Sample: Six Sigma Black Belt Project Report
Sample: Six Sigma Black Belt Project Report
SAMPLE
Six Sigma Black Belt Project Report
1
Aveta Six Sigma Online Black Belt Course
Executive Summary
As a new subsidiary of an established company moving into a new business, establishing a reputation for
solid customer service at a low price is paramount for the Security Department’s new serivce. Along the
way, the business manager discovered that the idea of a solid customer service reputation was in jeopardy,
but felt the personal service could not be beat. Under that presumption, he solicited help to use Six Sigma
processes to 1) validate the perception, 2) propose a recommendation for solutions and 3) put processes in
place to ensure control in the long run.
The Problem
After research and survey, we found that site managers were pleased to be moving to the new video
surveillance technology, but they were disappointed in the number of outages they were seeing in the
equipment. After measuring the process, we found there were several reasons for outages:
Of these, the latter proved to be the most costly and unexplainable. According to information from the
manufacturer, we should not see the kinds of problems we were having. The estimated cost for these
repairs exceeds $70,000 annually and has an untold impact on Operations.
The Process
Using the Six Sigma process of Define-Measure-Analyze-Improve-Control, we determined what the
priority is for the Security technical group. We then chartered a project and proceeded to understand and
define the problem. Through customer surveys, site visits and data gathering began to focus on the real
issues at hand. To help clarify the situation, we mapped the installation and support processes for the
security equipment finding and correcting issues as we went.
Eventually, the measurement and analysis processes pointed to the fact that we had a real issue that was
out of the ordinary for the equipment in service. Fortunately, we had clear concise records and good
support from the manufacturer to help research and resolve the problem.
Findings
As the old adage goes from a well-known Houston media personality, we had “slime in the ice machine!”
More importantly we had significant amounts of dirt in the machines. A by-product of the process/project
was that we discovered the Information Technology team was having the same issue, just not quite to the
same extreme.
With some research, the team did find a low cost solution to protect the machines. While it is early in the
post-solution phase, we are seeing improvements.
Conclusion
By using a systematic approach, we identified several areas in the process that needed modification. The
net result is a longer machine life with an expected savings of more than $70,000 annually as well as
improved customer service. Based on the proactive response to their issues, the Operations Management
teams of both the internal and external customers are beyond satisfied and are serving as excellent
references for the Security Department.
2
Aveta Six Sigma Online Black Belt Course
Definition Phase
Project Opportunities
As a new subsidiary business within a well established, large company, the Security Department
has several competing projects for a small staff. They find themselves needing to balance on-
going operations, roll out of more services to the parent company and new sales opportunities for
external customers. For internal customers, the goal is to provide excellent security service -
burglar, fire and equipment monitoring - as well as video coverage (with historical recordings) of
the operations area. For external customers, their strategy is to utilize their existing staff to
provide low cost services for monitoring alarms. Their goal continues to be low price and
excellent customer service. Excellent customer service is defined as reducing false alarms and
properly maintaining equipment for legitimate alarms as well as providing video services for
those wanting to pay for it. In order to fully understand what was important to the customers, we
conducted a survey to understand what people are expecting from the Security Department.
From that survey, table 1 lists potential projects1 identified from on-going operations and for
future customer sales.
In discussions with senior management, internal customers, call center employees and potential
external customers, the Security Department used a weighting to help determine what to focus on
first. Based on input, they weighed customer satisfaction as critical since their predominant
advertising mechanism is going to be word of mouth for the first year of the new subsidiary. By
using the results from Table 1, the Security Department decided to investigate the perception of
DVR failures since it had a direct link to customer services. As a side note, this was not even on
their list of potential projects prior to the survey.
Site Manager (parent company) - “Being able to review and monitor transaction
processing via video is critical. I never would have thought I would say that since I
avoided the technology. Now, I can’t live without it. When the camera systems are
down, it costs me money. If everyone knows it is down, I can’t image what they are
doing.”
1
Actual list is longer. The list was truncated to simplify this report
3
Aveta Six Sigma Online Black Belt Course
Safety Manager (parent company) - “By having video access (and more importantly
recording), I have ‘eyes in the back of my head’. This technology extends my ability
to cover a site and find issues before they have a negative impact on the business. An
outage, especially an extended one, raises a great deal of concern.”
Security Director (external customer, multiple sites) – “The potential of the service is
incredible, but the number of camera failures is frustrating. If we do not resolve this
problem, then I will have to cut services back to the basics.”
While these represent the extreme comments, several people made similar comments. The last
one (and others like it) is what made Management sit up and take notice of a problem. Based on
the scoring, conversations regarding customer service and potential impacts to their reputation of
service challenges, the Company decided to authorize a project to investigate the perception and
implement solutions if the allegations proved to be true. Remember this is a new subsidiary and
working under “word of mouth” advertising.
Project Charter
A summary (retyped version to simplify project submission) is shown in Table 2 below. The
original has full company and employee names along with telephone numbers and signatures.
PROJECT INFORMATION
Project Name: Chartered Date:
Investigate & Resolve DVR Failure 6/1/06
TEAM SPONSORS
Project Sponsor: Contact Number:
Doug – Security Monitoring Director
4
Aveta Six Sigma Online Black Belt Course
PRINCIPLE STAKEHOLDERS
Name Role
Zack VP – Security
Bill ABC Customer – Security Manager
Doug Security Monitoring Director & Sponsor
SLT Senior Leadership Team
PROJECT GOALS
Identify any deficiency in DVR performance. Assuming a deficiency, implement
corrective actions to resolve the problem and return performance to documented
performance standards. In the absence of a deficiency, document performance
expectations and discuss with the customers.
The following was added in revision 2 of the project charter after finding
installation issues:
PROCESS PROBLEM
The following was added in revision 2 of the project charter after finding
installation issues:
Under certain installation conditions, the DVRs are failing prematurely. The
apparent cause of the issue is dirt. Certain operational environments are outside
recommended standards – the actual offices are temporary spaces that have a high
volume of traffic in a construction type environment. The result is the server fans
are pulling in too much dust and dirt for the servers to function properly.
SCOPE OF PROJECT
The following are the items that have been identified as the scope requirements:
5
Aveta Six Sigma Online Black Belt Course
PROCESS IMPORTANCE
The video support function is a significant value added service provided by the
Security department. Some of the potential savings and findings are listed below:
Monitor cash point of sales to discover fraud. One site reported savings of
$500-$750 per day. The reports indicated that it had been going on for years.
While that kind of fraud is extreme and rare, it does occur.
In addition to these findings, the external customers are expecting to save a great
deal on safety audits and inventory shrinkage discovery. While they have not
documented their savings to the company, it is clear they are expecting to save
over $100,000 annually. As the project team interviews the stakeholders to
confirm their interest in the project, they will document more regarding cost
savings.
AUTHORIZED RESOURCES
While the sponsor will facilitate getting a funding stream, Zack will also
help. He is also responsible for answering to the Senior Leadership Team
6
Aveta Six Sigma Online Black Belt Course
Team Members –
Matt Security Supervisor
Alex Technician
Sharron Customer Service Representative
Barry Installation Specialist
Jeff IT Analyst
Nick DVR Vendor Representative
Outside Needs
Some travel to locations may be required as part of understanding the installation
process. The point of having experienced team members (Jeff, Nick and Barry)
on the team is to minimize that need since they have worked in the various sites.
Training needs are unknown at this time, but expected to be minimal based on
the experience of those selected to participate. They were chosen under the
theory that they have “seen everything”.
Table 2: Project Charter
7
Aveta Six Sigma Online Black Belt Course
Project Schedule
Figure 1 is a schedule drafted early in the discovery process the edited as data became available. The
control phase is documented in later sections.
8
Aveta Six Sigma Online Black Belt Course
Process map
Since the results of the original survey were a surprise to the security team, we documented the setup
process (figure 2) as well as the trouble shooting and repair processes (figure 3) as well.
Request review by
Cost review by site
Security Dept Implement Security orders
management & Yes
Request from Site (cost & equipment Video? equipment
Security
for Video estimate)
No
Equipment staging
(separate process
Counterproposal chart for this)
Yes Cost Issue?
for other options
No
Site prepares for
No implementation data and power
requirements
No
Special notes:
As a by product of creating the process maps for system setup, we discovered three significant points.
First, some items were not being configured consistently or at all. Some of that depended on the
technician handling the process. The second item is that the sites were not necessarily prepared for the
implementation process. In many cases, the local installation technician needed to arrange for power and
data cabling once on site. That loop is shown in the setup process above. The third was the need to create
a knowledge base for troubleshooting (figure 3 – troubleshooting). In evaluating the process, one
technician was generally perceived as a bottleneck. In reality, he had a better process for handling issues
which resulted in a better resolution rate. That is not documented in the results for this particular project.
9
Aveta Six Sigma Online Black Belt Course
Technician works
Problem Full system
Onsite personel Yes troubleshooting A
exists? outage?
notice issue and process*
call in Yes
No
Dispatch regional User resolvable Review camera Camera
No Yes
camera contractor with instruction? specific issue specific issue
Reboot DVR
No No
No Yes
Review DVR
Camera contract DVR Restart
processes with
contacts central Yes Functional normal?
Issue resolved user (training as
technician to Issue?
required)
diagnose &
resolve No
Yes
Review error
Return to messages
A No Issue resolved Yes Yes Yes
production
Resolve per
Microsoft or DVR
Software
Issue resolved vendor Yes
Error?
specifications &
standards
No
No
Hardware repaired
Customer ship unit Hardware
and returned per
to central support error?
set up process
From the troubleshooting and repair process, we found that several machines were being returned to the
central support group. The general perception is that anytime a machine is taken out to be shipped, the
overall outage is entirely too long and expensive. From that information and perception, we were in a
position to evaluate run times, environment and impact to the business. Some of the items that we felt are
critical to customer satisfaction or needed to be understood for comparison purposes are as follows (the
list grew after the first analysis iteration):
10
Aveta Six Sigma Online Black Belt Course
In addition, we did discover that the central technical support staff was keeping detailed notes on the
various things they were finding with each returned machine. They were just not making a point of
discussing how many machines they were seeing with the management team. In the long run, the notes
saved a great deal of time in getting to the final solution. That is noted in the section discussing the
Analyze Phase to follow.
Lastly, we also wanted to make sure that we understood the impact to the customer for each outage. The
general opinion was certain outages were “less expensive” than others. We would use the Measurement
Phase to help drive where to look:
Using the information from above regarding the key measures, we then determined that the
critical quality variable is system availability. That is generally stated as operating hours per
month at the DVR level or more importantly as the time in service before failure. In some cases,
the camera level data also becomes important, but not all cameras are equivalent. In order to
keep the measurement process at a definable level, we focused at the DVR level overall. Camera
level analysis at specific locations may become a target for review in the future.
Following the decision to treat issues at the DVR level, we worked to understand the relationship
among the different items as they relate to cost and business impact. The following are some of
the items that we discovered:
11
Aveta Six Sigma Online Black Belt Course
1) The hard dollar costs are a dependent item, so tracking them independently is not
required.
2) Network outages generally do not have a long term negative impact. The DVR
continues to record and the data can be accessed once the network is available. As a
result, we only used 4 weeks worth of data for analysis purposes. A later study will
work with the external network provider to improve that service.
3) Opinions on soft dollar outages vary significantly based on location type. For
example, sites with high volume of cash transactions (Operations) feel an outage is
significantly more expensive than an office environment. As such, those numbers are
not included in outage estimates in order to be more conservative on savings. Any
presentation to business leaders did discuss potential numbers around soft costs.
The end result is that the key variables for monitoring are the following:
1) Number of hours of outage – relates to total cost for the outage
2) Number of units returned to central support
3) Operating time to failure
The latter uses the definition of failure as some event that requires removing the machine for
maintenance (actual failure or diagnostics). Appendix A lists some of the raw data used to arrive
at the conclusions listed above and to create the Pareto chart shown in Figure 4 & 5. Due to the
correlation between labor effort and outage costs, Figure 5 pointed to the area needing attention –
specifically that the DVR hardware maintenance uses more labor. The next question needing
research was to find out how the DVRs were performing in relation to performance
specifications. Some of the data for figure 5 as well as subsequent analysis came directly from
the central support maintenance logs. A sample log sheet is shown in Appendix B.
140
120
100
80
60
40
20
0
Network DVR Hardware User issue Software Network Hardware
Cause of Outage
12
Aveta Six Sigma Online Black Belt Course
300
250
200
Total
150
100
50
0
DVR Hardware Network Hardware Software User issue Network
Cause of Outage
Taking figure 5 a step further, we then analyzed the outages over the sample time. Figure 6
shows the findings. Using the outages per week against an upper limit (lower limit was set to
zero since it could not be negative), we found the actual outages to be “in control” meaning that
whatever perception site management may have, it was consistent and unless we changed
something, it would continue; however, the perception remains that there were too many outages
for their expectations.
5
Count of Outages
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Week
Outages Average UL
Taking this information and translating that into business impact, each outage has an average
cost of $597 in repairs (labor, parts, shipping), an average outage of 70.15 hours and 2.44
outages per week. (Appendices B and C show cost and outage information.) The distribution of
the outages is shown in Figure 6 previously. This does not attempt to quantify the “soft” dollar
costs since the various locations have such a diverse definition of what the cameras are saving
them. However, we do know that Internal Audit has a concern about the availability of the video
to the point that they have not cancelled any trip in lieu of video coverage.
In order for Internal Audit to “get comfortable” with video coverage and to ease site
managements concern about outages, the management team mandated cuting the outages from
an average of over 2 per week to 2 per month (1 every other week). That mandate equated to
more than $60,000 savings annually in hard dollars. Again, the soft dollar costs are not
documented. The questions needing to be addressed where 1) is this possible within the
environment and 2) what would it take? The first question addresses the issue around why are
the DVRs failing and is the failure within the manufacturing tolerances. The second question is
based on the assumption that there was something within the environment causing the problem
and not a manufacturing issue.
In order to understand how the failure rate compared to what should be expected, we went back
to the original installation information. While much of the information was available, there were
some assumptions needed:
Using those assumptions, we then compared observed service life with expected performance.
While expected performance can be expressed in many terms, we elected to use a conservative
definition of warranty period.2 Based on that expectation, we found the following:
Number of Failures 39
Total Population 508
Average Time to Failure (days) 382.87
Warranty Period 1080
To further understand the outages and impact, we then analyzed which sites were experiencing
the problems. That also relates to the actual business impact of the outages. In theory, zero
revenue sites have less at stake (soft cost) than revenue sites. Table 3 shows the largest portion
of outages effect operational facilities. Table 4 gives the installation base as background.
14
Aveta Six Sigma Online Black Belt Course
We also took one more assumption – namely that all DVRs that have not failed will not fail
before reaching the warranty level (3 years). With that assumption, we then recalculated the
average time to failure as 1026.48 days with a standard deviation of 187.84 days. When plotting
that in a control chart, most all of the failed units are outside of the control limits. Figures 7 and
8 show that information (the tools are limited so that 508 points cannot be included in one chart).
These assumptions putting the failures outside of the control limits are conservative. Most
notably is that our sample mean is less than 3 years. The actual mean from the manufacturer is
more than three years – thus the warranty set at that point. A call to the manufacturer outlining
our problem got us this information. That call and subsequent discussions resulted in finding
that they are not seeing out of the ordinary challenges like this. After that call, they have
cooperated in our investigation by sending a systems engineer to work with us through the later
phases of the project.
15
Aveta Six Sigma Online Black Belt Course
1800
1600
1400
Days in Production
1200
1000
800
600
400
200
0
DVR (1-255)
1800
1600
1400
Days in Production
1200
1000
800
600
400
200
0
DVR (256-508)
2000
1800
1600
1400
Days in Production
1200
1000
800
600
400
200
0
Failed DVRs Time In Production
Based on this new data (or more accurately, based on this relevant comparison), we can conclude
that we are not seeing the expected life we should see. Something is causing the DVRs to fail
16
Aveta Six Sigma Online Black Belt Course
prematurely. At that point, the team used a brain storming session to develop the cause and
effect diagram shown in figure 7. Many of the items shown on the diagram were directly from
the technicians’ maintenance notes (sample form shown in Appendix B). While the
manufacturing area is a process that could have problems, we tended to focus on the items that
were handled internally. Everyone is aware that some machines will fail prematurely due to
manufacturing challenges. If we get to the point where that is the only cause, then we will
initiate another project to resolve that problem.
Manufacturing Installation
Damage in
shipping Improper
wiring
DVR
Failure
Power surges
No
Out of date Preventive
drivers Maintenance
Dirt
Missing virus
software Untrained
users
Configuration Production
& Staging Environment
Improvement Phase
Using the information from Figure 10 and the maintenance logs, we took each of the causes and
evaluated their true impact on the problem:
17
Aveta Six Sigma Online Black Belt Course
5) Untrained users
This is an issue for the technicians handling telephone calls. It is not a cause of
hardware failure. The user security and software prevent the users from damaging the
data. This topic will be analyzed for a future project.
6) Dirt
After reviewing the maintenance notes, this jumped out as the most likely cause of
issues in the operating locations. All of the maintenance logs for operations locations
referenced an abnormal amount of dirt in the machines. Based on that, the
installation specialist, technician and systems engineer from the vendor went to a
field location – specifically to a site of a failed DVR. The following outlines their
statements:
The operating locations tend to be temporary buildings much like you would find on a
construction site. One of the external customers is actually a construction firm.
Generally, there is a lot of dirt movement with large equipment causing a dusty
environment all around. The other observation was that the machines were not being
carefully placed. Basically, the site personnel tend to direct where the machines will
be placed and thinking of the machine’s health is not high on their list.
Based on the maintenance notes and site observations, we needed to find a way to protect the
equipment. Once again, the team headed into a brain storming session. Unfortunately, this time
did not produce a lot of results; however, Google™ saved the day. There are several inexpensive
covers and keyboard skins on the market. The resulting action plan followed:
1) All DVRs (and servers after a discussion with the IT group) in operations will have
dust covers.
2) All keyboards will have keyboard skins
3) IT staff will perform routine cleaning of the DVRs and servers when on site.
Compressed air cans are now standard issue.
Further checks will be needed to see if the above recommendations are necessary at transfer
stations and office locations.
To pilot the process, we pulled two machines at the same site (some sites have multiple DVRs)
from service for a quick preventive maintenance routine and cleaned them thoroughly. As they
went back into service, one was covered with a dust cover and key board skin and the other was
not. After a week, the team went back to the site to review the state of the machines. While it is
not conclusive, there was a noticeable difference in the machines. Only a longer period of time
and close review of the control charts of outages will clarify the understanding.
18
Aveta Six Sigma Online Black Belt Course
Control Phase
As noted throughout this document, there were several places where we discovered minor deviations from
best practices. As part of the ongoing control, there are several steps that are in place (or soon will be) to
control and monitor the production environment:
As you can tell from the brevity of the control section, we have not had time to confirm the results. This
has literally just been completed. Early indications from Security and IT are things are definitely on the
right track. Continued observation will tell the tale.
Conclusion
The net result of the project was more than anticipated in hard dollar savings. While we have not proven
that we are down to one outage every other week, the early indications are good. In addition, the IT
group is also seeing a reduced hardware outage issue, but not quite to the same degree. They had a better
preventive maintenance program in place, but protecting the machines and discussing the issue with site
management has proven productive. At this point, the estimated savings from this project is in excess of
$70,000 hard dollars. As stated many times above, there is no estimate on soft dollars. In addition to
that, we have also implemented new policies and practices. Some of those lessons learned include the
following:
By using a systematic approach and truly analyzing the problem, we improved customer service, proved
to be responsive and saved money.
19
Aveta Six Sigma Online Black Belt Course
Function Cost
Contract labor – on site camera work $75/hour
DVR Shipping $50 each way
Central Technical support $20/hour
Network connection (Frame) $1000/month/site
DVRs in production 508
Sites with DVRs 432
The following are the labor estimates for configuring, installing and troubleshooting (many of
these are subject to future study for improvement via Six Sigma):
20
Aveta Six Sigma Online Black Belt Course
The following is a blank maintenance log sheet as generated by the maintenance ticket system.
The process has the technician manually complete the form. Eventually, the data is entered into
the tracking system.
Repair Comments:
21
Aveta Six Sigma Online Black Belt Course
22
Aveta Six Sigma Online Black Belt Course
23