Par15 Final Report
Par15 Final Report
Final Report
GROUP 15
GROUP PERSONNEL:
ANDIKAPUTRA B.W. (1406607893)
FARACITRA AKUWALIFAH (1406607861)
MUSTIKA SARASWATI (1406552906)
NADIRA KAMILIA PERMATASARI (1406607956)
NADYA SAARAH AMELINDA (1406552824)
ii
Universitas Indonesia
PREFACE
Praise to God, The cherisher and sustainers of the worlds; God who has
been giving His blessing and mercy to the writer to complete this Final Report
entitled ― Preliminary Design Of Producing Benzene From Catalytic Fast
Pyrolisis Of Empty Fruit Bunches
This Final report is submitted to fulfill one of the requirements in
Chemical Plant Design Class as capstone course of Chemical Engineering Major
in Universitas Indonesia.
In finishing this report, the writer really gives his regards and thanks for people
who has given guidance and help, they are:
1. Prof. Dr. Ir. Widodo Wahyu Purwanto, DEA. , Dr. rer. nat. Ir. Yuswan
Muharam M.T. , Dr. Ing. Ir. Misri Gozan M.Tech., Dr. Tania Surya Utami,
S.T., M.T., and others lecturers, who has given their best guidance to the
writer in writing a great quality report and well developed chemical
product.
2. Our Parents, who always give their supports, prayers, and blessing.
3. All friends in Chemical Engineering Department batch 2014 who always
give their supports.
Finally, the writer realizes there are unintended errors in writing this final
report. The writer really appreciates all readers giving their suggestion to
improve its content in order to be made as one of the good examples for the next
report.
Writer Team
iii
Universitas Indonesia
ABSTRACT
Preliminary Design Of Producing Benzene From Fast Pyrolisis Of Empty
Fruit Bunches
Andikaputra Brahma Widiantoro, Faracitra Akuwalifah Kusumadewi, Mustika
Saraswati, Nadira Kamilia Permatasari, Nadya Saarah Amelinda
Chemical Engineering, Department of Chemical Engineering, Faculty of
Engineering, Universitas Indonesia
iv
Universitas Indonesia
EXECUTIVE SUMMARY
v
Universitas Indonesia
natural gas for this plant is 2000 L/h. It can be obtained from IWATA Diesel
Generator which is produced by PT Indotara Persada.
Benzene is produced with certain specification to be raw material of in
many petrochemical industries in Indonesia. We use several types of equipment
for benzene production. There are 26 equipments. The types of equipment are
reactor, pump, distillation column, three phase separator, heat exchanger, grinder,
conveyor, cyclone, filter plate and also storage tank.
These equipment also needs instrumentation controls to maintain the
desired operating condition. This instrumentation controls some of variable of
plant production such as temperature, pressure, flow rate because mostly plant in
the world works in not steady state condition. On the other hand, this
instrumentation also makes our plant safely works for plant with high pressure
operating condition.
For benzene plant, Health, Safety, and Environment analysis are needed to
support our production process. First, there must be some commitments between
the workers and the management about health, safety, and environment on the
rules of production process following the Government Regulations. The
commitments are including the workers behavior and management rules. For
supporting HSE, HAZID and HAZOP are analyzed.
Through economic analysis, the feasibility of our plant is seen. The total
capital expenditure that is needed to fulfill all the equipment in the plant is USD
15,739,387.61. The operating expenditure to pay all the operational costs annually
is USD 32,830,334. The equity from our plant will be fulfilled by bank loan 60%,
investor 40%. The WACC that is calculated is 5.29%. The net value of benzene
product is US$1,050 per tons, with sales revenue US$ 20,711,947 annually. With
such revenue, the payback period is 4 years and Net Present Value is US$
27,820,660,309. The Rate of Interest for benzene plant is 12.23%.
vi
Universitas Indonesia
LIST OF CONTENTS
vii
Universitas Indonesia
3.1.1. Fast Pyrolysis Reactor ...................................................................... 32
3.1.2. Hydrolysis Reactor ........................................................................... 32
3.1.3. Catalyst Regenerator ......................................................................... 33
3.2. Storage Tank ........................................................................................... 33
3.2.1. Biomass Warehouse.......................................................................... 33
3.2.2. Benzene Tank ................................................................................... 34
3.2.3. Demine Water Tank .......................................................................... 34
3.2.4. Coagulant Tank ................................................................................. 35
3.2.5. Filtration Tank .................................................................................. 36
3.2.6. Ion Exchanger Tank .......................................................................... 36
3.3. Heat Exchanger ....................................................................................... 37
3.3.1. Heat Exchanger (E-100) ................................................................... 37
3.3.2. Heat Exchanger (E-101) ................................................................... 38
3.3.3. Heat Exchanger (H-100) ................................................................... 39
3.4. Distillation ............................................................................................... 40
3.4.1. Distillation Column .......................................................................... 40
3.5. Three Phase Separator ............................................................................. 41
3.6. Conveyor ................................................................................................. 42
3.6.1. Elevator Conveyor ............................................................................ 42
3.6.2. Belt Conveyor ................................................................................... 42
3.7. Hammer Mills ......................................................................................... 43
3.8. Filter Plate & Frame ................................................................................ 43
3.9. Cyclone ................................................................................................... 44
3.9.1. Cyclone (Cy-100) ............................................................................. 44
3.9.2. Cyclone (Cy-101) ............................................................................. 45
3.10. Flue Gas Compressor (C-100) ................................................................ 46
3.11. Pump ....................................................................................................... 46
3.11.2. Water Pump (P-102) ....................................................................... 47
3.11.3. Water Pump (P-103) ....................................................................... 47
CHAPTER 4 PROCESS CONTROL STRATEGY ........................................ 49
4.1. Plant Control Tabulation ......................................................................... 50
4.2. Piping and Instrumentation Diagram
................................................. 53
4.2.1. Pre-Treatment ................................................................................... 53
4.2.2. Main Process ..................................................................................... 54
CHAPTER 5 PLANT LAYOUT ....................................................................... 55
5.1. Area Plant Layout ................................................................................... 55
5.1.1 Outside Battery Limit Zone .............................................................. 57
5.1.2. Total Factory Layout ........................................................................... 57
CHAPTER 6 ............................................................................................................
HEALTH AND ENVIRONMENTAL SAFETY ASSESSMENT .................. 61
6.1. HSE Aspect ............................................................................................. 61
6.1.1. Hazard Identification (HAZID)........................................................... 61
6.1.2. Hazard and Operation Safety ............................................................ 62
6.2. HSE Management ................................................................................... 62
6.2.1. Operation Details .............................................................................. 62
6.2.2. Personal Protective Equipment (PPE) .............................................. 66
viii
Universitas Indonesia
6.3. Material Safety Data Sheet (MSDS) ....................................................... 66
6.4. Emergency Action Plan .......................................................................... 68
6.4.1. Emergency Operating Procedures and Training ............................... 68
6.4.2. Emergency Alarm and Fire Fighting Equipment .............................. 70
6.4.3. Emergency Escape Procedures and Route ........................................ 71
6.6. Waste Management ................................................................................. 72
6.6.1. Solid Waste ........................................................................................ 72
6.6.2. Liquid Waste ...................................................................................... 73
6.6.3. Gas Waste........................................................................................... 73
6.6.4. Sound (Noise) Waste.......................................................................... 73
CHAPTER 7 ECONOMIC ANALYSIS ........................................................... 75
7.1 Cost Index ............................................................................................... 75
7.1.2. Capital Expenditure (CAPEX) ......................................................... 76
7.1.3 Comparison with Existing Plant ........................................................ 80
7.2. Operating Cost ........................................................................................ 80
7.2.1 Raw Material Cost ............................................................................. 80
7.2.2. Labor Cost ........................................................................................ 82
7.2.3. Utility Cost........................................................................................ 84
7.2.4. Maintenance Cost ............................................................................. 86
7.2.5. Insurance and Tax ............................................................................. 87
7.2.6 General Expense ................................................................................ 90
7.2.7. Cost Breakdown of Operational Expenses ...................................... 91
7.3. Economic Evaluation .............................................................................. 92
7.3.1. Price Prediction ................................................................................. 92
7.3.2. Cash Flow ......................................................................................... 93
7.3.2.1. Equity ............................................................................................... 93
7.3.3. Profitability Analysis ........................................................................ 96
CHAPTER 8 OUSTANDING ISSUE ............................................................. 102
8.1 Technical Aspect ................................................................................. 102
8.2 Economical Aspect.............................................................................. 104
CHAPTER 9 CONCLUSION .......................................................................... 105
APPENDICES ................................................................................................... 106
APPENDIX A: BLOCK FLOW DIAGRAM ................................................. 106
APPENDIX B : PROCESS FLOW DIAGRAM ............................................ 107
APPENDIX C : LIST OF EQUIPMENT SIZING ......................................... 109
APPENDIX D : PLANT LAYOUT AND HSE ............................................. 165
APPENDIX E : MATERIAL SAFETY DATA SHEET (MSDS).................. 182
APPENDIX F : PROJECT COST .................................................................. 220
ix
Universitas Indonesia
LIST OF FIGURES
x
Universitas Indonesia
LIST OF TABLES
xi
Universitas Indonesia
Table 7. 5. Raw Material Costs ............................................................................ 81
Table 7. 6. Direct Labor Cost ................................................................................ 82
Table 7. 7. Indirect Labor Cost ............................................................................. 82
Table 7. 8. Process Equipment Electricity ............................................................ 84
Table 7. 9. Supporting Electricity Requirement.................................................... 85
Table 7. 10. Water Utility Cost ............................................................................. 86
Table 7. 11. Fuel Utility Cost ................................................................................ 86
Table 7. 12. Maintenance Cost.............................................................................. 86
Table 7. 13. Insurance Cost ................................................................................... 87
Table 7. 14. Tax of Land & Building .................................................................... 87
Table 7. 15. Tax of Salary ..................................................................................... 88
Table 7. 16. Tax of Salary (continued) ................................................................. 89
Table 7. 17. Communication Cost......................................................................... 90
Table 7. 18. Product Shipping Cost ...................................................................... 90
Table 7. 19. Plant Overhead .................................................................................. 90
Table 7. 20. Printed Media Publication Cost ........................................................ 90
Table 7. 21. Website Development Cost............................................................... 90
Table 7. 22. Cost Breakdown ................................................................................ 91
Table 7. 23 Benzene Price History........................................................................ 93
Table 7. 24 Capital Loan ....................................................................................... 94
Table 7. 25. Bank Payment Scheme...................................................................... 94
Table 7. 26 Investment Payment Scheme ............................................................. 94
Table 7. 27. Overall Loan ..................................................................................... 95
Table 8. 1. Product Capacity Benchmarking of our Plant .................................. 103
Table 8. 2. Economical Benchmarking ............................................................... 104
xii
Universitas Indonesia
CHAPTER 1
INTRODUCTION
1
Universitas Indonesia
2
more sustainable than using starch and oil crops. Compared to the fossil-based
benzene, the fossil resource inputs and CO2 emissions of biomass-based benzene
are lower, so based on those two parameters biomass-based product promises to
be a sustainable option.
1.2. Product Description (Benzene)
Benzene is a hydrocarbon compound with the formula C6H6 molecule, and
its structural formula is a cyclic chain with double bonds of alternating tubes. The
position of the double bond on this carbon compound can move position. This
event is called double bond resonance. Due to the position of this uncertain
double bond, the compound is finally described as a circular specimen. The
double bonds found in benzene are called conjugated double bonds. Such a
structure was first introduced by Kekule. Compounds containing benzene rings
are known by the name of aromatic compounds. Aromatic compounds can contain
one, two, three, or more benzene rings.
Universitas Indonesia
3
using biomass as the feedstock in benzene production, it can lower demand for
diminishing crude oil supplies, lignocellulosic feedstock has crucial advantages
over other biomass supplies because they are non-edible portion of the plant and
therefore, they don’t interfere with food supplies. Also, developing country like
Indonesia has a comparative advantage for biomass-based production because of
greater availability of land, favorable climatic conditions for agriculture and lower
labor costs. Then, use of biomass as feedstock can reduces CO2 emissions, crop
residues conversion increases the value of agricultural output, replacing fossil-
based benzene with sustainable biomass-based benzene, and costs of getting rid of
municipal solid wastes.
1.3. Analysis
1.3.1. Raw Material Analysis
The main raw material of benzene plant is from biomass. Biomass is a
photosynthetic reaction product of carbon dioxide and water, which consists of
carbon, oxygen, and hydrogen, which are in the form of macroscobsic polymeric
complex.
Raw material to be used in this plant or process is empty fruit bunch. The
need of the raw material is based on lignin contained. Empty Fruit Bunch have
higher Lignin contained than others lignocellulosic biomass. Lignin is the
compound that will be process into BTX then will be distilled into Benzene. The
lignin composition in Rice Husk is also high, but it has a very high ash, which is
not good for production. It will have a problem in the yield of Benzene itself.
The second thought is the waste availability and the waste usage. Empty
Fruit Bunch waste is lower than others lignocellulosic biomass. Also, there are a
lot of Palm Oil Industry in Indonesia; however, they don’t use the empty fruit
bunches So the empty fruit bunch are disposed as wastes. As the effect of
agricultural country, Indonesia has so many potentials to produce palm.
Based on the data, Indonesia has total 11,300,370 hectares of Palm Land in
Indonesia, and 31,284,306 ton of Total Production in 2016.
To provide our raw material, empty fruit bunch from industries that use
palm as their raw material. Empty fruit bunch have been bought from PT Bangun
Universitas Indonesia
4
Tata Lampung Asri, PT Adikarya Gemilang, and PT Bangun Nusa Cipta Wahana
that is located in Teluk Betung Selatan, Bandar Lampung.
1.3.2. Market Analysis
It is a well-known fact that the human population is increasing. With that
increase, the demand for chemicals, solvents and medicines is also increasing.
This demand must be met, meaning amplification in the production of chemicals,
which are required for the manufacturing of these products, is essential. Here is a
table that describes the level of fuel needs in the period 2009-2022.
2009 487872
2010 470316
2011 486007
2012 546517
2013 563709
2014 582668
2015 601628
2016 620587
2017 639546
2018 658505
2019 677465
2020 696424
2021 715383
2022 734342
(Source: Ministry of Industry Indonesia, 2014)
From central statistical agency, the production of benzene in Indonesia
will increase in 2016, 2018, 2022 and 2025. In 2016, began to occur due to the
addition of biofuel production. Then, the benzene supply will increase in 2018 is
due to new benzene producers. Here are the details of biomass-based benzene
production for the period 2009-2022.
Universitas Indonesia
5
2009 324689
2010 317522
2011 335986
2012 333558
2013 192322
2014 225414
2015 258506
2016 291597
2017 324689
2018 357781
2019 390873
2020 423964
2021 457056
2022 490148
(Source: Ministry of Industry Indonesia, 2014)
Universitas Indonesia
6
Universitas Indonesia
7
Universitas Indonesia
8
Universitas Indonesia
9
Universitas Indonesia
CHAPTER 2
PROCESS SYNTHESIS
2.1. Process Selection
To determine the process that will be use, it is essential to know the basic
concepts of Benzene production from Biomass. Biomass can be converted into
different form such as Fuels, Power and Chemicals.
The three principal methods of conversion are combustion in excess air,
gasification in reduced air, and pyrolysis in the absence of air. Nowadays, the
most popular methods to process the Biomass to become Aromatics is Pyrolysis.
Pyrolysis technologies are generally categorized as “fast” or “slow” according to
the time taken for processing the feed into pyrolysis products.
10 Universitas Indonesia
11
2.1.1. Gasification
Biomass gasification is a process of converting solid biomass fuel into a
gaseous combustible gas (called producer gas) through a sequence of thermo-
chemical reactions. The gas is a low-heating value fuel, with a calorific value
between 1000- 1200 kcal/Nm3 (kilo calorie per normal cubic meter). Almost 2.5-
3.0 Nm3 of gas can be obtained through gasification of about 1 kg of air-dried
biomass. Since the 1980's the research in biomass gasification has significantly
increased in developing countries, as they aim to achieve energy security.
The Gasifier technology has been customized for a range of direct-heat
application and tested successfully in the field. Silk processing, large-cardamom
drying and gasifier-based crematoria are a few examples of the applications. This
technology is slowly replacing both traditional biomass use and gas-powered
systems, as it provides an excellent de-centralized source of energy at an
affordable cost. There are two main types of biomass gasifier:
Universitas Indonesia
12
and moderate temperatures and short vapour residence time are optimum for
producing liquids. Fast pyrolysis for liquids production is currently of particular
interest as the liquid can be stored and transported, and used for energy, chemicals
or as an energy carrier In fast pyrolysis, biomass decomposes very quickly to
generate mostly vapours and aerosols and some charcoal and gas.
A high yield of liquid is obtained with most biomass feeds low in ash. The
essential features of a fast pyrolysis process for producing liquids are:
1. Very high heating rates and very high heat transfer rates at the biomass
particle reaction interface usually require a finely ground biomass feed of
typically less than 3 mm as biomass generally has a low thermal conductivity,
2. Carefully controlled pyrolysis reaction temperature of around 500 C to
maximize the liquid yield for most biomass,
3. Short hot vapor residence times of typically less than 2 s to minimize
secondary reactions,
4. Rapid removal of product char to minimize cracking of vapors,
5. Rapid cooling of the pyrolysis vapors to give the bio-oil product.
As fast pyrolysis for liquids occurs in a few seconds or less, heat and mass
transfer processes and phase transition phenomena, as well as chemical reaction
kinetics, play important roles.
Liquid yield depends on biomass type, temperature, hot vapor residence
time, char separation, and biomass ash content, the last two having a catalytic
effect on vapor cracking. A fast pyrolysis process includes drying the feed to
typically less than 10% water. Fast pyrolysis liquid has a higher heating value of
about 17 MJ/kg as produced with about 25 wt.% water that cannot readily be
separated.
12 Universitas Indonesia
13
Figure 2. 3. Typical product weight yields (dry wood basis) obtained by different modes of
pyrolysis of wood.
(Source : Ramey David et al., 2010)
13 Universitas Indonesia
14
14 Universitas Indonesia
15
Primary Catalytic
Pre-Treatment Separation
Pyrolisis Cracking
The diagram will be the base for synthesis design. Basically, there are
several steps to convert biomass into benzene. These steps are Pre-Treatment,
Pyrolysis, Catalytic cracking and separation. The pathway of this process are
shown in the figure below.
15 Universitas Indonesia
16
16 Universitas Indonesia
17
size disposition, and the grain shape. This is the step to reduce its size and to
make its size uniform. The uniform powder is 0.3 mm size. The purpose of doing
this step is to reduce Empty palm fruit bunch size so it will enlarge the contact
surface area for the next processing in pyrolysis.
In material processing, a grinder is a machine for producing fine particle
size reduction through attrition and compressive forces at the grain size level. In
general, grinding processes require a relatively large amount of energy. So, this is
the operating condition for grinder as pre-treatment process. Based on Heuristic
50 to produce the 0.33 mm size reduction process and use grinder.
17 Universitas Indonesia
18
Figure 2. 8. Catalytic reaction route for the convention of pyrolysis vapors with Zeolit catalyst.
(Source : Cheng et al., 2010)
Hence, the most suitable reactor for CFP of biomass is CFB combined with
catalyst regenerator which is similar to a fluid catalytic cracking (FCC) unit in
petroleum refining industry. The pyrolysis vapors were then contacted with
catalyst to form aromatics and olefins. The spent catalysts, char, and hot product
vapors were trans- ported into cyclones (strippers) and were separated therein.
The spent catalysts mixed with char were subsequently burnt in a combustion bed
for regeneration. The regenerated catalysts were recycled to the riser for heat
carrier and reuse. The liquid production was obtained by the condensation and
collection of hot product vapors from cyclones, and the flue gas was recycled as
carrier gas. An advantage of CFB reactor is that it can be used at very high
18 Universitas Indonesia
19
throughputs.
Figure 2. 10. Process Block Flow Diagrams of in situ CFP and ex situ CFP.
(Source: Royal Society of Chemistry,2013)
However, owing to the short residence time of the pyrolysis vapor in the
in-situ CFP process, a high catalyst-to-biomass ratio is necessary to ensure a
better upgrading result and a higher yield of the liquid hydrocarbon products. In
19 Universitas Indonesia
20
20 Universitas Indonesia
21
most suitable catalyst to produce Benzene is TNU-9 and 𝛽 zeolite, because it has
selectivity more than 30% for benzene.
Figure 2. 12. Aromatic selectivity from CFP of glucose over different zeolites.
(Source: John Wiley & Sons Ltd, 2016)
21 Universitas Indonesia
22
22 Universitas Indonesia
2.3. Block Flow Diagram
Process consist of two main process, those are Pre-treatment and Main Process section. The block flow diagram of our plant can be
seen in Figure 2.14. and 2.15. below.
23 Universitas Indonesia
2.4. Process Flow Diagram
2.4.1. Pre-Treatment
24 Universitas Indonesia
2.4.2. Main Process
25 Universitas Indonesia
26
Mass Flow
Stream
In (kg/hr) Out (kg/hr)
Water 29024.7 55845.1
Air 0 4967
Biomass 66555.3 0
Benzene 0 20860.8
Hidrokarbon lain 0 13907.1
Total 95580 95580
Energy
Unit
In (106 kJ/day) Out (10^6 kJ/day)
M-100 1.08 0
G-100 1.08 0
R-100 0 1.231
E-100 1.74 0
E-101 1.963 0
V-100 1.61 0
V-101 0 3.486
V-102 0 2.756
TOTAL 7.47 7.473
Universitas Indonesia
27
9271.67 𝑘𝑔/ℎ𝑟
Mass Efficiency = 66555.1976 𝑘𝑔/ℎ𝑟 𝑥 100%
Universitas Indonesia
28
𝐻 =𝑄±𝑊 (2.1)
In heat exchanger, no mechanical work is being performed
𝑊 = 0 (𝑧𝑒𝑟𝑜) (2.2)
The above equation simplifies to
𝐻=𝑄 (2.3)
No. Stream In Stream Out Tin (°C) Tout (°C) T*in (°C) T*out (°C)
1 2 3 25 145 30 150
2 3 4 145 653 150 658
3 4 8 653 600 648 595
4 8 12 600 80 595 75
5 12 13 80 327 85 332
6 13 17 327 25 322 20
The basic approach can be developed into a formal algorithm known as the
problem table algorithm. The algorithm will be explained using the data from
Table 1.1 for ΔTmin. The first step is determined the shifted temperature intervals
(T*) from actual supply and target temperatures. Hot streams are shifted down in
temperature by ΔTmin/2 and cold streams up by ΔTmin/2 as detailed in Table 1.2.
Universitas Indonesia
Table 2. 9. Temperature Interval Heat Balance
29 Universitas Indonesia
30
After we have the problem table, we can cascade any surplus heat down
the temperature scale from interval to interval. This is possible any excess heat
available from the hot streams in an interval is hot enough to supply a deficit in
the cold streams in the next interval down. From the figure above, we can
determine the minimum utility requirement.
31 Universitas Indonesia
CHAPTER 3
EQUIPMENT DESIGN
3.1. Reactor
3.1.1. Fast Pyrolysis Reactor
32
33
Equipment Specification
Equipment Name Catalyst Regenerator
Equipment Code R-100
Function Regenerate catalyst
Number of Unit 1
Material SS 316
Operation Data
o
Regenerator Temperature ( C) 700
Catalyst Circulation Rate
40
(kg/m2s)
Pressure (atm) 1
Dimension
Regenerator Height (m) 6.59
Regenerator Diameter (m) 2.20
Regenerator Volume (m) 24.96
Regenerator Thickness (m) 9.35
3.2. Storage Tank
3.2.1. Biomass Warehouse
Universitas Indonesia
34
Equipment Specification
Equipment Name Demineralize Water Tank
Universitas Indonesia
35
Equipment Specification
Storage Type Liquid Storage
Function Storage for Demineralize Water
Number of Unit 1
Material Carbon Steel SA 167
Type of Tank Cylinder Vertical Concrete Foundation
Type od Head Flat Head
Operation Data
Temperature (oC) 25
Pressure (atm) 1
Mass Flow (kg/day) 76314
Bulk Density (kg/m )3 1004
Dimension
Capacity (kg/day) 76314
Volume tank (m3) 83.61
Volume of Liquid in Tank (m3) 76
Tank Diameter (m) 8.53
Tank Height (m) 17.062
Height of Liquid in Tank (m) 15.335
Design Pressure (bar) 2.88
Hydrostatic pressure (bar) 1.51
Shell Thickness (in) 0.52
Head Thickness (in) 1.84
3.2.4. Coagulant Tank
Equipment Specification
Equipment Name Coagulant Tank
Equipment Code
Number of Vessel 1
Type Rigid Base Circular
Determination of Diameter of the Water Tank
Mass Flow Rate 3197.5 kg/h
Density 1004 kg/m3
Volume 221.73 m3
Height 4.40 M
Diameter 8.40 M
Free board 0.40 M
Wall Thickness 6 Mm
Design of Base
Thickness of base 6 Mm
Universitas Indonesia
36
Equipment Specification
Equipment Name Filtration Tank
Equipment Code T-502
Function To Filter Suspended Solid (SS)
Number of Unit 4
Filter Specification
Filter Type Slow Sand Filter
Total Surface Area (m2) 267.1425
Max. Surface Per filter (m2) 50
Number of Filters 6
Surface Area per Filter (m2) 44.53
Dimension
Filtration Rate (m/h) 0.2
Required Tank Area (m2) 356.19
Long (m) 25
Width (m) 15
Height (m) 2.4
3.2.6. Ion Exchanger Tank
The ion exchanger is the essential equipment in water pretreatment
process. The final product of water utility would be demineralized water. This is
because the water that would be sent to oxygen plant which will be used in
absorption column required the demine water. If cation or anion is not removed,
there will be a contamination in absorption process. From the sizing calculation,
the specification of the ion exchanger is shown on table below
Universitas Indonesia
37
Unit: E-100
Operating Condition
Data Shell Side Tube Side Unit
Fluid Stream 43 6
Fluid Flow 22308 1328 kg/h
Temperature in 123 5 °C
Temperature out 243 100 °C
Operating pressure 1000 1000 kPa
No. of passes 1 2
Universitas Indonesia
38
Operating Condition
Fouling factor 0,00009 0,00009 m2 °C/W
Heat Duty 429 kW
LMTD 72 °C
Overall U 619 W/m2 °C
Dimension
Type of unit Fixed tube
Unit: E-101
Operating Condition
Data Shell Side Tube Side Unit
Fluid Stream 33 5
Fluid Flow 22308 1328 kg/h
Temperature in 5 486 °C
Temperature out 122 50 °C
Operating pressure 900 412 kPa
No. of passes 1 2
Fouling factor 0,00009 0,00009 m2 °C/W
Heat Duty 429 kW
LMTD 119 °C
Overall U 620 W/m2 °C
Dimension
Type of unit Fixed tube
Universitas Indonesia
39
Dimension
Tube OD 19,500 mm
Tube Length 4,880 m
Shell IDE 0,540 m
Tube Pitch 24 mm
Tube Thickness 1,650 mm
Number of tubes 30
Tube arrangement Triangular
3.3.3. Heat Exchanger (H-100)
Unit H-100
Operating Condition
Data Shell Side Tube Side Unit
Fluid Stream 5 3
Fluid Flow 22308 22308 kg/h
Temperature in 125 125 °C
Temperature out 100 700 °C
Operating pressure 100 1000 kPa
No. of passes 1 4
Fouling factor 0,00009 0,00009 m2 °C/W
Heat Duty 432 kW
LMTD 137 °C
Overall U 3188 W/m2 °C
Dimension
Type of unit Fixed tube
Material SS-316 atau SA-240
Heat Transfer Area 6,316 m2
Tube OD 20,150 mm
Tube Length 4,880 m
Shell IDE 0,540 m
Tube Pitch 25 mm
Tube Thickness 0,710 mm
Number of tubes 5
Tube arrangement Triangular
Universitas Indonesia
40
3.4. Distillation
3.4.1. Distillation Column
Universitas Indonesia
41
Universitas Indonesia
42
3.6. Conveyor
3.6.1. Elevator Conveyor
Universitas Indonesia
43
Equipment Specification
Equipment Name Hammer Mill
Equipment Code
Function Grinder
Number of unit 1
Material Carbon Steel
Type Hammer Mill Grinder
Operation Data
Rotate Speed (r/min) 800
Pressure (atm) 1
Capacity (ton/h) 50-70
Output Size (mm) 0.01-1
Power Requirement (kWh/hour) 377.502 kWh/hour
Dimension
Width (m) 2.1
Height (m) 1.8
Length (m) 1.8
3.8. Filter Plate & Frame
This section explains the sizing and specifications for plate & frame filters
used in benzene production plant.
Equipment Specifications
Equipment Name Plate and Frame Filtration
Equipment Code P&F-101
Separate lignin from other component
Function
such as hemicellulose, cellulose, etc.
Number of Unit 1
Type Hydraulic pressure/mechanical pressure
Operation Data
Temperature 162 oC
Pressure 1.013 bar
Flow rates 4,880,000 kg/hour
Universitas Indonesia
44
Construction Data
Filter Area 93 m2
Filtrate Volumetric 22.514 L
Number of filter plates 64
Number of filter cells 65
The thickness of filter cake (cm) 15
3.9. Cyclone
3.9.1. Cyclone (Cy-100)
Equipment Specification
Equipment Name Cyclone
Equipment Code Cy-100
Function Gas-solid separator
Number of unit 1
Material Carbon Steel
Type Cyclone Separator
Operation Data
Pressure (kPa) 1.013
Temperature (oC) 600
Volumetric flow rate 626526
Particle diatemer (m) 0.005
Grade efficiency (%) 97
Pressure drop (millibar) 130
Construction Data
D0 (m) 0.15
DB (m) 0.2
W (m) 0.08
S (m) 0.2
Hc (m) 0.3
H (m) 0.8
A (m) 0.15
B (m) 0.08
Universitas Indonesia
45
Equipment Specification
Equipment Name Cyclone
Equipment Code Cy-101
Function Gas-solid separator
Number of unit 1
Material Carbon Steel
Type Cyclone Separator
Operation Data
Pressure (kPa) 1.013
Temperature (oC) 700
Volumetric flow rate 560428
Particle diameter (m) 0.005
Grade efficiency (%) 97
Pressure drop (milibar) 130
Dimension
D0 (m) 0.15
DB (m) 0.2
W (m) 0.08
S (m) 0.2
Hc (m) 0.3
H (m) 0.8
A (m) 0.15
B (m) 0.08
Universitas Indonesia
46
Equipment Specification
Equipment Name Gas Compressor
Equipment Code C-100
To compress air that will use for HE
Function And flash drum
Amount 1
Material Carbon Steel
Operation Data
Inlet Temperature (K) 353
Discharge Temperature (K) 664,4735
Inlet mass flow rate (ton/day) 222,789
3.11. Pump
3.11.1. Screw Pump (P-101)
Universitas Indonesia
47
Operation Data
Density (kg/m3) 1007
Temperature (⁰C) 5
Differential Pressure (Pa) 57,000
Specification Design
NPSHa (m) 47.09
NPSHr (m) 45.51
Head (m) 92.03
FHP (kW) 2.42
BHP (kW) 24.20
3.11.2. Water Pump (P-102)
Equipment Specification
Equipment code P-102
Pump Type Centrifugal Pump
Function Pump for water to Heat Exchanger (B6)
Mode of Operation Continuous
Material Carbon Steel
Operation Data
Water Liquid
Mass flow (kg/s) 83.33
Flow rate (m3/s) 0.082754
Density (kg/m3) 1007
Temperature (⁰C) 5
Differential Pressure (Pa) 420,000
Specification Design
NPSHa (m) 9.37
NPSHr (m) 10.05
Head (m) 60.49
FHP (kW) 43.48
BHP (kW) 49.40
3.11.3. Water Pump (P-103)
Equipment Specification
Equipment code P-103
Pump Type Centrifugal Pump
Function Pump for water to Heat Exchanger (B7)
Universitas Indonesia
48
Equipment Specification
Mode of Operation Continuous
Material Carbon Steel
Operation Data
Water Liquid
Mass flow (kg/s) 257.56
Flow rate (m3/s) 0.255766
Density (kg/m3) 1007
Temperature (⁰C) 5
Differential Pressure (Pa) 312,000
Specification Design
NPSHa (m) 12.49
NPSHr (m) 10.05
Head (m) 48.23
FHP (kW) 91.31
BHP (kW) 121.75
Universitas Indonesia
CHAPTER 4
PROCESS CONTROL STRATEGY
There are three elements that must install at the system control to make
sure that our process doing well. Each of elements has its own function
1. Transmitter, which is used for indicate the recent condition of equipment.
Transmitter will always sent electric signal to indicator controller.
2. Indicator controller, which is used for receive the electric signal from
transmitter and determine the decision for final executed which will executed
directly by actuator or final element. Indicator controller always mounted at
the control room, so the operator on control room can monitor the process
condition and make the final instruction.
3. Actuator or final element, which is used for directly execute toward the
process after get an instruction from operator at the control room. The final
element generally formed as control valve.
This kind of controller should
always exist at the main equipment that has
a big influence for our process
and equipment that contain a hazardous material or process. So this control
system will monitor and guide the equipment to always run at the setting
condition.
49
Universitas Indonesia
4.1. Plant Control Tabulation
Table 4. 1. Control Details
Location
Manipulated of
No Device Control Variable Controller Control Sequence of instrumentation
Variable
Valve
When the temperature of the CSTR is not fit with the
wanted condition, the TI will give an electric signal to
Feed Cooling water Out CSTR
PI TC and then transfer that signal into a pneumatic signal
Temperature rate Reactor to flow control valve at the cooling water until the
condition become normal
CSTR
1 Reactor
(R-100) When the pressure of the CSTR is higher than the
Pressure of Feed CSTR design pressure, the pressure control valve will open to
Reactant flow
Reactor PI Reactor reduce the pressure on the CSTR
rate
50 Universitas Indonesia
Table 4.1. Control Details (continued)
Control Location of
No Device Variable Manipulated Variable Controller Control Valve Sequence of instrumentation
Release more gas to decanter
Pressure Pressure Safety Valve if pressure in column
distillation PI Top product line distillation II reach the set
point
51
Universitas Indonesia
Table 4.1. Control Details (continued)
52
Universitas Indonesia
4.2. Piping and Instrumentation Diagram
4.2.1. Pre-Treatment
53
Universitas Indonesia
4.2.2. Main Process
54
Universitas Indonesia
CHAPTER 5
PLANT LAYOUT
55
Universitas Indonesia
56
Universitas Indonesia
57
Universitas Indonesia
Figure 5. 4. Area Plant Layout
58
Universitas Indonesia
5.2. Equipment Plant Layout
59
Universitas Indonesia
60
Based on Figure 5.5, the first process stream, empty fruit bunch will be
sent to the ball mill to reduce its size. The grinded empty fruit bunch then will be
sent to the hydrolysis using bucket conveyor. In hydrolysis reactor, lignin was
produced and heated before enters catalytic fast pyrolysis reactor. In catalytic fast
pyrolysis reactor, the product will be fluidized and brought to the cyclone. In
cyclone, pyrolysis product and char will be separated. The product then will be
cooled, condensed, and sent to the three-phase separator to separate volatile gas,
aromatic product, and the water. Aromatic component will be separated into
phenol and BTX by distillation. BTX will also be separated by distillation with
benzene as the main product and toluene & xylene as by-product. The catalyst in
catalytic cracking reactor will be ineffective after some time of using because of
coke formation. The catalyst will be regenerated using combustion process in
catalyst regenerator. The air for combustion process will have some pre-heating
process through some of heat exchangers in our plant.
Besides the main process, benzene plant also has water treatment to pump
water into heat exchanger. The water is placed in a settling pit to separate the
sand and other particle. The water from settling pit then will be sent to
demineralizer tank to remove its mineral before used as cold utility. After used as
cold utility, the water will experience temperature increase until reach temperature
of 100oC. To use the energy in our utility, the water will be sent to boiler where
heating process is done and the water will be evaporated into superheated steam.
The superheated steam then will be used to rotate a turbin and produce energy.
The output from turbine will be condensed to make sure that there will be no
vapor sent to the pump.
Universitas Indonesia
61
CHAPTER 6
HEALTH AND ENVIRONMENTAL SAFETY ASSESSMENT
Universitas Indonesia
62
Universitas Indonesia
63
Universitas Indonesia
64
a chance to conduct the same tests. All shifts should be given the opportunity to
start up and shutdown each closed loop test.
Universitas Indonesia
65
Open utility valve for cooling water, oxygen, fuel, air, etc then check the
temperature.
All parameter in instrument which need controlling must be set, such as
pressure and temperature. This step to ensure the equipment under
condition.
Turn on the pump to deliver Lignin to process equipment.
Prepare the reactor for the process. This step is maintained the temperature
and pressure in reactor. This is to avoid the shock in reactor.
Prepare gas for the process of fast pyrolysis and catalytic cracking.
After temperature and pressure reached, the raw material is put to the
process.
Preparing the cyclone and blower to assist the material transport process
and to suck the air out of the atmosphere.
Preparing to start up the compressor and Heat Exchanger.
Preparing the flash drum and ensure the temperature and pressure in
accordance with the specification.
Preparing to start up the distillation column and ensure the temperature
and pressure in accordance with the specifications.
The preconditioning is done for 1 – 4 hours to see if the reaction occurs or
not.
If the reaction does not occur, the startup procedure should be repeated.
6.2.1.2. Shut Down Process
Shut Down for Pre-Treatment System
The Emergency Shutdown System (ESD) shall minimize the
consequences of emergency situations, related to typically uncontrolled flooding,
escape of hydrocarbons, or outbreak of fire in hydrocarbon carrying areas or areas
which may otherwise be hazardous. The safety shutdown systems based on the
following procedures:
a. Emergency Shutdown
Manual alarm
Shutdown all transportation of gas, liquid, and solid.
Universitas Indonesia
66
Universitas Indonesia
67
complete health and safety program. It also contains information on the use,
storage, handling and emergency procedures all related to the hazards of the
material. The MSDS contains much more information about the material than the
label. MSDSs are prepared by the supplier or manufacturer of the material. It is
intended to tell what the hazards of the product are, how to use the product safely,
what to expect if the recommendations are not followed, what to do if accidents
occur, how to recognize symptoms of overexposure, and what to do if such
incidents occur.There is a common symbols used on labels to quickly provide
information of the relative hazards of a material. Most of company use the
National Fire Protection Association (NFPA) warning diamond, which appears in
figure below.
Universitas Indonesia
68
Universitas Indonesia
69
the alarm, then let others know there is a fire, then to combat the fire if possible,
and finally, to evacuate if necessary. The plan works best when expressed as an
easily recalled acronym, such as SAFE:
a. S – Sound the alarm
Sound it yourself or call out to someone else to sound it. This allows the fire
department to be on its way while other activities are being performed.
b. A – Alert others
Quickly tell others in the area of the fire. Do this in a calm, firm manner. Do not
cause a panic. Secure the area for the fire department. Close all doors and
windows to prevent the spread of smoke and flames. Call security to give
verification and information about location of fire.
c. F – Fight the fire
Do this only in the case of a manageable fire, one that you have the training and
experience to fight. For example, fire in a wastebasket. If possible, two employees
should fight the fire together using two fire extinguishers. If you have any doubt
about your ability, then do not attempt to combat it.
d. E – Evacuate the area (if necessary)
There are some possible emergency situation to be happened and action that can
be done to minimize the effect from that emergency situation such as
o Gas Leak
When suspecting there are gas leak, safety procedure are as follow :
Avoid inhaling vapors and contact with liquid or gas
Turn off the supply also close the emergency shutdown valve (ESDV)
Never operate any valves when being panic, because a wrong action
although just a simple action will cause to another new emergency situation
Close the doors, windows or any gaps to block off the air vents if the leak is
near the building. It is done to prevent the gas from getting into the building.
Move and evacuate the people upwind from the gas leak-area.
Avoid any action which could generate smoke, such as smoking, turning is
the vehicle engine, etc.
Immediately call the local fire station
Universitas Indonesia
70
If in doubt, evacuate the building and inform the police as well as the
National Gas Emergency Service or your gas supplier
Gather with others in the muster point nearby
o Accident of Equipment
When there is accident from equipment, safety procedure are as follow
Check whether there are any leakage or not
Move people away from the area and gather in assembly point
Call the brigade, police and also ambulance
6.4.2. Emergency Alarm and Fire Fighting Equipment
There are several kinds of alarm to be used in our plant. All of alarm which used
for evacuation system has been meet the alarm system standard from OSHA. It
applies to provide an early warning for emergency actions or reaction time for
employees to safely escape the work place, the immediate work area, or both.
Type of alarms which used in this plant:
a. Audible Alarm
Audible alarm which used consists of horn and sirens. Horns produce a very loud
distinctive sound that immediately attracts attention. Horns can be useful to call
attention to critical situations. Signals other than those used for evacuation
purposes do not have to produce the temporal coded signal. Thus, sirens produce a
loud piercing wail that makes them ideally suitable for initiating a site-wide
evacuation.
b. Visible Alarm
Visual alarm which used consists of flashing/steady lights and strobe lights.
Steady lights are well suited for areas where ambient noise makes audible signals
difficult to hear, for an example in area where the compressor is in. These types of
lights come with different colored covers for increased attention and can be
ordered with rotating or flashing lights. Strobe lights use high intensity flash
tubes that are ideally suited for areas where high ambient light levels make
traditional rotating or flashing lights difficult to distinguish or where ambient
noise makes audible signals difficult to hear.
Universitas Indonesia
71
For firefighting, our plant has some equipment installed such as light fire
extinguisher (APAR), hydrant, and safety shower. As for firefighting equipment
should consider some parameter such as:
Appointment of fire wardens with subsequent training
Location of safety shower, fire hose, extinguisher and water sources
Access for emergency services
Provision of firewater lagoons
6.4.3. Emergency Escape Procedures and Route
The purpose of the escape procedure is to help the employee evacuate to be
predetermined assembly areas whenever the alarm sounds. Here is the procedure
of emergency escape:
a. In the event of an emergency, employees shall activate fire pull stations
without exposing themselves to serious hazards and leave the work area as
soon as possible via the emergency route assignments posted in immediate
work area.
b. All primary emergency escape routes and designated meeting locations shall
be provided to each employee by departmental managers as part of the
emergency planning process. These primary route and designated meeting
locations must be approved by the plant manager.
c. An orderly evacuation shall be supervised by departmental managers, line
supervisors, and designated wardens who will check all rooms/enclosed
spaces and report any problems via telephone or radio to plant security.
d. Each local manager or supervisor shall provide for the specialized
evacuation of any handicapped employees.
Next is about assembly point and the route from any side of our plant to go
to that assembly point. Escaping route should be the shortest and safest way to go
to assembly or meeting point in order to minimize after effect from emergency.
The Figure 6.10 will explain the escape route based on the plant layout.
Universitas Indonesia
72
Universitas Indonesia
73
Universitas Indonesia
74
generated noise will be equipped with ear plug in order to dampening noise.
Using ear plug can decrease noise up to 20dB so that they can keep working in the
save area.
Universitas Indonesia
CHAPTER 7
ECONOMIC ANALYSIS
PROJECTION
800
500
400
300
200
100
0
1995 2000 2005 2010 2015 2020 2025
75
Universitas Indonesia
76
(7.1)
So, in equipment cost calculation, cost each equipment in reference year is
multiplied by ratio of its CEPCI.
7.1.2. Capital Expenditure (CAPEX)
Capital expenditure should be known for convenience in cost accounting
and cost estimation. This expenditure is a one-time expense for the design,
construction, and start-up of a new plant or a revamp of an existing plant. As a
project for manufacturing a new or existing chemical by a new process progresses
from laboratory research through pilot plant development to a decision for plant
construction, a number of process-design studies of increasing complexity may be
made, accompanied at each step by capital-cost estimates of increasing levels of
accuracy as follows: order-of-magnitude estimate, study estimate, preliminary
estimate, and definitive estimate. The one which has been done up to this step is
the preliminary estimate.
Preliminary estimate is based on the individual factors method of Guthrie,
1969, 1974. This method is best carried out after an optimal process design has
been developed, complete with a mass and energy balance, equipment sizing,
selection of materials of construction, and development of a process control
configuration as incorporated into a P&ID. To apply the method, the f.o.b.
purchase cost of each piece of major equipment must be estimated. The equation
for the total capital investment by Guthrie method is
Universitas Indonesia
77
Total Bare-
Direct CTBM 100,249,369 Calculated
Module Cost
Cost
Universitas Indonesia
78
Universitas Indonesia
79
In Figure 1.2 is shown the breakdown of TCI. Direct cost is the highest cost in
TCI.
Universitas Indonesia
80
Universitas Indonesia
Table 7. 5. Raw Material Costs
Price
Annual Total Order Shipping
per Total Shipping Total Cost
Material Supplier Location Order Cost per Year Cost
tonnes per year (US$) (US$)
(tonnes) (US$) (US$/ton)
(US$)
Empty Fruit PT. Adikarya Bandar
642000 $ 10.0 6,420,000 $ 12.00 $7,704,000.00 $14,124,000.00
Bunch Gemilang Lampung
Custom ZSM-5
Catalyst Beijing 2000 $ 100.0 200,000 $ 2,800.00 $5,600,000.00 $5,800,000.00
Co., Ltd
Total (Rp) $644,000.00 $110.00 $6,620,000.00 $2,812.00 $13,304,000.00 $19,924,000.00
81
Universitas Indonesia
82
Universitas Indonesia
83
Universitas Indonesia
84
Universitas Indonesia
85
Total Price/year
$ 61,060.03
This plant use water that obtained from the river for process and utility.
The water treatment cost is approximately $ 0.67/m3 water (BPPT, 2015).
Universitas Indonesia
86
This plant needs fuel for generator which is solar and we buy it from PT.
Pertamina.
Universitas Indonesia
87
We also have to pay the tax of land & building. The amount is shown
below
Universitas Indonesia
Table 7. 15. Tax of Salary
Net
Salary per Insurance Total Net
Amount Bruto Position Income Taxable Salary Tax
Position month per per Insurance Income
(person) Income Cost per Income per year
person ($) month per year per year
Month
President Director $3,500.00 1 210 2,520.00 3,710.00 185.50 3,524.50 42,294.00 39,405.11 1,970.26
Secretary of
$1,000.00 1 60 720.00 1,060.00 53.00 1,007.00 12,084.00 9,195.11 459.76
President Director
Finance Manager $1,500.00 1 90 1,080.00 1,590.00 79.50 1,510.50 18,126.00 15,237.11 761.86
Assistant Finance
$900.00 2 54 1,296.00 954.00 47.70 906.30 10,875.60 7,986.71 798.67
Manager
HR and Legal
$800.00 1 48 576.00 848.00 42.40 805.60 9,667.20 6,778.31 338.92
Manager
Training Coordinator $450.00 1 27 324.00 477.00 23.85 453.15 5,437.80 2,548.91 127.45
HSE Engineer $650.00 2 39 936.00 689.00 34.45 654.55 7,854.60 4,965.71 496.57
Production Manager $1,500.00 1 90 1,080.00 1,590.00 79.50 1,510.50 18,126.00 15,237.11 761.86
Process and Facility
$850.00 3 51 1,836.00 901.00 45.05 855.95 10,271.40 7,382.51 1,107.38
Engineer
Maintenance
$750.00 2 45 1,080.00 795.00 39.75 755.25 9,063.00 6,174.11 617.41
Coordinator
Operational $800.00 2 48 1,152.00 848.00 42.40 805.60 9,667.20 6,778.31 677.83
88
Universitas Indonesia
Table 7. 16. Tax of Salary (continued)
Net
Salary per Insuranc Total
Amount Bruto Position Income Net Income Taxable Salary Tax
Position month per e per Insurance
(person) Income Cost per per year Income per year
person ($) month per year
Month
Product Planning and
Development $1,000.00 1 60 720.00 1,060.00 53.00 1,007.00 12,084.00 9,195.11 459.76
Manager
Product Distribution
$750.00 1 45 540.00 795.00 39.75 755.25 9,063.00 6,174.11 308.71
Supervisor
Marketing Executive $850.00 1 51 612.00 901.00 45.05 855.95 10,271.40 7,382.51 369.13
Marketing Staff $600.00 2 36 864.00 636.00 31.80 604.20 7,250.40 4,361.51 436.15
Supply Chain
$900.00 1 54 648.00 954.00 47.70 906.30 10,875.60 7,986.71 399.34
Manager
Security $350.00 4 21 1,008.00 371.00 18.55 352.45 4,229.40 1,340.51 268.10
Receptionist $450.00 2 27 648.00 477.00 23.85 453.15 5,437.80 2,548.91 254.89
Cleaning Service $325.00 2 20 468.00 344.50 17.23 327.28 3,927.30 1,038.41 103.84
Office Boy/Girl $325.00 3 20 702.00 344.50 17.23 327.28 3,927.30 1,038.41 155.76
Operator $375.00 12 23 3,240.00 397.50 19.88 377.63 4,531.50 1,642.61 985.57
Labour $350.00 12 21 3,024.00 371.00 18.55 352.45 4,229.40 1,340.51 804.31
Technician $375.00 6 23 1,620.00 397.50 19.88 377.63 4,531.50 1,642.61 492.78
Total 19,350 64 1,161 26,694.00 20,511.00 1,025.55 19,485 233,825.40 167,380. 13,156.27
89
Universitas Indonesia
90
Universitas Indonesia
91
2% 8%
Raw Material
Indirect Labor Salary
Direct Labor Salary
26%
Utilities
61% Maintenance
Insurance and Tax
General Expenses
0% 1%
2%
Universitas Indonesia
92
Universitas Indonesia
93
7.3.2.1. Equity
On the first year of cash flow the capital of this plant is loan from
institution like bank or investor. Bank is chosen based on the minimum rate of
interest, which is Bank Negara Indonesia with 10.25% of interest rate. Beside
bank, loan of investor is needed with 13% of interest rate. The higher the interest,
investors will be more interested in investing, but investors are constrained by the
high interest rate bank loan. The 60% of capital comes from bank and 40% from
investors. All loans are paid in 10 years. The detail scheme of payment is shown
below
Universitas Indonesia
94
Universitas Indonesia
95
7.3.2.2. Depreciation
Depreciation is the reduction in value of an asset. The way to depreciate an
asset is a way to account for the decreasing value of the asset to the owner and to
represent the diminishing value of capital funds invest. Salvage value is the
estimated trade-in or market value at the end of the asset’s useful life. The salvage
value, S expressed as an estimated dollar amount or as a percentage of the first
cost, may be positive, zero, or negative due to dismantling and carry-away costs.
The list of all equipment has been elaborated in Capital Expenditure section.
In this plant design, equipment and building as our assets. The equation used in
this declining balance method of depreciation is: (Blank & Tarquin: 5th edition.
Ch.16 Authored by Dr. Don Smith, Texas A&M University):
Universitas Indonesia
96
Where:
dmax = maximum depreciation rate
dt = depreciation rate for t-year
t = year of depreciation
The depreciation rate is for main equipment, supporting and also building.
The assumption of 10% is according to main depreciation for national assets. The
Deppreciation calculation can be seen in Appendix.
7.3.3. Profitability Analysis
In profitability analysis, different methods are used for each alternative
equipment lines with its alternative location. The method will be used are WACC,
Rate of Investment (ROI), Payback Period, Net Present Value (NPV), Break Even
Point (BEP), and Internal Rate of Return (IRR).
7.3.3.1. WACC
Weighted average cost of capital (WACC) is the average rate of return a
company expects to compensate all its different investors. The weights are the
fraction of each financing source in the company's target capital structure.
Before the new business is started or developed, first thing to do is an
experiment about the business that will be held, which will be advantageous or not.
To determine a project feasible or not to do, it is necessary a feasibility analysis of
investment. Investment is called feasible if it gives more profit than the expected.
Expected minimum profit are commonly known as the MARR, while profits are
calculated on the investment feasibility analysis are known as the IRR. MARR is
calculated using WACC (Weighted Average Cost of Capital).
WACC = E/V × Re + D/V × Rd × (1 − tax rate) (7.1)
Where,
E = market value of the firm’s equity
Universitas Indonesia
97
rejected. The payback period for this plant is 4.066 years, after calculate use
Microsoft Excel.
Our payback period is matched with the rule of thumb. The rule of thumb
said that the tolerable payback period is about 10 years and should be done after
all the loan are fully paid.
7.3.3.4 Break Even Point (BEP)
Breakeven point (BEP) is an analysis to determine and find the amount of goods
or services to be sold to consumers at a given price to cover the costs incurred and
the profit. Calculation to find the BEP is:
𝑇𝑜𝑡𝑎𝑙 𝐹𝑖𝑥𝑒𝑑 𝐶𝑜𝑠𝑡
𝐵𝐸𝑃 = (7.4)
(𝑃𝑟𝑖𝑐𝑒 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 − 𝑉𝑎𝑟𝑖𝑎𝑏𝑙𝑒 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡)
The total fixed cost is the fixed cost values tend to be stable and not
influenced by the amount of production and the variable cost is the variable cost
of the value depends on the amount of goods produced. This BEP value shows
that we have to produce and sell at least 298,580 tons of benzene to get the
investor money back with interest.
7.3.3.5 Internal Rate of Return (IRR)
Internal Rate of Return (IRR) is a measure of the maximum of interest rate
paid on project and still break even at the end of the project life. In other words,
the IRR is the interest rate when NPV = 0, so that the formula used to calculate
the IRR is:
𝑛=𝑇
𝐶𝐹𝑛
𝑁𝑃𝑉 = ∑ − 𝑇𝐶𝐼 = 0 (7.5)
(1 + 𝑟)𝑛
𝑛=1
With the value of r is the IRR. Calculating cash flow by using Microsoft excel,
IRR of 13% from benzene plant can be obtained. Compared the IRR with MARR
(12% (IRR) > 5% (MARR)), the difference is quite high (7%). According to the
definition of IRR itself, it means that IRR will be used to compare the working
capital as project with minimum probability.
7.3.3.6. Net Present Value (NPV)
Net Present Value (NPV) is the difference between the present value of
cash inflows and the present value of cash outflows. NPV is used in capital
Universitas Indonesia
99
where:
Ct = net cash inflow during the period t
Co = total initial investment costs
r = discount rate, and
t = number of time periods
A positive net present value indicates that the projected earnings generated
by a project or investment (in present) exceeds the anticipated costs (also in
present). Generally, an investment with a positive NPV (NPV > 0) will be a
profitable one and one with a negative NPV (NPV < 0) will result in a net loss.
This concept is the basis for the Net Present Value Rule, which dictates that the
only investments that should be made are those with positive NPV values.
From the calculation, this plant project’s NPV value is 136.626.246 It
shows that the project is not feasible to be done in 2020 because the NPV value is
less than 0. It will be examined in sensitivity analysis about this loss.
Sensitivity Analysis
7.3.3.7. Sensitivity Analysis
Sensitivity analysis is an approach to identify the effect of several
parameter’s fluctuations on economic analysis. It is done when the plant face an
unstable condition due to many factors such as selling price fluctuations, raw
material fluctuations, and direct operating labor’s salary fluctuations. This factors
are chosen because on general literature which usually used in factory in
determining value factor influence income per year. those parameters can be
increased or decreased based on the condition. Then analysis gives decision in the
factory benefit or losing for the company.
Universitas Indonesia
100
The first sensitivity analysis is done with decreasing and increasing the
product price. The selling price of products is one of the important variables that
can affect the stability of production because these variables will determine the
revenue and profit to be earned by the industry.
For the operational cost change, we choose to change the raw material
cost. Changes in the cost of material which takes a lot of portion in operational
cost can affect the cost of production in the factory, so that it can be used to
analyze the stability of the project. The cost of raw materials may fluctuate,
considering the price of raw materials is determined by suppliers and distribution
of raw materials also tend to change due to changes in fuel oil. The calculation of
economic feasibility parameters to changes in operating costs is below.
Maintenance cost is the incremental cost that should considered to our
plant. Maintenance can be effect in product capacity in our plant. The fluctuation
of maintenance cost will influence net present values and influence the operating
cost, so that the IRR and payback period is affected.
80,000,000,000
60,000,000,000
40,000,000,000
20,000,000,000
0
-20% -15% -10% -20,000,000,000 0%
-5% 5% 10% 15% 20%
-40,000,000,000
-60,000,000,000
Deviation
Universitas Indonesia
101
Deviation vs IRR
18.00%
16.00%
14.00%
12.00%
10.00%
IRR
8.00%
6.00%
4.00%
2.00%
0.00%
-20% -15% -10% -5% 0% 5% 10% 15% 20%
Deviation
7.000
6.000
5.000
4.000
3.000
2.000
1.000
0.000
-20% -15% -10% -5% 0% 5% 10% 15% 20%
Deviation
Universitas Indonesia
102
CHAPTER 8
OUSTANDING ISSUE
Universitas Indonesia
Figure 8. 1. PT Trans Pacific Petrochemical benzene plant Plant Diagram
The other issue is about the production capaity per year. Our production
capacity is small, comared to other benzene plant that exist in Indonesia, such as
PT Chandra Asri, PT Trans Pacific Petrochemical Indotama, Skyrindo Mono
Indonesia Industri,etc. Comparasion of the production capacity between the
Benzene plant in Indonesia is summarize in the table below:
103
Universitas Indonesia
104
PBP
Plant CAPEX (million IRR
(Years)
US$)
We are going to make profit from our plant . From the Table 8.2, we can
see that investment of our plant is acceptable compared to the existing plant. The
economical comparative mostly is quite same with this company. However, our
plant has IRR smaller than the existing Benzene plant.. From economic analysis,
our payback period is about 5.616 years. It is indeed fast payback period for a
new Benzene plant that have different process and raw material to other like our
planr. Our MARR is 9,62%. Our MARR is bigger than the deposito tax in the
bank, so our plant will attract investor to invest their money into our plant rather
than keeping their money in bank. IRR of our plant is 12,55%. This percentage is
actually high enough for investor.
Universitas Indonesia
CHAPTER 9
CONCLUSION
APPENDICES
APPENDIX A: BLOCK FLOW DIAGRAM
Universitas Indonesia
107
Universitas Indonesia
108
Universitas Indonesia
109
Sizing
Step 1 : Collect Literature’s Data
Catalyst ZSM-5
Universitas Indonesia
110
Flow rate actual this plant is 55730 kg/h and the journal is 46000 kg/hr. By
assuming the actual flow rate is 1.2 times than journal’s, so the volume actual this
plant is 1.2 bigger than journal’s as well.
Vtank actual = 1.2Vtank journal
Vtank actual = 1.2 x 8.544 m3
Vtank actual = 116.04 m3
Step 4: Calculate Diameter Actual
𝑉𝑡𝑎𝑛𝑘 = 𝑉𝑡𝑜𝑝 + 𝑉𝑏𝑜𝑡𝑡𝑜𝑚 + 𝑉𝑠ℎ𝑒𝑙𝑙
𝑉𝑡𝑎𝑛𝑘 = 0.0847 𝐷3 + 0.0847 𝐷3 + 0.7854 𝐿𝑠 3
𝑉𝑡𝑎𝑛𝑘 = (0.0847 + 0.0847 + (0.7854 x 4))𝐷3
116.04 m3 = (0.0847 + 0.0847 + (0.7854 x 4))𝐷3
𝐷3 = 66.686 m3
D = 4.055 m
Step 5: Calculate Ls
Ls = 3.5D
Ls = 4 x 1.728 m
Ls = 14.19 m
Step 6: Calculate Volume Liquid
In this case, the tank volume is assumed
100
𝑉𝑡𝑎𝑛𝑘 = 𝑉𝑙𝑖𝑞𝑢𝑖𝑑 𝑥
80
So the liquid volume is calculated as below
80
𝑉𝑙𝑖𝑞𝑢𝑖𝑑 = 𝑉𝑡𝑎𝑛𝑘 𝑥
100
80
𝑉𝑙𝑖𝑞𝑢𝑖𝑑 = 116.04 𝑥
100
𝑉𝑙𝑖𝑞𝑢𝑖𝑑 = 92.838 m3
Step 7: Calculate Liquid Height on the Tank
𝑉𝑙𝑖𝑞𝑢𝑖𝑑 = 𝑉𝑏𝑜𝑡𝑡𝑜𝑚 + 𝑉𝑙𝑖𝑞𝑢𝑖d 𝑖𝑛 𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟
𝐷2
92.838 m3 = 4.706 D3 + 𝜋 𝐻𝑙𝑖𝑞𝑢𝑖𝑑
4
𝐻𝑙𝑖𝑞𝑢𝑖𝑑 = 6.827 𝑚
Universitas Indonesia
111
D3 = 59.13 m3
DTeoritical = 3.89 m
- Teoritical Length
L = 3.5D
L =3.5 (3.89) m
L = 7.791 m
Step 11: Calculate Catalyst Volume and Weight
Condition :
Catalyst filled 80% of the reactor
Catalyst is ZSM-5
Universitas Indonesia
112
VCat = 74.27 m3
- Catalyst Weight
WCat = VCat 𝜌𝐶𝑎𝑡
WCat = 74.27 m3 x 720 kg/m3
WCat = 53474 kg
Universitas Indonesia
113
Temperature : 162oC
Pressure : 1 atm
- Volume of CSTR
To calculate the volume of CSTR, the flow rate of each material input to
hydrolysis tank should be known before. As for those flow rate has been
calculated in mass balance and will be written below.
After the flow rate has been known, the entering condition of the fluid like flow
rate, pressure, and temperature is needed. As for the assumptions R is equal to
Universitas Indonesia
114
3
8,314 kPa.dm /mol K and vo is calculated below
1 𝑥𝑖
= ∑( )
𝜌𝑇 𝜌𝑖
1 0.4615 0.5384
= +
𝜌𝑇 112 1830
1
= 0.00441512
𝜌𝑇
𝜌𝑇 = 226.494 kg/m3
so, the 𝜐𝑜 is
𝑚𝑎𝑠𝑠 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒 54166,67 𝑘𝑔/ℎ𝑟
𝜐𝑜 = = = 66.431 dm3/s
𝑑𝑒𝑛𝑠𝑖𝑡𝑦 226,494 𝑘𝑔/𝑚3
Assumptions:
From those assumptions above, the volume that needed for the reactor can be
calculated by equation
𝑦𝐴𝑂 . 𝑃𝑂
𝐹𝐴𝑂 = 𝐶𝐴𝑂 . 𝜐𝑜 = 𝜐
𝑅. 𝑇𝑂 𝑜
𝐹𝐴𝑂 = 0.028 𝑥 66. 4312 𝑑𝑚3 s
𝐹𝐴𝑂 = 1.860 mol/s
In the calculation above there were no fraction gas (yA0) because in this
reaction there will not be a gas.
Universitas Indonesia
115
𝑘 = 0.02054
𝑟𝐴 = 𝑘. [𝐶𝐴 ]
𝐹𝐴𝑂 . 𝑋
𝑉=
−𝑟𝐴
1.860 𝑥 0.75
𝑉=
−8.46 𝑥 10−5
𝑉𝑡𝑎𝑛𝑘 = 𝑉𝑓 (100⁄80)
𝑉𝑡𝑎𝑛𝑘 = 16.478(100⁄80)
𝑉𝑡𝑎𝑛𝑘 = 20.598 𝑚3
𝑉𝑡𝑜𝑝 = 0.0847 𝐷3
𝑉𝑏𝑜𝑡𝑡𝑜𝑚 = 0.0847 𝐷3
𝑉𝑠ℎ𝑒𝑙𝑙 = 0.7854 𝐿𝑠 3
𝐷3 = 42.597 𝑚3
D = 3.492 m = 137.49 in
- Liquid Height
Universitas Indonesia
116
1
30.63 𝑚3 = 0.0847 𝐷3 + 𝜋𝐷2 𝐻𝑙𝑖𝑞𝑢𝑖𝑑
4
1
33.439.63 𝑚3 = 0.0847 (3.497)3 + 𝜋(3.497)2 𝐻𝑙𝑖𝑞𝑢𝑖𝑑
4
𝐻𝑙𝑖𝑞𝑢𝑖𝑑 = 4.032 𝑚
𝐻𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 = 2𝐷 = 6.984 𝑚
- Impeller Sizing
To mix the streams well, the tank uses six-blade 45 ̊ open turbine, as for the
standard design for this impeller according to Walas, 1990 is:
Di : Dt = 1 : 3
W : Di = 1 : 8
Universitas Indonesia
117
C:W=1:3
Where Di = impeller diameter
Dt = tank diameter
W = agitator width
C = distance from bottom of the tank
Impeller diameter = 0.333 x tank diameter
Di = 0.333 x 3.492 m = 1.33 m
Impeller width = 0.125 x impeller diameter
W = 0.125 X 1.33 m = 0.16 m
Impeller distance from the bottom of tank = 0.333 x impeller width
C = 0.333 x 0.16 = 0.055 m
𝑙𝑖𝑞𝑢𝑖𝑑 ℎ𝑒𝑖𝑔ℎ𝑡 𝑥 𝑆𝐺
𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑖𝑚𝑝𝑒𝑙𝑙𝑒𝑟 =
𝐷𝑡
4.60 𝑚 𝑥 0.86014
𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑖𝑚𝑝𝑒𝑙𝑙𝑒𝑟 =
3.987 𝑚
𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑖𝑚𝑝𝑒𝑙𝑙𝑒𝑟 = 0.9932 ≈ 1 𝑢𝑛𝑖𝑡
Impeller’s speed = 100 rpm = 1.67 rps
Universitas Indonesia
118
−𝑟𝑐 = 𝑘𝑐 𝑃𝑂2 𝐶𝑐
Where,
Cc = Coke content on catalyst (%wt)
x = length of the reactor (m)
𝜖̅ = cross section average voidage
Gs = total catalyst flowrate (kg/m2s)
PO2 = partial pressure of O2 (atm)
Kc = 1.65 x 108 exp ( -1.612 x 105/RT)
R = 8.314 kJ/kmol K
Initial coke content on catalyst is assumed 0.05%wt and the final is
0.008%wt. Cross-section average voidage is assumed 0.8 and total catalyst flow
rate is 40 kg/m2.s.
The derivation of the equation is:
𝑑𝐶𝑐
= 𝑘𝑐 𝑃𝑂2 𝐶𝑐 𝜌𝑃 (1 − 𝜖̅)⁄𝐺𝑠 (64)
𝑑𝑥
Universitas Indonesia
119
From the polymath, the length of the reactor for coke combustion is 6.586 m
The diameter of the reactor is about 1/3-1/5 L. So that
𝐿 6.586
𝐷= = = 2.195𝑚
3 3
𝑃×𝑅
𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 = + 𝐶𝐴
(𝐸 × 𝑆) − (0.6 𝑃)
S is allowable stress (74514.7 psi for SS 316). E is joint efficiency 0.8 (Walas
1988). CA is corrosion allowance. For carbon steel the value of corrosion
allowance is 0.00889 m.
Universitas Indonesia
120
Universitas Indonesia
121
Before it got know the warehouse specifications, these are some data
which are:
a. Bulk density of empty fruit bunches = 355 kg/m3
b. The process will be done continuously
c. The amount of raw materials is = 100,000 kg/day = 4166.67 kg/hr
Basic Planning
Construction materials = Concrete
𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙𝑠 𝑆𝑡𝑜𝑟𝑒 = 𝑒𝑚𝑝𝑡𝑦 𝑓𝑟𝑢𝑖𝑡 𝑏𝑢𝑛𝑐ℎ𝑒𝑠 𝑎𝑠 𝑟𝑎𝑤 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙/𝑑𝑎𝑦𝑠
𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙𝑠 𝑆𝑡𝑜𝑟𝑒 = 100,000 𝑘𝑔/𝑑𝑎𝑦𝑠 𝑥 30 𝑑𝑎𝑦𝑠/𝑚𝑜𝑛𝑡ℎ
𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙𝑠 𝑆𝑡𝑜𝑟𝑒 = 3,000,000 𝑘𝑔
𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙𝑠 𝑆𝑡𝑜𝑟𝑒 = 3,000 𝑡𝑜𝑛𝑠
𝑇ℎ𝑒 𝑎𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑑𝑒𝑝𝑜𝑠𝑖𝑡𝑒𝑑
𝑅𝑎𝑤 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 =
𝑏𝑢𝑙𝑘 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑒𝑓𝑏
3,000,000 𝑘𝑔
𝑅𝑎𝑤 𝑀𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = = 8450.70 𝑚3
355 𝑘𝑔/𝑚3
Warehouse Specification
Length = 36.85 m
Width = 27.64 m
Height = 9.21 m
Universitas Indonesia
122
Universitas Indonesia
123
1
𝑉𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 = 𝜋𝐷2 𝑥𝐻𝑠
4
Based on the rule of thumb of cylindrical storage tank, the ratio of height
and diameter of the tank is 2:1, therefore Hcylinder = 2D, and the cylinder volume
formula can be modified into:
1
𝑉𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 = 𝜋2𝐷3
4
The tank total volume is the sum of cylinder volume and ellipsoidal head
volume. The volume of ellipsoidal head is:
1 2
𝑉ℎ 𝑒𝑙𝑙𝑖𝑝𝑠𝑜𝑖𝑑𝑎𝑙 =𝜋𝐷 𝑥𝐻ℎ
4
According to Walas (1990), the ratio between head height and diameter is
1:6, therefore Hh = 1/6 D, and the ellipsoidal head volume formula can be
modified into:
1 2 1 1
𝑉ℎ 𝑒𝑙𝑙𝑖𝑝𝑠𝑜𝑖𝑑𝑎𝑙 = 𝜋𝐷 𝑥 𝐷 = 𝜋𝐷3
4 6 24
Therefore, the total tank volume is;
1 1 13
𝑉 = 𝑉𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 + 𝑉ℎ = 𝜋2𝐷3 + 𝜋𝐷3 = 𝜋𝐷3
4 24 24
By arranging above equation, the tank diameter can be obtained:
3 24𝑉
𝑡
𝐷=√
13𝜋
3 24(406.5 𝑚3 )
𝐷=√
13𝜋
𝐷 = 19.35 ≈ 762.20 𝑖𝑛
Based on the previous rule of thumb, the tank height can be obtained from
diameter, and it is calculated below:
𝐻𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 = 2 𝑥 6.2 𝑚 = 38.71 𝑚
1
𝐻ℎ = 𝑥 6.2 𝑚 = 3.22 𝑚
6
𝐻𝑇 = 12.4 𝑚 + 1.03 𝑚 = 41.94 𝑚 = 1651.43 𝑖𝑛
Design Pressure
Universitas Indonesia
124
Where:
t = Material thickness
P = Pressure gauge
R = Shell radius
Di = Shell inner diameter
Universitas Indonesia
125
1 𝐷 2
K = ellipsoidal formula factor = 6 [2 + (2ℎ) ]
𝑡𝑤 = 0.57 𝑖𝑛 ≈ 14.478 𝑚𝑚
While the storage tank head thickness is:
1 762.20 𝑖𝑛 2
77.1197 𝑝𝑠𝑖 𝑥 762.20 𝑖𝑛 𝑥 [2+( ) ] 𝑖𝑛
6 2 𝑥 1651.43 𝑖𝑛
𝑡ℎ = 𝑙𝑏 + (0.0042 𝑥 30 𝑦𝑒𝑎𝑟𝑠) (100)
(2𝑥16,250 2 0.85)−(0,2 𝑥 77.11 𝑝𝑠𝑖) 𝑦𝑒𝑎𝑟
𝑖𝑛 𝑥
Universitas Indonesia
126
Universitas Indonesia
127
Universitas Indonesia
128
To calculate the shell thickness (ts), use the equation from Brownell, page 254
[𝑃𝑑 𝑥 𝐷𝑖 + 𝑐]
𝑆ℎ𝑒𝑙𝑙 𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 =
[2 𝑥 (𝑓 𝑥 𝐸 − 0.6 𝑥 𝑃𝑑)]
41.86 𝑝𝑠𝑖 × 336.11 𝑖𝑛 + 0.0042
𝑆ℎ𝑒𝑙𝑙 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 (𝑡𝑠 ) = = 0.52 𝑖𝑛
2 × (16750 × 0.8 − 0.6 × 41.86 𝑝𝑠𝑖)
Therefore, or flat head thickness that could determine the thickness used in
the equation from the literature. The head thickness based on rule of thumb is 3.5
times thicker from the shell thickness. The head thickness would be
𝐻𝑒𝑎𝑑 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 (𝑡ℎ ) = 3.5 × 𝑡𝑠 = 3.5 × 0.52 𝑖𝑛 = 1.84 𝑖𝑛
Universitas Indonesia
129
Then it could calculate the height of the tank with free board data. The
diameter of the coagulant tank that determined is 8.4 m with 4.4 m height. There
will be four tanks due to the big amount of water to be processed in the plant per
day. Hence, it got divided the mass flow rate to 4 tanks. The mass flow rate of
each tank would be 3197.5 kg/h.
Universitas Indonesia
130
Universitas Indonesia
131
Before calculate the tank area, the flow rate of water based on water
requirement in benzene plant is 7631 m3/day. Hence, the required tank
area calculation (Atank) would be as follows
1
𝐴𝑡𝑎𝑛𝑘 = 𝑚𝑎𝑠𝑠 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 𝑥 ( )
𝑓𝑖𝑙𝑡𝑟𝑎𝑡𝑖𝑜𝑛 𝑟𝑎𝑡𝑒
𝑚3 1
7631 𝑚
𝑑𝑎𝑦 0.15
𝐴= 𝑥 ( ) = 2119.72 𝑚2
ℎ ℎ
24
𝑑𝑎𝑦
For this area, this plant can use tank with 25 m long and 15 m wide. From
typical table above, the height of the tank require could be calculated from
provided data
- System underdrain + gravel = 0.4 m
- Filter bed = 0.85 m
- Supernatant water = 1 m
So the total tank height is 2.25 m
Thus, the dimension of the tank become 25 m long, 15 m wide and 2,25 m
height
Finally it can be calculated the number (n) of filters by divided surface
area of (A) and maximum surface per filter which known as 50 m2. The
total surface area of filter couldbe calculated fro equation below. The
design loading rate based on the table above. So, it takes 160 m3/m2 day
𝑄
𝑣𝑎 =
𝐴𝑠
7631 𝑚3 /𝑑𝑎𝑦
𝐴= = 47.69 𝑚2
𝑚3
160 2
𝑚 𝑑𝑎𝑦
47.69 𝑚2
𝑛= = 0.953 ≈ 1
50 𝑚2
Universitas Indonesia
132
Calculate
Examine Water Decide the use
Cation
Analysis of degasifier
Concentration
Consider the
Calculate resin
Calculate ionic aproximate
volume
load per cycle operating
required
capacity
Universitas Indonesia
133
Universitas Indonesia
134
𝐶𝑐 𝑄 4800000
𝑉𝑐 = = = 4800000 𝐿 .
𝑐𝑎𝑝𝑐 1
𝐶𝑎 𝑄 2884800
𝑉𝑎 = = = 5769600 𝐿
𝑐𝑎𝑝𝑐 0.5
Universitas Indonesia
135
10. At the end of this calculation, this must make sure that the specific flow
rate of both resin columns is compatible with the general recommendations of the
resin producer.
The specific flow rate in h—1 (often expressed in bed volumes per hour
BV/h) is equal to the flow rate in m3/h divided by the resin volume in m3. The
usual range is 5 to 50 h—1. For a compact plant with minimum investment cost,
use a specific flow rate around 30 to 35 h—1. If the specific flow rates calculated
from the resin volumes Vc and Va are too high, increase the running time t. If they
are too low, reduce the running time t.
Universitas Indonesia
136
Universitas Indonesia
137
Universitas Indonesia
138
6. Decide the type of shell and tube heat exchanger (fixed tubesheet, U-tube
etc.), outside diameter tube, inside diameter tube, tube thickness, length of
tube, number of pass, dan pitch type. Use the standard tube counts table for
this purpose.
Universitas Indonesia
139
- Diameter bundle, Db
1
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑡𝑢𝑏𝑒𝑠 𝑛1
𝐷𝑏 = 𝐷𝑜 ( )
𝐾1
The value of K1 dan n1 are obtained from table 12.4 in Chemical
Engineering Design vol 6, 2005
- Diameter shell Ds
𝐷𝑠 = 𝐷𝑏 + 𝑠ℎ𝑒𝑙𝑙 𝑏𝑢𝑛𝑑𝑙𝑒 𝑐𝑙𝑒𝑎𝑟𝑎𝑛𝑐𝑒
The value of shell bundle clearance is obtained from figure 12.10 in
Chemical Engineering Design vol 6, 2005
9. Estimate tube side heat transfer coefficient
- Reynlods Number, Prandtl Number, and L/D
𝜌 𝑢𝑡𝑢𝑏𝑒 𝐷𝑖
𝑅𝑒 =
𝜇
𝐶𝑝 𝜇
𝑃𝑟 =
𝑘
𝐿 𝑡𝑢𝑏𝑒 𝑙𝑒𝑛𝑔𝑡ℎ
=
𝐷 𝐷𝑖
- Tube side heat transfer coefficient, hi
𝑘
ℎ𝑖 = 𝑗𝐻 . 𝑅𝑒 . (Pr)0.33 ( )
𝐷𝑖
The value of jH is obtainable from figure 2.23 in Chemical Engineering
Design vol 6, 2005
10. Estimate shell side heat transfer coefficient
- Baffle spacing dan tube pitch
Baffle Spacing, lB = baffle spacing coefficient x inside diameter shell
Tube pitch, pt = tube pitch coefficient x outside diameter tube
The value of baffle spacing coefficient is 0.2 – 0.5 while tube pitch
coefficient is 1.25 – 1.35
- Shell Cross Flow Area
𝑝𝑡 − 𝐷𝑜
𝐴𝑠 = . 𝐷𝑠 . 𝑙𝐵
𝑝𝑡
- Equivalent Diameter, de
1.10
For triangular pitch: 𝑑𝑒 = 𝐷𝑜
𝑥 (𝑝𝑡2 − 0.917𝐷𝑜2 )
Universitas Indonesia
140
1.27
For square pitch: 𝑑𝑒 = 𝑥 (𝑝𝑡2 − 0.785𝐷𝑜2 )
𝐷𝑜
Universitas Indonesia
141
𝐷𝑠 𝐿 𝜌𝑈𝑠2
𝛥 𝑃𝑠 = 8 𝑗𝐹 . . .
𝐷𝑒 𝑙𝐵 2
Pressure drop must be below 0.5 bar. If the pressure drop above 0.5 bar, must
change the value of Uc in step 3.
Universitas Indonesia
142
Figure K.1. Relation between optimum-to-minmum ratio and Fensk separation factor of alfa
values
(Source: Mc Cabe, 1993)
1) Determine the value of log[ (𝑥𝐿𝐾 ⁄𝑥𝐻𝐾 )𝐷 (𝑥𝐻𝐾 ⁄𝑥𝐿𝐾 )𝐵 (𝑥𝐿𝐾 ⁄𝑥𝐻𝐾 )𝐹 ],
(𝛼𝐿𝐾⁄𝐻𝐾 )𝑎𝑣 .
2) Plot the data to the graph
Universitas Indonesia
143
Figure K.2. Optimum-minimum reflux ratio relationship to the column's feed, distillate, and
bottoms composition
(Source: Mc Cabe, 1993)
4) Determine the value of log[ (𝑥𝐿𝐾 ⁄𝑥𝐻𝐾 )𝐷 (𝑥𝐻𝐾 ⁄𝑥𝐿𝐾 )𝐵 (𝑥𝐿𝐾 ⁄𝑥𝐻𝐾 )𝐹 ],
(𝛼𝐿𝐾⁄𝐻𝐾 )𝑎𝑣 .
5) Plot the data to the graph
6) Drawn a line to the left, so get the 𝑅𝑜𝑝𝑡 ⁄𝑅𝑚𝑖𝑛
5. Determining θ.
The method is finding the value of 𝑥𝐿𝐾 /𝑥𝐻𝐾 on the feed, and the value
of 𝛼𝐿𝐾 with use Figure A.3 below
Universitas Indonesia
144
𝛼𝑖 −𝜃 𝛼𝑖 𝑋𝑖𝐷
6. Determining , and , that will be used for determining value of
𝛼𝑖 𝛼𝑖 −𝜃
𝛼𝑖 𝑋𝑖𝐷
∑ by using Figure A.4 below
𝛼𝑖 −𝜃
Universitas Indonesia
145
𝜌𝑣
𝐹𝐿𝑉 = 𝑠𝑙𝑜𝑝𝑒 × √
𝜌𝐿
Using the graph below, it can be known the value of K which will be
used to calculate the velocity of vapor and liquid.
𝜌𝑣
𝑣 = 𝐾×√
𝜌𝐿
Universitas Indonesia
146
4𝐴
𝐷=√
𝜋
’
Figure K. 6. Gilliand Equation and Graph
(Source: Mc Cabe, 1993)
𝑁−𝑁𝑚𝑖𝑛
4. Calculate the number of stage with equation 𝑁+1
Universitas Indonesia
147
Properties Value
Gas Flowrate (MMSCFD) 0.0464
Oil Flowrate (BOPD) 66.717
Water Flowrate (BWPD) 6.124
Total Liquid (BPD) 72.84
ATM Press. 14.7
Op Press (psig) 2529.46
Op Temp (F) 140
Gas Compressibility Z 0.95
Retention Time (min) t 10.00
Remove drops >__micron from gas 150
Remove H2O drops >__micron from oil 500
Remove oil drops >__micron from H2O 200
Vessel Liquid Level - beta 50%
Gas Molecular Weight 2.018
Oil Specific Gravity 0.84
Water Specific Gravity 1
Gas Viscosity m 0.009
Oil Viscosity ml 3.2
H2O Viscosity mw 0.69
Universitas Indonesia
148
0.5
𝑇𝑍𝑄
𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = 12 𝑥 ( ) = 0.7 𝑖𝑛
2.4𝑉𝑡(𝑃 + 𝑃𝑎)
Universitas Indonesia
149
Diameter
15 16 17 18 19 20
(in)
Leff (gas) 0.00301 0.00282 0.00266 0.00251 0.00238 0.00226
Lss (gas) 1.25 1.34 1.42 1.50 1.59 1.67
Universitas Indonesia
150
Leff
4.62 4.06 3.60 3.21 2.88 2.60
(liquid)
Lss
6.17 5.42 4.80 4.28 3.84 3.47
(liquid)
Lss (ft) 7 6 5 5 4 4
L/D 5.20 4.13 3.53 3.00 2.53 2.10
Since L/D must be in the range of 3-5, the chosen length and diameter for the 3-
phase separator are 6 ft and 16 in.
Universitas Indonesia
151
Velocity of Conveyor
𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦
𝑢=( ) 𝑥 100 𝑓𝑡/𝑚𝑖𝑛
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑓𝑟𝑜𝑚 𝑓𝑖𝑔𝑢𝑟𝑒
So, the velocity of conveyor :
250 𝑡𝑜𝑛𝑛𝑒/ℎ𝑟 𝑓𝑡
𝑢 = (238.5 𝑡𝑜𝑛𝑛𝑒/ℎ𝑟) 𝑥 100 min=104.82 𝑓𝑡/𝑚𝑖𝑛 = 174.70 ft/min
Universitas Indonesia
152
Power
26.24 250
𝑃ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 = (0.4 + ) (100) = 1.218 hp
300
Universitas Indonesia
153
- Belt Conveyor 2
Belt conveyor is used to transfer Empty Fruit Bunch from Warehouse to
Grinder.
Velocity of Conveyor
𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦
𝑢=( ) 𝑥 100 𝑓𝑡/𝑚𝑖𝑛
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑓𝑟𝑜𝑚 𝑓𝑖𝑔𝑢𝑟𝑒
So, the velocity of conveyor :
416.67 𝑡𝑜𝑛𝑛𝑒/ℎ𝑟 𝑓𝑡
𝑢 = ( 499.5 𝑡𝑜𝑛𝑛𝑒/ℎ𝑟 ) 𝑥 100 min=104.82 𝑓𝑡/ min = 83.41 𝑓𝑡/𝑚𝑖𝑛
Power
Universitas Indonesia
154
The power requirement for hammer mills is based on the extent of size
reduction that expressed by the following equation
𝑘𝑊ℎ 1 1
𝑊 ( ) = 10𝑊𝑖 ( − )
𝑡𝑜𝑛 √𝑑 √𝑑𝑖
Where d and di are the final and initial diameter (μm), and Wi is work
index for the material. The work index for Empty fruit bunch is 13.81.
𝑘𝑊ℎ 𝑘𝑊ℎ 1 1
𝑊 ( ) = 10 (13.81 )( − ) = 0.906857 𝑘𝑊ℎ/𝑡𝑜𝑛
𝑡𝑜𝑛 𝑡𝑜𝑛 √300 √20000
If the mass flow rate of empty fruit bunch is 416.67 ton/hour, the total power
requirement is
𝑘𝑊ℎ 𝑘𝑊ℎ 𝑡𝑜𝑛 𝑘𝑊ℎ
𝑊 ( ) = 0.906 𝑥416.67 = 377.503
𝑡𝑜𝑛 𝑡𝑜𝑛 ℎ𝑜𝑢𝑟 ℎ𝑜𝑢𝑟
To choose the dimension of hammer mills that needed, looking to the vendor
(SBM-Mining and Construction) PC4012-90 with the dimension 1800 mm x 1650
mm x 1800 mm.
Universitas Indonesia
155
Universitas Indonesia
156
Universitas Indonesia
157
𝑆 = 2𝐷 + (𝐷⁄8) = 5.397 𝑚
𝐻 = 4𝐷 = 10.159 𝑚
𝐷
𝐵= = 0.635 𝑚
4
Universitas Indonesia
158
Universitas Indonesia
159
Based on this graph, it can be known that the volume inlet flow and
discharge pressure are in centrifugal range are. This is the volume flow inlet
and discharge
pressure table.
Volume Discharge
Inlet Flow Pressure
Compressor (kg/hour) (kPa)
C-100 222789,365 800
(Source: Author’s Personal Data)
After this known what type compressor that will be used, then
calculate compressor power, discharge temperature and compressor head.
This is the detail calculation of first compressor (C-101), which use to
transport gas to membrane.
Compressor Power
Universitas Indonesia
160
Z = compressibility factor
R = universal gas constant
T
R1 = inlet temperature, K
P = standard pressure
T = standard temperature
E = overall efficiency
Q = gas flow rate
W = work (kJ/mol)
P2 = pressure outlet
P1 = pressure inlet
Discharge Temperature
After that, calculate the compressor power, and need to calculate the outlet
temperature from compressor. Here is the equation is to calculate discharge
temperature in compressor:
Compressor Head
Compressor head is like a compressor ability to reach maximum height of
other unit to transport gas. Here is the equation is to calculate compressor head in
compressor:
Universitas Indonesia
161
Universitas Indonesia
162
Universitas Indonesia
163
Pump is used in order to move liquid from one unit to another. For this
plant, the total pumps needed are around 6 pumps. Here is the brief description of
each pump usage.
The selected centrifugal pump as the type of pump in this plant because
the flow rate and viscosity is low, and there is no high temperature of mixture in
this plant. That used calculation based on handbook chemical engineering and
mechanical fluids course. The material that are going to use is carbon steel.
First, input all of the data that needed such as mass flow, density, pressure
suction and discharge (or pressure at destination), vapor pressure, temperature
suction, and static head in the excel.
In sizing pump, use that all the pump efficiency is 75%
∆𝑃 = 𝑃𝑎𝑡 𝑑𝑒𝑠𝑡𝑖𝑛𝑎𝑡𝑖𝑜𝑛 − 𝑃𝑎𝑡 𝑙𝑖𝑞𝑢𝑖𝑑 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑠𝑢𝑐𝑡𝑖𝑜𝑛
Then it can be calculated head by using this equation
𝐹𝐻𝑃
𝐻=
𝑔 𝑥 𝑚̇
Head Actual
𝐻
𝐻 𝑎𝑐𝑡𝑢𝑎𝑙 =
Ƞ𝑝
FHP
𝑑𝑊𝑝𝑜𝑚𝑝𝑎
𝐹𝐻𝑃 = 𝑚̇
𝑑𝑚
BHP
𝐹𝐻𝑃
𝐵𝐻𝑃 =
Ƞ𝑝
NPSHA
NPSH is calculated by many factor. The most important variable here is
the length t of pipe itself, equivalent length of valve and bending.
𝑃1(𝑎𝑡𝑚) 𝑉22 𝐹 𝑃𝑣𝑎𝑝𝑜𝑟
𝑁𝑃𝑆𝐻𝐴 = (𝑧 )
− 2 − 𝑧1 − − −
𝜌𝑔 2𝑔 𝑔 𝜌𝑔
NPSHR
𝑃𝑠𝑢𝑐𝑡𝑖𝑜𝑛 − 𝑃𝑣𝑎𝑝𝑜𝑟
𝑁𝑃𝑆𝐻𝑅 =
𝜌𝑔
Universitas Indonesia
164
Universitas Indonesia
165
Universitas Indonesia
166
Mosque 13 15 195
Cafetaria 13 10 130
Production Office 15 11 165
Fire Extinguisher Station 15 11 165
Park 20 15 300
Park 20 15 300
Maintenance Centre 15 15 225
Utility Control Room 15 10 150
Laboratory 40 15 600
HSE Office 13 11 143
Sparepart Chemical & Supply
36.85 27.64 1018.534
Warehouse
Control Room 20 15 300
R&D Plant Office 15 11 165
Open Area (road, parking area, etc) 200
Total Area (m2) 4208.534
Universitas Indonesia
167
High humidity
Universitas Indonesia
168
Potential Hazard
Location Description Causes Frequency Prevention
Hazard Effect
Regular checking and
Distillation Butanol High pressure and Fire and/or
Severe Likely temperature control
column purification temperature explosion
provisioning
Noise
Surfacing tools that
pollution that
Unit for Loud Operation generate noise with a
Pump can damage Minor Most
water flowing Noise silencer, and oblige the
the hearing of
use of earplug
workers
Noise
Surfacing tools that
pollution that
Unit for gas generate noise with a
Compressor can damage Minor Most
flowing silencer, and oblige the
the hearing of
use of earplug
workers
Unit for
Electricity Electrical Safety helmet, gloves, and
electricity Electricity current Severe Likely
Generator shock shoes, make barrier
production
Steam Utility To Produce High Pressure and Blowout and Routine inspections and
Major Likely
Unit Steam High Temperature high thermal controller instrumentation
Universitas Indonesia
169
Universitas Indonesia
170
Hazard
Location Potential Frequency
Description Causes Prevention
Hazard Effect
Low temperature Overflow from
To provide Control the output
Cold Utility Unit and high capacity cold utility Major Likely
cooling temperature
of cooling water which release to
water
which produce the environment
To distribute Protect the piping
Piping Network Damage and Major Likely
fluid in Corrosion, Failure network and control
leakage of pipe
process periodically
The contain of
Over Capacity of
Area for the pool will Minor Likely Level Control System
Waste Treatment Pool
treating the spill
Area
waste Environmental
Leakage of Pool Minor Likely Checking periodically
Pollution
Improve training and
Someone Slip Minor Likely
Quality move carefully
Spill Chemical
Laboratory Area Control Do not bring any fire
Substances
Assesment Flame Severe Unlikely source and provide some
fire exthinguisher
Provide training to the
To control Errors in operator about the
Control Room System will be Major Unlikely
operation in operating working procedure and
shut down
the plant procedures oblige supervisors to
perform daily briefing
Universitas Indonesia
171
Hazard
Location Description Causes Potential Hazard Frequency Prevention
Effect
To transport
Bucket elevator the material Dust from Major Most
Nature of material Using PPE
(empty fruit material
bunches)
Fluidized Regular checking and
For olefin
Catalytic High temperature Fire and/or Major Likely temperature control
production
operation explosion provision and place the
Cracking Reactor from bio-oil
reactor inside
Regular checking and
High pressure Major Likely pressure control provision
Explosion
operation and place the reactor
inside
Universitas Indonesia
172
Universitas Indonesia
173
Supply is not
appropriate
Less power portion
Increasing the
Less to move the Takes more
power
belt time to
distribute corn
cobs
2 Hammer G-100 Blade More Wrong set Particle size is Determining a Flow Control
Grinder Rotation point not enough new set point (FC)
Speed homogenous and controlled
Stock of material periodically
will be used
faster
Less Low driving Need more time Provide
power source to crush the corn additional
cobs electrical power
3 Condenser E-100, E- Flow More Overload in Filtration process Controlling Flow Control
101, E-102 pump will take time pump and flow (FC)
too long regularly
Less Blocking or Supply will be
Universitas Indonesia
174
leaking in decrease
pump
Pressure Low Leaking in There's still Analyze the Analyzer
filter or pipe some impurities outlet flow
to filter in outlet flow to composition
fermenter after filtration
Flow More Pump is not High input Controlling flow Flow Control
running temperature before come into (FC)
Less based on Low input condenser
required temperature
3 Condenser E-100, E- Temperature High Cooling High input Controlling the Temperature
101, E-102 water temperature temperature Control (TC)
temperature periodically
is too low
Temperature Low Water input Low input Controlling the Temperature
temperature temperature temperature Control (TC)
is too high Increase work in periodically
reboiler to
distillate the
feed
Universitas Indonesia
175
4 Pump P-100, P- Flow None Pump Process flow is Regular Flow Control
101, P-102, clogged hampered maintenance (FC)
P-103, More Excessive Broken pump and control the
impeller pump
performance periodically
Less Pump Processing
blockage liquid supply
hampered
Reverse Pump Reverse flow
clogged occur
5 Compressor C-100 Flow More Inlet flow is Overpressure Decrease flow Flow Control
too high into compressor (FC)
Failure in
Universitas Indonesia
176
pressure is occur
too low Compressor
can't distribute
the gas to the
next process
6 Distillation V-100 and Temperature High Steam equilibrium Reduce raw Temperature
Column V-101 temperature phase may not material usage Control (TC)
from reboiler occur and to heat boiler
is too high there's still
Low Steam another Increase steam
temperature component in flowrate intto
from reboiler outlet flow boiler
is too low
Level High Liquid flow Flooding Decrease the Level Control
into column inlet flow into (LC)
Mass transfer
is too high column
Universitas Indonesia
177
Universitas Indonesia
178
component join
into top product
flow
Low Steam Reboiler is not Decrease steam
flowrate is enough to heat flow to heat the
too low the inlet flow reboiler
Feed inlet is Increase inlet
too high flow to heat the
reboiler
Flow More Valve opens Increase steam Check flow Flow Control
too wide flowrate and control and (FC)
steam maintain the
temperature controller
Less Valve opens Decrease steam periodically
too small flowrate and
steam
stemperature
8 Heat HE-101 Temperature High Hot fluid Heat transfer Decrease hot Temperature
Exchanger flowrate is may not fluid flow to Control (TC)
too much effectively heat the reboiler
Universitas Indonesia
179
Universitas Indonesia
180
11 CSTR Flowrate No Control Valve Loss of cooling , Open valve is Flow Control
Fails closed possible runaway bigger (FC)
High Control valve Cstr cools Open valve is be
fails open smaller
Low Control valve Dimished Open valve is be
fails to cooling,possible bigger
respond run away Temperature
Temperature Low Low water Low water Increase the Control (TC)
supply supply temperature
temperature temperature
Universitas Indonesia
181
Universitas Indonesia
182
Universitas Indonesia
183
Universitas Indonesia
184
Universitas Indonesia
185
Universitas Indonesia
186
Universitas Indonesia
187
Universitas Indonesia
188
Universitas Indonesia
189
Universitas Indonesia
190
Universitas Indonesia
191
Universitas Indonesia
192
; \O
HQH 3 DJH RI
6 $ ) ( 7< ' $ 7$ 6 + ( ( 7
; \ OHQH
6 ( &7,2 1 ,GHQWLILFDW
LRQ RI W
KH VXEVW
DQFH P L[ W
XUH DQG RI W
KH
FRP SDQ\ XQGHUWDNLQJ
' DW
H LVVXHG
3 URGXFWLGHQW
LILHU
3 URGXFWQDP H ; \O
HQH
&KHP LFDOQDP H ; \O
HQH
6 \ QRQ\ P V ; \O
ROGLP HW
K\ OEHQ] HQH [ \ O
HQRO
5 ( $ &+ 5 HJ 1 R
&$ 6 QR
( & QR
,QGH[ QR
$ UWLFO
H QR
5 HO
HYDQWLGHQW
LILHG XVHV RI W
KH VXEVW
DQFH RUP L[ W
XUH DQG XVHV DGYLVHG DJDLQVW
8 VH RI W
KH VXEVW
DQFH SUHSDUDW
LRQ ) RUW
KH SUHSDUDW
LRQ RI SDLQW
V DQG DV D VRO
YHQW* HQHUDOSXUSRVH FO
HDQHU
' HW
DLOV RI W
KH VXSSOLHURI W
KH VDIHW
\ GDW
D VKHHW
0 DQXIDFWXUHU
&RP SDQ\ QDP H ) UHG + RO
P EHUJ &R $ %
2 IILFH DGGUHVV * HLMHUVJDWDQ
3 RVW DODGGUHVV %R[
3 RVW FRGH 6
&LW \ / LP KDP Q
&RXQW U\ 6 Z HGHQ
7HO
) D[
( P DLO LQIR# KROP EHUJ VH
: HEVLW H KWWS Z Z Z KROP EHUJ VH HQ
( P HUJHQF\ W
HOHSKRQH QXP EHU
( P HUJHQF\ W
HOHSKRQH ( XURSH
Universitas Indonesia
193
; \O
HQH 3 DJH RI
6 LJQDOZ RUG ' DQJHU
+ D] DUG VW
DWHP HQW
V + )ODP P DEO HO LTXLG DQG YDSRXU
+ + DUP IXOLQ FRQW DFWZ LW K VNLQ
+ &DXVHV VNLQ LUULW DWLRQ
+ + DUP IXOLI LQKDO HG
3 UHFDXW
LRQDU\ VW
DWHP HQW
V 3 . HHS DZ D\ IURP KHDWVSDUNV RSHQ IO DP HV KRWVXUIDFHV ± 1 R VP RNLQJ
3 . HHS FRQW DLQHUW LJKWO
\ FORVHG
3 7DNH SUHFDXW LRQDU\ P HDVXUHV DJDLQVWVW DWLF GLVFKDUJH
3 : HDUSURW HFW LYH JO RYHV SURW HFW
LYH FORWKLQJ H\ H SURW HFWLRQ IDFH SURW
HFWLRQ
3 3 ,) 6 : $ / / 2 : ( ' ,P P HGLDW HO\ FDOOD 3 2 ,6 2 1 &( 1 7( 5 RU
GRFWRUSK\ VLFLDQ
3 3 3 ,) 2 1 6 . ,1 RUKDLU 5 HP RYH 7DNH RII LP P HGLDW HO
\ DOO
FRQWDP LQDWHG FO RW KLQJ 5 LQVH VNLQ Z LW K Z DWHUVKRZ HU
3 ' R 1 2 7 LQGXFH YRP LW LQJ
3 3 6W RUH LQ D Z HO OYHQW LO
DWHG SODFH . HHS FRRO
2W
KHUKD] DUGV
2W
KHUKD] DUGV 1 RWNQRZ Q
; \O
HQH 3 DJH RI
XQFRQVFLRXV
,QGLFDW
LRQ RI DQ\ LP P HGLDW
H P HGLFDODW
WHQW
LRQ DQG VSHFLDOW
UHDW
P HQWQHHGHG
6 SHFLILF GHW
DLO
V RQ DQW
LGRW
HV 1 R UHFRP P HQGDW
LRQ JLYHQ
6 ( &7,2 1 ) LUHILJKW
LQJ P HDVXUHV
( [W
LQJXLVKLQJ P HGLD
6 XLW
DEO
H H[ W
LQJXLVKLQJ P HGLD ( [WLQJXLVK Z LW
K DO
FRKROUHVLVW
DQWIRDP FDUERQ GLR[ LGH GU\ SRZ GHURUZ DW
HU
IRJ
6 SHFLDOKD] DUGV DULVLQJ IURP W
KH VXEVW
DQFH RUP L[ W
XUH
) LUH DQG H[ SO
RVLRQ KD] DUGV 6 ROYHQWYDSRXUV P D\ IRUP H[ SO
RVLYH P L[ W
XUHV Z LW
K DLU
+ D] DUGRXV FRP EXVW LRQ SURGXFW
V ) LUH FUHDW
HV &DUERQ P RQR[ LGH &2 &DUERQ GLR[ LGH &2
$ GYLFH IRUILUHILJKW
HUV
) LUH ILJKW
LQJ SURFHGXUHV 1 R VSHFLILF ILUH ILJKW
LQJ SURFHGXUH JLYHQ
6 ( &7,2 1 $ FFLGHQW
DOUHO
HDVH P HDVXUHV
3 HUVRQDOSUHFDXW
LRQV SURW
HFW
LYH HTXLSP HQWDQG HP HUJHQF\ SURFHGXUHV
3 HUVRQDOSURW
HFW
LRQ P HDVXUHV ( QVXUH VXLW
DEOH SHUVRQDOSURW HFW LRQ LQFO
XGLQJ UHVSLUDWRU\ SURWHFW
LRQ GXULQJ
UHP RYDORI VSLO
ODJHV LQ D FRQILQHG DUHD 9 HQW LO
DWH Z HO
O6 WRS O
HDN LI SRVVLEO
H
Z LW
KRXWULVN $ YRLG FRQWDFWZ LWK VNLQ DQG H\ HV ' R QRWEUHDWKH YDSRXU
( QYLURQP HQW
DOSUHFDXW
LRQV
( QYLURQP HQW
DOSUHFDXW
LRQDU\ $ YRLG GLVFKDUJH LQW
R GUDLQV Z DW
HUFRXUVHV RURQW
RWKH JURXQG
P HDVXUHV
0 HW
KRGV DQG P DW
HULDOIRUFRQW
DLQP HQWDQG FO
HDQLQJ XS
&O
HDQLQJ P HW
KRG ' DP DQG DEVRUE VSLO
ODJHV Z LW
K VDQG HDUW
K RURW
KHUQRQ FRP EXVW
LEO
H P DW
HULDO
5 HIHUHQFH W
R RW
KHUVHFW
LRQV
2W
KHULQVW
UXFW
LRQV 1 R UHFRP P HQGDW
LRQ JLYHQ
Universitas Indonesia
195
; \O
HQH 3 DJH RI
' 1( / * URXS ,QGXVW ULDO
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW( W \OEHQ] HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS ,QGXVW ULDO
( [ SRVXUH URXW H ' HUP DO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW( W \OEHQ] HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW( W \OEHQ] HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H ' HUP DO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW( W \OEHQ] HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H 2 UDO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW( W \OEHQ] HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS ,QGXVW ULDO
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ 6 KRUWW HUP DFXW
H
&ULW LFDO&RP SRQHQW[ \ O HQ
9 DOXH P J NJ GDJ
' 1( / * URXS ,QGXVW ULDO
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW[ \ O HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS ,QGXVW ULDO
( [ SRVXUH URXW H ' HUP DO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW[ \ O HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ 6 KRUWW HUP DFXW
H
&ULW LFDO&RP SRQHQW[ \ O HQ
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H ,QKDODWLRQ
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW
HG
&ULW LFDO&RP SRQHQW[ \ O HQ
7\ SH RI HIIHFW6 \ VWHP LF HIIHFW
Universitas Indonesia
196
; \O
HQH 3 DJH RI
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H ' HUP DO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW HG
&ULW LFDO&RP SRQHQW[ \ O HQ
7\ SH RI HIIHFW6 \ VW HP LF HIIHFW
9 DOXH P J NJ GDJ
' 1( / * URXS &RQVXP HU
( [ SRVXUH URXW H 2 UDO
( [ SRVXUH IUHTXHQF\ / RQJ W HUP UHSHDW HG
&ULW LFDO&RP SRQHQW[ \ O HQ
7\ SH RI HIIHFW6 \ VW HP LF HIIHFW
9 DOXH P J NJ GDJ
( [ SRVXUH JXLGHO
LQHV &RXQW U\ RI RULJLQ 6 YHULJH
/ LP LWYDO XH W\ SH 1 * 9 PJ P
2 ( / 6 KRUW7HUP 9 DO XH PJ P
6 RXUFH 1 DW LRQHOOD K\ JLHQLVND JUl QVYl UGHQ $ ) 6
2W
KHU,QIRUP DW
LRQ 2 YDQVW nHQGH 1 * 9 UHVS . 79 Jl O O
HUEnGH [ \ O
HQ RFK HW
\OEHQ] HQ
( [ SRVXUH FRQW
UROV
2 FFXSDW
LRQDOH[ SRVXUH O
LP LW
V 3 URYLGH DGHTXDW H YHQW LO
DWLRQ 2 EVHUYH 2 FFXSDWLRQDO( [ SRVXUH / LP LW
V DQG
P LQLP LVH W
KH ULVN RI LQKDODWLRQ RI YDSRXUV 3 URW
HFWLYH JO
RYHV DQG JRJJO HV DUH
UHFRP P HQGHG 3 URYLGH H\ HZ DVK TXLFN GUHQFK
6 DIHW
\ VLJQV
5 HVSLUDW
RU\ SURW
HFW
LRQ
5 HVSLUDW
RU\ SURW
HFW
LRQ 5 HVSLUDW
RU\ SURW
HFWLRQ P XVWEH XVHG LI DLUFRQWDP LQDWLRQ H[ FHHGV DFFHSW
DEO
H
O
HYHO8 VH UHVSLUDWRU\ HTXLSP HQWZ LW
K JDV ILOW
HU W\ SH $
+ DQG SURW
HFW
LRQ
+ DQG SURW
HFW
LRQ 8 VH SURW
HFW LYH JO
RYHV &KHP LFDOUHVLVW DQWJORYHV UHTXLUHG IRUSURORQJHG RU
UHSHDW HG FRQWDFW* ORYHV RI QLW
ULO
H UXEEHU 3 9 $ RU9 LW
RQ DUH UHFRP P HQGHG
( \ H IDFH SURW
HFW
LRQ
( \ H SURW
HFW
LRQ 8 VH VDIHW
\ JRJJO
HV RUIDFH VKLHO
G LQ FDVH RI VSO
DVK ULVN
6 NLQ SURW
HFW
LRQ
6 NLQ SURW
HFW
LRQ H[ FHSWKDQGV : HDUDSSURSULDW
H FO
RWKLQJ W
R SUHYHQWDQ\ SRVVLELO
LW
\ RI VNLQ FRQW
DFW
+ \ JLHQH ( QYLURQP HQW
DO
6 SHFLILF K\ JLHQH P HDVXUHV : DVK KDQGV DIW
HUFRQW
DFW
; \O
HQH 3 DJH RI
9 DSRXUGHQVLW \ 9 DO
XH
6 SHFLILF JUDYLW
\ 9 DO
XH NJ P
7HVWW HP SHUDWXUH &
6 ROXELOLW
\ GHVFULSWLRQ 6 RO
XEOH LQ 2 UJDQLF VRO YHQW
V 1 RWVRO
XEO
H LQ Z DW
HU
3 DUWLW
LRQ FRHIILFLHQWQ RFWDQROZ DW
HU 9 DO
XH
6 SRQW DQHRXV FRP EXVW DELO
LW
\ 9 DO
XH ! &
9 LVFRVLW\ 9 DO
XH P 3 DV
0 HWKRG RI W
HVW LQJ . LQHP DW
LVN
7HVWW HP SHUDWXUH &
2W
KHULQIRUP DW
LRQ
6 ( &7,2 1 6W
DELO
LW\ DQG UHDFW
LYLW
\
5 HDFW
LYLW
\
5 HDFW
LYLW
\ + HDW
LQJ P D\ FDXVH D ILUH
&KHP LFDOVW
DELOLW
\
6W
DELO
LW
\ 6W
DEO
H XQGHUW
KH SUHVFULEHG VW
RUDJH FRQGLW
LRQV
3 RVVLELOLW
\ RI KD] DUGRXV UHDFW
LRQV
3 RVVLELO
LW
\ RI KD] DUGRXV UHDFW
LRQV 1 RWNQRZ Q
&RQGLW
LRQV W
R DYRLG
&RQGLW
LRQV W
R DYRLG $ YRLG KHDWIO
DP HV DQG RW
KHUVRXUFHV RI LJQLW
LRQ
,QFRP SDW
LEOH P DW
HULDOV
0 DW
HULDO
VWR DYRLG $ YRLG FRQWDFWZ LW
K R[ LGLVLQJ DJHQW
V H J QLW
ULF DFLG SHUR[ LGHV DQG
FKURP DW HV 6 W
URQJ DFLGV
+ D] DUGRXV GHFRP SRVLW
LRQ SURGXFW
V
+ D] DUGRXV GHFRP SRVLW
LRQ SURGXFW
V ) LUH FUHDW
HV &DUERQ P RQR[ LGH &2 &DUERQ GLR[ LGH &2
Universitas Indonesia
198
; \O
HQH 3 DJH RI
5 HSURGXFW
LYH W
R[ LFLW
\ 1 RWNQRZ Q
6 ( &7,2 1 ( FRO
RJLFDOLQIRUP DW
LRQ
7R[ LFLW
\
$ FXW
H DTXDW
LF ILVK 9 DOXH P J O
0 HW KRG RI W
HVWLQJ / &
) LVK VSHFLHV 5 RFFXV VD[ DW
LO
LV
' XUDWLRQ K
$ FXW
H DTXDW
LF DO
JDH 9 DOXH ! PJ O
0 HW KRG RI W
HVWLQJ ,&
$O JDH VSHFLHV 6 HO HQDVW
UXP &DSULFRUQXP
' XUDWLRQ K
$ FXW
H DTXDW
LF ' DSKQLD 9 DOXH PJ O
0 HW KRG RI W
HVWLQJ ( &
' DSKQLD VSHFLHV ' DSKQLD P DJQD
' XUDWLRQ K
3 HUVLVW
HQFH DQG GHJUDGDELOLW
\
3 HUVLVW
HQFH DQG GHJUDGDELOLW
\ /lW
WQHGEU\ W
EDUDY ELRO
RJLVND RUJDQLVP HU
GHVFULSWLRQ
&KHP LFDOR[ \ JHQ GHP DQG &2 ' 9 DO
XH
0 HWKRG RI W
HVW
LQJ &2 '
%LRO
RJLFDOR[ \ JHQ GHP DQG %2 ' 9 DO
XH
0 HWKRG RI W
HVW
LQJ %2 '
%LRDFFXP XODW
LYH SRW
HQW
LDO
%LRDFFXP XODW
LYH SRWHQWLDO : LO
OQRWELR DFFXP XO
DWH
%LRFRQFHQWUDW
LRQ IDFWRU %&) 9 DO
XH
0 HWKRG RI W
HVW
LQJ %&)
0 RELOLW
\ LQ VRLO
0 RELO
LW
\ 7KH SURGXFWLV LQVRO
XEO
H LQ Z DW
HUDQG Z LO
OVSUHDG RQ W
KH Z DW
HUVXUIDFH
5 HVXOW
V RI 3 %7 DQG Y3 Y% DVVHVVP HQW
3 %7 DVVHVVP HQWUHVXO
WV 7KLV VXEVW
DQFH LV QRWFO
DVVLILHG DV 3 %7 RUY3 Y%
2W
KHUDGYHUVH HIIHFW
V
2W
KHUDGYHUVH HIIHFW
V 5 HP DUNV 1 RQH NQRZ Q
6 ( &7,2 1 7UDQVSRUWLQIRUP DW
LRQ
8 1 QXP EHU
$' 5
5 ,'
,0 ' *
,&$ 2 ,$ 7$
8 1 SURSHUVKLSSLQJ QDP H
$' 5 ; </ ( 1 ( 6
Universitas Indonesia
199
HQH
; \O 3 DJH RI
5 ,' ; </ ( 1 ( 6
,0 ' * ; </ ( 1 ( 6
,&$ 2 ,$ 7$ ; </ ( 1 ( 6
7UDQVSRUWKD] DUG FODVV HV
$' 5
+ D] DUG QR
5 ,'
$' 1
,0 ' *
,&$ 2 ,$ 7$
3 DFNLQJ JURXS
$' 5 ,,,
5 ,' ,,,
,0 ' * ,,,
,&$ 2 ,$ 7$ ,,,
DOKD] DUGV
( QYLURQP HQW
&RP P HQW HYDQW
1 RWUHO
LRQV IRUXVHU
6 SHFLDOSUHFDXW
( P6 ) ( 6 '
R $ QQH[ ,, RI 0 $ 5 3 2 /
7UDQVSRUWLQ EXON DFFRUGLQJ W KH ,%& &RGH
DQG W
6 ( &7,2 1 DW
5 HJXO LRQ
RU\ LQIRUP DW
( & QR
\ KHDO
6 DIHW W DW
DOUHJXO
K DQG HQYLURQP HQW HJLVODW
LRQV O KH
LRQ VSHFLILF IRUW
VXEVW XUH
DQFH RUP L[ W
LRQ
KHU/ DEHO,QIRUP DW
2W 5 HJXO DWLRQ ( & 1 R KH ( XURSHDQ 3 DUO
RI W LDP HQWDQG RI W KH &RXQFLO
RI ' HFHP EHU RQ FODVVLILFDWLRQ ODEHO LQJ DQG SDFNDJLQJ RI VXEVW
O DQFHV
DQG P L[ WXUHV DP HQGLQJ DQG UHSHDO LYHV
LQJ ' LUHFW ( ( & DQG (&
DQG DP HQGLQJ 5 HJXO DWLRQ ( & 1 R K DP HQGP HQW
Z LW V
DW
/ HJLVO DW
LRQ DQG UHJXO LRQV ' DQJHURXV 6 XEVW DQFH ' LUHFWLYH ((&
7KH &KHP LFDO V + D] DUG ,QIRUP DWLRQ DQG 3 DFNDJLQJ IRU6 XSSO \ 5 HJXODWLRQV
6, 1R
7KH / LVWRI : DVW HV ( QJO DQG $ P HQGP HQW5 HJXO DWLRQV 6, 1R
$ YIDOOVI| URUGQLQJHQ
\ DVVHVVP HQW
&KHP LFDOVDIHW
6 ( &7,2 1 2W LRQ
KHULQIRUP DW
+ D] DUG V\ P ERO
5 SKUDVHV 5 )O DP P DEO H
5 ,UULWDWLQJ WR VNLQ
5 + DUP IXOE\ LQKDODW O
LRQ DQG LI VZ DORZ HG
5 ,UULWDWLQJ WR VNLQ
6 SKUDVHV 6 . HHS FRQW DLQHUW O
LJKW\ FORVHG
6 . HHS DZ D\ IURP VRXUFHV RI LJQLW LRQ 1 R VP RNLQJ
&ODVVLILFDW R
LRQ DFFRUGLQJ W )ODP / LT +
5 HJXODWLRQ ( & 1 R $ FXWHW R[ +
>&/ 3 * + 6 @ 6 NLQ ,UULW +
Universitas Indonesia
200
; \O
HQH 3 DJH RI
$ FXWHW R[ +
/ LVWRI UHO
HYDQW5 SKUDVHV XQGHU 5 ,UULWDWLQJ WR VNLQ
KHDGLQJV DQG 5 + LJKO \ IODP P DEOH
5 )O DP P DEO H
5 + DUP IXOE\ LQKDO DWLRQ DQG LQ FRQW
DFWZ LW
K VNLQ
5 + DUP IXOE\ LQKDO DWLRQ
/ LVWRI UHO
HYDQW+ SKUDVHV 6 HFW
LRQ + + DUP IXOLI LQKDOHG
DQG + + DUP IXOLQ FRQW DFWZ LW K VNLQ
+ + LJKO \ IO
DP P DEOHO LTXLG DQG YDSRXU
+ )O DP P DEO HOLTXLG DQG YDSRXU
+ &DXVHV VNLQ LUULW DWLRQ
5 HVSRQVLEO
H IRUVDIHW
\ GDW
D VKHHW ) UHG + RO P EHUJ &R $ %
Universitas Indonesia
201
Universitas Indonesia
202
Universitas Indonesia
203
Universitas Indonesia
204
Universitas Indonesia
205
Universitas Indonesia
206
Universitas Indonesia
207
Universitas Indonesia
208
Universitas Indonesia
209
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Date of issue: 03/21/2014 Version: 1.0
Universitas Indonesia
210
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Universitas Indonesia
211
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Universitas Indonesia
212
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Universitas Indonesia
213
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Universitas Indonesia
214
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Specific target organ toxicity (repeated : May cause damage to organs through prolonged or repeated exposure.
exposure)
Aspiration hazard : May be fatal if swallowed and enters airways.
Symptoms/injuries after inhalation : EXPOSURE TO HIGH CONCENTRATIONS: Headache. Nausea. Feeling of weakness.
Dizziness. Central nervous system depression. Narcosis. Mental confusion. Drunkenness.
Coordination disorders. Disturbed motor response. Disturbances of consciousness.
Symptoms/injuries after skin contact : Tingling/irritation of the skin.
Symptoms/injuries after eye contact : Irritation of the eye tissue.
Symptoms/injuries after ingestion : Risk of aspiration pneumonia. Nausea. Abdominal pain. Symptoms similar to those listed unde r
inhalation.
Chronic symptoms : ON CONTINUOUS/REPEATED EXPOSURE/CONTACT: Dry skin. Skin rash/inflammation.
Impairment of the nervous system. Tremor. Impaired memory. Impaired concentration. Brain
affection. Disturbances of heart r ate. Change in the haemogramme/blood composition.
Likely routes of exposure : Inhalation;Skin and eye contact
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
DOT Vessel Stowage Location : B - (i) The material may be stowed ‘‘on deck’’ or ‘‘under deck’’ on a cargo vessel and on a
passenger vessel carrying a number of passengers limited to not more than the larger of 25
passengers, or one passenger per each 3 m of overall vessel length; and (ii) ‘‘On deck only’’ on
passenger vessels in which the number of passengers specified in paragraph (k)(2)(i) of this
section is exceeded.
Additional information
Other information : No supplementary information available.
ADR
Transport document description : UN 1294 Toluene, 3, II, (D/E)
Packing group (ADR) : II
Class (ADR) : 3 - Flammable liquids
Hazard identification number (Kemler No.) : 33
Classification code (ADR) : F1
Danger labels (ADR) : 3 - Flammable liquids
Orange plates :
Transport by sea
UN-No. (IMDG) : 1294
Class (IMDG) : 3 - Flammable liquids
EmS-No. (1) : F-E
EmS-No. (2) : S-D
Air transport
UN-No.(IATA) : 1294
Class (IATA) : 3 - Flammable Liquids
Packing group (IATA) : II - Medium Danger
Universitas Indonesia
217
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
EU-Regulations
No additional information available
Universitas Indonesia
218
Toluene
Safety Data Sheet
according to Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations
Information in this SDS is from available published sources and is believed to be accurate. No warranty, express or implied, is made and LabChem Inc assumes no liability resultin g from the use of this
SDS. The user must determine suitability of this information for his application.
Universitas Indonesia
Universitas Indonesia
220
Universitas Indonesia
221
Refrigation
Accecories
Factory
Taishan Group 135,055,60 137,263,67 101
E-101 1 2016 672.2 9,994.12 3.17 435,125,844 32199.31251
Co.,Ltd 9 3 58
Siping Zhongbao
121
E-102 1 He Device 2016 672.2 16,206,691 1,199.30 16,471,659 3.17 52,215,160 3863.921854
9
Co.,Ltd
Reactor
Foshan Jct
1,107,463, 1,225,990, 4. 5,100,122,1
R-100 1 Machinery 2013 617.14 81,952 90723 377409.0368
545 893 16 14
Co.,Ltd
Wuci Teneng
675,277,00 747,549,17 4. 3,109,804,5
R-101 1 Power Machinery 2013 617.14 49,970.50 55319 230125.538
5 4 16 64
Co.,Ltd
Distillation Column
V-100;V- Zhengjiu 4.
2 2016 672.2 51,401,334 3804 52,241,710 3866 434,651,026 32164.17597
102 Machinery 16
Storage Tank
S-100 1 Mie Fibro Tech 2011 585.7 11,350,000 840 13,239,212 980 4. 55,075,122 4075.559043
Universitas Indonesia
222
& Engineering 16
S-101;S- Mie Fibro Tech 4.
2 2011 585.7 40,516,562 2,998.23 47,260,560 3497 393,207,855 29097.38132
102 & Engineering 16
Cyclone
Weihai Haiwang
Mining
C-100 1 2011 585.7 17,598,787 1,302.31 20,528,112 1519 1 20,528,112 20528112.16
Equipment
Co.,Ltd
Weihai Haiwang
Mining
C-101 1 2011 585.7 67,700,516 5,009.84 78,969,294 5844 1 78,969,294 78969293.77
Equipment
Co.,Ltd
Flash Drum
Weifang Jijanti
D-100 1 Equipment 2011 585.7 13,505,548 999.41 15,753,552 1166 1 15,753,552 1165.76288
Co.,Ltd
Utility
Pump
Pt. Dwijaya 3.
J-501 1 2016 672.2 8,232,000 609 8,366,587 619 27,609,739 2043.120656
Selaras 3
Universitas Indonesia
223
J-502;J-
Sentralpompa.Co 3.
503;J- 4 2016 672.2 2,875,000 213 2,922,004 216 38,570,456 2854.213744
m 3
504;J505
Sand Water Filter
2.
F-500 1 Pentair 2016 672.2 40,650,000 3008 41,314,599 3057 95,849,870 7092.890377
32
Ion Exchanger
R-501;R- 2.
2 Pentair 2016 672.2 40,650,000 3008 41,314,599 3057 191,699,740 14185.78075
502 32
Storage Tank
Tt-501, Mie Fibro Tech
2 2016 672.2 11,350,000 840 11,535,565 854 1 23,071,129 1707.263557
Tt-502 & Engineering
Mie Fibro Tech
Tt-503 1 2016 672.2 5,675,000 420 5,767,782 427 1 5,767,782 426.8158893
& Engineering
Aerator
Luqiang Energy
R-503;Cl-
2 Equipment 2016 672.2 13,505,548 999.41 15,753,552 1166 1 31,507,105 2331.52576
500
Co,Ltd
100,249,369.
Total Bare Module
15
Universitas Indonesia
224
Universitas Indonesia
225
Universitas Indonesia
226
Universitas Indonesia
227
The above costs are based on the Indonesia’s Law of Industry No 14 2001
and the service companies such as Telkom, Telkomsel, and PDAM. There are
other costs that are still need to be calculated. The calculation will be in the “Total
CAPEX” sub-chapter.
APPENDIX F4 : Depreciation
Universitas Indonesia
228
Supporting
Value Main Equipment Land and Building Total
Equipment
Initial
Value in 1st 82,958,831 101,639 87,300,748
year
D 8,295,883 10,164 8,730,075 17,036,122
Year 1
SV 74,662,948 91,475 78,570,673
D 7,466,295 9,148 7,857,067 15,332,510
Year 2
SV 67,196,653 82,328 70,713,606
D 6,719,665 8,233 7,071,361 13,799,259
Year 3
SV 60,476,988 74,095 63,642,245
D 6,047,699 7,409 6,364,224 12,419,333
Year 4
SV 54,429,289 66,685 57,278,020
D 5,442,929 6,669 5,727,802 11,177,399
Year 5
SV 48,986,360 60,017 51,550,218
D 4,898,636 6,002 5,155,022 10,059,660
Year 6
SV 44,087,724 54,015 46,395,197
D 4,408,772 5,402 4,639,520 9,053,694
Year 7
SV 39,678,952 48,614 41,755,677
D 3,967,895 4,861 4,175,568 8,148,324
Year 8
SV 35,711,057 43,752 37,580,109
D 3,571,106 4,375 3,758,011 7,333,492
Year 9
SV 32,139,951 39,377 33,822,098
D 3,213,995 3,938 3,382,210 6,600,143
Year 10
SV 28,925,956 35,439 30,439,888
D 2,892,596 3,544 3,043,989 5,940,128
Year 11
SV 26,033,360 31,895 27,395,900
D 2,603,336 3,190 2,739,590 5,346,116
Year 12
SV 23,430,024 28,706 24,656,310
D 2,343,002 2,871 2,465,631 4,811,504
Year 13
SV 21,087,022 25,835 22,190,679
D 2,108,702 2,584 2,219,068 4,330,354
Year 14
SV 18,978,320 23,252 19,971,611
Year 15 D 1,897,832 2,325 1,997,161 3,897,318
Universitas Indonesia
229
APPENDIX F5 : Depreciation
Deviation Product Price (US$) IRR NPV (US$) PBP (year)
-15% 935 5.90% -45,550,266,735 8.651
-10% 990 7.91% -21,093,291,053 6.897
-5% 1,045 9.80% 3,363,684,628 5.762
0% 1,100 11.60% 27,820,660,309 4.947
5% 1,155 13.33% 52,277,635,991 4.351
10% 1,210 15.01% 76,734,611,672 3.875
15% 1,265 16.65% 101,191,587,354 3.504
Deviation Raw Material Price (US$) IRR NPV (US$) PBP (year)
-15% 11,014,555 13.25% 51,014,949,895 4.370
-10% 11,662,470 12.71% 43,283,520,033 4.550
-5% 12,310,385 12.16% 35,552,090,171 4.742
0% 12,958,300 11.60% 27,820,660,309 4.947
5% 13,606,215 11.04% 20,089,230,448 5.184
10% 14,254,130 10.47% 12,357,800,586 5.444
15% 14,902,045 9.90% 4,626,370,724 5.724
Universitas Indonesia
230
Deviation Total Labor Cost (US$) IRR NPV (US$) PBP (year)
-15% 832,108 12.22% 36,384,060,360 4.724
-10% 881,055 12.01% 33,529,593,677 4.796
-5% 930,003 11.81% 30,675,126,993 4.871
0% 978,950 11.60% 27,820,660,309 4.947
5% 1,027,898 11.40% 24,966,193,626 5.028
10% 1,076,845 11.19% 22,111,726,942 5.117
15% 1,125,793 10.98% 19,257,260,259 5.207
Universitas Indonesia