This document discusses preliminary site works for construction projects, which include access to the site, clearing vegetation and structures, establishing boundaries, and performing soil investigations. Temporary access roads need to be constructed using materials like ballast, fabric, or timber sleepers. Sites must be enclosed with fencing or hoardings for security and safety. Demolition of existing structures is also covered, noting it should be done carefully by specialists to salvage materials when possible.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
281 views24 pages
Construction Practice 1 For Technician
This document discusses preliminary site works for construction projects, which include access to the site, clearing vegetation and structures, establishing boundaries, and performing soil investigations. Temporary access roads need to be constructed using materials like ballast, fabric, or timber sleepers. Sites must be enclosed with fencing or hoardings for security and safety. Demolition of existing structures is also covered, noting it should be done carefully by specialists to salvage materials when possible.
PRELIMINARY SITE WORKS These are the initial operations carried out on the site before the commencement of the actual structure. They include: 1. Access to the site 2. Clearing the site 3. Access on the site 4. Fencing and hoarding 5. Datum establishment 6. Provision of hutments 7. Provision of services 8. Soil investigation Access to the site Usually, roads are integral part of the contract especially if it is a housing estate or a factory. This means no special requirements will be necessary for the provision of access to the site. Otherwise if no permanent roads are required it is important to construct temporary roads. Factors to consider when constructing access to the site: 1. Distance to site location 2. Correct lay – out of hutments 3. Area size of the site 4. Sign post erection Site clearance This involves demolition existing structures (if any), grubbing out of roots, bushes, stumps etc. and topsoil removal. The depth of the vegetable topsoil may vary according to the geographical strata and information. The site may cleared using two one of two methods or both. This may be either mechanical or manual. The skimmer and grader are popularly used for this purpose. On small sites hand tools such as shovels, pick axes, cutlasses etc. are used for this purpose. The topsoil must not be used for any hardcore filling but for only agricultural purposes. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 2 Reasons for the removal of vegetable top soil 1. To provide a hard level surface for the commencement of the building 2. Vegetable soil contains the organisms and chemicals necessary for the growth of plants 3. It has unreliable bearing capacity 4. Vegetable top soil is also removed to prevent plants from growing underneath the ground floor and encourage dry rot 5. It is unstable and cannot be compacted into a solid natural foundation Temporary roads A hard dry surface must be provided to enable vehicles to be driven to the site. The materials for the road surfaces to be provided may include: i. Ballast, hogging or hardcore ii. Patent fabric of welded steel iii. Timber sleepers Ballast, hogging or hardcore This can be laid and rolled into a hard surface if good drainage is provided, this road can be most efficient and economical, provided it is laid on a hard dry surfaces. Patent fabric This gives an excellent riding surface and can be laid on a ground which is a little bit soft. The material also allows heavy vehicles to move safely on slightly soft ground. The ground is shaped and cambered to shed water. The edges of the fabric must be pinned down to prevent the edges from curling up, which could cause damage to lorry tires personnel tripping off. drainage trench 50mm hogging or75mm hardcore 4m road surfaced with hogging or hardcore Camber Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 3 Timber sleepers Timber is expensive but can be used to an advantage. The ground is prepared and two channels cut, one on each side. The sleepers are then laid and nailed to the lower members to prevent dislodging. Methods of Enclosing The Site & Their Protection There are two methods of site enclosure: a. Fencing b. Hoarding The type of protection and enclosure chosen will depend on the 1. Degree of security required 2. Cost implications 3. Type of neighbourhood drainage trench patent fabric 4m road surfaced with patent fabric fabric pegged down at dges Camber Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 4 4. Duration of contract The hoarding is erected when the work has started on the site for the following reasons: 1. To prevent the public from having free access 2. To safeguard the structure 3. To safeguard the building materials 4. To prevent the public from dust and noise associated with construction activities The fence is used for the following purposes: 1. Defines boundary 2. Limits the site 3. Serves as a barrier for protection 4. Restricts movement 5. Limits or stops view 6. Forms visual link/feature between unit blocks. Example of Fences 1. Chain link 2. Woven wire 3. Strained wire 4. Cleft chestnut pale 5. Close boarded. 6. Wooden palisades 7. Metal continuous bar 8. Woven wood wattle panel 9. Concrete panel Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 5 The fan hoarding The fan hoarding fulfils the function of directing falling debris back towards the building or scaffold. It is placed at a level above the normal traffic height. If hoarding is above public footpath it should be lined with polythene or similar sheeting. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 6 hole through existing wall for support supports @ 600 c/c sheeted deck struts @ 600c/c fan hoarding details Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 7 Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 8 Demolition This is the complete destruction of the structure. It is the reverse order of construction. The method of demolition a particular structure would be determined by 1. The size of the building 2. Its type and method of construction 3. Its location within the site boundary 4. The distance away from surrounding buildings 5. He amount of recoverable or salvageable materials 6. The expertise of a particular contractor Reasons for demolition 1. Structural failure - that is the structure is unsafe because of degeneration 2. Progress of society – no longer required due to changes in demand 3. Economic use of land Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 9 4. Economic consideration (the structure will cause too much to be repaired) This is a specialist operation and must be done by a specialist contractor. By employing an expert numerous advantages would be achieved, thus 1. He can salvage some of the materials 2. He can appreciate the factor affecting safety 3. He will also have adequate insurance cover in the event of any mishap There are two types of demolition 1. Total demolition 2. Partial demolition Total demolition This is where the whole structure is demolished. Partial demolition This is where only part of the structure is removed. Demolition techniques 1. Hand demolition 2. Fragmentation Hand demolition This involves progressive dismantling of the building in the reverse order to its construction. This may be used where there are severe site restrictions and/or partial demolition is required. This is employed where salvageable materials are valuable. The work is done with hand held tools plus lifting appliances to support main members as they are released and to lower them to the ground when freed. No debris should be allowed to fall free unless the point of fall is at least 6.0m or half the height from which it is dropped away from a public highway or adjoining property. Fragmentation This is the process of reducing a building to a heap of rubble by the cheapest methods available. The methods available are 1. Pusher arm Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 10 2. Deliberate collapse 3. Rope pulling 4. Explosives 5. Demolition ball 6. Bursting 7. Thermal methods Pusher arm This is done using a steel or timber beam attached to a mechanical excavator and pushes over sections of the structure rather than dismantling it. The machine should be operated from outside the building so that the debris falls inwards. This method is suitable for relatively low structures within the reach of the pusher arm. Deliberate collapse This technique reduces the building to a heap of rubble by the removal of a number of key structural members. It is quick and reasonably safe in expert hands but produces a lot of noise, vibration and dust. The removal of the key members may be effected by pulling them out by wire rope or blowing them out with explosives. Rope pulling This uses a wire rope which is well anchored winched or tracked or heavy vehicle pulling to pull over successive portions. It is suitable for masonry buildings over 21m. The pulling rope should always be of length such that the horizontal distance from the winch to the building is twice the height of the building being demolished. Explosives This is the most dramatic method. Charges of explosives are placed at the base of the structure and detonated to cause partial or complete collapse. For a larger structure there may be controlled succession of blasts which brings it down in stages. Demolition ball This method employs a weight, suspended from a crane and swung against or dropped onto the structural members. It is highly skilled operation and should only be carried out within clearly defined limits to avoid overloading or overstressing the crane. Usually the roof is removed, 50 to 75 percent of floors removed by hand before balling work starts. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 11 Bursting A cavity is formed in critical members of the building and are forced to enlarge . causing the members t fracture, leading to a controlled collapse. The force is applied by either a gas-expansion or hydraulic burster. The gas-expansion burster is made up of a cylinder filled with gas which, when ignited by electrical charge expands rapidly into the cavity. Thermal methods This method combines thermal reaction on structural steel members in conjunction with wire rope pulling. The beam or stanchion to be severed has a mixture of metal oxide and a reducing agent applied around critical point. When the mixture is ignited it liberates enough heat to soften the metal sufficiently to allow the member to be pulled down. Provision of Hutments These are usually wooden structures erected on site to provide for a simple temporary accommodation or for leisure activities and offices etc. Classification of hutments 1. Mobile 2. Semi-mobile 3. Framed A CRANE & A DEMOLITION BALL Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 12 4. Sectional 5. Portable framed 6. Air house Factors to consider when erecting hutments: 1. Duration of contract 2. Availability of space 3. Location of site 4. No of employees 5. Size of contract These hutments may also be used for storing the materials on site. Provision of services The services which may encountered on or around a site are 1. Water 2. Gas 3. Electricity 4. Telephone 5. Sewerage 6. Oil 7. Television All the services listed are classified into three areas: 1. National 2. Regional 3. Local The appropriate board must be notified before any connection can be made. The following information must be communicated to the local authority and permission granted before work commences. 1. Name and address of the developer 2. Location of the land to be developed 3. Description of the proposed development 4. Previous use of land 5. Whether a new access would be required from the highway Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 13 6. Plan to which the permission refers 7. 1:100 or 1:200 drawing to give a clear picture of the new building or alteration Storage and protection of materials The type of storage facilities required of any material depends on the following factors: 1. Durability – whether it needs protection from the elements 2. Vulnerability to damage 3. Vulnerability to theft Cement Cement is supplied in bulk, bags or in drums. Bulk cement is delivered to site by tankers and blown into storage silos by compressed air. Bagged cement, delivered on a wagon having a tarpaulin cover, should be stored in a close cabin, the floor of which is at least 150mmabove the ground. The bags should be stored closely together to prevent the circulation of air. Aggregates Aggregate should be stored on a hard, clean free draining surface. They may be stored in bins or hoppers so that the stockpiles do not mix thus ensuring that different aggregates, types and sizes are kept separately. Bricks and Blocks These may be supplied loose or strapped in unit loads and stored on raised timber pallets. Facing and coloured bricks should be covered to prevent contamination. tarpaulin covering cement storage weather boarded shield without windows Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 14 Timber and Joinery These should be stored horizontally and covered and provision made for air circulation. Timber sizes should be kept separately and raised off the ground to prevent contamination. Drainage pipes Should be supplied loose or strapped on timber pallets. It should be stored horizontally with the ends reversed in alternate rolls. Location of plants Plants must be placed at the most convenient and strategic points so that maximum benefit could be achieved from their use. Points to consider: i. Headlights should be set up truly horizontal ii. They should be securely fixed to a firm and solid base. iii. Cranes should be positioned so that they are able to reach all materials that need to be hoisted; e.g. cement, aggregate etc. iv. Mixers and mortar pans should be specially sited to keep the distance to wheeling concrete or mortar as short as possible. v. Batching plants should be set up in a central position on the site to be readily accessible for Lorries to discharge aggregates etc appropriately. Factors to be considered when allocating plants on site 1. The availability of space 2. Working room requirements 3. Mobility on site 4. Servicing requirements Provision for workers welfare and safety on site It is essential to have the interest of all workers on site and to provide the best facilities for their upkeep. Advantages from such provisions may include 1. It reduces pilfering 2. It serves as an incentive to the operatives 3. Boost workers morale 4. Increases productivity Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 15 Welfare and safety provisions include: 1. Notices and fees to local authorities – this include fees for water supply, public services and all other fees which may be demandable by the local authority. 2. Watching and lighting – to provide all requisite day and night watching. 3. Maintenance of public and private roads – there should be no damage to roadways, footpaths and all other properties. 4. Water for the works – the contractor must supply water for the site and responsible for the protection of meters and cocks. 5. Lighting and power – artificial lighting and power must be provided on the site for all personnel, including subcontractors and nominated subcontractors. Difficulties encountered when working in bad weather Rain, high winds, low temperatures, poor daylight levels are some of the weather effects that can seriously affect construction activities. The worse effects obviously occur when more than one of these occurs simultaneously. Shelter is required for the men during bad weather and somewhere to deposit the clothes not worn during working hours. Lessening of difficulties in hot weather 1. In very hot weather, the freshly laid concrete should be shielded from the direct sun until seven days to prevent rapid evaporation due to temperature, relative humidity and wind. 2. Mixing water and the materials must be kept as cool as possible. 3. Aggregate should be protected from the sun and sprayed with water to cool down immediately. Lessening of difficulties in cold weather 1. All aggregate should be pre-heated by perforated steam pipes to prevent the attack of frost. 2. Mixing water must be heated to a temperature not exceeding 80˚C with a water cement ratio of 0.5. 3. Concrete must be cured for longer periods due to the fact that low temperatures retard concrete hardening and strength gain. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 16 4. Additional Portland cement, high curing temperatures (steam curing), high early strength cement and other known methods may be employed to obtain high-early strength. Site & Soil Investigation The basic objective of site investigation is to collect systematically and to record all the necessary data which will be required in the design of the proposed work and their construction. Site investigation is thus all embracing, taking into account such factors as topography, location of existing services, means of access and any local restrictions. Soil Investigation specifically relates to the subsoil beneath the site under investigation and could be part of or separate from the site investigation. It is usually a means of obtaining data regarding properties and characteristics of sub-soils by providing samples for testing or providing a means of access for visual inspection. Methods of soil classification i. Physical properties ii. Geological origin iii. Chemical composition iv. Particle size distribution Generally soils are defined as coarse - grained or fine – grained each resulting in different properties. Coarse – grained soils These include sands and gravels having a low proportion of voids, negligible cohesion when dry, high permeability and slight compressibility which takes place almost immediately upon the application of load. Fine – grained soils These include cohesive silts and clays having a high proportion of voids, high cohesion, very low permeability and high compressibility which takes place slowly over a long period time. There is however several soils which can be described between these two extremes and are divided into particle size as follows: 1. Clay particles less than 0.002mm 2. Silt particles between 0.002 and 0.06mm Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 17 3. Sand particles between 0.06 and 2mm 4. Gravel particles between 2 and 60mm 5. Cobbles between 60 and 200mm Purpose of Soil Investigation a. Determine the suitability of the site for the proposed project. b. Determine an adequate and economic foundation design c. Determine the difficulties, which arise during the construction process and period. d. Determine the occurrence and or cause of all changes in subsoil conditions. Factors Affecting Method or Choice of Soil Investigation a. The size of the contract b. Type of proposed foundation c. Type of sample required d. Type of subsoil to be encountered Main methods of soil investigation The methods of soil investigation are Trial pits – small contracts where foundation depths are not likely to exceed 3.0m Bore holes- - medium to large contracts with foundations up to 30.0m depth. Trial Pit Primarily to obtain subsoil sample for identification, ascertaining the subsoil characteristics and properties. Trial pits and auger bore holes may also be used to establish the presence of any geological fault and upper or lower limit of the water table. Trial pit can also be used to expose and /or locate underground services. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 18 The trial holes are used purposely to: 1. Know the thickness of each layer of the subsoil 2. Know the composition of each stratum 3. Know the size of various particles of which the subsoil is composed in each stratum 4. The condition of each stratum 5. The water table level 6. The quantity of water below ground level Disadvantages i. Difficult to operate in high water tables and very loose soils ii. There is the need to provide for pumps for and timbering to provide dry land Bore hole These are carried out using either a hand auger (shallow bore hole) or mechanical auger (deep bore hole) to determine the suitability of a particular type of soil for a project. A shell boring tool consist of a cylindrical steel shell which is dropped into the soil causing soil to be forced into the cylinder either by friction in the case of cohesive soil or nonreturn flap in the case of non-cohesive soil. The diameter of the samples obtained varies from 100mm – 200mm according to the method employed in extracting the sample. Undisturbed soil samples can be obtained from Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 19 cohesive soils 450mm long x 100mm diameter sampling tubes which are driven into the soil to collect the sample within itself, upon removal the tube is capped, labeled and sent to laboratory for testing. Purpose of Auger Hole Primarily to obtain subsoil structure for identification, classification and ascertaining the subsoil characteristics and properties. Could be used if required to obtain subsoil samples at a depth beyond the economic limit of trial hole. Advantages i. Generally cheaper ii. Simpler than trial hole Setting out This is the process whereby the outline of the building on plan is transferred to the ground for excavation works to be done. Setting out should be carried out by competent persons and check by different persons with different methods. The setting out of the building can be divided into two distinct operations: Establishing the position of the building and setting up the profile. Sand or gravel auger clay auger hand augers Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 20 Establishing a datum peg and the transferring the required levels to various positions. Equipment For setting out i. Steel tape ii. Builders’ square iii. Crosscut saw & nails iv. Pegs v. Plumb bob/spirit level vi. Site square vii. Line Datum establishment The datum (TBM) is a basic level established on the site from which all measurements and/or levels for the building to be erected on the site can be taken. The level of the TBM is usually set to that of the ground floor level which is fixed in relation to other known levels in the vicinity, preferably an (OBM). A peg is driven down until the top reaches the desired height and other levels are transferred from it. One method of transferring this is by using a long leveling board and a spirit level. site datum or temporary bench mark hardwood peg(top level equals ground level). concrete Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 21 Transferring levels The level of the site datum can be transferred to other parts of the site in several ways. One method is using the straight edge and the spirit level. The straight edge and the spirit level must be reversed in the next move to cancel out minor errors that may occur. Requirements of setting out: 1. Should be in the correct position 2. Be at the correct level 3. Be erected vertically ground line 3.0m straigt edge straight edge& spirit level reversed datum peg peg transferring levels-straight edge spirit level method Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 22 Sequence of operation Note: all setting out is done from a building line. 1. Drive in pegs on the side boundary at the correct distance from and parallel to the centre line of the road 2. Strain a line between two nails placed at the centre of the pegs 3. Drive two pegs C and D along the building line to indicate the front corners of the building. 4. Set out lines at right angles to peg C and D and establish pegs E and F. Drive nails at the centres of the pegs and stretch lines between the four pegs. 5. Measure along lines CE and DF to establish pegs G and H in the far corners of the building. 6. Check diagonals CH and DG Note: Base line is the line on which the building commences Building line is the an imaginary line drawn from the centre of the road to the base line trench width wall width saw kerf arrangement for a corner profile Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 23 Frontage line is the line in front of which no other development is permitted by the local authority (and can be the building line or the base line). Setting out Curves To set out circular shape the easiest method is to determine the centre or striking point of the curve. Then a trammel or measuring tape is used to mark out the curve by securing the trammel at the centre point and swinging around in an arc. Using template 1. This method is applicable if the radius of the curve is short. 2. Mark out the chord AB and rise CD 3. Fix nails at points A B and C. 4. Nail battens together so that the first batten touches points A and C and the second points B and C 5. Nail the spreader across the two battens 6. Draw the curve by moving the frame so that it keeps in contact with points A and B with a pencil at the intersection. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 24 Setting out right angles 3:4:5 method 1. Mark out a triangle of sides 3:4:5 2. Measure three and four units respectively on the front and side lines 3. Position the side lines so that the distance between the two marked points is five units. Builders’ square Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 25 1. Using a large builders’ square set it up on pickings so that one leg is against the building line. 2. Position the side line so that it runs parallel to the other leg of the square. 3. Read off the right angle at the corner. 3:4:5 method builders’ square method Using the site square 1. Set out the base or building line with pegs at the required distance Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 26 2. Set the site square at the head of nail at the peg marking the corner to be set out 3. Sight onto the nail in the next peg along the base line and obtain the dead on position 4. Measure the required distance approximately at right angles to the peg from the peg from which the instrument is set up. Signalthe assistant to move pe sideways until it is on spot. 5. Place a nail at the top of the peg ensuring that the nail is at the centre and that the distance is the exact required. 6. Repeat the operations on all pegs to set out the corners of the structure. Setting out acute angles To setout 45˚ 1. Set out right anles using any known methods 2. Measure equal lenths from the vertex topoints B and C 3. Measure carefully halfway the length BC 4. Pull a line from A through the mid point of BC and this forms 45˚ to either of the lines forming the right angles. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 27 To setout 60˚ Measure any convenient distance between points A and B Hammer in pegs at these points A third point C is driven in from both points A and B Pull lines from peg A through peg B and from peg A through peg C The two lines will form 60˚ When this angle is halved 30˚, 15˚ and 7.5˚ can be set out Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 28 Timbering to trenches Timbering is the method used to support the ground when excavating is done. Factors to consider when timbering 1. The nature of the soil 2. The pressure to be supported 3. The depth of cutting 4. The water table level Purpose of timbering To prevent the sides of the trench from collapsing To safeguard the operatives working in the trench To save excessive excavation as in battered trenches Causes of collapse of timbering 1. Variation of the bearing pressure 2. Changes of angle of repose due to moisture content differences 3. Failure due to heavy loads placed near the edges of the trench 4. Overloading timbering members Methods of support 1. Timbering 2. Sheet piling 3. Battering 4. Cofferdams 5. Retaining walls 6. Caisson Safety requirements 1. Must be inspected by competent persons 2. Timbering must be done as the work proceeds 3. Suitable barriers should be provided Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 29 STAIRS A stair is a series of steps leading from floor to floor, floor to landing or landing to landing. A stair case or stair way is the complete system of treads, risers, strings, balustrades, and other component parts in one or more successive flights of stairs. The space occupied by a staircase is called a stairwell. The vertical distance between the floors served by a staircase described as the lift. Function The primary functions of any stairway are: 1. To provide the movement of people and goods from one floor level to another 2. To provide a suitable means of escape in case of fire Types of stairs i. Straight flight ii. Dogleg or half space landing iii. Open well iv. Geometrical v. Spiral vi. Helical Straight flight This the simplest form of stair and consists of a straight continuous flight or run of parallel steps. Dogleg A dogleg or half turn stair has one flight rising to an intermediate half-space landing, with the second flight travelling in the opposite direction to the first. Open-well or Open newel This stair contains a central well with newels at each change of direction and two or more flights of steps around the outside of the well. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 30 Geometrical stair This is a stair which takes the form of a spiral with the face of the steps radiating from the centre of a circle which forms the plan of the outer string and incorporates an open well. Spiral stair This is a form of geometrical stair without a well. Helical stair This is a stair which contains a helix round a central void. Regulations and Requirements 1. The pitch of a private stairway must not be more than 42˚. 2. The pitch of a common stairway must not be more than 38˚. 3. The rise per step of a common stairway must not be more than 190mm. 4. Maximum rise per step should be 220mm. 5. Minimum going should not be less than 225mm. 6. Twice the rise plus the going shall not be less than 550mm and not more than 700mm. (2R + G = 550 -700mm). 7. The minimum headroom shall not be less than 2m, measured vertically the pitch line. 8. The nosing of any tread in an open riser stair shall overlap the back edge of the tread below not less than 16mm. 9. Stairs with open risers shall be constructed such that the spaces between the open risers do not permit the passage of a 100mm sphere. 10. A stairway should not have more than 16 risers in a flight. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 31 quarter - space landing open newel stair dog-leg stair landing between two straight flights (fly landing) Straight flight Dog-leg Open Well Geometrical sectional elevation Pre- Cast Concrete Spandrel Stair (triangular section) Geometrical Up Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 32 Terms 1) Tread 2)Riser 3) Nosing 4)Going 5)Rise 6)Margin 7) Closed String 8) Cut (open string) 9) Newel 10) Bearer 11) Brackets 12) Trimmer 13) Blocks 14) Handrail 15) Baluster 16) Wedges Spiral (helical) Stair Plan REGULATIONS FOR COMMON STAIRWAY going not less than 225mm rise not less than 190mm 38° Pitch Line Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 33 420 REGULATIONS FOR PRIVATE STAIRWAY going not less than 212mm rise not less than 200mm Pitch Line Glue Block 16mm Riser HousedScotia METHOD OF FORMING STEPS 22mm Tread 9mm plywood Riser Glue Block HOUSED RISER Newel Fixing galvanised steel dowel grouted into concrete floor Newel Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 34 Guarding of stairway Setting out the stairs Assume a lift or total rise of 2400mm Assume a travel or total going of 2925mm Assume 14 risers Thus number of treads = 14 - 1 = 13 Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 35 Thus: rise = lift/ total rise = 2.400 = 172mm Number of risers 14 Going = travel/total going 2.950 = 225mm Number of treads 13 Check: 2R + G = 550 - 700mm; 2(172) + 225 = 344 + 225 = 569mm, thus the stair is satisfactory. Factors affecting the design of stairs 1. Purpose or use of the stair 2. Size and shape of the stairwell 3. Economic factors (type of construction, cost, material type etc.) 4. Total height of the building Defect in stairs 1. Poor fixing of newels and top nosings 2. Flights not rigidly fixed 3. Handrails not sanded smooth 4. Creaking of stairs resulting from poor securing of treads and risers Unprotected stairs, damage after installation and loosened items such as Disadvantages of timber stair 1. The main disadvantage is that it will help to spread fire in case of an outbreak. 2. Few timbers are resistant to decay or insect attack, thus for a prolonged life span, the timber should be preserved which may automatically increase the cost f construction. 3. Difficulty in the selection of good quality timber Advantages of concrete stair 1. Non combustible 2. Strong as compared to timber 3. Hard wearing 4. Obtained in in-situ or pre-cast for ready installation. Disadvantages of tapered steps Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 36 1. Hazard to the aged and the very young, due to the very small tread length at or near the newel post. 2. Difficult to carpet 3. Difficult to negotiate with furniture 4. Have little or no aesthetic appeal 5. Expensive to construct Pre-cast concrete stair construction Basically there are two methods of fixing stairs into walls: i. as the work proceeds ii. after the work has been completed Fixing after completion of the wall 1. Set out the position of the stairway as the wall proceeds to ensure the correct placement of the sand courses. 2. Remove the sand courses, brush out the indents and dampen the wall 3. Use a height rod to set out position of stair between two floors this should have the number of steps required marked on it 4. Measure the total going of the steps and divide into the number of steps 5. Use riser and tread gauges to allow for ease of checking 6. Bed the first step in a cement sand mortar (1:2) across the width of the stair, level in both directions, check for height and build into the wall 7. Wedge the steps at both ends and level the treads 8. Lay a straight edge against the nosings of the stair to check for accuracy 9. Use a line to check the alignment of the steps at their free ends Fixing the steps as the work proceeds 1. Set out the position of the stairway as the wall proceeds ( no provision of sand courses) 2. Use a height rod to set out position of stair between two floors this should have the number of steps required marked on it 3. Measure the total going of the steps and divide into the number of steps 4. Use riser and tread gauges to allow for ease of checking 5. Bed the first step in a cement sand mortar across the width of the stair, level in both directions, check for height Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 37 6. Lay a straight edge against the nosings of the stair to check for accuracy 7. Use a line to check the alignment of the steps at their free ends 8. If the steps are cantilevered a temporary support must be provided not less than 16mm Square for determining position of the step ( gauge) OPEN RISER STAIR WAY upper part of step reinforced Methods of checking the accuracy of the position of the steps Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 38 waist cut string treads fixed to string open riser stair Newel Handrail String Fitting Handrail & string to newel in timber stair Metal Bracket to wall Handrail screwed through bracket to plug Handrail plugged screwed Fixing handrails molten lead caulked into mortice around standard End of handrail flattened and bolted to side of concrete stair Metal standard of balustrade cement pointing standard ragged with saw cuts nut & washer nut & washer baluster bolted tread or landing fixng metal standard to concrete steps Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 39 tension lap starter bars distribution bars main bars stair waist distribution bars In-situ reinforced concrete stair details Straight egde to check nosing cleat strut joist sole plate wedges cleat margin piece soffit board strut props cleat struts outer cut string to both edges bracing Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 40 wedges string scotia mould nosing blocks riser tread line of nosing section through a string handrail top rail grooved into handrail plywood panels bottom rail capping string panelled balustrade B B A A Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 41 DOORS A door is a solid barrier fixed in a doorway or opening in a wall or partition to hinge, pivot or slide open to close for access to and from buildings and between rooms, compartment, corridors, landings and stairs. A door is classified by the way it is positioned in a building, by their function or their method of construction. The recommended size of a door opening is 900mm x 2100mm. this gives a door size of 800 x 2000in both width and height. Functional Requirements The primary function of a door is the means of access. The functional requirements of a door when closed are a. Privacy b. Strength c. Stability d. Weather resistance e. Durability or freedom from maintenance f. Fire security g. Resistance to the passage of heat h. Resistance to the passage of sound i. Exclusion of wind and rain (external door) Selection of Doors The factors affecting the choice of doors are: a. Position in the building b. The order of priority c. Appearance The order of priority of the performance requirements of a door are: i. Weather exclusion ii. Security iii. Fire iv. Thermal/sound insulation v. Privacy vi. Durability vii. Method of operation Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 42 The appearance of a domestic bathroom door is of little importance, whereas the doors to the office of a Managing Director should create a suitable impression on those entering. External doors These are used to close the access to the internal of a building and provide a means of security. They are thicker and more robust in design than internal doors. Internal doors These are used to close through internal walls within the building, partitions etc. they are made thinner than their external counterparts since weather protection is no longer a requirement. Classification (types) Battened doors –(match boarded doors) - ledge and batten doors, ledge, brace and batten doors and frame ledge brace and batten doors. 1. Panel doors 2. Glazed doors 3. Flush doors 4. Purpose made doors Ledge and batten doors The face of the door is made from tongue and groove boarding which has edge chamfers to one or both faces, forming a vee joint between consecutive boards. Normally three horizontal members called ledges, clamp the boards together making it a non standard form of a door. It is cheap to construct but has a disadvantage of dropping at the closing edge, thus pulling the door out of square. its use is limited to buildings such as sheds, outhouses, and small units like trap doors. Ledge brace and batten doors This is a standard battened door in which braces are incorporated to resist the tendency of the door to drop out of square. The braces are fixed between the ledges so that they are parallel to one another and slope toward the hanging edge. Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 43 Frame ledge brace and batten doors Another standard door in which mortise and tenon frame surrounds the match boarded panel, giving the door added rigidity. When the doors are wider, the braces become too low to be of value as an effective restraint and it must therefore be framed as a diagonal between the top and bottom rails. Treatment to doors in transit A door irrespective of the soundness of its construction will deteriorate if improperly treated during transportation, storage and after hanging. framed ledged brace & batten door ledged brace & batten door ledged & batten door ledge match board top rail brace stile bottom rail middle rail hanging edge 1,2,3,or 4 panelled doors top rail plywood or glazed panel stile bottom rail middle rail skeleton framing lightweight core filling plywood facing edge lipping flush door Construction Practice for Technician & Diploma Students -Volume One ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 44 Treatment 1. It should receive wood priming coat of paint before or immediately after delivery, 2. It should be stored in the dry and flat position so that it does not twist before and immediately after delivery 3. It should also receive finishing coat of paint as soon as practicable after hanging 4. Finished doors should be wrapped in building paper or polythene sheet to prevent damage to the finished door purpose made doors top rail plywood or glazed panel stile bottom rail middle rail purpose made doors top rail stile bottom rail intermediate rail frieze rail solid raised panel