Final Report PTK BMC 2017
Final Report PTK BMC 2017
17
ACKNOWLEDGEMENTS
It gives me immense pleasure to present this report carried out at Metallon gold Zimbabwe (How
Mine) Limited in partial fulfillment of the requirements of a Bachelor of Science Honours
Degree in Mining and Mineral Processing Engineering to the Department of Mining and Mineral
Processing Engineering. No work can be carried out without the help and guidance of various
individuals. I am happy to take this opportunity to acknowledge and express my profound
gratitude to those who have been helping me complete this report.
Firstly I would like to thank the lord Almighty for granting me this opportunity to be part and
parcel of Global Insurance Company Limited.
Secondly I would like to pass my gratitude to the following people who were inspiring in the
completion of my attachment programme and from whom I got to appreciate mining as a whole,
Mr Manyenje (The mine captain), my mentor Mr T. Chokera (The mine training officer), all the
miners at how mine and lastly to the management staff of How Mine for giving me the
opportunity to proceed with my studies.
My gratitude also goes to the MSU (Manicaland College of Applied Sciences) academic staffs
who have imparted their vast knowledge which has so much assisted me during my industrial
attachment. It is through their unwavering support that I was able to appreciate the theoretical
aspects of insurance and reinsurance Industry. Many heartfelt thanks for their unwavering
support.
Lastly I would also like to thank my parents for their unconditional love and support and for their
financial support.
ii
DEDICATIONS
Finally but not least, to all the MSU (Manicaland College of Applied Sciences)Mining Students
iii
ATTACHMENT SUMMARY
iv
Survey Survey methods of production 2 weeks Senior Surveyor
plan
Basic surveying of and
installation of pegs
Computers and surveying
Preparation of mine plans
Maintaining and updating of
plans
Assay Laboratory preparations 2 weeks Chief Assayer
Information generation for
production grade control
Shafts Shaft Exam and Maintenance 3 weeks Timber man
Construction Transportation of heavy material
Shift Boss
Construction work waste disposal
Engineering Drainage and pumping 2 weeks U/G Services
Electrical reticulation Foreman
Compressed air reticulation
Equipment over hauls
Maintenance facilities and
schedules
Basic welding and cutting skills
MBL Training Revision and mock tests SHEQ Officer
MBL examinations
Training Officer
v
Contents
1 EXECUTIVE SUMMARY................................................................................................................... 2
2 INTRODUCTION ................................................................................................................................ 2
2.1 Metallon Corporate Structure........................................................................................................ 4
2.2 Historical overview of the mine .................................................................................................... 4
2.3 Company profile ........................................................................................................................... 4
2.3.1 Vision .................................................................................................................................... 4
2.3.2 Mission statement ................................................................................................................. 5
2.3.3 Core Values ........................................................................................................................... 5
2.3.4 Operational statement ........................................................................................................... 6
2.4 ORGANISATIONAL STRUCTURE ........................................................................................... 6
3 DEFINITION OF TERMS.................................................................................................................... 7
4 GEOLOGY OF THE MINE ............................................................................................................... 13
4.1 GEOGRAPHICAL LOCATION ................................................................................................ 13
4.2 REGIONAL GEOLOGY SETTING .......................................................................................... 14
4.3 LOCAL GEOLOGY ................................................................................................................... 16
4.4 OREBODY MINERALISATION MODEL ............................................................................... 18
4.5 MINING METHOD.................................................................................................................... 19
5 INDUCTION ...................................................................................................................................... 20
5.1 Security Department ................................................................................................................... 20
5.2 SHEQ Department ...................................................................................................................... 20
5.3 Human Resources Department.................................................................................................... 20
5.4 Finance Department .................................................................................................................... 21
5.5 Technical Service Department ................................................................................................ 21
5.6 Metallurgical Department ........................................................................................................... 21
5.7 Mining department ...................................................................................................................... 22
5.8 Engineering department .............................................................................................................. 22
6 ATTACHMENT CONTENT ............................................................................................................. 23
6.1 Risks at the Company ................................................................................................................. 23
6.2 Lashing........................................................................................................................................ 24
vi
6.3 Drilling, charging and blasting.................................................................................................... 27
6.4 Explosives ................................................................................................................................... 33
6.5 Ptv (pipe and track laying) .......................................................................................................... 40
6.6 Production ................................................................................................................................... 43
6.7 SHAFTS...................................................................................................................................... 44
6.8 PLANT OPERATIONS (REDUCTION) ................................................................................... 47
6.8.1 General Overview of the Reduction Process ...................................................................... 48
6.8.2 Crushing .............................................................................................................................. 48
6.8.3 Milling................................................................................................................................. 51
6.8.4 Knelson concentrator .......................................................................................................... 54
6.8.5 Acacia plant ........................................................................................................................ 54
6.8.6 Hydro-cyclone..................................................................................................................... 56
6.8.7 Screens ................................................................................................................................ 57
6.8.8 Carbon in pulp..................................................................................................................... 58
6.8.9 Elution ................................................................................................................................. 60
6.8.10 Tailings disposal ............................................................................................................... 62
6.9 TECHNICAL SERVICES .......................................................................................................... 65
6.9.1 Survey ................................................................................................................................. 65
6.9.2 Geology ............................................................................................................................... 74
6.9.3 Assay ................................................................................................................................... 75
6.10 Recommendations ....................................................................................................................... 78
6.10.1 To the company................................................................................................................... 78
6.10.2 To the school ....................................................................................................................... 79
7 PROJECT PROPOSAL ...................................................................................................................... 80
vii
1 EXECUTIVE SUMMARY
This section gives a brief overview of aspects covered in this report. This report gives an account of the
activities covered by Pride Tafadzwa Kubvoruno, the Manicaland College of Applied Sciences student
(from here referred to as the Student) during the industrial attachment undertaken at Bulawayo Mining
Company- How mine (from here referred to as the Company). An industrial attachment is a pre-requisite
course for fourth year Mining and Mineral Processing students at the University in partial fulfillment of
the requirements of BSc Honours Degree in Mining and Mineral Processing. Bulawayo Mining Company-
How mine is located in Matebeleland-South province, about 30 kilometers southeast of Bulawayo town in
southern Zimbabwe which specializes in gold mining and processing. This report was compiled by the
Student and all materials used to compile this report were acquired legally from How mine officials and
approved by the training officer, Mr T. Chokera for academic use only. Any unauthorized use,
reproduction, distribution and publishing is prohibited or otherwise permission may be sought from the
author and/or directly from How mine.
This report provides a full account of the activities covered by the Student at the mine during the
attachment period highlighting the following key areas:
A summary of induction process which involve introduction to different departments, their roles,
regulations at the mine and how the departments work hand in hand.
A summary of different day to day activities, including the purpose, equipment, procedures,
observations and recommendations for each and every activity.
A brief account of the departmental visits done by the student to further understand linkages in the
mining industry.
The conclusion and lessons learnt during attachment period.
The challenges faced and recommendations brought forward by the student to both the University
and to BMC-How mine so as to continuously improve the Mining and Mineral Processing
industrial attachment program.
2 INTRODUCTION
Metallon Corporation limited is one of the leading gold producer, developer and explorer in Southern
Africa. The Portfolio of mineral assets in Zimbabwe comprises of five mining properties and two
exploration properties located within a significant land package (954.43km2).The mining properties
comprises of five separate underground gold mines: How, Shamva, Arcturus, Redwing and Mazowe
2
which are serviced by their own dedicated processing facilities and accompanying infrastructures. The
mines are located in different Achaean greenstone belts on the Zimbabwean craton as shown;
Figure 1 :Metallon mineral assets in Zimbabwe (Source: Metallon website).
Exploration activities at the mining assets are focused on extending existing orebodies and identifying
new orebodies both at existing and undeveloped sites. There is an exploration property at Motapa which is
the subject of active and ongoing exploration and some other exploration targets shown with yellow dots
on Figure 1 above. There is also significant exploration potential at all the mining operations, most of
which are the subject of active and ongoing exploration. Arcturus is currently under care and maintenance
due to poor performance and lack of funding for exploration, development and mining activities at the
mine; which is the main reason it was not included on the current corporate structure below:
3
2.1 Metallon Corporate Structure
Figure 2: Corporate Structure (Source: Metallon website).
The student was attached at Bulawayo Mining Company-How mine for the period of his industrial
attachment. Bulawayo Mining Company (BMC) owns How Mine which is Metallon's flagship low
cost, mining operation. It is one of the largest gold producers in Zimbabwe, producing at least
100kgs of gold per month
2.3.1 Vision
To be a world class precious metals mining company with a footprint across Africa.
4
The above statement is the inspirational position that the organization wishes to attain in the long run.
Metallon urges all its mines to adhere and align to this vision so as to globally recognized precious metals
mining company with traceable achievements in Africa in socially responsible manner.
5
2.3.4 Operational statement
To conduct all the mining processing and service operations in a safe efficient, cost effective and
environmental acceptable manner
Training and technical services support and plays an important part in realizing stated goals.
The company shall develop and maintain high standards for all aspects of mining and processing
operations and aim to continuously improve on them.
6
Figure 3: How Mine Organogram
3 DEFINITION OF TERMS
TERM DEFINITION
7
Abandoned or Disused An excavation where normal mining and related activities have not taken
End place for more than 6 months.
Air Column A column made of steel pipe for the conveyance of compressed air.
Anemometer An instrument for measuring the speed of the wind, or of any current of gas.
Barricade A device to limit, and or prevent, access to areas for the protection of all
personnel.
Battery Charging Bay A station that provides power to charge the batteries of a battery locomotive.
Battery Locomotive A battery powered self-propelled rail-bound machine used for pulling trains.
Blast Area The area near a blast within the influence of flying missiles, or damage-level
concussion
Blasthole A hole drilled into rock or other material for the placement of explosives.
Blowpipe A tool to which can be connected either a high pressure water supply or
compressed air and is used for revealing or cleaning the cavity of a blasthole
by forcing air or water into it.
Chain Ladder A ladder with stringers consisting of a mild steel link chains connected by
rungs of mild steel round bar.
Cocopan A small wagon running on narrow-gauge railway lines used in mines to ferry
ore.
Competent Assistant A person who assists a competent person; has had adequate training and
experience in a particular mine task; who is also able to assess the risks
related to the task and is able to perform the task without avoidable danger to
himself or any other person.
Competent Person A person who has had adequate training and experience in a particular mine
task who is also able to assess the risks related to the task and is able to
perform the task without avoidable danger to himself or any other person.
Coupling The degree to which an explosive fills the borehole. Bulk loaded explosives
are completely coupled. Untamped cartridges are uncoupled. (Also intimate
contact between explosives and rock.).
Cut The group of holes fired first in a round to provide additional free faces for
the succeeding shots.
Decoupling The use of cartridge products significantly smaller in diameter than the
borehole.
Delay Blasting The use of delay detonators or connectors that cause separate charges to
8
detonate at different times, rather than simultaneously.
Delay Connector A nonelectric, short interval delay device for use in delaying blasts that are
initiated by detonating cord.
Detonating Cord A flexible cord containing a centre core of high explosives which may be
used to initiate other explosives.
Development Call The total expected excavation advance from a development end over a
prescribed period of time.
Development Junction The connection between a main tunnel and sub-tunnel or crosscut.
Drain A channel or pipe or conduit carrying off water from one area to another.
Drilling A cutting process that uses a drill bit to cut or enlarge a hole of circular
cross-section in solid materials.
Drill Bit A rotary cutting tool, often multipoint which when cutting is pressed against
the rock face and rotated at rates from tens to hundreds of revolutions per
minute.
Drilling Machine A machine driven by either impact or simple rotation and used to drive
cutting tools into rock to bore holes or recover core.
Drilling Pattern An arrangement showing location, direction and depth of the holes drilled
into the face of a tunnel.
Drill Round The set of holes including their depth and direction drilled, to be charged and
blasted to excavate an opening.
Easer One of a ring of holes drilled around cut holes and fired after cut holes.
Egress A path or opening for going out or an exit which shall be an alternate shaft,
decline, ramp, portal or adit not normally used for day-to-day operations.
Emergency Evacuation The immediate and urgent movement of people away from the threat or
actual occurrence of a hazard.
9
Fan A machine for producing airflow, often for cooling.
Flat Development A horizontal tunnel mined to connect the workings to each other and to the
main mine access.
Flyrock Rock that is propelled through the air from a blast. Excessive flyrock may be
caused by poor blast design or unexpected zones of weakness in the rock.
Fragmentation The extent to which rock is broken into small pieces by primary blasting.
Fresh Air Natural air free of contaminants including explosive fumes (containing
nitrous oxide and carbon monoxide), airborne dust, and naturally occurring
gases such as methane, carbon dioxide, hydrogen sulphide and radon
Geological Mapping The depiction of geological features and their transposition onto paper in the
form of drawings or symbols
Grade Control Process to quality check and control the grade and variability of an ore.
Grizzly A grating placed over the top of a chute or ore pass for the purpose of
stopping the larger pieces of rock or ore that may hang up in the pass.
Hand Tramming The movement of rolling stock on rails, manually by a person or persons.
Ignitor Cord A fuse that burns progressively along its length with an external flame at the
zone of burning, used for lighting a series of safety fuses in a desired
sequence.
Jackhammer A tool designed for drilling blast, anchor and rock-splitting holes. It drills
diameters to 40 mm and depths up to approx. 3 m using pneumatic power for
impact and rotation.
Ladder A vertical or inclined set of rungs or steps. Rigid ladders consist of vertical
members called stringers or rails or stiles connected at specified spacing by
rungs or steps.
Lamproom The designated room or building where cap-lamps for issue to personnel
proceeding underground are stored, charged and maintained
Life of Mine The time in which, through the employment of the available capital, the ore
reserves (or such reasonable extension of the ore reserves as conservative
geological analysis may justify), will be extracted. The mining plan dictates
a schedule of ore delivery to the process plant.
10
Locomotive A self-propelled rail-bound machine which requires either a driver for
manual operation or an operator for automatic operation.
Magazine Any building or portable structure used to store explosives and blasting caps.
Mine Survey A branch of mining science and technology which includes all
measurements, calculations and mapping which serve the purpose of
ascertaining and documenting information at all stages from prospecting to
exploitation and utilizing mineral deposits both by surface and underground
working.
Ore Reserve The economically mineable part of a measured or indicted mineral resource
demonstrated by at least a preliminary feasibility study.
Overseer Miner A competent person possessing a full blasting licence who has had adequate
training and experience in supervising all mine tasks including lashing,
drilling, construction and production; and is given the responsibility over a
mine section or certain tasks in the mine.
Powder Factor The tons of rock affected per kilogram of explosives used.
Primed Cartridge A cartridge of explosives to which a detonator has been attached as a means
of firing, and intended to be placed in the bore hole or other explosive
chamber for the purpose of exploding the remainder of the charge.
Primary Blast The blasting operation covering all sections of the mine which takes place at
the end of the main operational shift.
Rail Track Rail track is the structure consisting of the rails, fasteners, railroad ties
(sleepers) and ballast (or slab track), plus the underlying subgrade. It enables
trains to move by providing a dependable surface for their wheels to roll.
Rail Sleeper A rectangular support for the rails in railroad tracks. Generally laid
perpendicular to the rails, sleepers transfer loads to the track ballast and
subgrade, hold the rails upright and keep them spaced to the correct gauge.
11
Re-entry The procedure of accessing an area or mine working in which blasting
operations have been conducted, where work is abandoned or temporarily
suspended to ascertain conditions and make safe.
Re-entry Period Time that is allowed to elapse before personnel are allowed to return to the
mine workings.
Round A set of holes drilled and charged with explosives in any phase of explosives
work, which are fired instantaneously or with delay detonators.
Safety Fuse A slow burning commercially used blasting fuse having a controlled burn
rate, usually consisting of a core of powder overspun with yarns and tapes,
and which ma y be treated with a waterproofing compound, and intended to
convey fire to the blasting caps or explosive mass while minimizing the
danger to the person lighting it.
Secondary Blasting Using explosives to break up larger rock masses resulting from the primary
blasts.
Socket Any shot hole or part of any shot hole, known not to be a misfired hole,
which remains after having been charged with explosives and blasted or
which, for any other reason, may be suspected of having contained
explosives at any time and includes any shot hole, or part of any shot hole,
from which all explosives have been extracted
Standard Raise An underground mine tunnel excavation at an inclination greater than 35o to
the horizontal and whose travelling height does not extend beyond 30m
Sublevel A horizontal mine tunnel developed between two main levels connecting the
mine workings which is accessed through raises and ramps.
Survey Grade A survey marker showing the desired elevation an excavation should
proceed at.
Survey Line A survey marker showing the desired direction an excavation proceed to.
Travelling Way Safe access and egress to and from the workplace and all work-related areas.
12
Travelling Way A structure for persons to land on which enables them to safely rest as they
Platform climb up or down the travelling way.
Ventilation The replacement of stale or noxious air with fresh air or the system used to
circulate air replacing stale air with fresh air.
Waiting Place A special bay in an underground mine provided for use by mineworkers
before they are deployed to their workplaces.
Waterblast A device which is designed to produce a jet of water vapour when connected
to high pressure water and compressed air.
13
Figure 4 How mine lease area along How shear zone (Source: How mine in-house document)
14
Figure 5 Regional geology (Source: How mine in-house document).
ESGODINI GRANITES
MATOPO GRANITES
All of the formations in the map above are constitutes in the Bulawayan Supergroup and are subdivided
into Upper Greenstones and Lower Greenstones. This forms the following stratigraphic column:
Table 1 Stratigraphy of the Bulawayo greenstone belt (Garson, 1991)
Unconformity
Unconformity
15
UPPER GREENSTONES SAUERDALE Ultramafic suite
Unconformity
UPPER GREENSTONES:
Tornbridge formation: consists of extrusive metabasalts, basal metakomatiites and associated with sills
and dykes of metadolerite and metagabbro, some of which are intrusive into the underlying Umzingwane
formation. The contacts between the two formations are not well exposed and those recognizable are
strongly tectonized making it difficult to establish the stratigraphical relationships.
Umzingwane formation: consists of the ferruginous cherts (BIF), rhyodacites clastic metasediments,
fine-coarse grained tuffaceous rocks, banded shale , siltstones, andesitic lavas and some dolerite dykes in
places noted underground but are barren (not mineralised). .
Avalon formation: comprises of a 3-km wide largely rhyodacitic dome and is also with associated
andesitic and rhyodacitic breccias. This formation is made up of Calc-alkaline metavolcanics.
Kensington formation: mainly comprises of meta-andesitic lavas and flow-breccias.
Sauerdale formation: consists of a suite of metamorphosed ultramfiic and mafic rocks ranging in
composition from peridotitic or pyroxenite or komatite to magnesia-rich basalt and theoleitic basalt.
Umganin formation: mainly comprises of metabasalts and intercalated high-magnesia metabasalts with
both rock types commonly pillowed.
Westarce formation: Clastic and calcareous metasediments with minor BIFs.
LOWER GREENSTONES:
Lonsdale: consist of calc-alkaline metavolcanics.
Vreigeviht Formation- mainly comprises of stripped amphibolitic gneisses consisting of highly deformed
volcanic pyroclastic and subordinate mixed pyroclastic-epiclastic rocks with altered mafic volcanic rocks.
16
How mine is located in the Umzingwane formation of the Bulawayo greenstone belt. The mapping of the
local area established the following sequence from southwest to northeast: Talc chlorite schist, laminated
black shale, silicate facies BIF, tuffaceous units and siltstone (see Fig 6).
Several ore zones occur as an en echelon array of parallel and steeply plunging linear shoots and these
shoots are confined within an extensional right-stepping, northerly trending strike-slip duplex.
Faulting has followed preferred lithological contacts. Mineralization is dominated by a pyrite-gold
association and occurs as disseminations. Alteration is widespread and dominated by carbonation,
silicification, and propylitic alteration. In the north area of the mine, ore zones are developed within the
fault-bounded tuff unit (e.g., the north 180 ore zone) and in the south the ore zones are parallel to the
Hanging-wall fault-shear zone and transgress major lithologic contacts. The occurrence of felsic porphyry
intrusions and mafic dykes in the quarries is also expressed in exposures underground. The disposition of
the quarries show that the ore channel locally transgresses lithological boundaries and is therefore not
strictly strata-bound. There are no big mines in the immediate environs of How Mine though several
17
small, narrow reef old workings do exist especially within the mining lease area. All the old workings are
currently inactive but are targets for off-mine exploration.
18
and the 400N on strike. During evaluation drilling other two small orebodies were discovered namely the
320N and 330N located also between the 300N and 400N but found on the far western side.
Information at hand shows that 400N and 350N have the same geological characteristics as the other
known orebodies. However, current evaluation work focuses on establishing the orebodies down dip
extension below 26 level. This discovery was thought to serve as a strong confirmation of the extensional
duplex theory. The mineralised zones at How Mine have sharp grade boundaries that in most cases can be
defined with confidence.
However current mapping at 28 level 10m carried out by R. Muzulu (Senior Geologist), Mr G. Sibanda
(Section Geologist) and two students on attachment, established presence of some positive flower
structures (faults) which are evidence of transpression which occur at strike slip fault zones making it
more complicated to establish a proper orebody model.
19
5 INDUCTION
This was covered prior to arrival at the mine; it involves general introductions to all departments so as to
get a brief know how of what How mine is mining, processes involved in each and every department, the
main roles of these departments and the standards that guides all activities being done. The following
departments were covered during induction:
20
Community Services responsible for housing and welfare services
LDV Country Club a social and recreational facility for senior staff.
21
b. Grinding- Ore is fed into the mill together with steel balls and water, the mill is run at 80% the critical
speed.
c. Thickening- Cyclone overflow is de-watered in the thickeners and the underflow from the thickener is
pumped to the CIP plant. In the first CIP tank, cyanide and oxygen are added into the leach pulp whilst
in the last tank activated carbon is added and allowed to flow with the pulp.
d. Elution- The loaded carbon is then transferred to the elution column where the carbon is stripped of
gold. The gold is brought to solution and elctrowinned.
e. Smelting- Gold from the cathodes from electro winning is collected and smelting is done in a furnace.
Stages of ore processing flow diagram
Figure 8 Processing of ore to gold bullion (Sourced from How mine in-house document
22
6 ATTACHMENT CONTENT
Heat Dilution
23
Cage overloading Malfunction of machinery
Pipe leakages
6.2 Lashing
It is the transfer of ore\waste from a blasted end to a tipping point.
Working areas
Lashing procedure
24
Purpose of lashing
Observations
development lashing
- Drive had dimensions of; 1.8m height, and a width of 1.5m
25
- Hole depth was 1.5m trying to achieve an advance in meterage of 1.3m
- Volume in cubic metres of ore per round was approximately1.8 1.5 1.5 = 4.053
- The specific gravity of the rock at How Mine is 2.8 tonnes/m3
- Volume in tonnage is then 1.8 1.5 1.5 2.8 = 11.34
- Wheelbarrows used have a capacity of (60litres) 0.06m3 , in tonnage, it then become
0.06 2.8 = 0.168
11.34
- Expected number of wheelbarrow loads per blasted round = 67.5,
0.168
approximately 68.
- No round produced exactly this amount of wheelbarrows, more than 68 were produced.
- This was because the wheelbarrows where not filled up to the 0.168 ton capacity and also
muck will be more than 11.34tonnes mostly.
- Therefore per round approximately a range of 80-100 wheelbarrows were produced.
- Student worked at 2 work places (2820 drive south and 2810 drive north)
- Distance from muck to tipping point at 2820 drive south was about 50-60m
2 manpower pushed wheelbarrows relaying to the tipping point.
A range of 1minute 30 seconds to 2 minutes was the cycle time to and from
tipping point with reference to loading point
A range of 30 to 90 seconds was taken to load one wheelbarrow depending on
availability of delays and also the effort by lashers.
Wheelbarrow trackers always found a wheelbarrow already full and ready to be
hauled hence the total cycle time only includes the cycle time of hauling and not
that of loading.
Manpower comprised of 4 people; gangleader, student and other 2 people
Distribution of manpower, 1 lasher and 2 on hauling and dumping
Equipment; 3 or 4 wheelbarrows and 1 or 2 shovels.
- Distance from muck to tipping point at 2810 drive north was about 70-80m
Manpower comprised of 5 people including gang leader and student. (2 lashers
and 2 wheelbarrow trackers)
Equipment; 2 shovels and 3 wheelbarrows
A range of 120 to 180 seconds cycle time was taken to and fro tipping point with
reference to loading point.
A maximum of 40 seconds was taken to load one wheelbarrow.
stope lashing
- This is the removal of broken rock from blasted ends (slipped ends) in stoping operations.
- The lashing crew from Stoping Section 2 are responsible for these duties and since their
work is not intensive they are very few compared to lashers from other sections.
26
- The reason there is less mucking in stoping operations is because after blasting most of
the broken rock falls directly into an ore pass or previously mined open stopes thus less
ore remains to be removed.
- This is done to clean a bench preparing for longhole drilling.
- Technical information about stope lashing is hard to get because some of muck blasted
fall directly into stope.
- Stope lashing is the most dangerous of all lashing operations due to the presence of open
stopes.
- Safe procedures to be followed.
- These include installation of a lifeline and a barricade.
- Therefore every time upon arrival at the working place after blasting a barricade and a
lifeline must be constructed or extended to make the area safe to work.
27
Jackhammers use a lubricant called RD compound oil which is constantly supplied to the
machine throughout its operation. The oil is supplied by means of a line lubricator which
is filled with the lubricant at the commencement of the drilling shift.
Tapper steel sizes used are 0.8m, 1m, 1.3m, 1.8m and 2.3m together with 38mm bits
(starters/collaring) and 36mm (finishers/deepening)
Spares, tools and equipment
ITEM SIZE QUANTITY
Hammer 2kg 1
jackhammer Standard 1
28
Upon arrival at the end, a pre task risk assessment is done whereby hazards associated
with work to be done are identified and controls are provided.
Water down from 8m away from the face, barring down advancing towards the face.
Expose lifters for a distance of 2m to make sure that there are no misfires from lifters of
the previous round.
Water down the face, searching and pumping out all misfired holes using an aluminum 2
way blow pipe.
All misfires are placed in a stout canvas bag and taken to 26L production for destruction
(secondary blasting)
Plug all sockets using wooden plugs.
Marking the round
Suspend 2 bobs on 2 survey pegs (Front Line and Back Line pegs) and project the centre
line on the roof and on the face.
Mark all the holes using a red paint or chalk and 15cm away from sockets. Holes are
marked according to the standard drilling patterns and dimensions as given on the
layouts, with sub-drives normally being 2m wide X 2m high and haulages 3m wide X 3m
high.
Mark direction lines on either sides of the centre line parallel to the centre line.
29
Figure 9 marking of a haulage face
3m
3m
30
cm
m
50cm
During drilling
30
Do not dry collar a hole. This leads to overheating and premature failure of the drill steel
and is also a health hazard since a lot of dust is produced.
Do not hammer jammed drill steels, but rather extracted using a key spanner.
Drill on marked positions and maintaining a distance of 15cm from sockets.
Avoid deviation as this lead to poor fragmentation of the blasted muck.
Use a rubber gasket when collaring to prevent grit from damaging ones eyes.
In a haulage, use a platform when drilling backholes to maintain a height of 3m.
Drilling sequence; Collaring(38mm bit, 0.8m tapered steel) deepening (finalized with a
36mm button bit and longer tapered steel)
Raise drilling
Before drilling can commence in raises, they are rigged. This is done by the PTV crew.
Raise rigging
- 16 L pins are used for both the safety and drilling platforms
- Chain ladders are secured with 4 pins
- Round poles and flat timber is used for raise rigging.
Making safe
Upon reaching the end to be drilled together with a competent person, connect the hoses
to the water valve outlet.
Water down the whole area around the brow of the raise and bar down thoroughly all bad
hangings.
With a grizzley hook standing clear off the raise, shake the ladders to dislodge any rock
which may have been caught up and to make sure that the ladders are still secure.
With a 12.5mm water hose and short pinch bar, climb up the raise and thoroughly water
down the face and bar down all bad hangings.
After extracting misfires, circle the sockets with a red paint. Socket plugs are not used in
raises since they can be hazards.
Face marking
Suspend bobs on 2 survey pegs and project a centre line of the raise on the face and roof.
The direction lines are marked on the side walls of the raise using a clinometer rule as
given in the survey layout.
31
5 hole burn cut is used in raise drilling
Drilling procedure is the same as the one in flat end drilling except that precaution is
taken when removing drill steels as these can accidentally fall, injuring workers.
Charging
Explosives used
29 X 270mm Megamite
- Nominal density - 1.14 g/cm3
- VOD 3500 to 5000 m/s depending on rock characteristics
- Gap sensitivity contact required for propagation
- Shelf life 12 month from date of manufacture
- Packaging 25 kg box, 125 cartridges per box
- Cartridge weight 200g
Shocktubes
Electric detonators
Igniter cord
Procedure
Test the water blast if its functioning and that it is properly positioned i.e. not more than
15m from the face.
Remove all equipment and place it in respective racks where it is safe from flyrock.
Dismiss all men not partaking in charging.
Post a no entry sign at a suitable distance.
Priming
This is a process of inserting a detonator inside a blasting cartridge.
Megamite and shocktubes are used.
Prepare one primer and insert in the blast hole at a time. Piling up of primers must not be
done because it can be a disaster in case of a premature detonation.
Charging and timing
Only a non-ferrous charging stick should be used to press the charges home and at How
mine, wooden charging sticks are used.
32
Insert a primer first followed by 3 cartridges covering 1.08m of the hole, leaving 0.42m
for stemming. (subdrives)
For haulage put 4 cartridges after primer thereby covering 1,5m leaving 0.5m for
stemming
Gently press home and compact the cartridges for a favorable coupling ratio.
Old explosives cardboard boxes are used for stemming.
Timing is done using shocktubes
Below is a time motion study showing time taken to drill a 1.5m hole, compressed air at
700Kpa
HOLE NUMBER 1M 0.5M
1 3min 12s 1min 55s
Using the average time taken to drill one 1.5m hole it shows that about (4mins 57sec x 23 holes)
114minutes whuch approximately 2 hrs for a subdrive face with 23 holes, if no delays occur
6.4 Explosives
Types of explosives
33
Fractures Accessories
1. Emex
This is a catridged emulsion explosive.
function
Emex is a packaged emulsion explosive. The emulsion is robust and sensitisation with
microspheres ensures excellent shelf-life and reliability of detonation. It is a firm, water resistant
cartridge which has a formable consistency for tamping. The high velocity of detonation (VOD)
and relatively lower gas volumes (compared to ANFO and watergel) ensure fi ner fragmentation
in tough ground whilst limiting over-break.
Description
The Emex range consists of four product grades with a RBS (Relative Bulk Strength) relative to
standard ANFO (Ammonium Nitrate Fuel Oil) of 129% to 179%. Cartridges are available in
specific diameters from 25mm to 50mm and specific lengths from 200mm to 550mm. The
cartridges are packed into a 25kg plastic inner bag inside a boldly printed carton, identifying the
product as Emex explosives.
Advantages
34
safety All products are brightly coloured for easy identification in storage and in the field.
All explosivesare classified as dangerous goods and can cause personal injury if not
handled correctly
reliability Emex is manufactured to order with excellent water resistance, flexibility and
performance reliability with every initiation
quality Manufacturing of this product conforms to the ISO9002 quality standard. All
materials are tested and approved before use. Tests are conducted to confirm that
the density, fuel content, moisture content and aluminium content conform to
specifications.
custom - Each carton is marked with a sticker that identifies the product according to grade,
packaging cartridge dimension, date of manufacture, production team, batch number and
carton number
-The information enables Sasol Nitro to refer to quality records in order to
investigate customer complaints.
The information allows full traceability of manufacturing details under the
ISO9002quality system
Product information
At The Company the product of emex used is E70 though there are other products; E30, E50 and
E90
Emex E70 is a high energy product designed for typical hard rock development, tunneling or
very tough stopping conditions
Emex E70
35
Water resistance Excellent
2. Explogel
This is a catridgedwatergel explosive
function
Explogel V is a revolutionary cartridgedwatergel explosive range that combines proven
explosive technology with the proprietary Expan Ammonium Nitrate technology. The inclusion
of Expan ensures a product with enhanced sensitivity and energy partitioning for improved
advance and generally coarser fragmentation.
Description
The Explogel range consists of six product grades; covering energies from 82% to 239% the
energy of standard ANFO (Ammonium Nitrate Fuel Oil). The products are sold in individual
cartridges , wrapped in a plastic sleeve which is crimped at both ends with an aluminium clip.
The cartridges are then packed into a plastic bag which, in turn, is packed into a boldly printed
carton, identifying the product as a watergel explosive
Advantages
Safety All products are brightly coloured for easy identification in storage and in the field.
All explosives are classified as dangerous goods and can cause personal injury if
not handled correctly.
Explogel cartridges are not impact and friction sensitive
36
Reliability Explogel is manufactured to order with very good water resistance, flexibility and
reliability withevery initiation.
Quality Manufacturing of this product conforms to the ISO9002 quality standard. Tests are
conducted on each batch to confirm that the density and PH levels conform to
specifications.
Product information
At How mine we make use of explogel v10 though there are other explogel products that is;
explosmooth, explogel v4,explogel v6, explogel v8, and explogel v12. They come in increasing
energy. V12 has an exceptional high energy compared to all others.
Explogel v10 is a high energy product particularly suited to deeper hole applications, such as
shaft sinking, surface and quarry mining, but we use it at longhole. The product is ideal when
used in cold conditions where other packaged products may become problematic.v6 or 8 is the
suitable for our stoping operations.
Explogel V10
37
Recommended storage months in magazines
(dry, well ventilated)
Magazine controller
How mine magazine controller is appointed as the person in charge of the How mine Explosive
Magazine as per requirement of clauses 4.4.1 of OHSAS 18001 standard, 4.4.1 of ISO
14001:2004 standard, 6.2.1 of ISO 9001:2008 and the statutory instrument 72 of 1989.
Temperatures in magazine
- According to the explosive regs, SI 72 of 1989 section 91. the temperature is supposed to
be regulated and maintained within range of 2 35oC
- (a) Provided with a reliable thermometer showing maximum and minimum temperatures;
and
- (b) Shielded from the suns rays or provided with other means so as to ensure that the
temperature inside the magazine does not at any time exceed 35C
EXPLOSIVE ISSUING
38
- Below shows a table showing date, type of explosives and workplace where they were
issued to.
- DV stands for development
- ST stands for stopping
- Prd stands for production
- IED instantaneous electric detonator
- Per box/case/pack/rim below are the amount of units/sticks/metres found;
1. 38x550 = 34sticks
2. 29x270 = 123
3. SB cord = 2rims x 250m
4. 15m Ezdets = 100units
5. 0.9m fuse = 600units
6. 2.4m shock tubes = 400units
7. 3m shock tubes = 275units
8. 3.6m shock tubes = 275units
9. IED = 1000
ST 28207N 60 15 1
ST 27/7N 84 24 1
ST 2820350 60 12 1
ST 2810350 90 18 1
DV 27/400N 105 21 1
Cub
DV 27/400 105 21 1
DV 28 180 35 1
haulage
DV 27107N 84 21 1
39
Drive south
DV2710400 84 21 1
DV2820400 105 21 1
DV2810400 105 21 1
DV2820320 84 21 1
DV2810320 72 18 1
track laying
pipe fitting and repairing
installation of water blasts at development ends
installation of force and exhaust fans
construction of ventilation doors
40
placing of barricades and lifelines
Spanners(sizes 24 and 48), size 48 ranch spanner, hacksaw, chisels, 4 pound hammer, bends, T-
pieces, clamps, blockers, nipples, spots, couplings, valves, reducers, gaskets, bolts and nuts,
Frenchs
Insallation of a waterblast,
The top of both tracks shall be 1m below the grade line and shall be horizontal. The spirit
level should be used to check this. At bends the outer rail should be 12mm above the
elevation of the inner rail
The top of the drain shall be at the same height as the bottom of the slippers in order to
allow the tracks to drain freely.
Track layout
0,61
Rail
Cotch screw mmm
45lb
Wooden
slipper
Drain apex
41
Salvaging of old slippers and cotch screws in old working areas which were to be used at 070
cross cut. Safety should be considered when working in old working areas since gases like
hydrogen sulphide are likely to be present.
Procedure
Lay out the curve on the footwall of the haulage or drive using chalk or paint.
Alternatively, use a curved rail as a guide, or use the line of holes in the sleeper.
Mark the crown of the rail every 0,3m. These will be the positions where the shoe of the
Jim Crow will bear. Do not bend up to the fish plate holes, except for particularly sharp
curves that will not be used for normal tramming.
Place the Jim Crow, with the claws gripping over the crown of the rail. Screw the shoe
hand down tightly.
Raise the arch of the Jim Crow to a horizontal position, and hold it in place by sliding a
pinch bar over the rail and under the arch.
Place a raise pin or piece of round bar into the hole in the screw head, and turn until light
strain is produced in the rail. The same amount of strain should be used for each bending
operation. Actual bending is measured by counting the number of turns of the screw
beyond this point.
Give the screw one complete turn. Release the screw and repeat at every chalk mark.
After completing a length of bend, check the track. Repeat the above steps if further
bending is required.
Supply of compressed air should be in such a manner that it is pure air without water hence water
traps should be incorporated in the main compressed air line. According to SI 72 of 1989 section
62 the air valves in case of raises should be placed at the foot of the raise.
Mending of leaks
Barricading
Safety barricades are put at all open stopes, ore passes, pits or anywhere else where there is a risk
of someone falling in
42
Barricades are removed prior to blasting operations and then re-constructed after are-entry
procedure
6.6 Production
This includes activities such as; Air loader lashing, Loco Tramming, Grizzly Operations, Ore
handling and hoisting and Secondary Blasting.
Tramming is the transportation of ore through a track work system to the designated tipping
point or using a LHD or conveyor in a trackless system. The main production levels are 26 and
28. Ore is trammed in haulages from the draw points where an air loader-locomotive
combination is used and then tipped at grizzley by the locomotives. Ore is mined from above
levels; it can be either from open Stope sublevels or from coning levels. Ore that is drilled and
blasted goes through ore-passes and is collected in the cones and goes through the ore passes to
the draw points.
Type of machinery used for tramming from draw points to the grizzleys
In the case of large boulders choking the cones or at the draw points, secondary blasting is
carried out to further fragment these large boulders
Secondary blasting
43
During secondary blasting, first an alarm is rang thrice then after initiating the ignitor
cords, verbal warnings should be given by guards who also barricade and prevent persons
from coming to the area to be blasted
The re-entry period is 15minutes, so after 15 minutes the compressed air pipe is closed as
it would have been opened soon after blasting
28 L there is a crusher
6.7 SHAFTS
Uses of shafts
- In use they had 3 shafts that were the north, main and 16N7
NORTH SHAFT
44
- The skip is for hoisting ore and waste from level 25 and transportation of heavy materials
MAIN SHAFT
- Is used to transport people and waste material, heavy material and explosives from
surface to 16L
16N7 SHAFT
- Is the one which takes from 16L all which proceeds to 28L which comes via main shaft
45
Shaft examination and maintenance
Shaft equipping
Log in the hoist drivers log book indicating time of commencement of exam and official
in charge before the exam starts
After logging in the book, communicate verbally with the hoist driver in regards to
carrying out the exam
Shaft examination of the main shaft was carried out on Tuesdays and Thursdays and that
of the north shaft was carried out everyday
6-6 bells are rang to indicate to the driver that shaft exam was to begin making use of the
key bell
Driver replies 6-6 bells acknowledging that the exam may begin
The cage was lowered using 2-2 bells so that a safety hood can be fastened on top of the
cage
1 short bell signals the driver to stop the conveyance
A platform was put once the cage was low enough such that the shaft crew can disembark
on top to fasten the hood , then the platform was removed
Safety chains must be used throughout this procedure
After the hood was fastened , the cage was raised slowly using 3-3 bells and stopped
using one short bell
The safety chains of the men are tied on the humble hook of the conveyance along with
the rest of the equipment they need which will be placed on top of the conveyance such
as cutting torch, hoses and the two gas cylinders, tool box containing spanners, hammers,
chisels, bolts and nuts, washers, tape measures, pinch bars, T-pieces and gaskets
After the men are satisfactory secured they then proceed with the examination
Movement of the conveyance was through the 2-2 and 3-3 bells
46
As the conveyance was descending slowly men will be knocking the runners with a
hammer to check for their rigidity and alignment as well as checking all the buntons to
make sure they are secure , all nuts that are loose should be tied and all bad hangings
should be brought down
All pipe leakages are sealed
The shaft was searched throughout its length and upon reaching the shaft bottom, it
returns to the surface where the hood was removed
Upon removal of the hood ,6-6-6 bells are rang to release the conveyance and to mark the
completion of the shaft examination
The official in charge then signs out in the hoist drivers log book
Crushing
Milling
Carbon In Pulp
Elution and Electro winning
Smelting
Tailings Disposal
47
6.8.1 General Overview of the Reduction Process
Jaw crusher
Crushing Gyratory crusher
Barmac crusher
Ball mills
Milling Hydrocyclones
Knelson Concentrators
Carbon
Carbon In Cyanide
Pulp Hydrogen Peroxide
Oxygen
6.8.2 Crushing
Crushing is the first mechanical stage in the process of comminution in which the main objective
is the liberation of the valuable minerals from the gangue.It is generally a dry operation and is
performed in three stages which are
Vibrating screens are placed in line with the crushers to remove undersize material, or scalp the
feed, and thereby increase the capacity of the crushing plant. Undersize material tends to pack
the voids between the large particles in the crushing chamber, and can choke the crusher, causing
damage, because the packed mass of rock is unable to swell in volume as it is broken.
Crushing may be in open or closed circuit depending on product size. In open-circuit crushing,
undersize material from the screen is combined with the crusher product and is then routed to the
next operation.Open circuit crushing is used in intermediate crushing stages. Since the tertiary
crusher produces ball-mill feed, closed-circuit crushing is employed in which the undersize from
48
the screen is the finished product. The crusher product is returned to the screen so that any over-
size material will be re-circulated.
Conveyor Belt 1
Fitted with a Tramp metal detector for detection of Ore size -150mm
metal objects on the conveyor
Vibrator 1
Screen size : 2.5m * 1.25m Undersize : - 50 mm
Aperture Size : 50 mm Oversize : + 50mm
Conveyor Belt 2
Fitted with magnet to trap metal objects that could
Ore size : -50mm
have escaped the tramp metal detector
Vibrating screen 2
Size : 2m * 1m Undersize : -25mm
Aperture size : 25mm Oversize : + 25mm
49
Gyratory Crusher
Size : 36 Inch Diameter
Ore Size Reduction : 50mm to - 25mm
Gap : 25mm
Conveyor Belt 3
Ore Size : -25mm
Conveyor Belt 4
Ore Size : -25mm
Conveyor Belt 6
Ore size : -25mm
Main Vibrator 3
Barmac Crusher Conveyor Belt 5
Size : 5.2 * 2.15 m
Ore Size : - 15mm Ore Size : +20mm
Poly Screens
Oversize : + 20mm
Undersize : -20mm
50
6.8.3 Milling
Process Flow
Description
Ore from the fine ore bin is fed onto Conveyor belt 1 through volumetric chutes and is
discharged onto conveyor 2 (incline conveyor). Conveyor 2 feeds Conveyor 3 (jump conveyor)
which in turn feeds conveyor 4. Ore on Conveyor 4 goes into the banana chute together with mill
feed water and oversize from the vibratory screen. 100mm steel balls are manually fed onto
conveyor 2 and are conveyed together with the ore until they go into the mill.steel ball addition is
done on morning shift and 2 tonnes are added daily.
Primary mill discharge is diluted and pumped to the vibratory screen. Oversize from the screen
goes back into the mill while underflow becomes Knelson Concentrator feed. Knelson
51
concentrator concentrates are deposited into a concentrates box and are later further processed in
the Acacia Plant. Knelson Concentrator tailings form Primary Mill Cyclone Feed. The Primary
mill cyclone overflow is discharged in the Regrind 1 and 2 mill discharge sumps while the
underflow becomes regrind 1, 2 and 3 feed.
Process Flow
Description
Primary mill cyclone underflow is split into three forming feed for the three regrind mills. A
tonne of 60mm steel balls are added to each regrind mill a day. Regrind mill 1 and 2 have similar
circuits where the mill discharge goes to the Knelson concentrator and tailings from there
become the cyclone feed. Underflow from each respective cyclone is fed back into the mill and
the overflow goes to the Delko Screen for trash removal. The underflow becomes the final
product that goes to downstream processes.
Major Equipment
- ball mills
52
- knelson concentrators
- acacia plant
- vibrating screens
- linear screen
- cyclones
- centrifugal pumps
Ball Mills
mill diagram
The ball mill is lined to protect the shell from the grinding media, At How Mine, the feed size of
the ball mills is generally fines, therefore interaction of the feed itself does not result in
comminution. Steel balls are fed into the ball mill as grinding media and comminution occurs
due to the interaction between the charge and the steel balls.
53
Comminution is mainly by abrasion, as grinding media is dragged against the shell and impact as
grinding media falls to the toe of the mill.
Feed slurry enters the unit through a stationary feed tube. It flows down into the concentrating
cone, where centrifugal force drives it outward to the cone wall. As the solids reach the wall,
they fill each ring starting from the bottom. Once every ring reaches capacity, a concentrating
bed is established. Water injected from the water cavity fluidizes this bed. Optimum fluidization
occurs when inward flow of water through the bed balances with outward forces of solids. This
enables fine grained target heavy mineral particles to sink into the bed through interstitial
trickling. Provided that the flow of fluidization water is maintained, the selection and
concentration of high specific gravity particles and rejection of low specific gravity particles will
continue.
When the concentrating cycle ends, the flush cycle is initiated and the rotor power is shut off.
When the rotor comes to a complete stop, the fluidization water flow valve is opened for several
seconds. Opening the valve while the rotor is stationary allows water flow into each ring to wash
out the concentrates. Concentrates flush out through the bottom of the concentrating cone and
into the concentrate launder. R
54
ACACIA Plant layout
55
The gold bearing solution, which is now all located in the solution tank, is transferred to
direct electrowinning feed tank
7. Discharge of the Leach Residue
The leached residue is fluidized and then discharged to the milling section.
8. Electrowinning
The pregnant solution is pumped to the electrowinning cell feed tank where it is sampled.
The solution in the electrowinning cell feed tank is pumped to the EW cell at controlled
flow rate. Solution is circulated on the cell for a specific period of time determined by the
cell tail assay.
9. Disposal of Electrowinning Tail
The EW tail is transferred in total to the CIL circuit
6.8.6 Hydro-cyclone
Hydro-cyclones are used for different purposes which include de-chipping, de-watering and
classification, at How Mine however, they are mainly used for classification.
hydro-cyclone
Feed is introduced under pressure through the tangential inlet generating a vortex with a low
pressure zone along the vertical axis. The particles in the feed are subjected to two opposing
forces, an outward centrifugal force and inward dragging force. The centrifugal force accelerates
the settling rate of the particles thereby separating them according to size and density. Heavier
and fast settling particles move to the wall where velocity is lowest and migrate to the apex or
spigot as underflow. The drag force pushes slower settling particles to the zone of low pressure
along the vertical axis where they are forced upwards through the vortex finder and report to the
overflow.
56
The internal of the hydro-cyclone is lined in order to protect the shell and to increase its life
span. Spigots wear out due to the abrasion forces as the coarse material exits. As a result they
should be measured regularly and replaced when worn out.
The How mine milling section has 4 cyclones, one for each mill and their main function is
classification.
6.8.7 Screens
Screening is the mechanical separation of particles on the basis of size by passing the particles of
various shape and sizes through holes or slots on the screen surface.
The milling section has two types of screens, the vibrating screen and the linear screen. The
Delko Linear screen is a non-vibrating linear screen.
linear screen
57
6.8.8 Carbon in pulp
After the final communition stage (milling) the pulp is normally dilute and thickening is
performed to increase pulp density to about 50% solids by mass. This reduces the size of the
leaching plant that would be required as-well as reduces the amount of leaching reagents
required. The leaching of gold can be conveniently be represented by the Elsener equation,
With optimum Cyanide concentration , clean gold particles dissolve forming a gold aurocyanide
complex in the aqueous phase which is readily adsorbed onto the activated carbon.In addition,
oxygen is a crucial reagent for leaching. Pulp may contain organic and inorganic components
that consume oxygen, reducing the overall level of dissolved oxygen in the pulp and thus
reducing the leach kinetics.
Pulp densities which are too high, as-well as those which are to low can affect gold leaching
performance. Densities should be maintained at 48 50% solids.
i. the concentration of free ions such as calcium, sodium and potassium, oxygen
concentration and pH
ii. mineralogy of the material,
iii. particle size of the feed and finely divided material is preferred.
58
18 : 180 cubic metres - 18
Leach Tank 1 Carbon Tank 2 Leach Tank 3 Leach Tank 4 Leach Tank 5
Addition of Production Tank Positioned Compressed Compressed
oxygen Pump agitation Sieve Bend air agitation air agitation
Compressed Round blowers Compressed
air agitation around carbon air agitation
retention screen
59
Tank 11
Tank 18
Tank 2
2 tonnes
barren carbon Production
Tank 14 Tank 10 Tank 7 tank
from elution
Loaded carbon
2 hours
receiving time
6.8.9 Elution
The final loaded carbon is removed by pumping out of the production tank 2, via a sieve bend
on tank 3 and trommel screen on tank 11, and transferred to the elution section where it pours
into the receiving hopper up to a marked 2 tonne level for 2 hours. It is soaked in
Hydrochloric Acid before undergoing elution or deposition of gold cyanide at high
temperatures and pH. The elution of loaded carbon is obtained by using a pressure elution of
60
2 bars at 1200C in 6-8 hours. The rich eluate solution that emerges from the elution process is
passed through electro winning cells where gold and other metals are precipitated onto the
cathodes.
6.8.9.1 Process flow of carbon and elute solution at the Elution section
61
2.8m3 of the 3 % acid solution is pumped from the bottom of the acid wash tank through
the carbon bed and over flows into a recovery sump. Carbon is soaked in acid for 1 hour
to remove in-organic flocculants.
Spent acid is drained from the bottom of the acid wash tank and caustic soda solution is
pumped from the bottom of the acid wash tank to neutralize residual acid remaining after
the acid wash cycle.
Treated 2 tonnes of carbon is transferred to the elution column by pumping using water.
The elution column loaded with carbon is pressured using cold water 2 bars and pre
heating using boiler steam is done to elevate temperatures to 120C.
2.8 m3 of Caustic cyanide solution is pumped from the bottom of the Elution column
through the bed of carbon. The overflow from the elution column as a result of pumping
the caustic cyanide solution is transferred to high grade tank 1A.
After transferring all the caustic cyanide solution into the elution column, carbon is
soaked for one and half hours at a temperature of 120C and a pressure of 2 bars.
Low grade strength recycled water (from HGC 3B) is pumped from the bottom of the
elution column to strip high grade mineral value from carbon. Carbon is fluidized and
suspended in solution by maintaining a solution flow rate of 2 bed volumes and the
resultant overflow is transferred into high grade tanks HGC1A and HGC2B.
High grade solution is immediately pumped to the electro-winning circuit when the
stripping process commences. After filling the two high grade tanks, a third tank is also
filled in preparation for the next elution (low grade strength solution). 30 minutes before
end of the elution cycle, the steam is switched off and a cold cycle strip is done (that is,
striping using cold water for 30 minutes).
The elution and electro wining process is carried out ensuring critical operating
parameters are within range, that is, a working pressure of 2 bars, working temperatures
of 1200 C and flow rates of 2 bed volumes for the elution process and flow rates of
20m3/h, a working voltage in the range of 4-6 V and current in the range of 350-500 A for
electro winning process.
i. Chemical spills
ii. Pressure vessels-explosions
iii. Ground flooding
iv. Air pollution
v. Suffocation, Respiratory effects and Fatalities due to (caustic-cyanide fumes)
vi. Steam &Heat stress (boiler steam)
vii. Electrocution
62
pumps per bank and 1 spare bank A used in case of emergencies, however currently bank
A is not functional as some pumps are not available.
The tailings attendant also checks the quality of water used for running the high pressure
pump in terms of clarity and open the water supply valves to the high pressure pump.
The tailings attendant starts the high pressure pump and the operating pressure for the
Curo pump should be in the range of 1500-1700 kpa before starting the banks.
After the required pressure for the high pump is achieved, the tailings attendant starts up
the banks. On starting the bank, the tailings attendant start by starting the first pump
(pump number 1) which is connected to the thickener discharge pipe followed by the
preceding pump up-to the last which is the fourth pump. The fourth pump is connected to
the tailings dam delivery line.
A plug is then inserted on the suction of the pumps which is before pump number 1 (drain
plug) and feed valve (thickener discharge valve) is opened to allow flow of pulp into the
pumps.
The tailings attendants hourly checks and records the amperage for the running banks and
Curo pump pressure. The operating amperages for the running bank(s) pumps should be
in the range of 30-35 Amps. If one the pumps operating amperage falls below the
standard operating amperage then the bank is immediately stopped and the pump is
inspected. If all the pumps operating amperage falls below the standard operating
amperage then the bank is immediately stopped and the delivery line to tailings dam is
inspected. A stand bybank is left running and if the running bank is not coping up with
the pulp inflow resulting in the thickener filling up ,the plant is immediately stopped to
prevent spilling of pulp from the thickener. Corrective action is taken to correct the
anomaly.
When shutting down the tailings plant, the tailings attendant stops the first pump and all
the pumps would stop immediately as they are interlocked. Pulp would back flow back
into the thickener and the pumps would be stationery after all the pulp in the delivery line
has been cleared through back flow. The attendant would then close the feed valve and
removes the drain plug.
Finally the high pressure pump is stopped and all water valves supplying water to the
high pressure pump are closed.
In case of emergence the tailings attendant allows the pulp to back flow into the thickener
before closing the feed valve and removing the drain plug. The CIP supervisor ensures
that the emergency pump near the emergence ponds is operating well and the drainages
feeding the emergence pond are clear or not blocked.
63
with an average percentage solid of 80% and overflow contains average percentage solids
of 20%.
Water from the cyclone overflow is temporarily contained in the pool which is centralised
in the dam and is pumped back to the plant for recycle/re-use. A free board of 9m is
maintained and a slope of 33 on the dam wall is maintained.
Pulp from C-Bank is discharged during paddock construction or bypassed to discharge in
the beach.
Under-drains were installed during initial bench constructions and they contains clear
water which is collected at the seepage pond. Water from the seepage pond is recycled
back to the dam for irrigation and suppression of dust on the dam wall. An automated
pump is used to pump seepage water.
The under-drains flow-rate are measured on a daily basis and the results logged.
The tailings facility has storm water drains around so as to contain and prevent all the
storm water from entering the dam.
Duties of the TSF supervisor include
1. Ensuring that all wall building, repairs of rat holes, erosion and gullies is done.
2. Measuring and logging the progress length on the dam wall
3. Ensuring that the catwalks are stable and are not damaged. Catwalks are constructed by
filling in empty lime bags with sand.
4. Inspection to ensure that the berm is maintained at 7m and the wall slope is maintained at
33. The dam wall is constructed until the vertical height is 9m and next wall has to be
constructed with the same parameters.
5. To inspect and check for any leaks along the delivery line and comments on the status of
the lines at the end of the shift and any deviations are corrected immediately.
Crest marker poles/ Datum poles are installed at the dam wall berms to measure
elevation, total free board and vertical free board. Currently there are 17 crest marker
poles around the dam wall approximately 40m apart, 10 basin marker poles in the beach
and a center marker pole in the pool/pond.
Dam 5 is 39Ha big and managed by the Fraser Alexander company based in South Africa
which has got great expertise in tailings management.
The cycloned dam wall is currently on bench 5. Cyclones A and B are used and
connected to the B-Bank delivery line.
5 under drain pipes were installed and discharge into the seepage pond
64
Phreatic levels are measured by a piezometer/ dip meter from the installed piezo pipes on
a monthly basis and weekly or daily in the rainy season.
Rehabilitation is in progress and it involves planting trees to avoid soil erosion.
1. The 1st stage is packing. This involves construction of boundary mounds of 30cm height,
33 slopes and a crest width of 50cm to form a rectangle of length 50m and width 13.
Butter boards are used to maintain angle of slope.
2. The 2nd stage is tipping. Pulp is discharged into the packed paddock pool from C-Bank
delivery lines. The off take valve with a connected armored hose is opened and the main
line valve is closed. Close monitoring of tipping pulp is observed to avoid packing failure
and pulp spillage.
3. The 3rd stage is decanting. Decant pipes are installed at the beach side crest of the packed
mound strongly secured by burying one end into the packing and leaving the other end to
discharge into the beach. As slime level rises in the packed pool, water is removed/
decanted into the beach and flows to the pond.
4. The last stage involves leaving the slime now level with the packing to dry off whilst
repeating the above stages in construction of the adjoining paddock. High consolidation
pulp is preferred as it dries faster. When the paddock ground has stabilized, the paddock
is raised by packing, tipping, decanting and drying to the next level.
6.9.1 Survey
The survey section is under Technical service department. It is responsible for
Plan preparation.
Layouts.
Directing mining by use of survey pegs, lines and measurements.
Ensure that the plans and layouts produced are being adhered to.
Ensures that accurate underground and surface plans are produced for mining
operations, guidance and control timorously.
Provides technical information in the form of mining layouts and surface plans on a
day to day basis.
65
Ensures that all development and stoping activities of the mine are measured
accurately in order to determine weekly/monthly achievements.
For the purposes of pre-planning and long term planning, the Survey department also
ensures that all development ends and stopes are up to date so that management can
be able to make feasible decisions during planning.
Month end measurements done to monitor and control mining operations so as to give
informed decisions to senior management by physically taking measurements.
The survey section also checks and signs all survey data plans for control and
compliance to mining regulations.
Ventilation team also ensures that there is a continuous supply of fresh air to all the
underground working areas.
Machine familiarization
The student started with the instruments used for basic traversing and taking survey
measurements for directing developments during peg installation.
The equipment includes
Theodolite
Tripod
Plumb bobs
Clinometers
Tape measures
Hammer and chisel
Spads
The following are some of the major equipments used and their functions:
Theodolite T16
This is the most important instrument used for accurate measurements of horizontal and
vertical angles. The instrument is setup on a tripod at approximately 1m above the ground.
After use and when moving from one peg to another the instrument must be put back in its
case correctly positioned and secured safely. The instrument should never be left unattended
and should never be transported on a tripod because that can damage the equipment.
66
To set the vertical axis of the instrument truly vertical and to adjust the plate bubble
To set the telescope sighting line at right angles to the horizontal or trunnion axis of
the instrument
To set the horizontal axis at right angles to the vertical axis
To adjust the altitude bubble and vertical circle zero
Tripod
This is used to support the theodolite when traversing. The tripod is set at 1m above the
ground and its clamps are securely tightened when setting up so that there will b e no
movement during taking of readings as this can affect the results.
Plumb bobs
A plumb bob is a brass weight, usually with a pointed tip on the bottom that is suspended
from a string and used as a vertical reference line.
Measuring tapes
These are used to measure distances between two or more points. The 50m tape is used for
measuring long traverse distances from one peg to another and the 5m tape is used to measure
machine heights and development off-sets such as width of the drive from the centre line to
the wall.
Basic Traversing
Traversing is a form of a control survey that is used in a wide variety of surveys. Traverses
are a series of established stations that are linked together by the angle and distance between
adjacent points. The angles are measured by theodolites, and the distances are measured by
an EDM
Traverse networks involved placing the survey stations along a line or path of travel, and then
using the previously surveyed points as a base for observing the next point.It is mandatory to
start by carrying out a pre-task risk assessment for each and every area to be surveyed where
you identify hazards, list the risks and ensure that they are controlled properly before
progressing to work.
67
Liaise with other employees working in the vicinity of your workplace to avoid
conflicts of interest.
Check that the pegs on the ground correspond with those on the plan.
Check that the pegs to be used have not been tampered with or disturbed by
blasting.
When establishing a new peg, make sure it is on competent ground and its safe
from future blasts or accidental disturbances.
68
Development and stoping month-end measurement is done so as to quantify the tonnage of
ore from the underground and to calculate the advance of development ends. A list of ends is
received from the mining department, and these are then allocated to surveyors. Contact with
mining is made before proceeding underground for the miners to escort the survey crew and
make sure that the ends are accessible and safe.
To quantify the amount of work done which has been done during the month.
This is when the potential development and production areas are identified.
For reconciliation of mining statistics i.e. how much was extracted from the mine.
Each section development and production figures can easily be estimated by using
these results compiled as a draft.
Preparatory Activities
Listing of development and stopping mined out areas for the month.
Updated development and stopping ends in terms of line peg extension.
Measuring equipment (5m, 30m and 50m tapes), distometer , field books.
69
Calculate the meters advanced for the month using the development reduction format.Plot the
measured distances on the plan. Measure the distance between the previous months date and
the current months date. Check the result with calculated advance. If it checks then the
measuring and plotting was correct.
Stoping ends Reduction
Plot the measured stope faces on the plan (CAD plans). Join the strings to the previous month
face. Create another string for the level below taking the orebody orientation into
consideration. Assign elevations to the created strings e.g. footwall elevation for the level
above, hanging wall elevation for the level below. Save the string in a DXF format. In Vulcan
import the strings. Create a solid model using the two strings. Calculate the tonnage using
Vulcan software applying as SG insitu of 2, 8.Send the stope models to geology for grade
estimation.
2. Installation of pegs
Equipment used: Theodolite T1, Tripod, 5m and 100m Steel tape, Field book and bobs.
This generally involves 2 types of pegs to be installed:
a) Installation of Line Pegs
Line pegs are used to control and direct mining. Activity took place at 27L10m; 28 Level
Haulage South and at 28L10-320N Dr North. The line pegs are at least 15m away from each
other. The instrument used to install these pegs is known as a Theodolite. The first step is to
install a Front-Line Peg (FLP) which is just used to align pegs. The Theodolite machine is
set on a tripod support bar accurately vertical. The peg position is determined and it is
installed using hammer and chisel. Checking is then done to ensure there are no errors of
distance and angles. The errors must not exceed 30 seconds for angles and must not exceed
0,008mm for distance.
b) Installation of Side Grades
Grade pegs are pegs installed on side walls to central either the inclination or declination of
any excavation such as that of drives, crosscuts, haulages, etc. These demarcate the orebody
boundaries and are also used in directing mining. Side wall grade pegs are installed in pairs,
each pair having the same elevation and set opposite one another so that the line joining them
is at right angles with the direction of the tunnel. Therefore, the angle measured is the angle
of deviation from the centre line. Sidewall grade pegs are installed at an interval distance of
3m. The Theodolite machine is set under the line peg.
70
This enabled the student to know how the measurements taken underground for
developments are then plotted on plan and layouts and how they are interpreted for geological
and mining purposes. This also included how Assay data is plotted on plan and how it is used
to delineate orebodies. This was done on a draughting film and use of rotrin pen. Set squares,
scale ruler, straight edges should be available.
Description of Draughting process or activity
Draw the grid lines in pencil at the front of the draughting film. Draw the border lines using a
0.5mm size rotrin.The grids are to be drawn at 25m apart for a 1:200 scale. Check the
dimensions of the grids. If there is variation, adjust to the required dimensions. If satisfied
with the pencil drawn grids, draw the same grid lines at the back of the film using a 0.25mm
rotrin pen and a straight edge. The rotrin pen should be upright when draughting. Make sure
the drawn grid lines are of the same width. All the survey draughting should be in black ink.
Erase the pencil marks at the front of the film. Write the grid coordinates on the grid line at
the edge of the plan. Draw the north sign at the right edge corner of the film. Draw the box at
the bottom right corner of the film. Fill the appropriate information e.g. level of the plan,
scale and sheet number. Write the survey system constants on the plan. Then plot any
required information e.g. peg and development offsets.
Description of Plotting process or activity
Use a sharp pencil for plotting pegs. Plot your work on the relevant plans and sections as
soon as the calculations are completed. All survey information to be neatly stencilled on
plans and sections using standard stencils. Assay results may be hand written. The symbols
used on South African mines to depict various features will be standard on all plans. All main
pegs to have their number and elevation. All offsets to be plotted and inked on standard mine
plans. All stoped areas to be indicated by bold broken lines with dates of updating. Where
there is some doubt of the accuracy of a survey, the draughting should be done in pencil until
such a time it is confirmed then it is inked.
Ventilation
The student managed also to spent time with the Ventilation Officers of How mine. The main
objective was to conduct ventilation measurements and investigate if the mine was complying
with the company standards and legal requirements. Ventilation is the continuous supply of
fresh air to the underground system and working sites. How mine uses mechanical ventilation
system to supply fresh air to all parts of the mine, since natural ventilation is normally
71
inadequate and unreliable. There is use of large out-casting/exhaust fans (45Kw) which
exhaust polluted air from the mine system. Down casting of air is through the shafts
supported by Auxiliary fans which pulls the air and directs it to the mining environments. The
pulling of air by auxiliary fans is what creates the negative pressure system, thus enabling
more down casting of air. The polluted air out-casted contains pollutants such as gases, dust
and heat. The objective of ventilation inspections done by the student were taking
measurements and investigating if the mine is complying with the company standards and
legal requirements. This is done through determination of the following parameters:
Air utilization
Leakages within the system
Temperature and humidity levels
There are three surface fans 1220(48)* 45Kw located at the Plant, Main shaft and Hill top
fan at How South. These acts as upcasting fans and there are also three downcasting shafts
which includes the North shaft, Main shaft and South raise bored shaft. Kestrel 4000
instrument is used to measure ventilation readings at How mine such as the temperatures,
humidity, volume and velocity of air both being down casted and being up-casted to ensure
that there is a balance and low leakages within the system. The Kestrel 4000 used is shown
below:
The air underground is further directed to different sublevel, haulages and drives by us of
pipes referred to as ventilation columns. The air circulation is also aided by raises that are
72
excavated from one main level to another. The ventilation parameters measured using the
Kestrel 4000 are compared with the ventilation standards shown below and
recommendations are then made basing on the results whether the ventilation conditions are
good or need to be improved.
Ventilation standards
Leakage 20%
Humidity 75%
Noise 85dbA'
73
6.9.2 Geology
This section oversees the direction of mining activities by drawing and analysing samples
and then advising the mining department on which areas to direct their efforts in the
extraction of ore. This section therefore has the task of determining and assessing ore
extracted daily, ore sent to the plant, grade control as well estimating the life the mine.
There are plans to begin exploration of new areas to complement existing operations. This
section is headed by the Senior Geologist
Mine
Exploration Planning
and Design
Monitoring
Reports
and Control
74
6.9.2.2 Sampling
Sampling is a means whereby small amounts of materials (samples) are used to evaluate a
much larger amount of material (the ore-body).Sampling methods used are channel
sampling, hand chip sampling, grab ( draw point )sampling and stock pile sampling
Stockpile Sampling
Samples are collected and ticketed from the entire face of the stock pile and samples are
sent to assay. A sketch of the stockpile is made and the location and ticket number of
every sample is included in the sketch, so that when the grades come back from assay
they are plotted on the sketch giving each sampling point its grade. Stockpile sampling is
used as a way of tracking the grade of gold that is expected to be processed at the plant.
6.9.3 Assay
Samples are received from geology and reduction plant for assessment and grade
determination. Samples are initially dried of all moisture in a drying room before being
crushed and pulverised into finer particles. Samples undergo a rigorous process of Fire
Assaying until the amount of gold in each sample can be measured and recorded. These
statistics are sent back to geology then mining to advise on mining direction.
A fire assay is a chemical fusion method for separating, concentrating, and measuring the
content of gold and silver in exploration samples, ores, and concentrates. The pulverized
sample is weighed, mixed with a lead oxide-alkali carbonate flux and a small amount of
reducing agent such as flour, and fused in a fire-clay crucible. The reduced lead collects
the precious metals as it settles down through the melt. The molten chargeis then poured
75
into a mold to cool. The lead sinks to the bottom of the mold and is broken from the
glassy slag when cool. The precious metals are separated from the lead by cupellation.
The lead button containing the precious metals is placed in a cupel of bone ash or
magnesia which is heated in the furnace under oxidizing conditions. The cupel acts as a
semi-permeable membrane allowing the lead oxide formed from the button to be
absorbed into the cupel, leaving the precious metals in a tiny bead on the surface of the
cupel. The gold and silver are separated chemically and quantified gravimetrically or by
instrumental analytical techniques.
The basic assay operations are
i. Sample receiving and drying
ii. Crushing and pulverizing
76
v. Sample parting
Principle of parting
To dissolve the gold silver alloy in parting acid and remove all silver to leave gold.
The bead obtained from cupellation must be flattened to facilitate ease of parting, it must
contain ratio of gold and silver of about 1:3.
Other conditions to observe are the kind of acid, purity of acid and wash water, acid
temperature, acid quantity, time of contact to achieve optimum separation.
vi. AA Finish
The AAS consist of a light source, an atom cell, a monochromat and a read out system. It
requires an energy source, a hollow cathode lamp (HCL) containing the same element as
that being investigated.
The solution is aspirated into a flame and the sample elements are atomized. The flame
then contains atoms of gold most of which are at ground state.
When a beam of light passes through a gaseous cloud of atoms, they absorb photons and
make a transition from ground state to an excited state. The net energy of this state is
equal to the energy of the absorbed photon.
The analysis of the sample is determined by measuring the absorption of the constant
intensity of the EMR that passes through the flame.
Final weighing
Zero the micro balance before weighing.
Calibrate the balance using standard weights.
Weigh the samples (prills) and enter the results in the Gold record book.
Calculate the sample(s) results as follows
77
- Concentration of gold in grams per tonne is 1000 divided by mass of sample taken multiply
by mass of final prill in miligrams (mg).
For further calculations and recording on the metallurgical sheet, only readings within 10%
deviation are used. Checks are conducted as follows:
Obtain the average of two grades: 5.08 + 4.78 = 4.93 g/t
2
Find difference between grade and average and divide by average: 5.08 4.93 = 3.04%
4.93
The two grades (5.08 and 4.78) can be recorded on the metallurgical sheet.
The major occupational hazards in the department are tabulated below, together with their
mitigation strategies.
6.10 Recommendations
78
- People who go underground within a space of 24 hours are too many compared to
caplamps available, there is need to buy more caplamps to avoid overusing the few
available which at most occasions do not last for the whole shift.
- Provision of spares will reduce the mean time between breakdowns; spare equipment
could also be used to avoid any production stoppages.
- Dust suppression mechanism required at 28L grizzly point. A dust scrubber is a better
option.
- All machines and their associated drilling equipment should be frequently monitored,
repaired and maintained to avoid breakdowns during drilling operations which affects
production expectations
79
7 PROJECT PROPOSAL
TOPIC:
A dissertation proposal submitted in partial fulfilment of the requirement for the Honours
degree in Mining and Mineral processing Engineering
By
OF
80
EXECUTIVE SUMMARY
Noticing the need for a creation of best working condition at 28 level, the thought of doing a
project which will help create a best possible working condition hit the proposer. The
proposer together with his team mates will design a system which will suppress dust by
sucking it from the ore pass and capture it by the use of fine water sprays in a cyclone. The
design of the system is drawn to scale, mathematical calculations done on how it will operate.
The teams members will each have a role to play doing tasks as per assigned until the
81
Problem Statement
comprised of sublevels and main haulage levels which are used as production levels
(tramming of ore). Currently 26 and 28 levels are being used as production levels. There is an
ore pass from 26 to 28 level passing through 28 level. At 28 level there is a grizzly also
used to tip ore into that same ore pass from 26 level. This ore pass is also used to downcast
some fresh air from 26 level to 28 . When tipping of ore is done at 26 level, the ore face
some attrition with the side walls of the ore pass as it go to 28 level, thereby dust results
from the attrition. An exhaust fan was installed facing the grizzly at 28 level to suck the dust
where by its efficiency is not seen as it exhaust the dust after it had already attacked those
working at grizzly and still the dust levels are more than the maximum required standards.
Unfortunately the dust created then becomes part of the down-casted air and is distributed
into 28 level through the grizzly openings and affects those working at the grizzly at 28 level.
Dust levels are more than the maximum required by How mine standards in conjunction with
OHSAS 18001.
Justification
- Bulawayo Mining Company has its own standards which they set extracting from the
OHSAS 18001 and they should abide to that all the times.
- Project also needs to reduce workplace hazards and boost employee morale.
- The project will strive to eliminate dust from the source with the use the wet scrubber
mechanism.
82
Objectives
- AIM to eliminate dust from foul air at 28L grizzly with the use of wet scrubber and
- At the end of the project there is hope of dust being completely exhausted direct from
the source into the wet scrubber mechanism and dealt with to an extent that we have
destinations
83
- The design will have an exhaust fan which will suck foul air from the ore pass and
create a negative pressure system to give room for the 28 level grizzly to down cast
some air. The foul air exhausted is entered into a cyclone where fine sprays of water
are introduced to it to capture al dust particles and to dissolve some gasses present.
The captured dust particles will come as underflow as the air will continue as
overflow but now with mist in it. A mist eliminator will then do the magic to produce
a clear air which will be tested for gasses and dust before used for ventilating working
areas.
Methodology
1. Recognizing the need; listening to the workers needs and say about the dust at 28
level. Noting down of the dissatisfaction with the existing situation. Planning for
the best possible working condition for the workers and maintain their wellness at
workplace.
84
2. Defining the problem; with the needs of the workers and the standards and
regulations say, I define a problem statement as explained above, the goal for the
response to the problem, its objectives and also laying out the constraints of the
include the survey department, ventilation department and the geology department of
Bulawayo Mining company. Solutions to the similar problems are researched and also
5. Planning the project; with the Bulawayo Mining Company ventilation department
putting a helping hand, activities will be broke down to certain individuals which are
part of the project and the company management will be asked to help financially and
Project management; departments to add value to the system include the survey,
ventilation, mine planning and the projects of the Bulawayo Mining company.
ii) Evaluation
iv) Budget
Time factor;with the situation underground the project is way much behind hence the
85
Assumptions and constraints;
i. assumptions
o the design will be able to deliver an output of fresh air perfect to ventilate
again
ii. constraints
6. Project delivery; installation of the system, training of staff to operate the system,
performing of acceptance test, post project review and providing warranty support
Expected results;
Safe production
86
Project Team;
Pride
Engineering (HIT)
technician
Officer
87