Project Resource Requirement:
Raw Material 150TPD 300TPD 1 Plant Incharge
Capex (lac) 380 560 1 Foreman/Mechanic Incharge
Opex (lac) 27 32 1 Electrical Maintenance In charge
IRR (yr) 2.5 1.5 3 Production Incharge
3 Admin Employees
Land (m2) 8000 9000
1 RM Quality and Oil Sale Incharge
Shade (m2) 4500 6000 14 to 18 Unskilled Workers
Power (hp) 250 320
Lead time (months) 4 5 Project Guarantees:
Manpower 24 28 1. 330 day per annum plant capacity
Assumptions: Land & building are provided by Municipal 2. 100% achievement of plant capacity
Corporation, tipping fees of 500/mt from Municipal 3. 1 year machinery warranty
Corporation. Contact us for detailed financial calculations.
4. After sales support and guidance
Pyrocrat assures above project performance
Projects Scope of work: guarantees when the plant is operated as per the
guidelines mentioned in authorised product manual &