This document provides a 16-step method statement for brick laying and plastering works. The steps include setting out brickworks according to drawings, installing damp proof courses, cutting bricks, checking alignments, curing completed blocks, applying spatterdash coats to RC walls, mixing mortar on site, applying plaster to the required thickness, and curing completed plastered surfaces. Proper tools and materials will be used at each step to ensure quality work according to specifications and drawings.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100%(2)100% found this document useful (2 votes)
1K views
Bricks & Plastering Method Statement
This document provides a 16-step method statement for brick laying and plastering works. The steps include setting out brickworks according to drawings, installing damp proof courses, cutting bricks, checking alignments, curing completed blocks, applying spatterdash coats to RC walls, mixing mortar on site, applying plaster to the required thickness, and curing completed plastered surfaces. Proper tools and materials will be used at each step to ensure quality work according to specifications and drawings.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1
WNE ONE ENTERPRISE LLP
BRICK LAYING & PLASTERING WORKS
METHOD STATEMENT
S/No Description Remarks
Setting out of brickworks: Lay-out and place markings 1 with reference to the grid lines and columns accordding to the drawing. Locate the position of the stiffener(if needed) and cast 2 before brickworks. Site Batching of mortar mix: To used standard size 3 bucket to ensure correct proportion of materials. Mixing of Cement mortar as specified in the construction drawing/specification. And to regulate the quantity of 4 mortar being mixed, so that the mortar can be used up within the working time. Check the installation of Damp Proof Course on the ground floor. Ensure that a layer of bituminous 5 compound is laid on the concrete floor base before laying of the bituminous felt and the 12mm thick base cement mortat. Every three course exmet wire and the tie rod to be 6 bedded and ensure proper lapping of joining exmet wire. Lintels to be installed for doors and windows opening Cutting of Bricks: To used proper cutting machine or 7 with bolster and hammer. Check alignment both horizontal and vertical as per work 8 progress. Check consistency of the 10mm thick cement mortar 9 bedded on bricks. Completed blocks to be left to cured for required period 10 of time. Plastering works:Lay-out and place level pact on 11 completed masonry wall.
12 To apply spatterdash coat on RC wall.
Site Batching of mortar mix: To used standard size
13 bucket to ensure correct proportion of materials. Mixing of Cement mortar as specified in the construction drawing/specification. And to regulate the quantity of 14 mortar being mixed, so that the mortar can be used up within the working time. Apply the plaster with plastering trowel to the required 15 thickness. Completed plastered surface to be left to cured for 16 required period of time.