Los Calatos
Los Calatos
Los Calatos can be accessed via the Pan American Highway from
Moquegua, and a 50 kilometre unsealed road north of the highway to
the Project. The port of Ilo is located approximately 160 kilometres
by road to the southwest of the project area (Figure 1).
Back to top
Brief History
The Los Calatos Project was first claimed by Acuarios Minera y
Exploradora S.R.L in the 1990’s. Between 1995 – 1996, Phelps
Dodge held an option on the project from Arequipa Resources
(Acuarios’ affiliate), who in the interim had sold their assets
(including the Los Calatos tenements) to Barrick Gold Corporation
(Barrick).
In December 2008 Metminco made a scrip offer for all the shares in
Hampton. The offer closed on 8 July 2009 with Metminco having
acquired a 36.5% interest, and becoming the major shareholder in,
Hampton. Hampton was a public unlisted Australian company with a
portfolio of six projects located in Chile and Peru.
During the first half of 2010 Metminco raised funds through an AIM
listing in London (granted on 1 April 2010), increased its holding in
Hampton to 69.4% by exercise of the JIC Option, and completed the
purchase of North Hill. On 6 December 2010, Metminco completed
the acquisition of Hampton’s minority shareholder’s interests resulting
in Hampton becoming a wholly owned subsidiary of Metminco.
The following sequence of events summarise the key events that led
to Metminco advancing the project from a potential resource of 20 to
40Mt at ±0.86% Cu to a mineral resource estimate of 352Mt at a Cu
grade of 0.76% and a Mo grade of 0.032%. Key to the substantial
increase in the mineral resource was the recognition of the fact that
Los Calatos is a typical Andean-type porphyry deposit, the geometry
of which was constrained through the culmination of a comprehensive
drill hole program using inclined diamond drill holes:
Back to top
Ownership
Metminco, through its wholly owned subsidiary, Minera Hampton Peru
SAC, holds a 100% interest in Los Calatos.
Back to top
Project of National Interest
In July 2013 the Peruvian Government approved an increase in the
area that Hampton Peru may purchase under the Project of National
Interest designation from 2,800 ha to 12,700 ha to accommodate the
surface infrastructure required to exploit the Los Calatos porphyry
copper – molybdenum deposit. The surface infrastructure required
for the proposed mine includes the open pit and underground
workings, waste and ore stockpiles, plant, mine and administration
structures and a tailings dam.
Mineralisation Stages
Four main stages of Cu and Cu-Mo mineralisation have been
identified at Los Calatos, namely:
Mineralised Breccias
The anhydrite breccias consist of 50 to 600m wide elongated bodies
in excess of 1,500m in vertical and lateral extent. They comprise
crackle to jigsaw breccias with monolithic clasts from pre-existing
lithologies with little displacement, and are rooted within dacitic dyke
swarms.
The breccias cross-cut earlier litho- and alteration types, and tend to
be poorly developed in those rocks that have undergone potassic
alteration with strong to moderate secondary biotite, for rheological
reasons.
Back to top
Exploration
Extensive, regional scale mapping, geochemical and geophysical
programs have historically been undertaken by Metminco over the
project area, which identified 8 targets.
The Company re-evaluated the prospectivity of the broader project
area in August 2014, which resulted in the definition and refinement
of several exploration targets. These targets have been classified
into those targets which are drill-ready, and those which require
further exploration to better constrain the targets for follow-up drill
testing.
Of the four drill ready targets, target TD 2 has the highest priority,
whereas of the four exploration targets, TE 2 has the highest
priority. A site inspection in October 2014 of the TD 3 and TE 2
targets, would suggest that the Los Calatos Porphyry Complex may
extend in a south-easterly direction (Figure 5) into these two target
areas.
Figure 6 shows the structural setting for both the main Los Calatos
desposit, and the TD 2 Target.
Mineral Resource
Following the completion of the detailed re-logging program by
Metminco in early 2015, and the completion of a revised geological
model, SRK Consulting (Chile) S.A (SRK) were requested to prepare
an updated mineral resource estimate for Los Calatos, which was
finalised in June 2015 (Table 1). This follows an earlier mineral
resource estimate completed by SRK in February 2013 that was
announced on 4 March 2013, which was the subject of a mining study
completed by NCL and RPM in March 2013 and August 2013
respectively.
Tonnes Cu Mo
Resource Category
(million) (%) (%)
Measured 73 0.73 0.051
Indicated 63 0.73 0.034
Total Measured & Indicated 136 0.73 0.043
Inferred 216 0.78 0.024
The Study was based on the 3-D block model provided by Metminco,
with related economic information being sourced from both Metminco
and NCL for similar projects in the Region. In estimating the Life of
Mine tonnes milled, Measured, Indicated and Inferred Mineral
Resources were considered, with 23% of the tonnes reporting into the
mining plan having been derived from Inferred Mineral Resources.
Back to top
Mine Production Study - RPM (August 2013)
As mentioned above, RPM focussed primarily on optimising operating
costs and capital expenditure. To this effect, they evaluated the
opportunity to increase production rates from the open pit and
underground block cave operations, as well as the opportunity to
delay underground development until such time as production from
the open pit had commenced.
Note:
1. Cash operating costs exclude government royalties, but include
all other costs and royalties.
2. By-product credits based on commodity prices Cu =
US$2.95/lb, Mo = US$12.78/lb, Au = US$1,348/oz, Ag =
US$25.00/oz and Re = US$5,773/kg.
Production Profile
A production profile was constructed for the Expansion Case based on
a steady state production (and milling) rate of 6.5Mtpa (Figures 7 and
8).
Two conceptual designs have been proposed, the key difference being
that one design has a central vertical shaft system in addition to the
eastern and western declines, whereas the alternate design provides
for a central decline / conveyor system. Although preliminary cost
estimates have been determined for the designs, a detailed trade-off
study has yet to be completed. As such, a contingency of
approximately 25% of total mine capital has been provided.
Design 1
Regional Infrastructure
Over the period 2012 to 2014, Poch y Asociados Ingenieros
Consultores S.A. (“POCH”) conducted a number of studies on Los
Calatos in terms of road access, power supply and the location of a
water and concentrate pipeline to the coast, for which capital and
operating costs were estimated (Figure 10).
The estimated operating and capital costs for the Expansion Case are
summarised in Tables 4 and 5 respectively.
As can be seen from Table 4, the C1 cash operating cost after by-
product credits is US$1.29/lb. Figure 11 shows how Los Calatos
ranks in terms of C1 Cash Costs by comparison to the cumulative
tonnes per annum paid copper production for some 268 copper
projects.
Opportunities
RPM has identified a number of opportunities that have the potential
to improve the economics of the Project, which include:
Back to top
Metallurgical Testwork
A preliminary metallurgical testwork program was conducted on 11
sulphide composites (derived from drill core samples) in 2009 at the
SGS Lakefield Laboratories in Santiago. The results provided a
provisional indication of the expected recoveries and likely
concentrate grades for a commercial operation, namely:
The scope of work for the proposed metallurgical testing will comprise
the following key phases:
Flowsheet development program – Grinding Circuit.
Flowsheet development program – Flotation Circuit for sulphide
ores.
Metallurgical mapping program – Grinding Circuit.
Metallurgical mapping program – Flotation Circuit.
Pilot plant testwork in order to generate sufficient bulk copper-
molybdenum concentrate for copper-molybdenum separation
testwork.
Environmental characterisation program of metallurgical
products.
Back to top
Planned Metallurgical Circuit
Based on the preliminary metallurgical testwork conducted to-date,
the planned metallurgical circuit will be identical to that of other
porphyry hosted copper-molybdenum operations in the Region, as
depicted in Figure 13 below, producing separate copper and
molybdenum concentrates.