Home Organisational Structure About Us Services Staff Projects Client List News and Events Reference Materials Contact Recruitment Links
Home Organisational Structure About Us Services Staff Projects Client List News and Events Reference Materials Contact Recruitment Links
page=84
SUBMIT!
Home
Organisational
Structure
About Us
Services
Staff
Projects
Client List
News and Events
Reference Materials
Contact
Recruitment
Links
Printable Version
Latest News
Cannonway Awarded
Contract On Major LNG
Project in Malaysia....
Read More
1 of 2 4/17/2017 9:23 PM
Valuing Variations http://www.cannonway.com/web/page.php?page=84
At issue in the case was the rate to be applied when valuing the additional work required by
a tender addendum and also substantial additional work instructed of a similar nature. The
applicable rate was unusually high because a lump sum adjustment post tender had been
mistakenly expressed as covering only part of the work for which it was calculated.
The Conditions of Contract (based upon the ICE 6th edition) provided:
"the rates and prices in the Bill of Quantities shall be used as the basis for valuation so far
as may be reasonable failing which a fair valuation shall be made."
Alstom first argued that the lump sum adjustment could not be used to extrapolate a rate,
as it was not "a rate or price in the Bill of Quantities" or, alternatively, that to do so would
require a notional breakdown of the price. The Court held that the post tender agreement
had the effect of modifying the Bill of Quantities, even though there was no express
agreement to do so, and so the lump sum adjustment was a price in the Bill of Quantities
for the purposes of the valuation of a variation. Further, the Conditions of Contract did not
oblige the contractor to provide any information as to how a rate or price was arrived at (it
is interesting to note that the West Rail Conditions contain an express requirement for the
contractor to provide a breakdown).
Alstom's main argument (which found favour with the arbitrator) was that it would not be
"reasonable" to use the price as a basis for valuing a variation, because the price was high
due to a mistake in the tender. The Court stated that what was reasonable in this context
was to be determined by looking at the nature of the work itself and not extraneous
economic or financial considerations. That the result of the use of the rate or price might be
unreasonable was irrelevant, because the rate or price was already unreasonable before the
variation was ordered; the rate or price was not made unreasonable by the execution of the
variation. The Court ordered that rates derived from the lump sum adjustment should be
used for the valuation of the variations.
"It is one of the skills of tendering for a construction contract ... to anticipate where there
may be departures from the estimated quantities or item descriptions which might prove to
be to the contractor's advantage."
This is a clear statement that it is legitimate to load rates, and the burden is on the
employer to scrutinize the tender with care to see that no advantage is taken by such
means.
In summary, the Court was keen to provide commercial certainty to construction contracts,
whilst acknowledging their approach may lead to rates being applied that resulted in
substantial profit or loss for a contractor. The moral of the story for employers is that they
should give as much attention to the rates set out in tenders as to prices.
Back to top
8/F Tung Chiu Commercial Centre | 193 Lockhart Road | Wanchai, Hong Kong | Tel: 2529 1117 | Fax : 2866 2725 | [email protected]
2 of 2 4/17/2017 9:23 PM