Chapter 8 Homework Assignment Ver 1.0

This document contains a homework assignment with 6 questions about drawing activity-on-node diagrams, calculating expected times using the PERT method, and identifying critical paths and project durations for schedules with multiple activities. The student is asked to draw diagrams, calculate values, and identify key details like critical paths and slack for a variety of scheduling scenarios.

Uploaded by

Sashi Velnati
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views

Chapter 8 Homework Assignment Ver 1.0

This document contains a homework assignment with 6 questions about drawing activity-on-node diagrams, calculating expected times using the PERT method, and identifying critical paths and project durations for schedules with multiple activities. The student is asked to draw diagrams, calculate values, and identify key details like critical paths and slack for a variety of scheduling scenarios.

Uploaded by

Sashi Velnati
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Chapter 8 Homework Assignment

Chapter 8

Questions

1. Draw an Activity-on-Node Diagram for the following:


Activity Name Predecessor(s)
A None
B A
C A,B
D C
E D
F E

2. Draw an Activity-on-Node Diagram for the following:


Activity Name Predecessor(s)
A None
B None
C A
D A,B
E D
F C
G F,E
H G

3. Using the PERT (Program Evaluation Review Technique) estimating method, calculate the
expected time (TE) for each of the following activities.
Activity Optimistic (days) Pessimistic (days) Most Likely (days)
Activity A 2 12 4
Activity B 5 25 20
Activity C 10 50 18
Activity D 3 10 7
4. Draw an Activity-on-Node Diagram, identify project duration and project critical path for the
following:
Activity Name Predecessor(s) Duration (Weeks)
A None 20
B None 10
C A 10
D A,B 40
E D 10
F E 20

5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and
project critical path for the following:
Activity Name Predecessor(s) Duration (Weeks)
A None 20
B None 10
C None 10
D A,B 40
E C 10
F C,D 20
G E,F 10

6. Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project
duration, and project critical path for the following:
Activity Name Predecessor(s) a m b
A None 20 50 90
B None 10 30 40
C None 10 20 30
D A 20 10 30
E B,C 10 20 30
F C,D 20 30 60
G F 10 20 50