Cathodic Protection Field Testing
Cathodic Protection Field Testing
MIL-HDBK-1136/1
(SUPERSEDES NAVFAC MO-306.1)
1 February 1999
CATHODIC PROTECTION
FIELD TESTING
Civil Engineering
Page
Chapter 1, Operation of Cathodic Protection Systems
1.1 Maintaining Cathodic Protection Systems......................................5
1.2 Close Interval Corrosion Survey....................................................5
1.3 Corrosion Survey ........................................................................ 10
1.4 Water Tank Calibration ............................................................... 13
1.5 Rectifier Operational Checkout ................................................... 14
1.6 Impressed Current Anode Bed Survey ......................................... 16
1.7 Impressed Current System Check ................................................ 17
1.8 Galvanic Anode check ................................................................ 18
1.9 Resistance Bond Checkout .......................................................... 19
1.10 Leak Survey................................................................................ 21
1.11 Record Keeping Requirements .................................................... 22
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 2
Figures
1.1 Using Data Logger for Close Interval Survey .................................5
1.2 Using Pipe Locator to Make Measurements Directly Over .............8
Pipeline
1.3 Synchronizing Current Interrupters .............................................. 10
1.4 Measuring Rectifier Output Voltage............................................. 15
1.5 Measuring Rectifier Output Current ............................................. 15
1.6 Measuring Potential of Galvanic Anode ....................................... 19
1.7 Measuring Output Current of Galvanic Anode.............................. 20
2.1 Using Induction Method to Locate Anodes................................... 29
2.2 Measuring AC Voltage at Rectifier Taps ...................................... 30
2.3 Verifying Continuity of Fuse........................................................ 31
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 3
Tables
CHAPTER 1
OPERATION OF CATHODIC
PROTECTION SYSTEMS
1.2. The Close Interval Corrosion Survey is conducted to ensure that the
entire structure has adequate cathodic protection.
1.2.4.2. Normally, the interval used is kept uniform over the entire structure.
1.2.4.2.2. Use pipe locator to ensure measurements are taken directly over
pipelines (figure 1.2).
1.2.6.2. If instant off potential measurements are exactly the same after
moving the structure connection, this may not be required.
1.2.6.4. This condition should be noted in the data, so that the location can
be re-visited for future testing and troubleshooting.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 9
1.2.8. Data should be entered into a computer database and checked for
erroneous readings.
1.2.8.1. Erroneous readings can result from not making good contact to earth
with the reference cell, lifting the reference cell too early or by pressing the
trigger too early.
1.2.8.2. All data should be reviewed for errors when entered into the
database.
1.2.9. Graphing Data: After verification of the data, the data should be
graphed by data base software or by copying the data into a spreadsheet
application. This graphical presentation of the data allows for easy analysis.
1.2.10.2. Trends, which may not have been apparent when looking at the
potential measurements, will be readily seen on the graphs.
1.2.10.3. Looking at the graph of the data may uncover areas of the structure
where further testing or troubleshooting is required.
1.2.10.4. The data may also be overlaid with previous survey data or future
survey data to allow easy recognition of changes or other anomalies.
1.2.11. Other tests required include anode and rectifier checks shown in table
1.2 (these requirements are detailed in MIL HDBK 1136).
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 10
1.3. The Corrosion Survey is conducted to reasonably ensure that the entire
structure still has adequate cathodic protection.
1.3.3.1. Data from the close interval corrosion survey should be analyzed to
determine the best locations for data collection during the corrosion survey.
1.3.3.2. This is normally the low and/or the high potential locations,
according to the trends in that data.
1.3.3.3. If a close interval survey has never been done, it would be wise to
perform the close interval survey in lieu of the corrosion survey.
1.3.3.4. "On" and "instant off" potential measurements must be taken. If data
from a close interval corrosion survey is not available, sufficient test
locations should be selected to ensure that the entire structure is protected.
1.3.7. Other tests required include anode and rectifier checks shown in table
1.4. These requirements are detailed in MIL HDBK 1136.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 12
1.4. The Water Tank Calibration is conducted to ensure that the entire
structure has adequate cathodic protection, without the presence of over
voltage, which may damage the coating.
1.4.3.2. The tank bottom should have potential measurements taken directly
below tank wall anode strings, stub anode strings, and between the anode
strings.
1.4.3.3. For elevated towers with "wet" risers, close interval measurements
should be taken near the riser wall for the entire length of the riser (normally
every 2 to 5 feet).
1.5.3. Preferred Equipment: Handheld multimeter with AC, DC, ohms, and
diode circuits and suitable test leads.
1.5.4.3. Measure the output voltage and current and calibrate the rectifier
meters, if present (figures 1.4 and 1.5).
1.5.4.4. For rectifiers with more than one circuit, measure the output voltage
and current for additional circuit(s), and calibrate other rectifier meters, if
present.
1.5.4.5. For rectifiers with potential voltmeters, measure and calibrate each
meter. Using a known good reference electrode, measure the potential
difference to the installed permanent reference electrode.
1.6.1. Preferred Equipment: Data Logger, motorized wire reel, and data
probe with copper/copper sulfate electrode. Other equipment which may be
used includes high input resistant DC voltmeter (10 megaohms or higher),
wire reels, intermediate electrode extension, and copper/copper sulfate
electrode.
Table 1.5. Recommended Over the Anode Intervals For The Impressed
Current Anode Bed Survey.
CP SYSTEM TYPE TEST MEASUREMENT
Connect structure lead to negative terminal of
REMOTE rectifier.
SHALLOW ANODE Anode-to-soil potentials taken at 2 foot intervals
GROUND BEDS along the length of the anode bed, beginning 10 feet
before the first anode, and ending 10 feet past the
last anode in the ground bed
Plot test results on graph paper to give a visual
indication of the anode bed condition
DISTRIBUTED One anode-to-soil potential with the reference cell
SHALLOW ANODE located directly over each anode
GROUND BEDS One anode-to-soil potential with the reference cell
located 10 feet on two opposite sides of the anode
In lieu of anode potential measurements, measure
DEEP ANODE anode circuit current
GROUNDBEDS Measure the anode current for each anode if separate
leads are available
1.7. The impressed current system check is performed to ensure that the
system is operating at the same level as the last survey and to reasonably
ensure that the current output of the system is still sufficient.
1.7.2.4. Take potential measurements at the locations of the three lowest and
the highest potential measurements identified in the most recent close interval
or corrosion survey.
1.7.2.5.2. If potential measurements do not meet the criteria, and the rectifier
current output meets the current requirement from the last survey, adjust or
supplement the CP system as necessary and repeat testing. Conduct a
corrosion survey 30 days after adjustment or modification to the cathodic
protection system to establish the new current requirement.
1.8.3. Disconnect anode and measure potential with reference cell over the
anode (figure 1.6).
1.9.1. Preferred Equipment: Handheld Multimeter with AC, DC, ohms and
diode check circuits, wire reel, and a copper/copper sulfate electrode. Other
equipment that may be used includes Data Loggers with data probes,
waveform analyzers, or high input resistant DC voltmeter (10 megaohms or
higher).
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 20
1.10. The leak survey is performed to determine the cause of the leak and to
determine the corrective action required in preventing future leaks.
1.10.3. Measure the potential with the reference electrode near the surface of
the structure.
1.10.4. Measure the pH of the electrolyte near the surface of the structure.
1.10.5. Perform a visual inspection of the structure coating and note its
condition.
1.10.6. Inspect the structure surface at and around the point of the leak.
1.11. Records must be kept on file for all structures with cathodic protection
systems.
1.11.1. All surveys included in this section should be filed in a folder for
that specific cathodic protection system.
1.11.2. All these records are instrumental for future operations, maintenance
and testing of cathodic protection systems and protected structures.
1.11.7. In some cases public law requires these records to be maintained for
specific intervals.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 23
CHAPTER 2
MAINTENANCE OF CP SYSTEMS
2.1. CP Systems require unscheduled maintenance to repair systems when
they are not operating properly.
2.1.6. Galvanic systems are normally trouble free, until anode life has been
reached.
2.2.3. Measure the DC current output of the rectifier using one of the
following methods (in order of accuracy):
2.2.7. Use table 2.2 to determine possible problems and take the actions
required to isolate the problem.
2.2.8. Loss of structure isolation is the most common reason of low
potentials with normal or high rectifier output.
2.2.8.1. Check potentials on both sides of dielectrics. Higher than normal
potentials on the house side of the dielectrics indicate a short somewhere in
the system.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 25
2.2.8.1.2. If all dielectrics check good, look for new services, shorts around
dielectrics, current pickup on foreign structures, and/or underground shorts
by conducting over-the-line survey using Audio Frequency (or 120-Cps) pipe
locator or cell-to-cell procedures.
2.2.9. For systems that are not isolated, the most common reason of low
potentials with normal rectifier output, is a change in the amount of structure
protected. This may also occur on isolated structures.
2.2.9.2. Check for new projects which may affect the structure (other new
utilities which may be shorted to the structure).
2.2.10.1. Check for construction near structure that may have damaged
coating.
2.2.11. Error of installed meters may indicate low output, even though
output is normal.
2.2.12.1.1. If potentials do not meet criteria because the soil around the
anodes has dried out, do not adjust rectifier.
2.2.12.1.2. Anodes are normally deeper than the structure. If anodes are
dried out, then the structure is also dried out, lowering the corrosion rate.
2.2.13.3.3. Perform a close interval survey over entire length of anode bed
(1 or 2 ft intervals).
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 28
2.2.13.5.1. Look for any excavations which have occurred in the area of the
anode cable.
2.2.13.5.2. Use audio frequency pipe locator or fault detector to locate break
in cable.
2.2.14.1.3. Trace the anode lead from the rectifier towards the anode bed.
Repair break.
2.2.14.2.3. Connect signal generator directly to the anode cable at the anode.
2.2.14.2.4. Use a low resistance, isolated ground for the signal generator.
2.2.14.2.5. Use the fault detector and cable locator to trace the anode lead
from the anode towards the rectifier.
2.2.14.2.6. If this is still unsuccessful, replace the anode lead from the
rectifier to the first anode.
2.2.15. For anodes in water tanks, if the water level goes down, anodes will
no longer be in contact with the electrolyte. If the water level is below all
anodes, no current will flow.
2.2.16.3. Pull fuse from holder and use ohmmeter to verify continuity.
2.2.16.4. Check DC Fuse(s). Pull fuse from holder and use ohmmeter to
verify continuity (figure 2.3)
2.2.16.5. Check AC voltage to both sides of circuit breaker with breaker on.
2.2.18.4.2. Install proper size fuse. If proper size fuse still fails, repeat tests
in paragraph 2.2.18.
2.2.19.1. Air flow in cabinet may be restricted by dirt, nests, other foreign
materials.
2.2.20.5.2. And automatic operation is required (water tank where the water
level constantly changes), troubleshoot automatic circuit. If automatic circuit
is on a removable card, replace card with troubleshooting card (if supplied)
or replacement card (spare, if available) and retest. See rectifier operating
manual for troubleshooting procedures.
2.4.1.2. Higher than normal potentials on the house (unprotected) side of the
dielectrics indicate a short somewhere in the system.
2.4.1.2.2. If all dielectrics check good, look for new services, shorts around
dielectrics, current pickup on foreign structures, and/or underground shorts
by conducting over-the-line survey using 120-cps pipe locator or cell-to-cell
procedures.
2.4.1.2.3. Low potentials on the house side of all dielectrics is normal and
indicates good isolation. Other problems are causing the loss of protection.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 36
2.4.4. If the failure was sudden, a cable break can be expected. This is most
common when anodes are installed on a continuous header cable, and
connected to the structure at a test station.
2.4.4.1.2. Disconnect anode. Connect positive meter lead to the anode lead.
Measure potential with reference cell over the anode. Measure anode output
current.
2.4.5.1. Look for any excavations which have occurred in the area of the
anode cable.
2.4.6. If a failed anode is indicated, replace the anode, unless general failure
of all anodes can be expected (see above).
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 38
CHAPTER 3
CP TEST PROCEDURES
3.1. CP Test Procedures. Potential measurement is the fundamental test
procedure used in CP testing.
3.2.1.1. In soil and fresh water conditions the copper/copper sulfate reference
electrode should be used.
3.2.2.2. Under rocky or very dry conditions the voltmeter should have up to
200 million ohms input resistance.
3.2.4.6. For full details about these five errors, see MIL HDBK 1136.
3.3.1. The test method used depends first on the criteria which is being used
to evaluate the adequacy of the CP applied to the structure. The criteria
selected depends mostly on the type of the structure; isolation/non-isolation
of the structure; structure coating type and efficiency; the type of CP system;
the soil resistivity; the amount of current supplied by the CP system, and the
instrumentation available for testing.
3.3.2.3. For very small and well coated structures (such as valves, elbows,
tie-downs, etc.), the 100 mV polarization criteria should be used.
3.3.2.4. If the system is designed to allow interrupting the current from all
anodes simultaneously, the 100 mV polarization criteria should be used.
3.3.2.5. The -0.85 instant off criteria is not attainable in many soil conditions
with galvanic anodes.
3.3.2.5.1. Unless the native potential of the structure is very high and/or the
soil resistivity is very low.
3.3.2.5.2. The -0.85 instant off criteria should not be used for galvanic CP
systems except in rare cases. The 100 mV shift criteria or the -0.85 on
criteria (considering IR) should be used.
3.3.3.2.2. For structures with a high dielectric strength coating, the -0.85
instant off criteria may be the easiest to use; the 100 mV polarization criteria
may be used. The -0.85 on criteria (considering IR) should not be used.
3.3.3.2.3. For structures which are bare, poorly coated, or have a deteriorated
coating, the 100 mV polarization criteria may be the easiest to use; the -0.85
instant off criteria may be used. The -0.85 on criteria (considering IR) should
not be used.
3.3.4.5. Interruption of the CP current does not fall under this criteria, since
that would pertain to the -0.85 instant off or the 100 mV polarization criteria.
3.3.4.6.3. The location of the reference cell in relation to the anodes and the
structure.
3.3.5.1. This criteria requires the measurement of the potentials when there is
no CP current flowing.
3.3.5.2. For various methods used to measure the instant off potential see
MIL HDBK 1136 section 7.2.5, Instant Off Test Methods which include:
3.3.6.1. The test method for this criteria is similar to the negative 0.85 instant
off criterion, with the additional requirement of comparing the instant off
reading to a native or depolarized reading.
3.3.6.2.1. Perform a thorough native survey and identify the most anodic area
(highest negative) reading.
3.3.6.2.2. Determine the instant off reading required to meet the 100 mV
shift criterion at that point (example, if the most negative reading was -0.625
Volts DC, the instant off would have to be -0.725 Volts DC).
-0.700 volts DC), annotate those exact locations; add 100 mV to those
readings; or compare future instant off readings to those specific readings at
those specific locations. If a significant percentage of the pipeline is over -
0.700 Volts DC, consider using the -0.85 instant off criterion for the entire
pipeline.
3.3.6.3.2. Determine the instant off reading required to meet the 100 mV
shift criterion for the rest of the structure (example, if the most negative
reading for the rest of the structure was -0.603 Volts DC, the 100 mV instant
off would have to be -0.703 Volts DC).
3.3.6.3.3. Apply that instant off criteria to the rest of the structure.
3.3.6.4.1. If native survey data is available, analyze data and use procedures
as above for unprotected isolated or non-isolated structures, as appropriate.
structure coatings, high resistivity soil, low levels of oxygen, and soils which
seal the structure from water and oxygen will slow depolarization.
Considerably more current is required to polarize the structure to a level
where the 100 mV depolarization will occur in a relatively short time period
(seconds or minutes).
3.3.6.4.5. If the instant off potential is 100 mV more negative than the native
potential (or depolarized) potential, this criterion has been met.
3.4.1.1. If the gas is produced faster than it can permeate out through the
coating, bubbling of the coating will occur.
3.4.3.5. The instant off potentials must never exceed -1.10 volts DC.
3.4.4.2. The only true way to measure the possibility for coating damage is
with an error free measurement (see paragraphs 3.2 and 3.3).
3.4.4.3.1. Instant off measurements over -1.22 volts DC are not theoretically
possible. Look for other DC current sources.
3.4.4.4. For fusion bonded coatings the instant off potentials should not
exceed -1.07 volts DC and must never exceed -1.12 volts DC.
3.4.4.5. For Coal Tar coatings the instant off potentials should not
exceed
-1.12 volts DC and must never exceed -1.20 volts DC.
3.4.4.6. For Plastic Tape coatings the instant off potentials should not
exceed -1.02 volts DC and must never exceed -1.07 volts DC.
3.4.4.7. For other coatings refer to specifications for cathodic disbondment
properties compared to above coatings.
3.4.4.8. For uncoated structures there is theoretically no potential limit.
Instant off readings over -1.00 generally waste power and anode material.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 51
3.4.4.9. Table 3.1 assumes an IR drop error and is given for information
only.
3.5.1.3. The polarity of the voltage difference between the two reference
cells indicates the direction of current flow.
3.5.2. The accuracy of the reference electrodes (half cells) used to take cell to
cell measurements must be determined:
3.5.2.1. The accuracy of the two half cells is determined by measuring the
difference in potential between the two half cells being used for the test. Use
a suitable high input resistance voltmeter on the millivolt scale, place the two
cells cone to cone, and measure the potential difference. The potential
difference should not be in excess of 5 mV.
3.5.2.3. Equal spacing between the reference cells must be made to evaluate
any magnitude differences in measurements.
3.6.1.3. Calculating the input in watts (revolutions per hour of the KWH
meter disc X PF (Power Factor) shown on the face of the KWH meter).
3.6.2.5.1. The type of AC power (Single or Three Phase). Three phase units
are much more efficient.
3.6.2.5.4. The percent of load of the unit. Units are most efficient at full
rated output.
3.7.1.3.2. According to the size and coating of the structures involved, this
could be from less than 1 ohm to several thousand ohms, and does not give
any indication of the resistance across the dielectric.
3.7.2.3. Some methods for testing a dielectric look for a voltage difference
across the two sides, which is an indication of that dielectrics condition:
3.7.2.3.3. Use of the headset type of insulation tester (similar to Tinker &
Rasor model "IT"). If tone is heard, voltage is present the dielectric is not
shorted. If tone is not heard, voltage is not detected (see above).
3.7.2.4.2. This method will not read through other parallel paths, even when
these paths are in the immediate vicinity. Therefore, this method should be
used for testing when any other method is not conclusive.
3.7.3.3.3. If the dielectric is good and the house side of the dielectric has a
potential more negative than expected (for example, if the house side
potential reading is over -0.65, with a street side potential more negative),
another shorted dielectric in the area should be suspected. Further
investigation is required.
3.7.4.2. Using a long wave length signal (low frequency) pipe locator:
3.7.4.2.3. Use pipe locator and attempt to follow signal past dielectric. If
signal stops at dielectric, dielectric may not be shorted. If signal can be
followed past dielectric, dielectric is shorted.
3.7.4.3. Using a fault detector and the signal from an impressed current
system (DC output has a 120-cps component, sometimes called "pulsating
DC").
3.7.4.3.1. This method can only be used with impressed current systems with
a single phase rectifier, and works best with no output choke or filter
(stronger signal).
3.7.4.3.2. Must use a fault detector (such as the Pipe Horn Model 200FDAC)
or a pipe locator (with built in fault detector) capability of following a 120-
cps signal.
3.7.4.3.5. Use fault detector and attempt to follow signal past dielectric. If
signal stops at dielectric, dielectric may not be shorted. If signal can be
followed past dielectric, dielectric is shorted.
3.8.1.1. Do not use an ohmmeter to measure between a casing and the carrier
pipeline:
3.8.1.2.1. They totally shield the carrier pipeline inside the casing from
receiving any CP.
3.8.1.2.2. They steal current which would otherwise protect a large area of
the pipeline outside the casing. Casings are normally not coated (or poorly
coated). Have a relatively low resistance to earth (than the coated carrier
pipeline). Provide a lower resistant path for CP current.
3.8.2. Casing test stations normally have four wires: two to the casing; two
to the carrier pipeline. If there is not a test station already installed, one
should be installed prior to testing. At a minimum, there must be a metallic
connection made to the carrier pipeline and a vent pipe which is connected to
the casing. If there is no vent pipe or carrier pipe test point in the vicinity of
the casing, excavation must be made to the carrier pipeline or the casing, as
required, and test connections made.
3.8.5.3.1. Connect test leads to the meter left terminals. Temporarily short
test lead ends together; turn contact check circuit on; zero needle to full scale,
and disconnect test leads.
3.8.5.3.3. Connect one test lead to carrier pipeline. Full scale deflection
indicates the casing is shorted to the carrier pipeline.
Deflection of 75% to almost full scale deflection, or deflection past
100% (or pegged) is inconclusive. Reverse test lead connections. Same
reading indicates there may be a partial short. Use underground
insulated flange tester to verify. Opposite side of full scale reading
indicates casing isolation is good. For example, a 90% reading, when
leads are reversed, reads over 100% (pegs), or a reading over 100%
(pegged) when leads are reversed. reads under full scale.
Deflection from 30% to 75% is inconclusive: could be partial short.
Reverse leads and test as above. Use other test procedure to verify
casing condition.
3.9.1.2.1. Connect test leads to the meter left terminals. Temporarily short
test lead ends together; turn contact check circuit on; zero needle to full scale,
and disconnect test leads.
3.9.1.2.3. Connect one test lead to carrier pipeline. Full scale deflection
indicates the two structures are connected.
Deflection of 75% to almost full scale deflection, or deflection past
100% (or pegged) is inconclusive. Reverse test lead connections. Same
reading indicates there may be a partial short between the structures.
Other testing should be conducted to verify. Opposite side of full scale
reading indicates structures are isolated. For example a 90% reading,
when leads are reversed, reads over 100% (pegs), or a reading over
100% (pegged) when leads are reversed. reads under full scale.
3.9.2. Testing for a short between two structures with CP on one structure:
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 65
3.9.2.3. If the two potential readings are not significantly different (under 10
mV):
3.9.3. Testing for a short between two structures with CP on both structures.
previous test procedure leaving the other systems rectifier on and repeat
testing. Turn off both rectifiers and use radio frequency insulation tester or
multi-combination meter continuity check circuit (see procedures above).
3.10.5.1. If not known, they should be located as remote as possible from the
structure to be protected.
3.10.5.1.1. Without any foreign structures in the area of the temporary anode
bed.
3.10.5.1.2. Without any foreign structure between the temporary anode bed
and the structure under test.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 69
3.10.5.2.2. Do not use any metallic structure for a temporary anode which is
shorted to the structure being tested. Large current surges which can cause
injury to personnel and damage to equipment would result. Test temporary
anode for continuity to structure under test (see testing for continuity between
two structures).
3.10.5.3.10. The better the coating of the structure being tested, the smaller
the number of temporary anodes required. Very well coated structures will
exhibit a noticeable potential change with a small amount of current (1 or 2
amps). Poorly coated structures will not exhibit a noticeable potential change
except with a larger amount of current (10 to 20 amps).
3.10.5.6. For physical strength and low resistance, #6 AWG copper cable or
larger must be used. No. 2 AWG or greater is desired, especially if long runs
in either the structure or anode cable is required. Connections can be made
with pipe clamps, ground rod connectors, test clamps, split bolts, and
exothermic welding. All wire and connections must be made to
accommodate the voltage and current required for the testing.
3.10.5.8. Beginning at a low voltage setting, turn power on. Ensure the
potential shift of the structure is in the negative direction. Gradually increase
voltage and current to desired output. Periodically check potential to ensure a
corresponding negative shift occurs as current is increased. If maximum
voltage is reached and more current is still required, turn system off.
Supplement the temporary anode bed. Consider using multiple power
sources and/or multiple temporary anode beds.
3.10.5.12. Once the potential shift is ascertained, and the current to get that
shift is known, approximation of the actual current requirement can be
calculated.
3.10.5.15. If a current requirement test includes more than one anode bed
location, all current sources should be interrupted simultaneously to measure
the potential shift of the structure:
3.10.5.16. Upon completion of testing, turn all power sources off; disconnect
all cables, and remove temporary anodes. For ease of removal of ground rods
or small diameter pipes and conduit, use three flat metal bars as shown in
MIL HDBK 1136.
3.11.2.3. The output of both galvanic anodes and impressed current anodes is
dependent upon the resistivity of the electrolyte.
3.11.3. Four Pin Method: The most commonly used means of measuring soil
resistivity is by the four pin method.
3.11.3.1. In this method, a current is passed through two outer electrodes and a
drop in potential through the soil due to the passage of the current is measured
with a second pair of inner electrodes.
3.11.3.3. In order to reduce the influence of any stray currents in the area, the
instrument uses a unique 90 cycle square wave.
3.11.3.5. The electrodes should be inserted into the ground at an equal depth,
normally 4 inches.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 74
3.11.3.6. The soil resistivity is calculated from the indicated reading by using
the following formula:
3.11.3.7. In this method, the average resistivity of the soil between the two
center electrodes to a depth equal to the pin spacing is measured. Readings are
normally taken at approximately 2.5, 5 and 10 (see chart below for using
common multipliers). For multipliers for common distances and distances for
even multipliers see table 3.2.
3.11.3.8. If the reading is greater as the pin spacing is increased, the actual soil
resistivity at the greater depth is greater than indicated.
3.11.3.9. If the average soil resistivity decreases at greater depths then the
actual soil resistivity at that depth is lower than indicated.
3.11.4. Two Pin Method. In the two pin method the potential drop is
measured between the same pair of electrodes used to supply the current. The
equipment used to make this type of measurement is often called the "Shepard
Canes" after its inventory. The probes are placed one foot apart. If the soil is
too hard for the probes to penetrate the reading is taken at the bottom of two
augured holes. The instrument is calibrated for a probe spacing of one foot and
gives a reading directly in Ohm-cm. This method is:
3.11.4.2. Measures the resistivity of the soil only near the surface.
3.11.5. Other Methods (Soil Rod, Soil Box). A soil rod is essentially a two pin
resistivity measuring device where the electrodes are both mounted on a single
rod. Like the other two pin method, the resistivity of the soil to a very shallow
depth is measured. Also, the soil must be soft enough to allow penetration of
the rod. Measurements using the soil rod can, however, be made quickly when
making measurements in soft soil.
3.11.5.1. Soil samples can be taken and the resistivity of the sample can be
determined by the use of a soil box.
3.11.5.2. The measurement made on the soil sample is essentially the four pin
method.
3.11.5.3. Metal contacts in each end of the box are used to pass current through
the sample.
3.11.5.4. Potential drop is measured across probes inserted into the soil.
3.11.5.5. The resistivity is calculated using constants furnished with the
particular size of soil box being used.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 78
3.11.5.7.4. Less likely to represent true in place soil resistivity than an actual
field test.
3.12.1. pH ranges from 0 to 14: 0-7 being acidic; 7 being neutral., and 7-14
being alkaline.
3.12.2.2. The antimony electrode must be cleaned prior to each use. Special
cleaning procedures must be used. Clean the antimony electrode as per
instructions in MIL HDBK 1136, Cleaning of the Electrode. Antimony is
very brittle, treat it carefully. The antimony tip must be kept smooth, there
must be no rough surface or pits.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 79
3.12.2.3. Place the antimony electrode and the copper/copper sulfate half cell
in contact with the electrolyte and measure the potential difference using a
high input resistance voltmeter.
3.12.2.5. Avoid taking these measurements with CP current on. Current flow
in the electrolyte will affect the accuracy. If current flow cannot be stopped,
place the two electrodes close together, perpendicular to the direction of
current flow. To measure for the presence of any current flow in the
electrolyte. Place one copper/copper sulfate half cell in the electrolyte. Place
a second copper/copper sulfate half cell a few inches from the other reference
cell. Measure the potential difference using a high input resistance voltmeter.
Take measurements in several directions. If no current is present, the
measurements will read the same. If current is present, the lowest
measurement will be where the least amount of current is flowing.
3.12.3.4. The paper is wetted with the solution being measured and the
resulting color is compared with color standards to determine the pH.
3.13. Calibration of IR Drop Test Span. The IR drop test span is a type of
CP test station which is vital for determination of the direction and magnitude
of DC current flowing through a pipeline.
3.13.3. This method uses the metallic pipeline or cable as a shunt which is
then calibrated and used to measure a Millivolt "IR Drop", from which the
current can be calculated.
3.13.3.2. The resistance can be calculated if the length and wall thickness of
the pipeline test span is accurately known. See table 3.4 to estimate the
resistance of the test span.
3.13.3.3. The line current can be calculated using ohms law, E = I * R, where
E is the measured voltage drop, R is the Resistance of the test span.
3.13.4. One other method for determining the direction and magnitude of DC
current flowing through a pipeline is to use a clamp-on milliammeter. This
method requires a very specialized piece of equipment, sized to the pipeline,
and an excavation or access to the pipeline, for placement of the probe around
the pipeline.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 81
3.13.5.1. The current flowing on pipeline or cable will flow through the
meter and damage could result.
3.13.5.2. If that current does not damage the meter, the measurement would
not indicate a true resistance value. The voltage would be interpreted by the
meter as coming from the internal battery instead of the external electrical
circuit being measured.
3.13.6. The preferred method is to measure the actual resistance of the pipe
using test current. This method:
3.13.6.6. The amount of test current required depends on the diameter of the
pipeline and the distance of the test span.
3.13.6.7. The larger the pipeline, the larger the amount of current required.
3.13.6.8. The shorter the distance of the test span, the larger the amount of
current required.
3.13.7.1.5. A portable rectifier may be used as the current source, switch and
the means of adjustment.
3.13.8. Pipelines and cables inherently will have current flowing at all times.
Therefore, a change in voltage drop measurement is compared to the amount
of test current applied.
3.13.10. With Outside Circuit switch off, record the mV measurement of the
inside circuit. Starting at a low current level:
3.13.13.1. For example, 4.1 mV on, minus 1.3 mV off, is a voltage change of
2.8 mV.
3.13.14. Record the resistance of the test span and the calibration factor
established. If the temperature of the pipeline or cable remains constant, this
calibration factor can be stenciled on the IR Drop Test Station and used for
future measurements. If doubt exists or temperatures change, perform the
calibration steps each time measurements are taken.
3.13.15. Direction of current flow is determined by the polarity of the mV
reading taken on the inside circuit, with meter positive on left, negative on
right. A positive IR Drop indicates current flow from left to right. A
negative IR Drop would indicate current flow from right to left.
3.13.16. The resistance of the pipeline can be calculated if the distance of the
test span is known and the size of the pipeline is accurately known.
Resistance joints or insulators cannot be present on the pipeline in the test
span. Variations in temperature will adversely affect the accuracy of these
calculations.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 84
mV IR Drop
Current =
Resistance
3.13.20. The direction of the current flow is determined from the polarity of
the mV IR Drop reading measured. For example, a positive IR Drop
indicates current flow from right to left, while a negative IR Drop would
indicate current flow from left to right.
3.14.3. Corrosion occurs at the current discharge point. Current can cause
corrosion damage by passing between two structures or across high-resistance
joints in the same structure.
3.14.6. See MIL HDBK 1136, section 2.2.4 for explanations and sources of
interference current.
3.14.9. See section MIL HDBK 1136, section 5.6 for information on
Interference Corrosion Control.
3.14.10.1. CPs systems are a major source of stray current on other metallic
structures.
3.14.10.3. A foreign structure may provide an alternate path for the current
flowing from the impressed current anodes to a protected structure.
3.14.10.5. Since there is no metallic return path, the current will discharge
from the surface of the foreign structure to the electrolyte in order to return to
its source, resulting in severe corrosion.
3.14.10.11. Current flow (IR drop) readings show the relationship between
pick-up and discharge areas on a foreign structure.
3.14.11.1. The algebraic difference between the "on" and "off" reading
(potential shift) gives the interference effect on the foreign structure.
3.14.11.5. If metallic continuity exists between the foreign structure and the
negative terminal of the rectifier, this is not interference, it is protection, and
no discharge area exists (and therefore, by definition is not a foreign
structure).
3.14.14.3. The pickup area is normally near the anode system, which is
causing the interference. Locating the pickup area is important in locating the
source of the interference, since it shows the direction that the current is
coming from.
3.14.15. Measurement of the current flow (IR drop) on a foreign pipeline can
be accomplished if other methods are inconclusive.
3.14.15.1. Current flow (IR drop) readings show the relationship between
pick-up and discharge areas on a foreign structure.
3.14.18.2. Required drainage current can also be computed from test data.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 92
3.14.18.3. When the same owner maintains the protected structure and the
foreign structure, this method may be easily used.
3.14.18.5. When site conditions warrant, the bond may be sized to apply
partial or full protection to the foreign structure.
3.14.18.6. If the foreign structure is small or well coated, and the protected
structure is poorly coated, this option may be taken when sufficient CP
current is still available to maintain protection on the protected structure.
3.14.19.5. Locating the discharge point(s) and pickup areas are still crucial.
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 93
3.14.20. All the basic measurements can be used in studying fluctuating stray
currents. Perhaps the most informative are measurements similar to those
used in interference testing; structure-to-electrolyte potentials and IR drops
along structure or electrolyte. Methods of analysis, however, are different
and specialized equipment is used. The major concern in performing a stray
current survey is to find out the degree of damage and determine the source
of the stray DC current.
3.14.21.4. Data taken is used to locate areas for taking additional data.
3.14.21.5. Once gathered, this data is used exactly like the data for cathodic
interference detailed previously.
3.14.21.7. Once the pickup area and time is determined, the source of the
current may be located (see MIL HDBK 1136, section 2.2.4 for sources of
fluctuating stray currents).
AFH 32-1290(I)/MIL-HDBK-1136/1 1 February 1999 94
3.14.22.4. By analyzing the current direction and magnitude at the time the
interference is occurring, the relationship and direction of the pickup areas
and discharge areas can be determined.
3.14.22.5. Once the time of interference is known, the area of pickup can be
searched for possible sources of the current pickup (see MIL HDBK 1136,
section 2.2.4 for sources of fluctuating stray currents).
3.14.22.6. Outside of the necessity of taking simultaneous readings due to
the fluctuating current, this method is the same as conventional line current
measurement.
EDUARD A. DAILIDE
CAPTAIN, CEC, USN
Assistant Commander for Program Coordination