App R Failure Modes Effects Analysis
App R Failure Modes Effects Analysis
PO Box 7005
Bozeman, MT 59771
Geomin Resources, Inc.
Black Butte Copper Project Mine Operating Permit Application
A FMEA is often used to structure mitigation for risk reduction based on either failure (mode)
severity reduction, or based on lowering the probability of failure’s occurrence or both. FMEA is
used to evaluate processes and facilities for possible failures and to prevent them by correcting
the processes or design proactively, rather than reacting to adverse events after failures have
occurred. This emphasis on prevention can significantly reduce risk of harm to human health
and the environment. FMEA is particularly useful in evaluating a new process prior to
implementation, and in assessing the impact of a proposed change to an existing process.
FMEA provides a documented method for selecting a design with a high probability of
successful operation and safety.
Tintina conducted its first FMEA evaluation early in the mine planning process. In this review
they critically looked at the proposed operational processes and the design of facilities. The
results of the FMEA evaluations were used to modify mining methods, milling processes and
facilities for more effective, efficient and safer operations. The focus of these modifications was
on minimizing risk to environmental resources and human health, while enhancing both
environmental and operational performance and safety.
Method of Analysis
Two critical analysis need to be carried out before beginning a FMEA: identifying the cause of
failures and the probability of their occurrence, and the ranking the severity of the potential
impact of the failure.
Probability
The first step in developing a FMEA is to identify the cause of a failure mode and the likelihood
of its occurrence. This is often done by examination of similar processes or construction
methods and the failure modes that have been historically documented. A failure cause is
looked upon as a design weakness. All the potential causes for a failure mode should be
identified and documented. The probability of occurrence for various failure modes for this
analysis over the 19 year mine-life included: unlikely (0), remote (0-1), infrequent (1-2),
occasional (2-4), and likely (annually) and are specified in detail in Table 1. A failure mode is
then given a probability ranking. In order to rank various failure modes probability criteria must
be developed that explicitly define the range of failures to be compared and the range of
frequency of occurrence for which they will be compared. Table 1 presents the probability table
developed for criteria evaluated in these FMEAs.
Consequences
In addition to probability, the severity of the impact or consequences of the identified failure
mode must be identified and criteria developed which can be used to compare the
consequences. Table 2 presents the consequence criteria evaluated in these FMEAs including:
environmental, human health, changes in operations or permitting impacts, and cost.
Residual Risk
Residual risk is the combination of probability of a failure occurring and the consequences of the
failure. Risk levels are typically depicted on a matrix table that compares the effects of both
probability and consequences. The higher the risk level, the more justification and mitigation
that is needed to lower the risk to an acceptable level. The risk categories developed for this
FMEA include: extremely low, low, moderate, high and unacceptable or extreme. The risk level
matrix is presented as a function of both probability and consequence in Table 3.
No human health
Human health risk No injuries Possible minor injuries Injury, no fatality Injuries with fatalities
risk
Prolonged delay in
facility operations Complete loss of
Short term loss of
requiring major function requiring
facility in operation
Resulting change in No changes Maintenance action reconstruction, may facility replacement or
requiring minor
operations required only result in agency loss of project viability,
reconstructions; other
initiated temporary suspension of mine
resources available
suspension of permits
operations
Site-Specific Example
Table 4 presents part of the selection processes for developing lists that characterize facilities to be
examined for failure modes at the Project site. In Table 4 facilities were grouped by HDPE lined
facilities with both mine water and waste storage stored on the facility, and then by the hazard ranking
of the facility; other screening criteria segregated facilities with mine waste but with no water stored on
them, and finally there is a screened sub-group of unlined facilities with stockpiles of soils or
construction materials only.
Table 3. Mine Storage Facilities Types having Failure Modes with Potential
Impacts to Water Quality
Cemented
High Hazard Storage > 50 acre-feet 60,000 m3
Tailings Facility
Dam, with mine (78,500 cu yds.) possible loss of
wastes and mine human life, extensive property or
water storage ecological damage. Process Water
Pond
Storage <50 acre-feet 60,000 m3,
(78,500 cu yds.) Routinely pumped
Low Hazard Dam,
back to water treatment plant, pond
with mine wastes
will have almost no water except for Contact Water
and water
after storm events, no expected loss Pond
storage
of human life, damage limited to
owner’s property, minor ecological
risk.
Low Hazard Dam,
with no mine No expected loss of human life, Non-Contact
wastes, and fresh damage limited to owner’s property. Water Reservoir
water storage
HDPE Lined Facilities with Mine Waste Storage Only
Potentially acid-generating rock, Waste Rock
waste rock pile may not reach Storage
Mined Material saturation in 2-years, seepage
Copper-
Storage Facility reports to contact water pond or
enriched Rock
diverted directly to water treatment
Storage
plant.
Unlined Stockpiles with Construction Material Storage Only
Excess
Construction
Non-acid Generating Materials. Construction
Materials
Top- and Subsoil
With the FMEA model developed for probability, consequence and residual risk, each facility and
process was subjected to the analysis, identifying failure modes and probability of their occurrence, the
consequences of the failure and then analyzing the resulting residual risk. For components with high
residual risk, mitigations were developed by which processes were modified and facilities redesigned to
mitigate the identified risk. This analysis produced extensive tables of data inputs and results. At the
end of the analyses of the FMEA study, the early unmitigated developed processes and facility designs
were compared against the mitigated counterparts and compared for residual risk. Table 5 is a portion
of the FMEA analysis with a selected group of failure modes looking at various facilities and processes
by comparing the unmitigated alternative for facility design or select processes with the mitigated
alternative. In Table 5 the transition from warm to cool colors represent transitions from likely to
unlikely occurrence of a failure mode, and from catastrophic or extreme to negligible consequences.
Table 5. Comparison of FMEA for Select Unmitigated and Mitigated Processes or Facility Construction Scenarios
Revised Revised
Probability Consequence
Failure Mode Cause Facility Name Tintina Proposed Design Mitigation Probability Consequence
Unmitigated Mitigated
Tailings
Remote Catastrophic Probable Maximum Flood Event Storage Unlikely Catastrophic
(CTF)
Process Water Probable Maximum Flood Event Storage Plus
Remote Catastrophic Unlikely Catastrophic
Overfilling and Discharge with or Inadequate (PWP) 1:500 Year Event Storage of CTF
without embankment failure Storage Capacity Contact Water Pond
Infrequent Critical 1:200 Year Event Storage Remote Critical
(CWP)
Noncontact Water
Infrequent Modest 1:200 Year Event Storage Unlikely Negligible
(NCWR)
Table 5. Comparison of FMEA for Select Unmitigated and Mitigated Processes or Facility Construction Scenarios
Revised Revised
Probability Consequence
Failure Mode Cause Facility Name Tintina Proposed Design Mitigation Probability Consequence
Unmitigated Mitigated
(NCWR) 1.2)
Opn. FOS na/1.2 (up/downstream) (min 1.1)
Table 5. Comparison of FMEA for Select Unmitigated and Mitigated Processes or Facility Construction Scenarios
Revised Revised
Probability Consequence
Failure Mode Cause Facility Name Tintina Proposed Design Mitigation Probability Consequence
Unmitigated Mitigated
Figure 1 is a schematic that plots failure probability vs. consequence to define fields of residual
risk, as an example of how specific case studies will be examined for the remainder of
alternatives and mitigations considered. On Figure 1 the categories of residual risk are ranked
as very low, low, moderate, high and extreme or unacceptable.
Figure 1. Schematic plotting probability vs. consequence to define fields of residual risk
On the following graphics each of the failure modes from Table 5 is sequentially examined first
by identifying the failure mode and its cause, and then by looking at each facility to be
compared. First the facility is ranked for the probability and consequences and the residual risk
for the unmitigated condition. Then the proposed mitigations are enumerated, and finally the
same facility is ranked for the probability of the failure mode and it consequences under the
mitigated set of conditions. Graphically each of the facilities are labeled with unmitigated
ranking shown in red font and the mitigated ranking shown in green font. Finally an arrow is
drawn between the two rankings to illustrate the change in residual risk that results from
implementation of the mitigations. Figures are titled as a function of the failure mode.
The first set of five figures (Figures 2, 3, 4, 5, and 6) considers mine facilities that store both
mine wastes and water for various failure modes.
Figure 2. Overfilling of facility and discharge resulting from inadequate water storage
capacity
Figure 3. Overfilling of facility and discharge resulting from lack of pump-back capability
The next two figures (Figures 7 and 8) consider mine facilities that store only mine wastes (no
ponds of water) for various failure modes. Note that the Temporary WRS facility may not reach
saturation or generate seepage in as little as its proposed 2-years of operation (prior to
reclamation and closure).
Figures 9 examines facilities or ditches whose BMPs fail to control either contact water
collection or storm water and sediment discharge.
Figures 10 examines facilities or ditches whose BMPs fail to collect either contact water or
storm water sediment.
Figure 10. Discharge resulting from failure to collect contact water sediment
Figure 11 examines the resultant risk from failure to site mine openings above the water table.
Figure 11. Discharge from mine opening resulting from portal and raise locations
The final figure (Figure 12) examines the resultant risk to air quality and potentially to surface
water from failure due to shipping concentrate in open trucks with multiple laydown areas along
the transport route vs shipping concentrate in closed and sealed shipping containers.
Figure 12. Risk of contaminating air or laydown areas during concentrate shipping
Summary
A few examples of how selected failure modes for operational processes, facility siting, and
facility construction criteria can be evaluated using FMEA are presented above. This analysis
was used to identify and then propose mitigations to more typical historical mine planning in
order to enhance the success of this Project. The FMEA analysis documents that the
incorporation of these mitigations consistently and significantly reduces residual risk of failure.
The analysis allows the selection of improved processes, better selection of facility locations,
and incorporation of improved changes in construction or design methods. The list of proposed
mitigations at the beginning of Section 5.1 of the Mine Operating Permit Application points out
some of the highlights of this planning process that Tintina believes will lead to a successful
mining operation that substantially mitigates impacts to human health and the environment.