in
the ISO clearing problem under two different approaches based on
Nodal and PTDF formulation, respectively. nt = rt Anr (max
t
min
t
) n N, t T (12)
L
The Nodal formulation of the system constraints comprises: power ow limits (7) and voltage phase angle limits (8), and 1
equality constraint for the denition of the voltage phase angle of
(a) The power balance constraint at every node (6), which enforces the reference bus (9). The number of the unknown variables in this
that the algebraic summation of the power injections minus formulation is I F + N, where I F is the number of the unknown
the load withdrawals on every node is equal to the algebraic variables qift denoting the producer optimal offer quantities and
summation of the power ows on the branches connected to N is the number of the unknown variables nt related to the volt-
the respective node; the corresponding Lagrange multipliers age phase angles during hour t. On the other hand, for every hour
nt denote the wholesale electricity price (marginal electricity t the PTDF formulation requires only 1 system-wide power bal-
cost) at node n (during hour t). ance equality constraint (10) and L two-sided branch power ow
(b) The capacity limits of each branch (7), which ensure that the inequality constraints (11). Constraint (12) is used ex-post for the
power ow of each branch does not exceed its respective capac- calculation of the resulting LMPs in each node of the system, once
ity limits. the optimization problem has been solved. The number of unknown
(c) The upper and lower bound for the voltage phase angle of each variables in this formulation is restricted to I F denoting the pro-
bus (8). ducer optimal offer quantities qift .
(d) The requirement that the voltage phase angle of the system Finally, the numerous binary variables needed in the Nodal
reference (slack) node be equal to zero (9). formulation for the linearization of the non-linear complementar-
ity constraints of the two-sided inequalities on the voltage phase
The PTDF formulation comprises: angles (8) are avoided in the PTDF formulation, making the latter
far more efcient.
(a) The system-wide power balance constraint (10), which in this
case is enforced system-wide (one constraint for the entire sys-
2.2. MILP formulation of the producer prot maximization
tem) and not separately for each node. This equation enforces
bi-level problem
that the algebraic summation of the power injections minus
the load withdrawals of all nodes must be equal to zero. The
A common method to address a bi-level optimization problem is
dual variable associated with the power balance equation, rt ,
to transform it into a single-level problem. A well-known strategy
is the system marginal price. It represents the increase in the
that is followed in optimization theory is to replace the lower-level
hourly system operating cost ($/h) for the supply of an addi-
problem (in this case the ISO market clearing problem) with its
tional MW of load demand. Since the increase in load demand
KKT rst-order optimality conditions. This is allowed mathemat-
will be supplied by the marginal generator, located at the sys-
ically, since the lower-level problem is linear and, hence, convex.
tem reference bus, the system marginal price is equal to the
The KKT rst-order optimality conditions of the ISO market clear-
reference bus marginal price rt of the Nodal formulation.
ing problem are presented in detail in Appendix, only for the PTDF
(b) The capacity limits of each branch (11), which ensure that the
formulation, since a detailed representation of the resulting MPEC
power ow of each branch does not exceed its respective capac-
model for the Nodal formulation is presented in [17].
ity limit. The dual variables associated with the upper and lower
After replacing the lower-level problem by its KKT rst-order
transmission line ow limits max t
, min
t
represent the trans-
optimality conditions, the MPEC problem is formulated, which con-
mission capacity scarcity premium (in either direction of ow).
sists of:
(c) Constraints (12), which dene the locational marginal price
(LMP) of bus n in hour t, in terms of the second level problem
dual variables rt , max
t
, min
t
[33]. (i) The Producer units constraints (1)(3), which constitute the
upper-level problem.
In the Nodal formulation (6)(9) for every time interval t T the (ii) The KKT optimality conditions (13)(18) of the lower-level
nodal voltage phase angles nt are explicitly modeled and an active problem, which are analyzed in detail in Appendix.
power balance equation is written for every node of the system in (iii) Eq. (12) which determines LMP of bus n in hour t, which is com-
(6); the corresponding Lagrange multipliers nt denote the whole- puted by post-processing of the second-level problem solution.
sale electricity price (marginal electricity cost) at node n (during
hour t). Since the nodal voltage phase angles are explicitly modeled,
The resulting MPEC is a non-linear and non-convex optimization
the branch power ows are expressed in terms of the phase angles
problem that is difcult to solve. The nonlinearities of the MPEC
in the two-sided branch ow constraints (7).
are restricted to the existence of the product of variables ni t qift
In the PTDF formulation (10)-(11) for every time interval t T
in the objective function (1) and the complementarity conditions
the nodal voltage phase angles are eliminated from (6) and (7)
(15)(18).
resulting in a single, system-wide power balance Equation (10),
In [17] the authors proposed an efcient method to nd a linear
where Lagrange multiplier rt is the system marginal price; the
expression for the term ni t qift , based on the KKT conditions and
branch power ows are now expressed in terms of the nodal
the strong duality theory. Based on this method, a linear expression
injections (nodal supply minus demand), multiplied by the cor-
for the term ni t qift is derived, as shown in Appendix, for the PTDF
responding PTDFs in the transmission constraints (11). The two
formulation only, since a similar analysis for the Nodal formulation
formulations are equivalent. Since in the PTDF formulation only a
has already been presented in [17].
single system-wide electricity price, rt , is computed from the sin-
The non-linearities arising due to the complementarity condi-
gle power balance constraint (10), the LMPs in the PTDF formulation
tions are linearized based on the linear expressions proposed in
are computed by post-processing of the second level problem solu-
[34]. A detailed description of the resulting linearizations is also
tion, using (12) which expresses the LMP of node n (during hour t) in
presented in Appendix.
terms of the reference price rt , the PTDFs Anr and the transmission
Using these linearizations the MPEC is converted to an MILP
capacity scarcity premiums (max min ).
t t model, which consists of:
Regarding the computational complexity of the two formula-
tions, we note the following: For every hour t, the Nodal formulation
comprises N nodal power balance equality constraints (6), (L + N) (i) The Producer units constraints (1)(3), which constitute the
two-sided inequality constraints for the enforcement of branch upper-level problem.
E.G. Kardakos et al. / Electric Power Systems Research 109 (2014) 141149 145
Table 2
Summary test results.
Test case Model Total daily Prot ($) Execution Test case Model Total daily Prot ($) Execution
production time (s) production time (s)
(MW) (MW)
24.A without Base 7714.05 923,723.8 5.8 24.B with UC Base 4149.60 527,082.1 8.9
UC PTDF Reduced 7570.79 925,109.9 8.2 PTDF Reduced 4351.32 553,297.7 39.8
PTDF Full 7570.79 925,109.9 12.4 PTDF Full 4351.32 553,297.7 94 min
Nodal 7570.79 925,109.9 73.1 Nodal 4351.32 553,297.7 659 min
24.A with UC Base 7985.70 909,793.8 10.9 24.C with UC Base 4149.60 527,082.1 8.9
PTDF Reduced 7833.56 905,241.7 81.6 PTDF Reduced 4102.79 559,555.8 13.8
PTDF Full 7833.56 905,241.7 693.2 PTDF Full 4102.79 559,555.8 12.3
Nodal 7640.76 899,842.9 720 min(3.49% gap) Nodal 4102.79 559,555.8 302
Table 3
Case A - test results.
Test case Model U76 (#1) U76 (#1) U155 (#23) U155 (#23) U100 (#7) U100 (#7) Total Total prot
(MW) (MW) (MW) (MW) (MW) (MW) production ($)
(MW)
24.A with UC PTDF reduced 1086.26 1042.21 2865.34 2839.75 0.00 0.00 7833.56 905,241.7
Base offers & ISO-OPF 978.55 976.55 2901.50 2787.51 0.00 0.00 7644.11 887,508.9
Difference 107.71 65.66 36.16 52.24 0.00 0.00 189.45 17,732.8 (1.95%)
Table 4
Cases B & C test results.
Test Case Model U76 (#1) U76 (#1) U76 (#2) U76 (#2) Total Total prot
(MW) (MW) (MW) (MW) production ($)
(MW)
24.B with UC PTDF reduced 1048.80 1067.60 1094.92 1140.00 4351.32 553,297.7
Base offers & ISO-OPF 1068.80 1114.19 1081.20 912.00 4176.19 547,363.1
Difference 20.00 46.59 13.72 228.00 175.13 5,934.6 (1.07%)
24.C with UC PTDF reduced 1075.20 1094.40 1068.06 865.13 4102.79 559,555.8
Base offers & ISO-OPF 1046.00 1110.40 1081.20 912.00 4149.60 527,082.1
Difference 29.20 16.00 13.14 46.87 46.81 32,473.8 (5.80%)
3.1.3. Test case 24.C In this test case, it is considered that the Producer owns 7 gen-
In the third case, the same Producer with case 24.B is consid- erating units located on different nodes throughout the electricity
ered. In this case, the capacity of branch #10 is set slightly above its network (Table 1).
respective maximum power ow observed in the Base model solu- A single case, with UC modeling of the Producer units, is con-
tion, i.e. equal to 99 MW, while the capacity of all other branches sidered. The capacity of branches #54, #88, #133, #153, #167 and
remains unchanged. This case shows how the Producer can re- #176 is set equal to the 95% of their respective maximum power
dispatch his units so as to create congestion on branch #10 and ow observed during the 24-h scheduling period in the Base model
increase his prots. solution. The solution of the problem results in the congestion of
In this case, the incorporation of the network constraints in all these branches and the total congestion-hours are equal to 16.
the Producer offering strategy model gives him the opportunity to Table 5 shows that the solution times to reach a proven optimal
exercise locational market power. Similarly to the previous cases, solution of both the Base model and the PTDF Reduced model on
Table 4 shows that under the proposed strategy (PTDF Reduced) the the 118-bus system are considerably higher than the respective
Producer manages to cause congestion on branch #10 and increase
his daily prot by 5.8% with respect to the case where the Pro-
ducer offering strategy model neglects transmission constraints,
yet the ISO market clearing takes them into account (Base offers &
ISO-OPF).
Fig. 1 illustrates (a) the resulting SMP of the Base model, which is
identical for all buses, since congestion is neglected (network con-
straints are ignored) and (b) the LMP of buses #1 and #2, where the
strategic producers units are located, in the PTDF Reduced model.
It is evident from Fig. 1 that by congesting branch #10 during hours
19, 20, 21, the producer succeeds to increase the LMP of buses #1
and #2, where his units are located.
Table 5
IEEE 118-bus system summary test results.
Test case Model Total daily production (MW) Prot ($) Execution time (s)
ones on the 24-bus system. Both the other two network models
examined (PTDF Full and Nodal) failed to converge to an optimal
solution, which shows their inability to deal with large test systems. qift Ldt = 0 t T (14)
iI, f F i dD
4. Discussion conclusion
max
0 qift ift 0 i I, f F i , t T (15)
This paper presented an MILP model for the solution of the
optimal bidding strategy problem for a strategic producer who max
0 Qift qift ift 0 i I, f F i , t T (16)
participates in a transmission-constrained day-ahead electricity
market. The transmission network was modeled under two dif-
ferent approaches, based on the Nodal and PTDF formulation,
respectively. 0 Flmax Anr qift Ldt max 0
Test results on the IEEE 24-bus system and a modied IEEE 118- t
nN in , f F i dn
bus system demonstrate the benets of incorporating the network
constraints in the Producer offering strategy model. In addition, the L, t T (17)
proposed PTDF-based formulation of the transmission constraints
has proved computationally far more efcient than the Nodal for-
mulation, especially when the size of the system and the number
of congested branches increase.
0 Flmax + Anr qift Ldt min 0
Regarding the applicability of the proposed method, it is rec- t
nN in , f F i dn
ognized that it suffers from the standard modeling limitations of
similar methods addressing the complex topic of developing opti- L, t T (18)
mal bidding strategies for electricity producers. The main modeling
limitations are:
As already mentioned in Section 3.2, the resulting MPEC is a
non-linear and non-convex optimization problem. The nonlineari-
(a) The second-level ISO market clearing problem ignores the non-
ties of the MPEC are restricted to: (a) the existence of the product
convex unit commitment constraints. This modeling does not
of variables ni t qift in the objective function (1) and (b) the com-
allow for the exact formulation and solution of the ISO day-
plementarity conditions (15)(18).
ahead market clearing followed by most US ISOs/RTOs.
Based on the KKT conditions and the strong duality theory, a
(b) The ISO local market power mitigation (LMPM) procedures
linear expression for the term ni t qift can be produced [17].
incorporated in the day-ahead electricity markets of most US
According to the strong duality theory, the objective functions
ISOs/RTOs are ignored.
of the primal and dual problems have the same value in the opti-
(c) It is assumed that the producer has full knowledge of the trans-
mal solution, when the problem is convex. Therefore, the following
mission system as well as perfect information regarding his
equation arises:
rivals energy offers.
pift qift
Overcoming the above limitations will be the focus of our future
iI, f F i , tT
research.
max
= ift Qift max
t
(Flmax + And r Ldt )
Acknowledgements iI, f F i , tT L, tT dD
This work was nancially supported by the State Scholarships min
t
(Flmax And r Ldt ) + rt Ldt (19)
Foundation of Greece in the context of the IKY Fellowships of L, tT dD dD
Excellence for Postgraduate studies in Greece - Siemens Program.
By multiplying both sides of Eq. (13) with qift and summing for
all i IS , f Fi , t T, the following condition arises:
Appendix.
pift qift
The KKT rst-order optimality conditions of the ISO market
iI S , f F i , tT
clearing problem are presented in the following Eqs. (13)(18) only
for the PTDF Formulation, since a detailed representation of the
max min
= rt qift (ift ift ) qift
resulting MPEC model for the Nodal Formulation is presented in
[17]. iI S , f F i , tT iI S , f F i , tT
max min
rt ift + ift Ani r (max min ) pift =0
t t (max min ) Ani r qift (20)
L t t
L, tT iI S , f F i
i I, f F i , t T (13)
148 E.G. Kardakos et al. / Electric Power Systems Research 109 (2014) 141149
thus
max
ift vmax M i I, f F i , t T (34)
max max ift
ift qift = ift Qift (23)
iI S , f F i , tT iI S , f F i , tT
By processing (20), (21), (23), we get: Anr qift Ldt + Flmax 0 L, t T
nN in , f F i dn
pift qift
(35)
iI S , f F i , tT
max
= rt qift ift Qift
min
t
0 t T, L (36)
iI S , f F i , tT iI S , f F i , tT
(max min ) Ani r qift (24) Anr qift Ldt + Flmax (1 vt
L min
) ML
t t
L, tT iI S , f F i nN in , f F i dn
[7] F.J. Diaz, J. Contreras, J.I. Munoz, Optimal scheduling of a price-taker cascaded [22] C.K. Simoglou, P.N. Biskas, A.G. Bakirtzis, Optimal self-scheduling of a domi-
reservoir system in a pool-based electricity market, IEEE Trans. Power Syst. 26 nant power company in electricity markets, Int. J. Electr. Power Energy Syst. 43
(2011) 604615. (2013) 640649.
[8] H.M.I. Pousinho, V.M.F. Mendes, J.P.S. Catalao, A stochastic programming [23] B.F. Hobbs, C.B. Metzler, J.S. Pang, Strategic gaming analysis for electric power
approach for the development of offering strategies for a wind power producer, systems: an MPEC approach, IEEE Trans. Power Syst. 15 (2010) 638645.
Electr. Power Syst. Res. 89 (2012) 4553. [24] C.J. Day, B.F. Hobbs, J.S. Pang, Oligopolistic competition in power networks: a
[9] S. Nojavan, K. Zare, M.R. Feyzi, Optimal bidding strategy of generation station conjectured supply function equilibrium approach, IEEE Trans. Power Syst. 17
in power market using information gap decision theory (IGDT), Electr. Power (2002) 597607.
Syst. Res. 96 (2013) 5663. [25] V.P. Gountis, A.G. Bakirtzis, Efcient determination of Cournot equilibria in
[10] J. Garcia-Gonzalez, J. Barquin, Self-unit commitment of thermal units in a electricity markets, IEEE Trans. Power Syst. 19 (2004) 18371844.
competitive electricity market, in: Proceedings of the IEEE Power Engineering [26] L.A. Barroso, R.D. Carneiro, S. Granville, M.V. Pereira, M.H.C. Fampa, Nash equi-
Society Summer Meeting, 2000. librium in strategic bidding: a binary expansion approach, IEEE Trans. Power
[11] S. De La Torre, J.M. Arroyo, A.J. Conejo, Price maker self-scheduling in a pool- Syst. 21 (2006) 629638.
based electricity market: a mixed-integer LP approach, IEEE Trans. Power Syst. [27] C.A. Diaz, J. Villar, Electricity market equilibrium based on conjectural varia-
17 (2002) 10371042. tions, Electr. Power Syst. Res. 80 (2010) 15721579.
[12] V.P. Gountis, A.G. Bakirtzis, Bidding strategies for electricity producers in [28] C. Ruiz, A.J. Conejo, Y. Smeers, Equilibria in an oligopolistic electricity pool with
a competitive electricity marketplace, IEEE Trans. Power Syst. 19 (2004) stepwise offer curves, IEEE Trans. Power Syst. 27 (2012) 752761.
356365. [29] E.G. Kardakos, C.K. Simoglou, A.G. Bakirtzis, Short-term electricity market sim-
[13] A. Baillo, M. Ventosa, M. Rivier, A. Ramos, Optimal offering strategies for gener- ulation for pool-based multi-period auctions, IEEE Trans. Power Syst. 28 (2013)
ation companies operating in electricity spot markets, IEEE Trans. Power Syst. 25262535.
9 (2004) 745753. [30] S.O. Kimbrough, F.H. Murphy, Strategic bidding of offer curves: an agent-based
[14] M.V. Pereira, S. Granville, M.H.C. Fampa, R. Dix, L.A. Barroso, Strategic bidding approach to exploring supply curve equilibria, Eur. J. Oper. Res. 229 (2013)
under uncertainty: a binary expansion approach, IEEE Trans. Power Syst. 20 165178.
(2005) 180188. [31] S.J. Wang, S.M. Shahidehpour, D.S. Kirschen, et al., Short-term generation
[15] A.G. Bakirtzis, C.K. Simoglou, N.P. Ziogos, A.C. Tellidou, G.A. Bakirtzis, Electricity scheduling with transmission and environmental constraints using an aug-
producer offering strategies in day-ahead energy markets, in: Proceedings of mented lagrangian-relaxation, in: Proceedings of the 1994 IEEE/PES Summer
the 2007 iREP Symposium Bulk Power System Dynamics and Control VII, Meeting, San Francisco, CA, July, 1994.
Revitalizing Operational Reliability, August, 2007. [32] R.D. Christie, B.F. Wollenberg, I. Wangensteen, Transmission management in
[16] T. Li, M. Shahidehpour, Strategic bidding of transmission-constrained GEN- the deregulated environment, Proc. IEEE 88 (2000) 170195.
COs with incomplete information, IEEE Trans. Power Syst. 20 (2005) [33] E. Litvinov, Design and operation of the locational marginal prices-based elec-
437447. tricity markets, IET Gen. Transm. Distrib. 4 (2010) 315323.
[17] C. Ruiz, A.J. Conejo, Pool strategy of a producer with endogenous formation of [34] J. Fortuny-Amat, B. McCarl, A representation and economic interpretation of a
locational marginal prices, IEEE Trans. Power Syst. 24 (2009) 18551866. two-level programming problem, J. Oper. Res. Soc. 32 (1981) 783792.
[18] L. Xu, R. Baldick, Y. Sutjandra, Bidding into electricity markets: a transmission- [35] Reliability System Task Force, The IEEE reliability test system-1996: a report
constrained residual demand derivative approach, IEEE Trans. Power Syst. 26 prepared by the reliability test system task force of the application of proba-
(2011) 13801388. bility methods subcommittee, IEEE Trans. Power Syst. 14 (1999) 10101020.
[19] A.G. Bakirtzis, N.P. Ziogos, A.C. Tellidou, G.A. Bakirtzis, Electricity producer [36] Electrical and Computer Engineering Department Illinois Institute of Tech-
offering strategies in day-ahead energy market with step-wise offers, IEEE nology. Network Data for the IEEE 118-Bus System [Online]. Available:
Trans. Power Syst. 22 (2007) 18041818. http://motor.ece.iit.edu/data/IEEE118bus data gure.xls
[20] L.A. Barroso, A. Street, M.V. Pereira, S. Granville, Offering strategies and simu- [37] U.S. Energy Information Administration (EIA). Fuel Prices [Online]. Available:
lation of multi-item iterative auctions of energy contracts, in: Proceedings of http://www.eia.gov/forecasts/steo/tables/pdf/2tab.pdf
the General Meeting of the IEEE Power and Energy Society, San Diego, CA, July, [38] World Nuclear Association. Nuclear Fuel Prices [Online]. Available:
2012. http://www.world-nuclear.org/info/inf02.html
[21] H.M.I. Pousinho, J. Contreras, A.G. Bakirtzis, J.P.S. Catalao, Risk-constrained [39] A. Brooke, D. Kendrick, A. Meeraus, GAMS Users Guide, The Scientic Press,
scheduling and offering strategies of a price-maker hydro producer under Redwood City, CA, 1990 [Online] Available: http://www.gams.com/docs/
uncertainty, IEEE Trans. Power Syst. 28 (2012) 18791887. document.htm