Cost Estimation PDF
Cost Estimation PDF
Cost Estimation
Reference:
Max Peters, Klaus Timmerhaus, Ronald West
1
Cumulative Cash Position of a project
2
Cumulative Cash Position of a project (contd 1)
Figure 6.2 depicts the cumulative cash position over the life
cycle of a project
Land value is included in the total capital investment
Zero point on the time line represents the point at which plant
construction is complete and ready for start-up
Total capital cost at zero point includes land cost,
manufacturing and non-manufacturing fixed capital investment,
and working capital
Cash position is negative at this point of time equal to total
capital investment
Thereafter cash starts flowing in from the operation; net profit
(after taxes) + depreciation starts to accumulate and gradually
repays the total capital investment
3
Cumulative Cash Position of a project (contd 2)
The chart assumes a constant cash flow rate from time zero
until the end of operations (not reality)
At shutdown, the working capital and land value are recovered.
The relationships presented in Fig. 6 2 are very important for
the understanding of the factors to be considered for cost
estimation
Fig. 6 2 is highly simplified and neglects the time value of
money and assumes constant annual profit and constant
annual depreciation (not reality)
4
Business Decision-making
5
Business Decision-making (contd 1)
Funding
Equity market
Debt (Banks, financial institutions)
Business acumen
Risk taking ability
9
Factors affecting Investment and Production Costs
10
Investment and Production Cost (contd 1)
Price fluctuations
Prices vary widely over a period of time
A chemical engineer must keep up to date on price
fluctuations
Plant location
Land availability
Market for product
Raw material availability
Environmental standards
Tax breaks
11
Investment and Production Cost (contd 2)
Company Policies
Strict safety regulations
Company accounting procedures e.g., how is corporate
cost allocated among various companies
Preferred mode of setting up a plant
- EPCM
- EPC (LSTK)
- Design / Supply
12
Investment and Production Cost Factors (contd 2)
13
Capital Investment
15
Capital Investment (contd 2)
16
Capital Investment (contd 3)
17
Estimation of Capital Investment
18
Estimation of Capital Investment (Contd 1)
19
Estimation of Capital Investment (Contd 2)
20
Estimation of Capital Investment (Contd 3)
21
Estimation of Capital Investment (Contd 4)
22
Type of Capital Cost Estimates
23
Predesign Cost Estimate
24
Cost Estimating Information Guide
Next four slides are a guide to the various types of information required for cost
estimates, and the stages at which they are required.
25
Cost Estimating Information Guide (contd 1)
Order-of-magnitude Estimate
Preliminary Estimate
Definitive estimate
Detailed Estimate
Location
General description
Soil bearing
Site
Location, roads, impounds, fences
Rough sketches
Engineered
Engineered specifications
General arrangement
(a) preliminary
(b) engineered 26
Cost Estimating Information Guide (contd 2)
Order-of-magnitude
Definitive estimate
Detailed Estimate
Study Estimate
+/- 10% range
Detailed drawings
Order-of-magnitude Estimate
Preliminary Estimate
Definitive estimate
Detailed Estimate
Rough specifications
28
Cost Estimating Information Guide (contd 4)
Order-of-magnitude Estimate
Preliminary Estimate
Definitive estimate
Detailed Estimate
Distribution specifications
Well-developed drawings
Supervision
29
Cost Indexes
30
Cost Indexes (contd 1)
Common indexes:
Marshall and Swift: all Industry and Process Industry
equipment indexes
Engineering News Record Construction index
Nelson Farrar refinery construction index
Chemical Engineering plant cost index
31
Cost Indexes (contd 2)
32
Cost Indexes (contd 3)
All cost indexes are based on limited sampling of the goods and
services in question. Therefore the results can differ
considerably.
Marshall and Swift index and Chemical Engineering plant cost
index recommended for process equipment and chemical plant
estimates
Similar indexes not available for India. Some Engineering
companies have created cost data bases. Quite often they get
budgetary quotes from vendors with whom they do business
regularly.
33
Cost Components in Capital Investment
34
Cost Components in Capital Investment (contd 1)
35
Cost Components in Capital Investment (contd 2)
36
Example Estimation of FCI using Table 6-3
37
Example Estimation of FCI using Table 6-3
38
Cost Components in Capital Investment (contd 3)
39
Cost Components in Capital Investment (contd 4)
40
Graphs of Equipment Cost v/s Capacity
41
42
43
44
45
46
47
48
49
50
51
Purchased Equipment Cost by Scaling
52
Purchased Equipment Cost by Scaling (contd 1)
Caution
> check out the size range for which the exponent is
applicable
> In general it should not be used beyond ten-fold
range.
> Make certain the two pieces of equipment are similar
with regard to type, material of construction,
temperature, pressure, operating range, country of
origin
53
Purchased Equipment Cost by Scaling (contd 2)
54
Purchased Equipment Cost by Scaling (contd 3)
55
Purchased Equipment Cost by Scaling (contd 4)
56
Methods for estimating capital investment
57
Methods for estimating capital investment (contd 1)
58
Methods for estimating capital investment (contd 2)
59
Methods for estimating capital investment (contd 3)
61
Methods for estimating capital investment (contd 5)
63
Methods for estimating capital investment (contd 7)
64
Methods for estimating capital investment (contd 8)
65
Methods for estimating capital investment (contd 9)
66
Methods for estimating capital investment (contd 10)
68
Methods for estimating capital investment (contd 12)
69
Methods for estimating capital investment (contd 13)
71
Estimation of Revenue (contd 1)
72
Estimation of Total Product Cost
73
Total Product Cost, Itemwise
Raw materials
Operating labour
Operating supervision
Utilities
Electricity
Fuel
Refrigeration
Steam
Water, process
Water, cooling
Waste treatment and disposal
Maintenance and repairs
Operating supplies
Laboratory charges
Royalties (if not on lump-sum basis)
Catalysts and solvents
Subtotal : Variable production costs
74
Total Product Cost, Itemwise (contd 1)
Depreciation
Taxes (property)
Financing (interest)
Insurance
Rent
Subtotal : Fixed Charges
Medical
Safety and protection
General plant overhead
Payroll overhead
Packaging
Restaurant
Recreation
Salvage
Control Laboratories
Plant superintendence
Storage facilities
75
Subtotal : Plant overhead costs
Total Product Cost, Itemwise (contd 2)
Total of :
Subtotal : Variable production costs
Subtotal : Fixed Charges
Subtotal : Plant overhead costs
= Manufacturing costs
Executive salaries
Clerical wages
Engineering
Legal costs
Office maintenance
Communications
Subtotal : Administrative expenses
Sales offices
Sales personnel expenses
Advertising
Technical sales service
Subtotal : Distribution and marketing expenses
76
Research and Development expenses (Subtotal : R & D expenses)
Total Product Cost, Itemwise (contd 3)
Total of
Administrative expenses
Distribution and marketing expenses
R & D expenses
= General Expenses
77
Raw Materials
79
Operating Labour
Operating Labour
- Divided into skilled and unskilled
- Best estimated from company experience with similar
processes and company policy
- Considerable difference between estimates for US and India
- As automation and controls have increased, labour
requirement has come down substantially
Supervisory labour
- Depends greatly on the type of plant and company
experience and policy
80
Utilities
Utilities
- Required types and quantities are established from flow
sheets
- Cost of utilities such as steam, process and cooling water,
refrigerants, dow therm, compressed air, fuel oil etc. and
waste water treatment and disposal vary widely depending
on source, plant location, amount needed, etc.
- A utility may be purchased at a predetermined rate from an
external source or generated internally
81
Utilities (contd)
82
Repairs and Maintenance, Operating supplies
Operating supplies
- Covers consumables such as lubricants, test chemicals, etc.
- Annual cost is around 15% of cost for repairs and
maintenance
83
Laboratory Charges; Patents and Royalties
Laboratory charges
- Covers cost of laboratory tests for control of operations and
product quality control
- Can be taken as 10% to 20% of operating labour
85
Fixed Charges
Fixed charges
- Fixed charges are expenses which are practically
independent of production rate:
Depreciation
Property Taxes
Insurance
Financing costs (Loan interest)
Rents
- Depreciation should be calculated separately as per Income
Tax rules
- Fixed charges roughly amounts to about 10% to 20% of
total product cost
86
Plant Overhead Costs
87
General Expenses
88
Gross Profit
89
Net Profit; Cash flow from process
Net Profit is the amount retained of the profit after income taxes
have been paid
- Net Profit (Npj) in the year j is
Npj = Gj (1 )
where
= fixed income tax rate as a fraction of annual
gross profits
90
Break Even Point
Occurs when
Total annual product cost = Total annual sales
Total annual product cost =
Variable production cost
+ Annual fixed charges (including depreciation)
+ overhead costs and general expenses
91