Maximum Loads

This document provides data on nine anchor supports that were identified in the Chiller basement of the Princess Noura Bint Abdulrahman University for Women Project in Riyadh, Saudi Arabia. It lists the joint number, forces (Fx, Fy, Fz), and moments (Mx, My, Mz) for each support, as well as the maximum values of each parameter. The data comes from revised output files from the CESAR II structural analysis software.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
57 views

Maximum Loads

This document provides data on nine anchor supports that were identified in the Chiller basement of the Princess Noura Bint Abdulrahman University for Women Project in Riyadh, Saudi Arabia. It lists the joint number, forces (Fx, Fy, Fz), and moments (Mx, My, Mz) for each support, as well as the maximum values of each parameter. The data comes from revised output files from the CESAR II structural analysis software.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

Princess Noura Bint Abdulrahman University for Women Project Joint venture

Riyadh, Kingdom of Saudi Arabia El Seif/CCC


part / package: package 3 - Utillity area references: time: date:
department: ENGINEERING 1:58 PM 1/16/2018
calcs by: Aleksandar Jankovic sr.str.eng

From the attached revised out put files from CESAR II done by DAR, there are identified nine
anchor supports in the Chiller basement as per following data:

joint No Fx(kN) Fy(kN) Fz(kN) Mx(kNm) My(kNm) Mz(kNm)


190 229.6 77.16 2.143 67.53 6.73 14.62
1620 59.76 74.51 8.7 67.63 86.147 10.52
4375 152.71 166.52 34.307 42.95 20.615 208.38
8390 14.297 104.94 1.64 30.976 40.665 9.93
10045 139.78 48.71 13.09 30.27 51.39 0.717
12570 39.162 67.716 17.448 72.37 57.213 5.08
14300 26.503 76.42 1.43 15.155 26.08 51.51
15640 195.91 90.68 7.247 17.69 74.69 9.814
16815 12.779 100.018 1.43 16.97 13.48 62.213

max: 229.6 -166.52 34.307 72.37 86.147 208.38


Building / area: Chiller bldg rev: CHILLER BUILDING Sheet:
issued for: APPROVAL 1 anchor supports 0 0 4
Joint venture
El Seif/CCC