Mobilisation Dismantle Roof Covering Demolition of Brick Wall Erecting New Brick Wall Site Clearance

The document outlines the schedule for a construction project involving site clearance, demolition, new construction, and installation of various building components. It includes 25 separate tasks ranging from dismantling the existing roof to landscaping, occurring between December 2017 and February 2018. Various crews identified by abbreviations like GW, SL, and Electrician will work on different tasks over the duration of the roughly two month project.

Uploaded by

David Law
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

Mobilisation Dismantle Roof Covering Demolition of Brick Wall Erecting New Brick Wall Site Clearance

The document outlines the schedule for a construction project involving site clearance, demolition, new construction, and installation of various building components. It includes 25 separate tasks ranging from dismantling the existing roof to landscaping, occurring between December 2017 and February 2018. Various crews identified by abbreviations like GW, SL, and Electrician will work on different tasks over the duration of the roughly two month project.

Uploaded by

David Law
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Site Clearance Mobilisation Dismantle Roof Covering Demolition of Brick Wall Erecting New Brick Wall

Start: Wed 12/20/17ID: 2 Start: Sun 12/24/17 ID: 3 Start: Mon 12/25/17ID: 4 Start: Mon 1/15/18 ID: 7 Start: Thu 1/18/18
Finish: Sat 12/23/17 Dur: 4 days Finish: Sun 12/24/17Dur: 1 day Finish: Sun 1/14/18 Dur: 21 days Finish: Wed 1/17/18Dur: 3 days Finish: Fri 1/19/18
Res: GW1, GW2, GW3, GW4 Res: GW1, GW2, GW3, GW4 Res: GW1, GW2, GW3, GW4, GW6 Res: GW1, GW2, GW3, SL 1 Res: GW1, GW2, GW3, SL

Erecting New Partition Wal


Start: Thu 1/18/18
Finish: Thu 2/1/18
Res: GW4, GW5, GW6, SL

Erecting New Glass Wall


Start: Thu 1/18/18
Page 1
Start: Thu 1/18/18
Finish: Mon 1/22/18
Res: GW7, GW8, GW9, SL

Demolition of Partition Wall


Start: Mon 1/15/18 ID: 8
Finish: Mon 1/15/18Dur: 1 day
Res: GW4, GW5, GW6, SL 2

Dismantle Doors and Windows


Start: Mon 12/25/17ID: 5
Finish: Mon 12/25/17Dur: 1 day
Res: GW7, GW9, GW8

Remove Electrical Wiring and Appliances


Start: Mon 12/25/17ID: 6
Finish: Mon 12/25/17Dur: 1 day
Res: GW11, GW10, Electrician 1, Electrician 2

Page 2
New Brick Wall Installing Roof Covering
u 1/18/18 ID: 9 Start: Fri 2/2/18 ID: 12
i 1/19/18 Dur: 2 days Finish: Sun 2/4/18 Dur: 3 days
W1, GW2, GW3, SL 1, SL 2 Res: GW1, GW2, GW3, GW4, GW5, SL 1, SL 2, SL 3

Installing Door Frame Installing Door


Start: Fri 2/2/18 ID: 14 Start: Sun 2/4/18 ID: 15
Finish: Sat 2/3/18 Dur: 2 days Finish: Mon 2/5/18 Dur: 2 days
Res: GW7, GW8, GW9, GW10, GW11, SL 5, SL 6 Res: GW7, GW8, GW9, GW10, GW11, SL 5, SL 6

Installing Window Installing Mechanical Services


Start: Sun 2/4/18 ID: 16 Start: Mon 2/5/18 ID: 19
Finish: Sun 2/4/18 Dur: 1 day Finish: Tue 2/6/18 Dur: 2 days
Res: GW12, GW13, GW14, SL 7, SL 8 Res: A/C Technician 1, A/C Technician 2, A/C Technician 3, A/C Technician 4

Electrical Wiring and Switches Installing Lamp Fitting


Start: Mon 2/5/18 ID: 20 Start: Wed 2/7/18 ID: 21
Finish: Tue 2/6/18 Dur: 2 days Finish: Wed 2/7/18 Dur: 1 day
Res: GW15, GW16, Electrician 1, Electrician 2, Electrician 3, Electrician
Res: Electrician
4, Electrician
1, Electrician
5 2, Electrician 3

Plastering Wall Painting Work Road Work Signage


Start: Sat 1/20/18 ID: 17 Start: Sun 1/21/18 ID: 18 Start: Mon 1/22/18 ID: 22 Start: Wed 1/24/18 ID: 23
Finish: Sat 1/20/18 Dur: 1 day Finish: Sun 1/21/18 Dur: 1 day Finish: Tue 1/23/18 Dur: 2 days Finish: Wed 1/24/18Dur: 1 day
Res: Plastering Labour 1, Plastering Labour 2 Res: Painter 1, Painter 2, Painter 3, Painter 4 Res: SL 1, SL 2 Res: SL 1, SL 2

Landscaping
Start: Wed 1/24/18 ID: 24
Finish: Thu 1/25/18 Dur: 2 days
Res: SL 5, SL 6

Installing Gutter
Start: Fri 2/2/18 ID: 13
Finish: Fri 2/2/18 Dur: 1 day
Res: GW6, SL 4

New Partition Wall


u 1/18/18 ID: 10
hu 2/1/18 Dur: 15 days
W4, GW5, GW6, SL 3, SL 4

New Glass Wall


u 1/18/18 ID: 11
Page 3
u 1/18/18 ID: 11
on 1/22/18Dur: 5 days
W7, GW8, GW9, SL 5, SL 6

Page 4
Demobilisation
Start: Thu 2/8/18 ID: 25
Finish: Fri 2/9/18 Dur: 2 days
Res: GW1, GW2, GW3, GW4

Page 5
Page 6
Critical Milestone Critical Inserted Marked Project Summary
Project: PM
Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Tue 12/12/17
Critical Milestone Summary Critical Marked External Highlighted Noncritical

Page 7