Best Practices Document-Introduction
Best Practices Document-Introduction
Engineering And
Construction
Organisation Best
Practices
This document is designed to impart SAP Best Practices for securing good project
delivery utilizing the SAP information system at various levels of the
organization. The idea is to provide the Best Practices suiting to the
organization without making changes in the existing project delivery mechanism
of the organization
Disclaimer
This document does not endorse any specific SAP Process and that the selection
of the specific process would depend on the individual organization’s size and
existing project delivery mechanism. The views and opinion of authors in this
document shall not be used for any advertising or process endorsement of SAP in
the name of Highbar Technologies. In particular, Highbar Technologies shall not
be liable for any loss or damage whatsoever, arising from the usage of
information contained in this document.
2
Contents
3
1. Executive Summary
Today the Engineering and Construction sector is grappling with multiple challenges in the area
of Project Selection, Workforce Productivity, Payment Delays, Design Changes, Cost Overrun,
Material Delays, Subcontracts Management, Schedule Overrun, Inventory Management, Safety,
Policy Changes, Corruption. Despite persistent uncertainty in the engineering and construction
industry, optimism remains high as growing global demand for infrastructure development,
improving economic conditions, and increased availability of project financing provide industry
participants with new growth opportunities.
The construction industry is one of the most complex and multipurpose economic sectors. Its
value added chain encompasses activities which include the production of raw materials and
processed goods (ranging from simple sand extraction, wood processing and woodworking, to
the manufacture of cement and steel, to metal products, such as fixtures), civil and heavy
construction works, as well as project engineering, development and management.
6. Achieve balanced people, process and technology changes across all areas.
7. Apply planning and program management practices throughout the program life cycle of a
project.
4
2. SAP Best Practices
SAP Best Practices is functionality preconfigured for a particular vertical industry. This
document covers following processes on the Engineer and Construction Project.
The controlling area is the basic organizational unit in Controlling. A controlling area
represents a closed system that is used for cost accounting. Cost allocations can
only be carried out within one controlling area, they cannot relate to objects in
other controlling areas.
The company code is the balance sheet unit in Financial Accounting. Balance sheets
and profit and loss statements are prepared at company code level in order to meet
the legal Reporting requirements.
The plant is a manufacturing facility. It is the central organizational unit in the R/3
components Materials Management and Production Planning. In the definition of
organizational structures, plants are assigned to company codes.
Purchasing organizations and sales areas are organizational structures for
Purchasing or Sales and Distribution.
6
2.5 Revenue Planning
To monitor the dates for a project, you compare the actual dates with the basic
dates or the forecast dates.
Actual dates can be set manually for WBS elements. If you are using network
activities, actual dates are updated by confirming activities.
If activities are assigned to a WBS element, the actual dates of the activities are
proposed to the WBS element as provisional dates, which can be transferred to the
actual dates of the WBS element, if necessary.
The incident/accident management component gives you the support you need to
comply with such statutory requirements by providing the following functions:
Entry and editing of all relevant event data in an incident/accident log
Besides entering recordable accidents, you have the option of recording
accidents that result in an employee being absent from work for less than three
days, or not being absent at all. You can also enter any ‘near-accidents.‘
Automatic transfer of data from the injury/illness log to the incident/accident
log if required
Creating and shipping of the accident report required by law for notifiable
accidents in the SAP System
Evaluation of the incident/accident log
Actual data is recorded by means of purchasing and sales documents and the
customer and vendor subsidiary ledgers.
The actual data can be evaluated in the PS Information System by means of
cost/revenue and payment reports
As the project is executed, invoices are generated using billing and appear in the
project as actual revenues and customer payment obligations. In the case of down
payment data, the billing program generates down payment requests which are
recorded in the payment data for the project.
You can create a billing plan for a sales order, a sales order item, or for a billing
element in the WBS.
The invoicing plan is relevant to planned costs and planned outgoing payments.
The dates for the down payment are relevant to payments only (not costs). The
payment terms (example: payment two weeks after invoice issue, with 3%
discount) are important for dates and amounts.
You can create invoicing plans for externally-processed activities, service activities,
cost activities, and externally-procured material components.
As your project is executed, you may experience delivery problems, price variations,
unforeseeable bottlenecks, and so on, that give rise to variances from the project
plan. In this event, it is very important to clarify which partner(s) to the contract
is/are responsible and in what degree. Claim Management ensures that claims
arising from variances are either prepared or lodged against the contractual partner
at the right time or, if the claim is in the other direction, that it can be deflected.
You can use the claim management feature in the Project System to document any
variances from your project plan, identify the party responsible, and initiate follow-
up activities.
9
The cost forecast determines the remaining costs expected to be incurred in order
to complete the project. Planned, actual and commitment values as well as the
confirmed forecast dates and forecast work are used as a basis for this.
Cost forecasts can be made for projects with activity-assigned, appended networks;
the forecast takes account of activity costs and the costs of material components
managed as collective stock.
2.19 Project Closure – Technical and Financial
10
Construction Projects Cost Planning and Budgeting
Estimator
Cost Planning V.1 and V.0
Management Commercial
Head
End
4.1.3. Benefits
11