Load Testing
Load Testing
RI 04-006
February, 2005
TECHNICAL REPORT DOCUMENTATION PAGE
CIESfor the facts and the accuracy of information presented herein. This document is
disseminated under the sponsorship of the Center for Infrastructure Engineering
05-57Studies
C (CIES), University of Missouri-Rolla, in the interest of information
exchange. CIES assumes no liability for the contents or use thereof.
ii
The mission of CIES is to provide leadership in research and
education for solving society's problems affecting the nation's
infrastructure systems. CIES is the primary conduit for communication
among those on the UMR campus interested in infrastructure studies and
provides coordination for collaborative efforts. CIES activities include
interdisciplinary research and development with projects tailored to
address needs of federal agencies, state agencies, and private industry as
well as technology transfer and continuing/distance education to the
engineering community and industry.
Written by:
Submitted
January 2005
The opinions, findings and conclusions expressed in this report are those of the principal investigators. They are not
necessarily those of the Missouri Department of Transportation, U.S. Department of Transportation, Federal
Highway Administration. This report does not constitute a standard, specification or regulation.
II
IN-SITU LOAD TESTING OF BRIDGE A6358
OSAGE BEACH, MO
EXECUTIVE SUMMARY
This report presents the assessment of a High Performance Steel (HPS) bridge located at the
Lake of the Ozarks in Miller County, MO. The bridge number is A6358 and it is located on US
Rt. 54/Osage River. Two different modern techniques for Structural Health Monitoring (SHM)
were applied for this purpose, in order to advance their field validation process.
Displacements of the girders during the pouring of the concrete deck and a diagnostic load test,
conducted after the bridge completion, were evaluated using an optical non-contact measurement
technique based on an automated total station system. The setup included a total of 22 reflecting
prisms mounted onto the bottom flange of the girders, plus four reference targets placed outside
the bridge superstructure.
Strain and temperature distributions along some of the girders were measured during the
diagnostic load test using a fiber optic distributed Brillouin sensing technique. The method is
based on the “Brillouin” phenomenon, which defines a linear relation between the axial strain in
an optical fiber, and the corresponding shift in the frequency distribution of the scattered
Brillouin light generated when an optical impulse runs through a fiber. A single optical circuit,
comprised of bare fibers and a custom-made novel glass FRP tape with embedded sensing fibers,
was installed on the web of the girders at different depths, along two continuous spans.
Experimental deflection and strain data were verified to be consistent with each other and
allowed to evaluate the actual girder distribution factors. The comparison between experimental
and theoretical results based on the AASHTO LRFD Bridge Design Specifications (AASHTO,
1998) allowed establishing the safety of the structure, although pointing out a significant drop in
the expected behavior of one of the external girders, which may call for further assessment.
III
ACKNOWLEDGMENTS
The project was made possible with the financial support received from the Missouri
Department of Transportation (MoDOT), and the University Transportation Center (UTC) on
Advanced Materials. Several people and parties actively participated:
• Mr. John Wenzlick and Mr. Rick Simmons (MoDOT), in organizing and performing the
load tests;
• Leica Geosystems, in particular in the persons of Mr. Gerard Manley and Mr. Jim
Naismith, in the setup of the automated total station surveying system and providing
assistance during the load test;
• Pirelli Cavi e Sistemi S.p.A., in particular in the person of Dr. Enrico Consonni, by
donating the optical fibers;
• Rocafix/Isaberg Rapid Group, in particular in the person of Mr. Fabio Ruggeri, by
donating the low temperature glue;
• Yokogawa Corporation of America, Test & Measurement Division/ANDO Product
Group, in particular in the person of Dr. Nobuyuki Morita, in the cooperation and efforts
to make the strain analyzer unit available;
• SEAL S.p.A. (SAATI Group), and in particular Mr. Paolo Grati, in manufacturing the
custom-made smart GFRP tape;
• Rolla Technical Institute (RTI), in particular in the persons of Mr. Max Vath, the
personnel and students of the Machine Technology and Precision Manufacturing, in the
design and construction of the modular cart;
• Strongwell, in particular in the person of Mr. Richard Altice, by donating the GFRP
pultruded structural panels used in the modular cart.
All of these precious contributions are gratefully acknowledged.
IV
TABLE OF CONTENTS
V
3.1.2 Modular cart for sensor installation ...........................................................................35
3.1.3 Connection and preliminary testing of the sensing elements.....................................36
3.1.4 Sensing system calibration.........................................................................................38
3.1.5 Installation of resistive strain gauges.........................................................................39
3.2 Test procedure................................................................................................................40
3.3 Test results .....................................................................................................................41
3.3.1 BOTDR strain measurement......................................................................................41
3.3.2 Resistive strain gauge measurements.........................................................................44
3.4 Discussion of results ......................................................................................................44
4. CONCLUSIONS......................................................................................................................51
5. REFERENCES ........................................................................................................................52
APPENDIX I – LOAD TEST STOPS...........................................................................................55
APPENDIX II – RAW DATA.......................................................................................................57
II.a Deflection data (ATS)....................................................................................................57
II.b Strain data (BOTDR) .....................................................................................................59
VI
LIST OF FIGURES
Figure 1 – Bridge A6358, U.S. Rt. 54/Osage River, Lake of the Ozarks, Miller County, MO...... 3
Figure 2 – Bridge details (not to scale)........................................................................................... 4
Figure 3 – Framing plan (not to scale, all dimensions in inches) ................................................... 5
Figure 4 – ATR TS system equipment for non-contact deflection measurement........................... 6
Figure 5 – Representation of quantum energy level of Brillouin scattering process showing both
Stokes (left) and anti-Stokes (right) collisions........................................................................ 8
Figure 6 – simplified schematic diagram of self-heterodyne BOTDR. .......................................... 9
Figure 7 – Schematic of correlation between elapsed time (T) and scanned length (l). ................. 9
Figure 8 – Brillouin OTDR............................................................................................................. 9
Figure 9 – Brillouin technology for structural monitoring ........................................................... 10
Figure 10 – Smart GFRP tape....................................................................................................... 11
Figure 11 – Portable data acquisition system (“Orange Box”)..................................................... 12
Figure 12 – Target positions: plan view (not to scale, all dimensions in ft)................................. 13
Figure 13 – Reflecting prisms mounted on steel I-girders............................................................ 13
Figure 14 – Pouring of concrete deck and deflection measurement via ATS .............................. 14
Figure 15 – Progression of deck pouring at deflection measurement steps.................................. 14
Figure 16 – Measured longitudinal deflections (deck pouring, Girder 1) .................................... 15
Figure 17 – Measured longitudinal deflections (deck pouring, Girder 3) .................................... 15
Figure 18 – Measured longitudinal deflections (deck pouring, Girder 5) .................................... 16
Figure 19 – Measured transversal deflections (deck pouring)...................................................... 16
Figure 20 – Comparison between theoretical and experimental longitudinal deflections (deck
pouring, Girder 1) ................................................................................................................. 18
Figure 21 – Comparison between theoretical and experimental longitudinal deflections (deck
pouring, Girder 3) ................................................................................................................. 19
Figure 22 – Comparison between theoretical and experimental longitudinal deflections (deck
pouring, Girder 5) ................................................................................................................. 20
Figure 23 – Dump trucks used for load test.................................................................................. 21
Figure 24 – Transverse position of trucks during load test (not to scale)..................................... 22
Figure 25 – Total station in load test configuration...................................................................... 23
Figure 26 – Experimental longitudinal deflection (load test, Girder 1)........................................ 23
Figure 27 – Experimental longitudinal deflections (load test, Girder 3) ...................................... 24
VII
Figure 28 – Experimental longitudinal deflections (load test, Girder 5) ...................................... 24
Figure 29 – Experimental transversal deflections at midspan of Span 1 (load test)..................... 25
Figure 30 – Experimental deflections for Girder 1, Stop 8 and Girder 5, Stop 6 (load test)........ 25
Figure 31 – Girder 1 fallen due to wind during erection of bridge superstructure ....................... 26
Figure 32 – Comparison between AASHTO provisions and experimental longitudinal deflections
(load test, Girder 1) ............................................................................................................... 28
Figure 33 – Comparison between AASHTO provisions and experimental longitudinal deflections
(load test, Girder 5) ............................................................................................................... 29
Figure 34 – Comparison between AASHTO and experimental girder load distribution factor at
midspan between Abutment 1 and Pier 2 in case of one lane loaded (Stop 3, 4, 5, 6 and 8) 30
Figure 35 – Comparison between AASHTO and experimental girder load distribution factor at
midspan between Abutment 1 and Pier 2 in case of two lanes loaded (Stop 1, 2 and 7) ..... 30
Figure 36 – Schematic of fiber circuit placement......................................................................... 32
Figure 37 – Detailed location of fiber optics on girder web (not to scale, dimensions in in)....... 33
Figure 38 – Smart FRP installed on Girder 1 and folded at Pier 2 location to extend circuit ...... 34
Figure 39 – Sensing fibers installed onto web plate of Girder 2 .................................................. 35
Figure 40 – Sensing fibers installed onto web plate of Girder 5 .................................................. 35
Figure 41 – Modular frame cart for sensor installation ................................................................ 36
Figure 42 – Optical fiber core-alignment fusion splicing field operation .................................... 37
Figure 43 – Optical loss measured along sensing circuit.............................................................. 37
Figure 44 – Strain calibration fixture............................................................................................ 38
Figure 45 – Linearity of measured and imposed strain for different fibers tested........................ 39
Figure 46 – Strain-temperature correlation................................................................................... 39
Figure 47 – Close-up of strain gauges installed on top flange of Girder 1................................... 40
Figure 48 – Field equipment for distributed strain measurement ................................................. 41
Figure 49 – Proprietary software for strain data processing ......................................................... 41
Figure 50 – Experimental strain distribution (Stop 1) .................................................................. 42
Figure 51 – Experimental strain distribution (Stop 2) .................................................................. 42
Figure 52 – Experimental strain distribution onn Girder 5 (Stop 4)............................................. 42
Figure 53 – Experimental strain distribution (Stop 7) .................................................................. 43
Figure 54 – Experimental strain distribution on Girder 1 and Girder 2 (Stop 8).......................... 43
Figure 55 – Time history of strain gauge readings ....................................................................... 44
Figure 56 – Strain gauge data computed for Stop 1-8 accounting for thermal compensation...... 44
Figure 57 – Comparison between experimental and predicted strain profiles (Stop 1)................ 45
VIII
Figure 58 – Comparison between experimental and predicted strain profiles (Stop 2)................ 46
Figure 59 – Comparison between experimental and predicted strain profiles (Stop 4)................ 47
Figure 60 – Comparison between experimental and predicted strain profiles (Stop 7)................ 48
Figure 61 – Comparison between experimental and predicted strain profiles (Stop 8)................ 49
IX
LIST OF TABLES
Table 2.1 – Properties of steel girder sections (as in Figure 2b) for deflection computation during
deck pouring.......................................................................................................................... 17
Table 2.2 – Dump trucks used for load test: weight distribution assumed for analysis ............... 21
Table 2.3 – GDFs as per AASHTO LRFD Bridge Design Specifications (1998) ....................... 26
Table 2.4 – Input data for calculation of GDFs (AASHTO, 1998) .............................................. 27
Table 3.1 – Properties of Wabo MBrace saturant for fiber optics installation (Wabo, 2004) ...... 32
Table 3.2 – Type, identification and location of sensing elements installed ................................ 33
Table 3.3 – Type, identification and location of strain gauges installed ...................................... 40
NOTATIONS
XI
1. INTRODUCTION
1.1 Background
1
and 36 ksi steel for webs, or using 70 ksi steel for flanges and 50 ksi steels for webs. This
limitation was not confined to HPS. It also applied to hybrid girders fabricated with 50
and 36 ksi steels. What made this limitation important was the fact that it has been shown
that the best use of HPS in plate girders is in the hybrid form where flanges are
constructed using 70 ksi steels and webs are constructed using 50 ksi steels (Horton et al.,
2000). Design studies have indicated that for many typical situations, hybrid girders will
produce the most economical designs (Barker and Schrage, 2000; Horton et al., 2000;
Clingenpeel and Barth, 2003).
• Current specifications place limits on the maximum allowable live load deflections.
These requirements have not typically controlled the geometry of sections designed with
steel having fy < 50 ksi. However, due to the reduced section geometries required when
HPS 70W steel is incorporated, these limits may be the controlling limit state for some
design situations. Therefore, research has been initiated to investigate the rationale
behind the current limits and to assess their influence on the serviceability and economy
of HPS bridges.
• In addition to incorporating HPS 70W in traditional I girder configurations, it was felt
that innovative concepts capitalizing on both the increased strength and improved
toughness of the steel may also produce cost effective structures. Some of the design
innovations that have been developed may prove to be beneficial for various steel grades
(e.g., Grade 50, HPS 70W and HPS 100W, with minimum yield strength of 100 ksi).
2
substantial increase in traffic on existing life-lines, lack of routine inspection and inadequate
maintenance in addition to the effect of the harsh and changing environment. The deficient
bridges are posted, repaired or replaced, with the disposition of bridges involving clear
economical and safety implications. To avoid high costs of replacement or repair, the evaluation
must accurately reveal the present load carrying capacity of the structure and predict loads and
any further changes in the capacity (deterioration) in the applicable time span (Deza, 2004).
Frequently, diagnostic load tests reveal strength and serviceability characteristics that exceed the
predicted codified parameters. Usually, codified parameters are very conservative in predicting
lateral load distribution characteristics and the influence of other structural attributes. As a result,
the predicted rating factors are typically conservative (Chajes et al., 1997).
1.3 Objectives
The scope of this project is the assessment of a High Performance Steel (HPS) bridge located at
the Lake of the Ozarks in Miller County. The bridge number is A6358 and it is sited on the U.S.
Rt. 54/Osage River.
In the project two different innovative techniques for Structural Health Monitoring (SHM) have
been applied:
3
1. An optical non-contact measurement technique, based on an automated target recognition
Total Station (TS) system, used to measure the vertical deflections of the girders during
the pouring of the concrete deck and the diagnostic load test, conducted after the
completion of the bridge;
2. A distributed Brillouin sensing technique, utilizing a “smart” glass FRP (GFRP) tape
with embedded sensing fibers and bare optical fibers, used to determine the strain
distribution at different depths of the web for some of the girders. Strains were measured
during the diagnostic load test only, since at the time when the deck was poured the
optical sensors had not been installed yet.
3' 8' 8" 8' 8" 8' 8" 8' 8" 3'
a) Cross section
PL. 18x1 1/8 PL. PL. PL. PL. 16x1 1/8 PL. PL.
HPS 485 W 18x1 1/8 14x3/4 16x1 1/8 HPS 485 W 16x1 1/8 16x3/4
PL. 5/8 PL. 9/16 PL. 5/8 PL. 5/8 PL. 9/16 84
18 28 98 21 20 20 19 108 0.92
185 147
Span 2 Span 1
C
L C
L C
L
Pier 3 Pier 2 Abutment 1
20 19 122 19 20
200
Span 3
C
L C
L
Pier 4 Pier 3
b) Girder elevation (structural steel ASTM A709 Grade HPS 345 W unless specified)
4
Span 3 Span 2 Span 1
Girder 1
Girder 2
Girder 3 4 spa.
@ 8' 8"
Girder 4
Girder 5
2 spa. 2 spa.
4 spa. @ 22' 24' 4 spa. @ 22' @ 20' 9" 4 spa. @ 24' 6" @ 22' 9" 22' 5 spa. @ 25'
CL CL CL CL
Pier 4 Pier 3 Pier 2 Abutment 1
a) Layout
8' 8"
b) Typical cross frame (structural steel ASTM A709 Grade HPS 70 W unless specified)
1.4 Methodology
To evaluate the response of the bridge, a nondestructive field test was conducted. Experimental
load testing on bridges can be either categorized as diagnostic or proof test. In a diagnostic test, a
predetermined load, typically near the rated capacity of the structure, is placed at several
different locations along the bridge. The corresponding response is measured, and then used to
develop a numerical model of the bridge to allow estimating of the maximum allowable load. In
a proof test, incremental loads are applied to the bridge until either a target load is reached or a
predetermined limit state is exceeded. Using the maximum load achieved, the capacity of the
bridge can be determined. Although diagnostic tests provide only an estimate of the load
carrying capacity of a bridge, they have several practical advantages including lower cost,
shorter testing time, and less disruption to traffic. Because of these advantages, diagnostic testing
was used in this case.
The bridge was tested under different static loads using six fully loaded dump trucks, and the
comparison between theoretical displacement and strain profiles based on the AASHTO LRFD
Bridge Design Specifications (1998) and experimental results allowed determining the safety of
the structure.
A major difficulty in the testing and evaluation of bridges in the field is the measurement of
vertical deflections. The use of instruments such as mechanical dial gauges, linear
potentiometers, linear variable differential transducers (LVDTs), and other similar types of
deflection transducers is not always feasible, because a fixed base is needed from which relative
5
displacements are measured. This often requires access under the bridge to erect a temporary
scaffolding to mount the instrument or for running a wire from the instrument to the ground. In
the present case, these difficulties were overcome by means of a non-contact deflection
measurement technique using an automated target recognition TS system. The solution allows to
measure the spatial coordinates of discrete points on a bridge in three dimensions without need
of touching the structure. The reliability of this method has been previously demonstrated in a
companion report (Galati et al., 2004), where the percentage variation of the total station with
respect to LVDTs displacement readings was estimated in the range between 0.1% and 9.7%.
TSs have been used to measure the movement of structures and natural processes with good
results (Hill and Sippel, 2002; Kuhlmann and Gläser, 2002). Leica Geosystems quotes accuracies
of better than 1 mm for their bridge and tunnel surveys. They use a remote system that logs
measurements 6 times daily via a modem, with measurements still possible at peak times.
Kuhlmann and Gläser (2002) used a reflectorless TS to monitor the long term deformation of
bridges. Measurements on a whole bridge were taken every six years and statistical tests were
used to confirm whether the points had moved over time. Hill and Sippel (2002) used a TS as
part of a multiple-sensor system for landslide monitoring. Merkle (2004) used the TS as part of a
5-year monitoring program for the in-situ load testing prior to and after the strengthening of five
existing concrete bridges, geographically spread over three Missouri Department of
6
Transportation (MoDOT) districts. The five bridges were strengthened using five different Fiber
Reinforced Polymer (FRP) technologies as part of a joint MoDOT – University of Missouri-
Rolla (UMR) initiative (Lynch, 2004).
There are advantages and disadvantages of using a TS for dynamic deformation monitoring. The
advantages include the high accuracy as quoted above, the automatic target recognition which
provides precise target pointing (Hill and Sippel, 2002) and the possibility of measuring indoors
and in urban canyons in kinematic operating modes (Radovanovic and Teskey, 2001). The
disadvantages include the low sampling rate (Radovanovic and Teskey, 2001; Meng, 2002),
problems with measurement in adverse weather conditions (Hill and Sippel, 2002) and the need
for a clear line of sight between the TS and the prism.
Radovanovic and Teskey (2001) conducted experiments to compare the performance of a robotic
TS with GPS. This experiment was conducted because GPS is not an option in many application
areas such as indoors. TSs are now capable of automatic target recognition and they can track a
prism taking automatic measurements of angles and distances once lock has been established
manually. It was found that the TS performed better than GPS in a stop and go situation, where
measurements were taken of a moving object only when it was stationary. In a completely
kinematic situation, GPS performed the best. It was found that there were two main problems
with the TS in kinematic mode; these were a low electronic distance measurement (EDM)
accuracy due to a ranging error that was linearly dependent upon the line of sight velocity, and
an uneven sampling rate over time worsened by no time tagging.
7
telecom fiber optics as fully-intrinsic sensors. This results in the following practical
considerations:
• The sensor is a standard, inexpensive telecom-grade optical fiber, with easy and
immediate off-the-shelf availability for any required length;
• At each point, the fiber acts as a strain sensor, allowing detection and evaluation of
phenomena that are hard to locate in advance, such as cracks, debonding, fatigue and
defect-triggered faults, along with local discontinuities that cannot be detected on real
structures by means of point sensors;
• Low cost, in addition to distributed sensitivity, makes possible long-haul sensors to be
installed extensively over the length, area or volume of large structures, thus allowing
better understanding of the structural behavior and producing a global overview of the
damage distribution, which cannot be retrieved even with long measure-basis sensors;
• Low cost and distributed sensitivity make the system suitable for disposable sensors. For
instance, in case of monitoring of tendons during pre-stressing operations, or for
emergency sensors that can be left “sleeping” in the structure without heavy additional
costs in all cases when it is not possible to know in advance whether the sensor will be
used during the life-cycle of the structure or not;
• The whole fiber length can be scanned from the same end point (up to several tenths of
km), a characteristic that dramatically simplifies installation and management of cabling;
• Using an Optical Time Domain Reflectometer (OTDR) based on spontaneous Brillouin
scattering, no end-to-end full cable continuity is required, which allows operations even
with damaged sensing fibers, performing separate scans for the two survival half-lengths.
In addition to these peculiarities, the Brillouin reflectometry maintains all the advantages that are
typical of fiber optic sensing technologies (Casas and Cruz, 2003), i.e.
• Absolute insensitivity to Electro-Magnetic Interferences (EMI);
• Long-term durability even in chemically aggressive or harsh environments;
• Current technology top miniaturization grade;
• Complete compatibility with FRP composite materials.
8
1.5.2.2 Practical applications
Even though primarily developed for telecom cable testing, Brillouin Optical Time-Domain
Reflectometry (BOTDR) can be effectively applied for strain distribution monitoring in large-
scale civil structures, with some limitations (Komatsu et al., 2002). BOTDR combines the self-
heterodyne analysis of the spontaneous Brillouin backscattered light spectrum (Horiguchi et al.,
1994), illustrated in Figure 6, with OTDR (Barnoski and Jensen, 1976). The first allows the
evaluation of the strain level of a certain length of fiber, while OTDR enables determining the
distance along the fiber where the strain information is retrieved by exploiting the relation
between the speed of light (c), the sum of the distances traveled by the injected and backscattered
light pulses, and the delay time at which the backscattered pulse is detectable (Figure 7).
For the purpose of this test program, the evaluation of the strain distribution has been performed
using a Brillouin OTDR AQ8603 optical fiber strain analyzer manufactured by Yokogawa-Ando
Corporation of Kawasaki, Japan (Figure 8). The unit allows measurements of strain distribution
along a single-mode optical fiber from one end of the optical circuit.
In addition, recent experimental tests have evidenced that performances can overcome the
declared limits when the strain distribution under evaluation has no steep discontinuities and has
positive peak strain values of at least 100 µε. Under these conditions the relative error versus
conventional resistive strain gauges has been experimentally shown to be lower than 5%
(Bastianini et al., 2003).
9
Figure 9 shows the flow chart for structural testing and monitoring using BOTDR technique. It
requires the following steps:
1. Preliminary structural analysis to identify the areas that have strategic relevance for the
structural behavior and are subject to strain value and distributions that are within the
detectable strain range of the BOTDR equipment;
2. Design of the optical fiber circuit, including strain sensitive hauls, thermal compensation
hauls and access points for future bypass patches in accordance with the areas located
during step 1;
3. Installation of the optical fiber circuit providing suitable strain transfer and fiber
protection, typically using fiber-equipped “smart” composite materials and other products
developed for the specific purpose, and then connecting the various circuit branches
through fusion splices and other suitable joints;
4. Optical loss testing in order to ensure that the total optical loss is within the maximum
acceptable losses that allow BOTDR operation within the desired accuracy limits;
5. Identification of the 3-D structure points / 1-D sensing fiber correspondence, needed to
translate the strain distribution measured along the optical fiber to the strains in the
specific areas of the structure equipped with the same fiber. Brillouin co-sensitivity to
temperature may be conveniently used in this phase to locate specific temporarily heated
points;
6. Load testing of the structure with BOTDR, retrieving the strain distribution along the
fiber circuit in different condition, i.e. without any load applied and during the various
steps of static load tests;
10
7. Data interpretation, based on the 3-D/1-D correspondence retrieved during step 5;
8. Health status monitoring, performing Brillouin analysis on a periodical basis, or, if
required, continuously.
11
32 thermocouple channels, as well as interfacing with TS surveying. The high-level channels
may receive DC LVDT's, string transducers, linear potentiometers, or any other +/− 10 Volt DC
signal. The strain channels can be used to monitor and record strain gauge signals, load cells,
strain-based displacement transducers, or any strain based signal. The 32 thermocouple channels
are configured for type T thermocouples.
The unit consists of a shock-mounted transport box, with removable front and rear covers.
Removal of the front cover exposes the computer keyboard and LED display, as well as the front
panel of the data acquisition equipment. Removal of the back panel exposes the connector bay,
where cables from all the transducers terminate.
The data acquisition system is comprised of National Instruments equipment, listed below:
a) A PXI-1010 SCXI combination unit, which houses the industrial-grade 2.2 GHz Pentium
4 computer, floppy drive, and CDR/W module;
b) A PXI-6030E Analog to Digital converter module for doing the A/D conversion in the
system;
c) A pair of SCXI-1520 modules to interface strain based sensors;
d) A SCXI-1102B module for multiplexing high-level sensors;
e) A SCXI-1102B module for multiplexing thermocouple sensors;
f) I/O devices in order to connect additional peripherals and other data acquisition systems
such as a Leica TS surveying instrument.
The data acquisition system is controlled by a custom made LabVIEW program installed on a
built-in computer, which allows control of data rate, sensor selection and calibration, and display
of the data.
12
2. ATS BASED DISPLACEMENT MEASUREMENT: FIELD EVALUATION
185 147
Figure 12 – Target positions: plan view (not to scale, all dimensions in ft)
An additional prism was mounted on Pier 2 in order to evaluate possible settlements. Finally,
two additional prisms were mounted on two piers of the existing bridge running parallel to the
one under investigation (Figure 1), and two more prisms were mounted on tripods fixed to the
ground. These four additional targets were used as reference points for triangulation.
13
2.2 Deck installation
1 1/4 spans
2 spans
2 3/4 spans
4 spans
5 spans
Data were retrieved without any interruption of the pouring or interference with the personnel on
the bridge. Therefore, the accuracy of the measurements was expected to be influenced also by
potential settlements and loading due to the crane and equipment moving along the bridge. In
addition, it is envisaged that the deflections during the second day were slightly affected by a
certain amount of deck/girder composite action in Span 3, 4 and 5.
14
Figure 16, Figure 17 and Figure 18 for Girder 1, Girder 3 and Girder 5, respectively. Figure 19
shows the transversal midspan deflections in Span 1 measured on Girder 1 to 5 through Target
20, 17, 12, 9 and 3, respectively, wherein data from the same reading have been piecewise
connected with straight lines for clarity. Raw data are provided in Appendix II.a.
2.0
1.5 1 1/4 spans - Exp.
1.0 2 spans - Exp.
Deflection [in]
-1.0
Bolted joint
Bolted joint
Abutment 1
Bolted joint
-1.5 Pier 1
Pier 2
-2.0
-2.5
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
2.0
1.5 1 1/4 spans - Exp.
-1.0
Bolted joint
Bolted joint
Abutment 1
-1.5
Bolted
Pier 1
Pier 2
-2.0
joint
-2.5
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
15
2.0
1.5 1 1/4 spans - Exp.
0.5
Deflection [in]
2 3/4 spans - Exp.
-1.0
Bolted joint
Bolted joint
Abutment 1
Bolted joint
-1.5
Pier 1
Pier 2
-2.0
-2.5
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
2.0
1.5
1.0
0.5
0.0
-0.5
-1.0
-1.5
-2.5
1 2 3 4 5
Girder No.
16
Table 2.1 – Properties of steel girder sections (as in Figure 2b) for deflection computation during
deck pouring
Flexural Stiffness,
Length Interval Moment of Inertia, Is
EsIs (Es = 29 msi)
(ft) (Span) (in4) (kip·in2)
0-108 (1) 70,879 2.06E+09
108-188 (1,2) 96,090 2.79E+09
188-286 (2) 88,245 2.56E+09
286-371 (2,3) 104,243 3.02E+09
371-432 (C.L., 3) 108,323 3.14E+09
Figure 20, Figure 21 and Figure 22 show the comparison between analytical and representative
experimental results for Girder 1, 3 and 5. It can be observed that the predictions fairly describe
the measured deflections. Some apparent inconsistencies due to relatively high deflections for
Girders 1, 3 and 5, as the concrete was poured on Span 4 in particular, and Span 5, may be
attributed to the following variables:
• Additional loading due to the steel crane, loading the two external girders directly, and
the workers and equipment moving along the bridge during the pouring operations (see
Figure 14);
• Deflections induced by thermal loads;
• Settlements, due to the additional uniform dead load of the concrete poured;
• Deck/girder composite behavior in Span 3, 4 and 5, as far as the measurement of the
second day are concerned, as the concrete poured during the first day was already
considerably hardened;
• Approximation of the loading steps considered in the calculations (see Figure 15) versus
the actual load conditions, as the pouring operations were never interrupted for deflection
measurement purposes, in order not to interfere with the personnel on the bridge.
However, it is noted that a comparison between Figure 20d and Figure 22d points out a rather
significant midspan deflection of Girder 1 (1.193 in), which is 32% and 14% greater than the
correspondent in Girder 5 (0.898 in) and the theoretical value (1.025 in), respectively. Due to the
variety of factors that may affect measurements, as specified above, more thoughtful conclusions
cannot be drawn herein.
17
2.5 2.5
2.0 Analytical 2.0 Analytical
1.5 Experimental 1.5 Experimental
1.0 1.0
Deflection [in]
Deflection [in]
0.5 0.5
0.0 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
Bolted joint
Bolted joint
-1.5 -1.5
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
2.5 2.5
Bolted joint
2.0 2.0
1.5 1.5 Analytical
Analytical
1.0 1.0 Experimental
Experimental
Deflection [in]
Deflection [in]
0.5 0.5
0.0 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
Bolted joint
-1.5 -1.5
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
c) 4 spans d) 5 spans
18
2.5 2.5
2.0 2.0 Analytical
1.5 Analytical 1.5 Experimental
1.0 Experimental 1.0
Deflection [in]
Deflection [in]
0.5 0.5
0.0 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
Bolted joint
Bolted joint
-1.5 -1.5
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
2.5 2.5
Bolted
2.0 2.0
joint
Deflection [in]
0.5 Experimental 0.5
0.0 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
-1.5 -1.5
Bolted
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
joint
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
c) 4 spans d) 5 spans
19
2.5 2.5
2.0 2.0
1.5 Analytical 1.5 Analytical
Deflection [in]
0.5 0.5
0.0 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
Bolted joint
Bolted joint
-1.5 -1.5
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
2.5 2.5
Bolted joint
Bolted joint
2.0 2.0
1.5 1.5 Analytical
1.0 1.0 Experimental
Deflection [in]
Deflection [in]
0.5 Analytical 0.5
0.0 Experimental 0.0
-0.5 -0.5
-1.0 -1.0
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
-1.5 -1.5
Pier 2
Pier 2
Pier 3
Pier 3
-2.0 -2.0
-2.5 -2.5
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
c) 4 spans d) 5 spans
20
2.3 Load test
5' 15'
5' 11"
6' 11"
P2 P2 P1
The trucks were weighed before testing and coded with a number from 1 to 6. Table 2.2
summarizes weight and assumed load distribution between front and rear axles.
Table 2.2 – Dump trucks used for load test: weight distribution assumed for analysis
A total of eight stops were planned, and details are reported in Appendix I. Marks were made on
the concrete deck to indicate the trucks stops, and the distance between the front axle of each
truck and the rear axle of the truck in front in the line load was 9 ft.
Stop 1, 2 and 7 were intended to produce the maximum deflections on Girder 1 and 5 using both
directions of traffic with two symmetrical lanes of two (Stop 1) and three (Stop 2 and 7) trucks
each. Stop 3, 4 and 6 were intended to produce the maximum deflections on Girder 5 in Span 3,
21
2 and 1, respectively, using a train of six trucks. Stop 5 was planned to induce the maximum
negative moment on Girder 5, at Pier 2. Finally, Stop 8 was intended to produce the maximum
deflections on Girder 1 in Span 1 using a single lane of six trucks. Figure 24 shows the
transverse position of the trucks for the different stops.
In order to minimize the influence of systematic errors in the displacement measurements, and
during the load test only, the TS was mounted on a leveling steel plate fixed on a concrete pile
(Figure 25).
Once the TS was leveled and acclimatized, initial readings were taken for each prism. Then, the
trucks drove to the first stop. At each stop, 15 minutes were allowed for potential settlements,
before acquiring the data. To ensure stable measurements, four readings were taken for each
target, two direct and two inverse, in order to average out possible errors. Once the reading was
terminated, the trucks moved to the next stop and the same procedure was repeated.
22
Leveling steel plate
Concrete pile
1.0
Bolted joint
Bolted joint
Bolted joint
Abutment 1
0.5
Stop 2 - Exp.
-0.5 Stop 3 - Exp.
Stop 4 - Exp.
-1.0 Stop 5 - Exp.
Stop 6 - Exp.
-1.5 Stop 7 - Exp.
Pier 2
Pier 3
Stop 8 - Exp.
-2.0
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
23
1.0
Stop 1 - Exp.
0.5 Stop 2 - Exp.
Stop 3 - Exp.
0.0 Stop 4 - Exp.
Deflection [in]
Stop 5 - Exp.
-0.5 Stop 6 - Exp.
Stop 7 - Exp.
-1.0 Stop 8 - Exp.
Bolted joint
Bolted joint
Bolted joint
Abutment 1
-1.5
Pier 2
Pier 3
-2.0
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
1.0
Stop 1 - Exp.
0.5 Stop 2 - Exp.
Stop 3 - Exp.
0.0 Stop 4 - Exp.
Deflection [in]
Stop 5 - Exp.
-0.5 Stop 6 - Exp.
Stop 7 - Exp.
-1.0 Stop 8 - Exp.
Bolted joint
Bolted joint
Bolted joint
Abutment 1
-1.5
Pier 2
Pier 3
-2.0
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
24
1.5
Stop 1 Stop 2 Stop 3 Stop 4
1.0
Stop 5 Stop 6 Stop 7 Stop 8
0.5
Deflection [in]
0.0
-0.5
-1.0
-1.5
-2.0
1 2 3 4 5
Girder No.
It can be observed that the readings are consistent from stop to stop, while the curves generally
exhibit a smooth transition from point to point. However, a comparison between the deflections
of Girder 1 and 5 during Stop 8 and 6, points out that the first reached values 28% higher when
subjected to absolutely similar load conditions, as shown in Figure 30. Such difference cannot be
explained by accounting for possible concurrent factors that played a role in determining the
measurement results. A preliminary, yet reasonable explanation may lie in the fact that Girder 1
fell during construction (Figure 31), due to the action of wind, and likely experienced some
damage either during the falling or re-positioning. This calls for further verification by means of
the results from BOTDR based strain measurement, along with a comparison with analytical and
numerical predictions.
1.0
Abutment 1
Bolted joint
Bolted joint
joint
Bolted
Pier 2
Pier 3
0.5
0.0
Deflection [in]
28%
-1.5
-2.0
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
Figure 30 – Experimental deflections for Girder 1, Stop 8 and Girder 5, Stop 6 (load test)
25
Figure 31 – Girder 1 fallen due to wind during erection of bridge superstructure
Table 2.3 – GDFs as per AASHTO LRFD Bridge Design Specifications (1998)
Girder No. of Lanes AASHTO GDF GDF
No. Loaded Formula Span 1 Span 2
1, 5 1 Lever rule 0.658 0.658
0.4 0.3 0.1
⎛ S ⎞ ⎛ S ⎞ ⎛ Kg ⎞
2, 4 1 GDF = 0.06 + ⎜ ⎟ ⎜ ⎟ ⎜ 3⎟ 0.432a 0.406a
⎝ 168 ⎠ ⎝ L ⎠ ⎝ Ltc ⎠
de
1, 5 2c GDF = e ⋅ GDF2,4 , e = 0.77 + ≥1 0.641a,b 0.613a,b
109.2
0.6 0.2 0.1
c ⎛ S ⎞ ⎛S⎞ ⎛ Kg ⎞
2, 4 2 GDF = 0.075 + ⎜ ⎟ ⎜ ⎟ ⎜ 3⎟ 0.641a 0.613a
⎝ 114 ⎠ ⎝L⎠ ⎝ Ltc ⎠
a
See Table 2.4 for parameters and units
b
de = distance from center of exterior beam and inside edge of barrier = 36 – 16 = 20 in, therefore e = 1
c
In the case of two load lanes (Figure 24b), the closer to the girder considered was assumed for computation
26
Table 2.4 – Input data for calculation of GDFs (AASHTO, 1998)
Value Value
Parameter (unit) Definition
(Span 1) (Span 2)
S (in) Girder spacing 104 104
L (in) Span length 1,764 2,220
Kg (in4) Longitudinal stiffness parameter 1.836·106 2.189·106
=
Es
Ec
( I s + As eg2 )
The width of the concrete slab section was selected as the average spacing of adjacent beams
[4.6.2.6.1], i.e. S = 104 in, for both interior and exterior beams. It is noted that the contribution of
the structurally continuous concrete barrier has been accounted for [C4.6.2.6.1-1], thus
determining a theoretical flange width for the external girder as
S A 104 328
+ woverhang + b + 36 + 107.3 in,
2 2tc 2 2 ⋅ 8.5
wherein woverhang is the width of the overhang (in), Ab the cross sectional area of the barrier (in2),
and tc the deck thickness (in). Since the difference between the flexural stiffness of the
equivalent interior and exterior girders is of the order of 0.5%, the 104 in flange width was used
for all the beams.
Figure 32 and Figure 33 show the comparison between the deflections measured on Girder 1 and
5, respectively, and the analytical deformed shapes. The deflections measured through the ATS
system are generally smaller than the theoretical values, and clearly well below the L / 800 limit
[2.5.2.6.2] of 2.2 in and 2.8 in on Span 1 and Span 2, respectively, as shown in Figure 32d and
Figure 33d and f, thereby demonstrating the safety of the structure. Nevertheless, comparison of
Figure 32d and Figure 33d and f points out the tendency of Girder 1 to approach the theoretical
limits, differently from Girder 5, when directly subjected to essentially the same load conditions.
As previously mentioned, the falling of the girder occurred during construction may have
determined some alteration of the structural response, which may call for further assessment.
27
Conversely, the response of Girder 5 confirms the conservativeness of the design provisions.
2.0 2.0
1.5 AASHTO 1.5 AASHTO
1.0 Experimental 1.0 Experimental
0.5 0.5
Deflection [in]
Deflection [in]
0.0 0.0
-0.5 -0.5
-1.0 -1.0
-1.5 -1.5
Bolted joint
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Bolted joint
Abutment 1
Bolted joint
-2.0 -2.0
Pier 2
Pier 3
Pier 2
Pier 3
-2.5 -2.5
-3.0 -3.0
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
a) Stop 1 b) Stop 2
2.0 2.0
Abutment 1
Bolted joint
Pier 2
1.5 AASHTO 1.5
1.0 Experimental 1.0
0.5 0.5
Deflection [in]
Deflection [in]
Bolted joint
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Bolted joint
-2.0 -2.0
Pier 3
Pier 2
Pier 3
-2.5 -2.5
-3.0 -3.0
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
c) Stop 7 d) Stop 8
Figure 32 – Comparison between AASHTO provisions and experimental longitudinal deflections
(load test, Girder 1)
28
2.0 2.0
1.5 AASHTO 1.5 AASHTO
1.0 Experimental 1.0 Experimental
0.5 0.5
Deflection [in]
Deflection [in]
0.0 0.0
-0.5 -0.5
-1.0 -1.0
-1.5 -1.5
Bolted joint
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
-2.0 -2.0
Pier 2
Pier 3
Pier 2
Pier 3
-2.5 -2.5
-3.0 -3.0
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
a) Stop 1 b) Stop 2
2.0 2.0
Bolted
Bolted
Pier 3
joint
joint
1.5 AASHTO 1.5
1.0 Experimental 1.0
0.5 0.5 AASHTO
Deflection [in]
Deflection [in]
0.0 0.0 Experimental
-0.5 -0.5 L/800 Span 2
-1.0 -1.0
-1.5 -1.5
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Abutment 1
Bolted joint
-2.0 -2.0
Pier 2
Pier 3
Pier 2
-2.5 -2.5
-3.0 -3.0
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
c) Stop 3 d) Stop 4
2.0 2.0
Abutment 1
joint
joint
joint
Pier 2
Bolted
Bolted
Bolted
1.5 AASHTO 1.5
1.0 Experimental 1.0
0.5 0.5
Deflection [in]
Deflection [in]
0.0 0.0
-0.5 -0.5
-1.0 -1.0 AASHTO
-1.5 -1.5 Experimental
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Pier 3
Pier 2
Pier 3
-2.5 -2.5
-3.0 -3.0
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
e) Stop 5 f) Stop 6
2.0
1.5 AASHTO
1.0 Experimental
0.5
Deflection [in]
0.0
-0.5
-1.0
-1.5
Bolted joint
Bolted joint
Bolted joint
Abutment 1
-2.0
Pier 2
Pier 3
-2.5
-3.0
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
g) Stop 7
Figure 33 – Comparison between AASHTO provisions and experimental longitudinal deflections
(load test, Girder 5)
29
Since all the beams considered for the 1-D analysis were assumed to have essentially the same
geometrical and material characteristics, i.e. an equivalent flexural stiffness, the GDF for the ith
girder at the midspan in Span 1 was estimated from the deflection data retrieved as
5
GDFi = δ i / ∑δ
j =1
j ,
wherein δi = deflection of the ith girder. Figure 34 and Figure 35 shows the distribution factors
calculated at each stop with one and two lanes loaded, respectively.
0.8
AASHTO LRFD Limit for Girder 1 and 5 = 0.658
Load Distribution Factor [Load Lanes]
0.6
AASHTO LRFD Limit for Girder 2, 3 and 4 = 0.432
0.4
0.2
0.0
-0.4
1 2 3 4 5
Girder No.
Figure 34 – Comparison between AASHTO and experimental girder load distribution factor at
midspan between Abutment 1 and Pier 2 in case of one lane loaded (Stop 3, 4, 5, 6 and 8)
0.8
Load Distribution Factor [Load Lanes]
0.4
Stop 1
0.2 Stop 2
Stop 7
0.0
1 2 3 4 5
Girder No.
Figure 35 – Comparison between AASHTO and experimental girder load distribution factor at
midspan between Abutment 1 and Pier 2 in case of two lanes loaded (Stop 1, 2 and 7)
30
The load distribution factors determined experimentally at the midspan section between
Abutment 1 and Pier 2 (Figure 12) are always smaller than those based on the AASHTO
provisions, which are proved to be conservative for the case under consideration. The main
reason typically lies in the inherent conservativeness of neglecting the transverse stiffening
action of the diaphragms when using either the design formulas, wherein the thickness of the
deck is the only parameter that explicitly accounts for a degree of transverse stiffness in the
structural system, or the lever rule.
31
3. BOTDR BASED STRAIN MEASUREMENT: FIELD EVALUATION
Table 3.1 – Properties of Wabo MBrace saturant for fiber optics installation (Wabo, 2004)
bare fibers
Smart GFRP
tape
Span 1 Span 2
Abutment 1 Pier 2 Pier 3
Figure 36 – Schematic of fiber circuit placement
32
3 bare fibers
C on Girder 5
Strain sensing fiber
Figure 37 – Detailed location of fiber optics on girder web (not to scale, dimensions in in)
33
The smart GFRP tape was applied over the web plate of all the girders monitored. The tape was
drawn through the corner holes between the welded vertical stiffeners and the plate girder and
then installed about 0.4 in above the bottom flange, in order to allow detection of a strain level
reasonably close to the actual maximum attained.
Girder 1 was instrumented on Span 1 using smart tape. The tape circuit end was also lengthened
for 32.8 ft after Pier 2. The additional FO installed on the web, at a distance of 15 in from the
adjacent surface of the top flange (Figure 38), was used to gain additional data and therefore to
estimate the position of the neutral axis. Since it was not possible to keep the tape perfectly flat
in the vicinity of the cross frames, a certain disturbance of the data retrieved in those areas was
expected.
Girder 2 was instrumented on Span 1 and 2. The smart tape was installed at 0.4 in from the
bottom flange surface. In addition, two bare fibers, one for strain sensing and the other for
thermal compensation, were bonded at 28 in from the bottom flange (i.e. at one third of the
height of the plate web), (see Figure 39a). This was done in an attempt to evaluate the position of
the neutral axis; however, the need to draw the fibers through the holes between the welded
vertical stiffeners and the plate girder required several sharp bending areas of the fibers, as
shown in Figure 39b, which are believed to be the cause of an undesired increase of the optical
losses and significant perturbations of the strain distribution measured.
Girder 4 was instrumented on Span 1 and 2 with FRP tape only, bonded at the web base.
Girder 5 was instrumented on Span 1 and 2 with optical fiber-embedded composite tape at the
web base. In addition, two bare fibers, one for strain sensing and the other for thermal
compensation, were installed at 3 in from the upper flange surface (Figure 40), in order to
retrieve data to estimate the temperature gradient throughout the web height, and of the strain
profile, especially in the negative moment zone.
Rubber band
Figure 38 – Smart FRP installed on Girder 1 and folded at Pier 2 location to extend circuit
34
a) Smart FRP (lower blue stripe) and bare fibers (upper b) Bending of fibers to pass
blue stripe) through transversal stiffeners
35
safety pins, while a total of eight electric actuators allowed the axles to extend out of the
transverse member for 18.5 in on each side of the vehicle, as shown in Figure 41c.
Transverse stiffener
Electrically-actuated
steel axle
36
some unwanted sources of optical loss, likely due to fiber damages which occurred during
installation. The amount of optical losses in the sensing circuit is of crucial importance in
BOTDR systems, since it may be highly detrimental to the strain sensitivity and accuracy. The
hauls were series-connected in the field using a fiber optic fusion splicer (Figure 42), obtaining a
single circuit with a total length of 3,802 ft. The solution allowed containing the total optical loss
within a value of 6 dB in the first 3,366 ft from the optical test end (Figure 43), thus enabling
strain measurement with a minimum accuracy of 0.004% (±40 µε) on a length resolution of 6.5
ft, setting the AQ8603 analyzer for laser pulses with a length of 20 ns. Since a significant optical
loss is detected before the last portion of the circuit, i.e. Girder 4, Location A, the correspondent
measured strain profiles were expected to have a lower degree of accuracy.
46
44
Optical loss @ 1550 nm (dB)
6 dB @ 3,366 m
42
40
38
36
34
0 300 600 900 1,200 1,500 1,800 2,100 2,400 2,700 3,000 3,300 3,600 3,900
Distance (ft)
37
3.1.4 Sensing system calibration
The correlation between the strain and the Brillouin frequency shift (characteristic of the fiber
used), was determined using a strain calibration fixture that allowed to induce a predetermined
uniform strain in the fiber tested, over a reference length of 24.34 ft (Figure 44a).
Using the strain data collected with the calibration fixture (Figure 44b), a specific set of
correction coefficients was computed for each type of fiber used, in order to improve accuracy
and linearity with respect to the standard equipment settings. The best linearization was obtained
for the sensing fiber embedded into the custom designed and manufactured GFRP tape, as shown
in Figure 45.
In addition, since the AQ8603 unit does not allow direct temperature estimate, a suitable strain-
temperature correlation was established by testing an optical fiber spool placed in an
environmental chamber at different temperature levels. The results are summarized in Figure 46.
a) Schematic
38
1,300
Pirelli
Pirelli tight ∅ 900 bare
tight 900um µm B
1,100 Pirelli tight ∅ 900 µm T
Pirelli tight 900um tape
Pirelli
Pirelli tight ∅ 900
tight tape µm T (corr.)
corrected
Corning ∅ 900 µbare
Corning tight 900um mB
900
semiloose 900 µ
∅
Measured strain (µε)
300
100
-100
0 200 400 600 800 1,000
Imposed strain (µε)
Figure 45 – Linearity of measured and imposed strain for different fibers tested
10,000
8,000
Experimental
Apparent strain (µε)
4,000
2,000
0
20 30 40 50 60 70 80 90 100 110 120 130
o
Fiber temperature ( F)
39
location of the strain gauges installed.
40
Figure 48 – Field equipment for distributed strain measurement
41
-300 -300
Bolted joint
Bolted joint
-200 -200
Pier 3
-100 -100
0 0
Strain [µε]
Strain [µε]
100 100 Girder 4 - bottom - Exp.
Girder 1 - bottom - Exp.
Girder 5 - bottom - Exp.
200 Girder 2 - bottom - Exp. 200
Girder 5 - top - Exp.
Girder 2 - h/3 - Exp.
300 G3 (Girder 1 - bottom) 300
Bolted joint
Abutment 1
Abutment 1
Bolted joint
Bolted joint
Bolted joint
G2 (Girder 1 - top)
400 400
Pier 3
Pier 2
Pier 2
G5 (Girder 2 - h/3)
500 500
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
-300 -300
Bolted joint
Bolted joint
-200 -200
Pier 3
-100 -100
0 0
Strain [µε]
Strain [µε]
Bolted joint
Bolted joint
Bolted joint
Abutment 1
Bolted joint
Pier 2
Pier 3
Pier 2
G5 (Girder 2 - h/3)
500 500
0 30 60 90 120 150 180 210 240 270 300 330 0 30 60 90 120 150 180 210 240 270 300 330
x [ft] x [ft]
-300
0
Strain [µε]
100
200
300
Abutment 1
Bolted joint
Bolted joint
Bolted joint
400
Pier 3
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
42
-300
Bolted joint
Bolted joint
-200
Pier 3
-100
Strain [µε]
100 Girder 1 - bottom - Exp.
Girder 2 - bottom - Exp.
200
Girder 2 - h/3 - Exp.
Abutment 1
Bolted joint
G2 (Girder 1 - top)
400
G5 (Girder 2 - h/3)
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
a) Girder 1 and 2
-300
-200
-100
0
Strain [µε]
Bolted joint
Bolted joint
400
Pier 3
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
b) Girder 4 and 5
-300
Bolted joint
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
Bolted joint
G2 (Girder 1 - top)
400
G5 (Girder 2 - h/3)
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
43
3.3.2 Resistive strain gauge measurements
Of the seven strain gauges installed, only G1, G2, G3, G4 and G5 worked properly during the
load test. The strain reading history throughout the test and the values at each stop, computed
accounting for thermal compensation, are provided in Figure 55 and Figure 56, respectively.
Strain (µε)
Time (sec)
350
150
100
50
-50
-100
1 2 3 4 5 6 7 8
Stop #
Figure 56 – Strain gauge data computed for Stop 1-8 accounting for thermal compensation
44
-150
Bolted joint
Bolted joint
-100
Pier 3
-50
0
Strain [µε]
Bolted joint
G3 (Girder 1 - bottom)
250
Pier 2
G5 (Girder 2 - h/3)
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
a) Girder 1 and 2
-150
Bolted
Bolted
Pier 3
joint
joint
-100
-50
0
Strain [µε]
Bolted joint
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
b) Girder 4 and 5
45
-150
Bolted
Bolted joint
joint
-100
Pier 3
-50
0
Strain [µε]
50
Girder 1 - bottom - Exp.
100 Girder 1 - bottom - AASHTO
Girder 2 - bottom - Exp.
150 Girder 2 - bottom - AASHTO
Girder 2 - h/3 - Exp.
200
Girder 2 - h/3 - AASHTO
Abutment 1
Bolted joint
Pier 2
G5 (Girder 2 - h/3)
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
a) Girder 1 and 2
-150
Abutment 1
-100
-50
0
Strain [µε]
250
Bolted
Bolted
Pier 3
Pier 2
joint
joint
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
b) Girder 4 and 5
46
-300
Abutment 1
-200
-100
0
Strain [µε]
100
Girder 5 - bottom - Exp.
200 Girder 5 - bottom - AASHTO
Girder 5 - top - Exp.
300
Girder 5 - top - AASHTO
Bolted joint
Bolted joint
400
Bolted
Pier 3
Pier 2
joint
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
47
-150
Bolted
Bolted joint
joint
-100
Pier 3
-50
0
Strain [µε]
Bolted joint
G3 (Girder 1 - bottom)
250
Pier 2
G5 (Girder 2 - h/3)
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
a) Girder 1 and 2
-150
Bolted joint
Bolted
joint
-100
Pier 3
-50
0
Strain [µε]
50
Girder 4 - bottom - Exp.
100
Girder 4 - bottom - AASHTO
150 Girder 5 - bottom - Exp.
Girder 5 - bottom - AASHTO
200
Abutment 1
Bolted joint
300
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
b) Girder 4 and 5
48
-300
Bolted joint
Bolted
joint
-200
Pier 3
-100
0
Strain [µε]
Bolted joint
400 G3 (Girder 1 - bottom)
Pier 2
G5 (Girder 2 - h/3)
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
The strain readings from the optical fibers embedded in the GFRP tape fairly follow the
analytical profiles in all the girders in case of one load lane (Stop 4 and 8), and in the exterior
members, Girder 1 and Girder 5, in case of two load lanes (Stop 1, 2 and 7), when the
distribution factor in the interior girders is not representative of the actual load test conditions.
The offset is generally consistent with the strain gauge readings and the deflection results from
ATS measurements, thus verifying the conservativeness of the AASHTO design provisions
(1998).
As expected, the strain measurement on Girder 4, Location A (adjacent to the bottom flange),
yields less accurate values, due to the significant optical loss before the interested portion of the
circuit. The experimental results also point out the relation between measurement accuracy and
strain level, with reliable outputs generally provided at strain levels beyond 100 µε.
The BOTDR experimental data confirm the concerns raised by the ATS measurements on Girder
1. In particular, the strain profile at Stop 8 (Figure 61a) shows the clear tendency to approach the
theoretical values, in accordance with the deflection results shown in Figure 32d This indicates
that the structural member deforms as under a vertical load significantly close to that associated
with the theoretical conservative distribution factor of 0.658 load lanes. Conversely, the strain in
Girder 2 at Stop 8 (Figure 61a) remains well below the analytical threshold.
Local effects, such as that at the bolted joints, may result in disturbances that affect the strain
readings in a relatively large adjacent portion of the circuit, although the profiles are qualitatively
correct as they often reflect the presence of local strain gradients. The issue is evident in Girder
5, Stop 1 (Figure 57b) and Stop 2 (Figure 58b) on Span 1, and Girder 5, Stop 4 (Figure 59) on
49
Span 1, whereas it seems not of concern in case of relatively high strain levels (beyond 100 µε)
for positive moment regions. This suggests that localized inconsistencies may be essentially due
to initial fiber misalignment and/or local disbond, with reduced effect as the fibers are
progressively stretched.
It is finally noticed that the data retrieved from the bare fibers did not have the same quality of
that from the GFRP tape, in particular in Girder 2, Location B (at hweb/3, Figure 37), where
practically zero strain was detected. This may be principally due to the presence of several
vertical circuit portions, sometimes partially unbonded, in the vicinity of the transverse
stiffeners, which likely caused undesired perturbations in the signals detected.
50
4. CONCLUSIONS
Conclusions based on the deflection measurement via ATS during pouring of the deck slab and
diagnostic load test, strain measurement via BOTDR during the load test, and comparison with
analytical results based on the AASHTO LRFD Bridge Design Specifications (1998), can be
summarized as follows:
1. The structural assessment confirms the safety of the bridge, since the experimental
deflection and strain results were found to be smaller than the theoretical values
determined according to the design provisions (AASHTO, 1998);
2. A significant drop in the behavior of one of the exterior girders (Girder 1) was assessed,
with differences in the Span 1 midspan deflection between Girder 1 and Girder 5 of the
order of 30%, under similar load conditions. In the case of the load test, such difference
cannot be justified considering concurrent factors that typically affect the experimental
results. A preliminary explanation may account for a possible alteration of the structural
response as a consequence of the falling of the steel girder during erection of the
superstructure. The issue calls for further verification and monitoring during the life of
the bridge;
3. Experimental results from both techniques employed fairly describe the global response
of the bridge both in terms of deflections and strains, and were consistent with each other;
4. ATS confirms its cost-effectiveness for deflection measurement. The fact that the
technology allows for non-contact measurement significantly enhances its versatility;
5. BOTDR is a promising, novel method for global structural assessment, with the unique
ability to detect the distributed strain along a structural member. In particular, the
adhesively bonded custom-made GFRP tape with embedded optical fibers for strain
measurement provided a far better performance than bare fibers.
51
5. REFERENCES
52
Lexington, MO”, CIES Report 04-002, University of Missouri-Rolla, Rolla, MO, U.S.A.
Hill, C.D. and Sippel, K.D. (2002), “Modern Deformation Monitoring: a Multi Sensor
Approach”, Proc. XXII FIG International Congress, International Federation of Surveyors, April
19-22, 2002, Washington, D.C., 12 pp., http://www.fig.net/pub/fig_2002/Ts6-3/TS6_3_hill
_sippel.pdf.
Hill, K.O., Johnson, D.C. and Kawasaki, B.S. (1976), “CW Generation of Multiple Stokes
and Anti-Stokes Brillouin-Shifted Frequencies”, Applied Physics Letters, 29, pp. 185-187.
Horiguchi, T., Kurashima, T. and Tateda, M. (1989), “Tensile Strain Dependence of
Brillouin Frequency Shift in Silica Optical Fibers”, IEEE Photonics Technology Letters, 1[5], pp.
107-108.
Horiguchi T., Kurashima, T. and Koyamada, Y. (1994), “1-m Spatial Resolution
Measurement of Distributed Brillouin Frequency Shift in Single-Mode Fibers”, Proc. NIST/IEEE
Symposium on Optical Fiber Measurements, Boulder, CO, Sep. 1994, pp. 73-76.
Horton, R., Power, E., Van Ooyen, K. and Azizinamini, A. (2000), “High Performance Steel
Cost Comparison Study.’’ Proc. Steel Bridge Design and Construction for the New Millennium
with Emphasis on High Performance Steel, Baltimore, MD, pp. 120-137.
Komatsu, K., Fujihashi, K. and Okutsu, M. (2002), “Application of the Optical Sensing
Technology to the Civil Engineering Field with Optical Fiber Strain Measurement Device (B-
OTDR)”, presented at the SPIE Smart Sensor Technology and Measurement Systems Conference
(SPIE 4694), San Diego, CA, Mar. 17-21, 2002.
Kuhlmann, H. and Gläser, A. (2002), “Investigation of New Measurement Techniques for
Bridge Monitoring”, Proc. 2nd Symposium on Geodesy for Geotechnical and Structural
Engineering, Berlin, Germany, pp. 123-132, http://www.uni-stuttgart.de/iagb/publikation/
newmeasure_bridge.pdf.
Leica Geosystems, Automated High Performance Total Station TCA2003, http://www.leica-
geosystems.com/surveying/product/totalstations/tc2003.htm.
Lynch, R.J. (2004), “Provisional Design Guide in AASHTO Language for FRP Bridge
Strengthening”, Master Thesis, University of Missouri-Rolla, Rolla, MO, U.S.A.
McDermott, J.F. (1969), “Local Plastic Buckling of A514 Steel Members”, ASCE Journal of
the Structural Division, 5[9], pp. 1837-1850.
Merkle, W.J. (2004), “Load Distribution and Response of Bridges Retrofitted with Various
FRP Systems", Master Thesis, University of Missouri-Rolla, Rolla, MO, U.S.A.
Meng, X. (2002), “Real-Time Bridge Deflection and Vibration Monitoring Using an
Integrated GPS/Accelerometer/Pseudolite System”, Proc. 11th FIG Symposium on Deformation
Measurements, Santorini, Greece, May 25-28, 2003, www.fig.net/commission6/santorini/I-
Monitoring%20Static%20and%20 Dyn/I5.pdf.
Pelous, J. and Vacher, R. (1975), “Thermal Brillouin Scattering Measurements of the
Attenuation of Longitudinal Hypersounds in Fused Quartz from 77 to 300 K”, Solid State
Communications, 16[3], p. 279.
Roeder, C.W., Barth, K.E. and Bergman, A. (2004), ‘‘Effect of Live-Load Deflections on
53
Steel Bridge Performance”, ASCE Journal of Bridge Engineering, 9[3], pp. 259-267.
Roeder, C.W., Barth, K.E., Bergman, A. and Christopher, R.A. (2001), “Improved Live-Load
Deflection Criteria for Steel Bridges”, NCHRP Interim Report No. 20-07/133, National
Cooperative Highway Research Program, Washington, D.C.
Radovanovic, R.S. and Teskey, W.F. (2001), ‘‘Dynamic Monitoring of Deforming
Structures: GPS versus Robotic Tacheometry Systems”, Proc. 10th FIG Symposium on
Deformation Measurements, Orange, CA, May 19-22, 2001, http://rincon.gps.caltech.edu/
FIG10sym/pdf/Session%20II_Paper%204.pdf.
Strongwell Corporation (2004), Fiberglass Flooring and Decking System brochure,
http://www.strongwell.com/PDFfiles/SafdeckSafplank/FlooringandDecking0304.pdf.
Thomas, P.J., Rowell, N.L., van Driel, H.M. and Stegeman, G.I. (1979), “Normal Acoustic
Modes and Brillouin Scattering in Single-Mode Optical Fibers”, Physical Review B, 19, pp.
4986-4998.
Watson Bowman Acme Corporation (2004), Wabo® MBrace Saturant Data Sheet,
http://www.wbacorp.com/downloads/DataSheets/Composites/MBraceSaturant.pdf.
Yariv, A. (1989), “Quantum Electronics”, 3rd ed., John Wiley & Sons.
54
APPENDIX I – LOAD TEST STOPS
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
2 1
Girder 2
Girder 3
Girder 4
4 3 Girder 5
C
L CL C
L CL
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 1
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
5 2 1
Girder 2
Girder 3
Girder 4
6 4 3 Girder 5
C
L C
L C
L C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 2
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
Girder 2
Girder 3
Girder 4
3 4 1 2 6 5 Girder 5
C
L C
L C
L C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 3
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
Girder 2
Girder 3
Girder 4
3 4 1 2 6 5 Girder 5
C
L C
L CL C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 4
55
L3 = 200 ft L2 = 185 ft L1 = 147 ft
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
Girder 2
Girder 3
Girder 4
3 4 1 2 6 5 Girder 5
CL C
L C
L C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 5
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
Girder 2
Girder 3
Girder 4
3 4 1 2 6 5 Girder 5
CL C
L CL CL
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 6
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
5 2 4
Girder 2
Girder 3
Girder 4
6 1 3 Girder 5
C
L C
L CL C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 7
L3 / 2 L3 / 2 L2 / 2 L2 / 2 L1 / 2 L1 / 2
Girder 1
6 1 3 5 2 4
Girder 2
Girder 3
Girder 4
Girder 5
C
L C
L C
L C
L
Pier 4 Pier 3 Pier 2 Abutment 1
Stop 8
56
APPENDIX II – RAW DATA
Concrete-deck pouring
x 1 1/4 spans 2 spans 2 3/4 spans 4 spans 5 spans
[ft] [in] [in] [in] [in] [in]
Girder 1
3.0 1.74E-02 2.53E-02 8.27E-03 6.57E-02 -9.76E-02
50.0 1.02E-01 1.26E-01 -9.96E-03 5.16E-01 -1.13E+00
73.5 1.16E-01 1.32E-01 -1.02E-01 4.98E-01 -1.19E+00
111.0 5.50E-02 6.75E-02 -1.46E-01 3.23E-01 -5.93E-01
143.0 1.97E-04 -2.09E-02 -3.48E-02 6.76E-02 -3.87E-02
Girder 2
73.5 7.14E-02 1.39E-01 -1.04E-01 7.11E-01 -1.05E+00
Girder 3
3.0 1.22E-02 2.75E-02 4.17E-02 1.30E-01 -2.22E-02
50.0 2.22E-02 1.42E-01 -2.43E-02 9.12E-01 -9.54E-01
73.5 2.22E-02 1.35E-01 -1.51E-01 9.00E-01 -1.03E+00
111.0 9.80E-03 6.55E-02 -1.72E-01 6.15E-01 -4.95E-01
143.0 7.40E-03 1.51E-02 -2.76E-02 8.24E-02 -2.30E-02
188.0 -2.50E-02 -6.09E-02 3.75E-01 -1.21E+00 -6.01E-01
234.5 -4.62E-02 -1.34E-01 9.67E-01 -1.77E+00 -1.14E+00
Girder 4
73.5 -3.90E-02 1.21E-01 -7.80E-02 1.12E+00 -8.82E-01
Girder 5
3.0 1.26E-02 1.59E-02 N.A. N.A. N.A.
50.0 -1.19E-01 8.03E-02 -1.26E-01 1.11E+00 -8.62E-01
73.5 -9.86E-02 8.47E-02 -1.70E-01 1.19E+00 -8.98E-01
111.0 -4.94E-02 5.15E-02 -1.93E-01 8.04E-01 -4.27E-01
143.0 1.97E-04 2.11E-02 -5.35E-03 1.00E-01 9.13E-03
151.0 1.62E-02 5.51E-03 4.89E-02 -1.21E-01 -1.15E-02
188.0 5.86E-02 -6.25E-02 4.01E-01 -1.34E+00 -6.66E-01
234.5 5.79E-03 -1.67E-01 9.08E-01 -2.03E+00 -1.35E+00
57
Diagnostic load test
x Stop 1 Stop 2 Stop 3 Stop 4 Stop 5 Stop 6 Stop 7 Stop 8
[ft] [in] [in] [in] [in] [in] [in] [in] [in]
Girder 1
3.0 -5.56E-02 -9.90E-02 -1.78E-02 -1.26E-02 7.64E-03 7.95E-03 -6.41E-02 -1.55E-01
50.0 -4.99E-01 -8.19E-01 -1.50E-01 -2.11E-01 -1.24E-01 4.67E-02 -8.29E-01 -1.37E+00
73.5 -4.79E-01 -8.25E-01 -1.37E-01 -1.95E-01 -6.80E-02 7.81E-02 -8.48E-01 -1.50E+00
111.0 -2.20E-01 -4.75E-01 -7.78E-02 -1.23E-01 -6.54E-02 5.33E-02 -4.57E-01 -9.85E-01
143.0 1.34E-03 -2.92E-02 2.30E-02 1.08E-02 3.80E-02 2.83E-02 -1.57E-02 -1.26E-01
Girder 2
73.5 -4.19E-01 -7.17E-01 -1.00E-01 5.76E-02 -4.24E-02 -1.76E-01 -7.47E-01 -9.57E-01
Girder 3
3.0 -1.64E-02 -5.19E-02 9.72E-03 4.98E-02 3.40E-02 -1.46E-02 -4.34E-02 -3.03E-02
50.0 -3.67E-01 -6.07E-01 -5.47E-02 2.20E-01 -3.07E-02 -3.88E-01 -6.03E-01 -4.57E-01
73.5 -3.84E-01 -6.41E-01 -6.20E-02 2.79E-01 -4.46E-02 -4.35E-01 -6.55E-01 -5.18E-01
111.0 -2.18E-01 -3.76E-01 -4.75E-02 2.34E-01 7.09E-03 -2.78E-01 -3.80E-01 -3.27E-01
143.0 3.94E-05 -3.43E-02 6.30E-04 6.14E-02 2.76E-02 -3.00E-02 -2.16E-02 -2.62E-02
188.0 1.59E-01 2.27E-01 1.38E-01 -3.82E-01 -1.22E-01 1.61E-01 2.23E-01 1.82E-01
234.5 1.75E-01 2.50E-01 2.81E-01 -6.56E-01 -2.21E-01 1.76E-01 2.44E-01 1.86E-01
Girder 4
73.5 -5.26E-01 -7.62E-01 -1.65E-01 3.38E-01 -2.26E-01 -8.98E-01 -7.62E-01 -2.36E-01
Girder 5
3.0 -4.68E-02 -7.66E-02 -8.66E-03 7.24E-02 -1.46E-03 -9.99E-02 -4.90E-02 2.30E-02
50.0 -5.97E-01 -8.10E-01 -1.48E-01 5.19E-01 -2.53E-01 -1.10E+00 -7.35E-01 1.26E-01
73.5 -5.23E-01 -7.72E-01 -9.66E-02 7.16E-01 -2.23E-01 -1.17E+00 -7.05E-01 1.88E-01
111.0 -3.06E-01 -4.65E-01 -1.23E-01 5.90E-01 -1.34E-01 -8.24E-01 -4.20E-01 1.21E-01
143.0 2.99E-03 -2.75E-02 -6.14E-03 9.46E-02 5.87E-03 -7.16E-02 -2.47E-02 2.07E-02
151.0 4.40E-02 3.18E-02 3.53E-02 -7.43E-02 -3.19E-02 4.79E-02 4.31E-02 6.61E-03
188.0 1.38E-01 1.90E-01 2.27E-01 -1.11E+00 -5.19E-01 2.85E-01 1.67E-01 -6.39E-02
234.5 1.37E-01 1.90E-01 4.91E-01 -1.85E+00 -7.61E-01 2.61E-01 1.38E-01 -1.08E-01
58
II.b Strain data (BOTDR)
Bolted joint
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
Stop 1
100 Stop 2
200 Stop 7
300 Stop 8
Abutment 1
Bolted joint
400
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
100
Stop 1
200 Stop 2
300 Stop 7
Abutment 1
Bolted joint
Stop 8
400
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
59
Girder 2 (Location B, Table 3.2)
-300
Bolted joint
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
100
Stop 1
200 Stop 2
300 Stop 7
Abutment 1
Bolted joint
Stop 8
400 Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
100 Stop 1
200 Stop 2
300 Stop 7
Abutment 1
Bolted joint
Stop 8
400
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
60
Girder 5 (Location A, Table 3.2)
-300
0
Strain [µε]
100
200
300
Bolted joint
Abutment 1
Bolted joint
Bolted joint
400
Pier 3
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
Bolted joint
-200
Pier 3
-100
0
Strain [µε]
100 Stop 1
Stop 2
200
Stop 4
300
Stop 7
Abutment 1
Bolted joint
400 Stop 8
Pier 2
500
0 30 60 90 120 150 180 210 240 270 300 330
x [ft]
61