0% found this document useful (0 votes)
281 views24 pages

Construction Practice 1 For Technician

This document discusses preliminary site works for construction projects, which include access to the site, clearing vegetation and structures, establishing boundaries, and performing soil investigations. Temporary access roads need to be constructed using materials like ballast, fabric, or timber sleepers. Sites must be enclosed with fencing or hoardings for security and safety. Demolition of existing structures is also covered, noting it should be done carefully by specialists to salvage materials when possible.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
281 views24 pages

Construction Practice 1 For Technician

This document discusses preliminary site works for construction projects, which include access to the site, clearing vegetation and structures, establishing boundaries, and performing soil investigations. Temporary access roads need to be constructed using materials like ballast, fabric, or timber sleepers. Sites must be enclosed with fencing or hoardings for security and safety. Demolition of existing structures is also covered, noting it should be done carefully by specialists to salvage materials when possible.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

Construction Practice for Technician & Diploma Students -Volume One

ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 1


PRELIMINARY SITE WORKS
These are the initial operations carried out on the site before the commencement of the
actual structure. They include:
1. Access to the site
2. Clearing the site
3. Access on the site
4. Fencing and hoarding
5. Datum establishment
6. Provision of hutments
7. Provision of services
8. Soil investigation
Access to the site
Usually, roads are integral part of the contract especially if it is a housing estate or a
factory. This means no special requirements will be necessary for the provision of access
to the site. Otherwise if no permanent roads are required it is important to construct
temporary roads.
Factors to consider when constructing access to the site:
1. Distance to site location
2. Correct lay – out of hutments
3. Area size of the site
4. Sign post erection
Site clearance
This involves demolition existing structures (if any), grubbing out of roots, bushes, stumps
etc. and topsoil removal. The depth of the vegetable topsoil may vary according to the
geographical strata and information. The site may cleared using two one of two methods or
both. This may be either mechanical or manual. The skimmer and grader are popularly used
for this purpose. On small sites hand tools such as shovels, pick axes, cutlasses etc. are
used for this purpose. The topsoil must not be used for any hardcore filling but for only
agricultural purposes.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 2
Reasons for the removal of vegetable top soil
1. To provide a hard level surface for the commencement of the building
2. Vegetable soil contains the organisms and chemicals necessary for the growth of
plants
3. It has unreliable bearing capacity
4. Vegetable top soil is also removed to prevent plants from growing underneath the
ground floor and encourage dry rot
5. It is unstable and cannot be compacted into a solid natural foundation
Temporary roads
A hard dry surface must be provided to enable vehicles to be driven to the site. The
materials for the road surfaces to be provided may include:
i. Ballast, hogging or hardcore
ii. Patent fabric of welded steel
iii. Timber sleepers
Ballast, hogging or hardcore
This can be laid and rolled into a hard surface if good drainage is provided, this road can
be most efficient and economical, provided it is laid on a hard dry surfaces.
Patent fabric
This gives an excellent riding surface and can be laid on a ground which is a little bit soft.
The material also allows heavy vehicles to move safely on slightly soft ground. The ground
is shaped and cambered to shed water. The edges of the fabric must be pinned down to
prevent the edges from curling up, which could cause damage to lorry tires personnel
tripping off.
drainage trench
50mm hogging or75mm hardcore
4m
road surfaced with hogging or hardcore
Camber
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 3
Timber sleepers
Timber is expensive but can be used to an advantage. The ground is prepared and two
channels cut, one on each side. The sleepers are then laid and nailed to the lower members
to prevent dislodging.
Methods of Enclosing The Site & Their Protection
There are two methods of site enclosure:
a. Fencing
b. Hoarding
The type of protection and enclosure chosen will depend on the
1. Degree of security required
2. Cost implications
3. Type of neighbourhood
drainage trench
patent fabric
4m
road surfaced with patent fabric
fabric pegged down at dges
Camber
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 4
4. Duration of contract
The hoarding is erected when the work has started on the site for the following reasons:
1. To prevent the public from having free access
2. To safeguard the structure
3. To safeguard the building materials
4. To prevent the public from dust and noise associated with construction activities
The fence is used for the following purposes:
1. Defines boundary
2. Limits the site
3. Serves as a barrier for protection
4. Restricts movement
5. Limits or stops view
6. Forms visual link/feature between unit blocks.
Example of Fences
1. Chain link
2. Woven wire
3. Strained wire
4. Cleft chestnut pale
5. Close boarded.
6. Wooden palisades
7. Metal continuous bar
8. Woven wood wattle panel
9. Concrete panel
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 5
The fan hoarding
The fan hoarding fulfils the function of directing falling debris back towards the building
or scaffold. It is placed at a level above the normal traffic height. If hoarding is above
public footpath it should be lined with polythene or similar sheeting.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 6
hole through existing
wall for support
supports @ 600 c/c
sheeted deck
struts @ 600c/c
fan hoarding details
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 7
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 8
Demolition
This is the complete destruction of the structure. It is the reverse order of construction.
The method of demolition a particular structure would be determined by
1. The size of the building
2. Its type and method of construction
3. Its location within the site boundary
4. The distance away from surrounding buildings
5. He amount of recoverable or salvageable materials
6. The expertise of a particular contractor
Reasons for demolition
1. Structural failure - that is the structure is unsafe because of degeneration
2. Progress of society – no longer required due to changes in demand
3. Economic use of land
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 9
4. Economic consideration (the structure will cause too much to be repaired)
This is a specialist operation and must be done by a specialist contractor. By employing
an expert numerous advantages would be achieved, thus
1. He can salvage some of the materials
2. He can appreciate the factor affecting safety
3. He will also have adequate insurance cover in the event of any mishap
There are two types of demolition
1. Total demolition
2. Partial demolition
Total demolition
This is where the whole structure is demolished.
Partial demolition
This is where only part of the structure is removed.
Demolition techniques
1. Hand demolition
2. Fragmentation
Hand demolition
This involves progressive dismantling of the building in the reverse order to its
construction. This may be used where there are severe site restrictions and/or partial
demolition is required. This is employed where salvageable materials are valuable. The
work is done with hand held tools plus lifting appliances to support main members as they
are released and to lower them to the ground when freed. No debris should be allowed to
fall free unless the point of fall is at least 6.0m or half the height from which it is
dropped away from a public highway or adjoining property.
Fragmentation
This is the process of reducing a building to a heap of rubble by the cheapest methods
available. The methods available are
1. Pusher arm
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 10
2. Deliberate collapse
3. Rope pulling
4. Explosives
5. Demolition ball
6. Bursting
7. Thermal methods
Pusher arm
This is done using a steel or timber beam attached to a mechanical excavator and pushes
over sections of the structure rather than dismantling it. The machine should be operated
from outside the building so that the debris falls inwards. This method is suitable for
relatively low structures within the reach of the pusher arm.
Deliberate collapse
This technique reduces the building to a heap of rubble by the removal of a number of key
structural members. It is quick and reasonably safe in expert hands but produces a lot of
noise, vibration and dust. The removal of the key members may be effected by pulling
them out by wire rope or blowing them out with explosives.
Rope pulling
This uses a wire rope which is well anchored winched or tracked or heavy vehicle pulling to
pull over successive portions. It is suitable for masonry buildings over 21m. The pulling
rope should always be of length such that the horizontal distance from the winch to the
building is twice the height of the building being demolished.
Explosives
This is the most dramatic method. Charges of explosives are placed at the base of the
structure and detonated to cause partial or complete collapse. For a larger structure
there may be controlled succession of blasts which brings it down in stages.
Demolition ball
This method employs a weight, suspended from a crane and swung against or dropped onto
the structural members. It is highly skilled operation and should only be carried out within
clearly defined limits to avoid overloading or overstressing the crane. Usually the roof is
removed, 50 to 75 percent of floors removed by hand before balling work starts.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 11
Bursting
A cavity is formed in critical members of the building and are forced to enlarge . causing
the members t fracture, leading to a controlled collapse. The force is applied by either a
gas-expansion or hydraulic burster. The gas-expansion burster is made up of a cylinder
filled with gas which, when ignited by electrical charge expands rapidly into the cavity.
Thermal methods
This method combines thermal reaction on structural steel members in conjunction with
wire rope pulling. The beam or stanchion to be severed has a mixture of metal oxide and a
reducing agent applied around critical point. When the mixture is ignited it liberates
enough heat to soften the metal sufficiently to allow the member to be pulled down.
Provision of Hutments
These are usually wooden structures erected on site to provide for a simple temporary
accommodation or for leisure activities and offices etc.
Classification of hutments
1. Mobile
2. Semi-mobile
3. Framed
A CRANE & A DEMOLITION BALL
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 12
4. Sectional
5. Portable framed
6. Air house
Factors to consider when erecting hutments:
1. Duration of contract
2. Availability of space
3. Location of site
4. No of employees
5. Size of contract
These hutments may also be used for storing the materials on site.
Provision of services
The services which may encountered on or around a site are
1. Water
2. Gas
3. Electricity
4. Telephone
5. Sewerage
6. Oil
7. Television
All the services listed are classified into three areas:
1. National
2. Regional
3. Local
The appropriate board must be notified before any connection can be made. The following
information must be communicated to the local authority and permission granted before
work commences.
1. Name and address of the developer
2. Location of the land to be developed
3. Description of the proposed development
4. Previous use of land
5. Whether a new access would be required from the highway
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 13
6. Plan to which the permission refers
7. 1:100 or 1:200 drawing to give a clear picture of the new building or alteration
Storage and protection of materials
The type of storage facilities required of any material depends on the following factors:
1. Durability – whether it needs protection from the elements
2. Vulnerability to damage
3. Vulnerability to theft
Cement
Cement is supplied in bulk, bags or in drums. Bulk cement is delivered to site by tankers
and blown into storage silos by compressed air.
Bagged cement, delivered on a wagon having a tarpaulin cover, should be stored in a close
cabin, the floor of which is at least 150mmabove the ground. The bags should be stored
closely together to prevent the circulation of air.
Aggregates
Aggregate should be stored on a hard, clean free draining surface. They may be stored in
bins or hoppers so that the stockpiles do not mix thus ensuring that different aggregates,
types and sizes are kept separately.
Bricks and Blocks
These may be supplied loose or strapped in unit loads and stored on raised timber pallets.
Facing and coloured bricks should be covered to prevent contamination.
tarpaulin covering
cement storage
weather
boarded shield
without
windows
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 14
Timber and Joinery
These should be stored horizontally and covered and provision made for air circulation.
Timber sizes should be kept separately and raised off the ground to prevent
contamination.
Drainage pipes
Should be supplied loose or strapped on timber pallets. It should be stored horizontally
with the ends reversed in alternate rolls.
Location of plants
Plants must be placed at the most convenient and strategic points so that maximum
benefit could be achieved from their use. Points to consider:
i. Headlights should be set up truly horizontal
ii. They should be securely fixed to a firm and solid base.
iii. Cranes should be positioned so that they are able to reach all materials that need
to be hoisted; e.g. cement, aggregate etc.
iv. Mixers and mortar pans should be specially sited to keep the distance to wheeling
concrete or mortar as short as possible.
v. Batching plants should be set up in a central position on the site to be readily
accessible for Lorries to discharge aggregates etc appropriately.
Factors to be considered when allocating plants on site
1. The availability of space
2. Working room requirements
3. Mobility on site
4. Servicing requirements
Provision for workers welfare and safety on site
It is essential to have the interest of all workers on site and to provide the best facilities
for their upkeep. Advantages from such provisions may include
1. It reduces pilfering
2. It serves as an incentive to the operatives
3. Boost workers morale
4. Increases productivity
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 15
Welfare and safety provisions include:
1. Notices and fees to local authorities – this include fees for water supply, public
services and all other fees which may be demandable by the local authority.
2. Watching and lighting – to provide all requisite day and night watching.
3. Maintenance of public and private roads – there should be no damage to roadways,
footpaths and all other properties.
4. Water for the works – the contractor must supply water for the site and
responsible for the protection of meters and cocks.
5. Lighting and power – artificial lighting and power must be provided on the site for
all personnel, including subcontractors and nominated subcontractors.
Difficulties encountered when working in bad weather
Rain, high winds, low temperatures, poor daylight levels are some of the weather effects
that can seriously affect construction activities.
The worse effects obviously occur when more than one of these occurs simultaneously.
Shelter is required for the men during bad weather and somewhere to deposit the clothes
not worn during working hours.
Lessening of difficulties in hot weather
1. In very hot weather, the freshly laid concrete should be shielded from the direct
sun until seven days to prevent rapid evaporation due to temperature, relative
humidity and wind.
2. Mixing water and the materials must be kept as cool as possible.
3. Aggregate should be protected from the sun and sprayed with water to cool down
immediately.
Lessening of difficulties in cold weather
1. All aggregate should be pre-heated by perforated steam pipes to prevent the
attack of frost.
2. Mixing water must be heated to a temperature not exceeding 80˚C with a water
cement ratio of 0.5.
3. Concrete must be cured for longer periods due to the fact that low temperatures
retard concrete hardening and strength gain.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 16
4. Additional Portland cement, high curing temperatures (steam curing), high early
strength cement and other known methods may be employed to obtain high-early
strength.
Site & Soil Investigation
The basic objective of site investigation is to collect systematically and to record all the
necessary data which will be required in the design of the proposed work and their
construction. Site investigation is thus all embracing, taking into account such factors as
topography, location of existing services, means of access and any local restrictions.
Soil Investigation specifically relates to the subsoil beneath the site under investigation
and could be part of or separate from the site investigation. It is usually a means of
obtaining data regarding properties and characteristics of sub-soils by providing samples
for testing or providing a means of access for visual inspection.
Methods of soil classification
i. Physical properties
ii. Geological origin
iii. Chemical composition
iv. Particle size distribution
Generally soils are defined as coarse - grained or fine – grained each resulting in different
properties.
Coarse – grained soils
These include sands and gravels having a low proportion of voids, negligible cohesion when
dry, high permeability and slight compressibility which takes place almost immediately upon
the application of load.
Fine – grained soils
These include cohesive silts and clays having a high proportion of voids, high cohesion, very
low permeability and high compressibility which takes place slowly over a long period time.
There is however several soils which can be described between these two extremes and
are divided into particle size as follows:
1. Clay particles less than 0.002mm
2. Silt particles between 0.002 and 0.06mm
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 17
3. Sand particles between 0.06 and 2mm
4. Gravel particles between 2 and 60mm
5. Cobbles between 60 and 200mm
Purpose of Soil Investigation
a. Determine the suitability of the site for the proposed project.
b. Determine an adequate and economic foundation design
c. Determine the difficulties, which arise during the construction process and period.
d. Determine the occurrence and or cause of all changes in subsoil conditions.
Factors Affecting Method or Choice of Soil Investigation
a. The size of the contract
b. Type of proposed foundation
c. Type of sample required
d. Type of subsoil to be encountered
Main methods of soil investigation
The methods of soil investigation are
Trial pits – small contracts where foundation depths are not likely to exceed 3.0m
Bore holes- - medium to large contracts with foundations up to 30.0m depth.
Trial Pit
Primarily to obtain subsoil sample for identification, ascertaining the subsoil
characteristics and properties. Trial pits and auger bore holes may also be used to
establish the presence of any geological fault and upper or lower limit of the water table.
Trial pit can also be used to expose and /or locate underground services.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 18
The trial holes are used purposely to:
1. Know the thickness of each layer of the subsoil
2. Know the composition of each stratum
3. Know the size of various particles of which the subsoil is composed in each stratum
4. The condition of each stratum
5. The water table level
6. The quantity of water below ground level
Disadvantages
i. Difficult to operate in high water tables and very loose soils
ii. There is the need to provide for pumps for and timbering to provide dry land
Bore hole
These are carried out using either a hand auger (shallow bore hole) or mechanical auger
(deep bore hole) to determine the suitability of a particular type of soil for a project. A
shell boring tool consist of a cylindrical steel shell which is dropped into the soil causing
soil to be forced into the cylinder either by friction in the case of cohesive soil or
nonreturn
flap in the case of non-cohesive soil.
The diameter of the samples obtained varies from 100mm – 200mm according to the
method employed in extracting the sample. Undisturbed soil samples can be obtained from
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 19
cohesive soils 450mm long x 100mm diameter sampling tubes which are driven into the soil
to collect the sample within itself, upon removal the tube is capped, labeled and sent to
laboratory for testing.
Purpose of Auger Hole
Primarily to obtain subsoil structure for identification, classification and ascertaining the
subsoil characteristics and properties.
Could be used if required to obtain subsoil samples at a depth beyond the economic limit of
trial hole.
Advantages
i. Generally cheaper
ii. Simpler than trial hole
Setting out
This is the process whereby the outline of the building on plan is transferred to the
ground for excavation works to be done. Setting out should be carried out by competent
persons and check by different persons with different methods.
The setting out of the building can be divided into two distinct operations:
Establishing the position of the building and setting up the profile.
Sand or
gravel
auger
clay
auger
hand
augers
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 20
Establishing a datum peg and the transferring the required levels to various
positions.
Equipment For setting out
i. Steel tape
ii. Builders’ square
iii. Crosscut saw & nails
iv. Pegs
v. Plumb bob/spirit level
vi. Site square
vii. Line
Datum establishment
The datum (TBM) is a basic level established on the site from which all measurements
and/or levels for the building to be erected on the site can be taken. The level of the TBM
is usually set to that of the ground floor level which is fixed in relation to other known
levels in the vicinity, preferably an (OBM). A peg is driven down until the top reaches the
desired height and other levels are transferred from it. One method of transferring this
is by using a long leveling board and a spirit level.
site datum or
temporary bench mark
hardwood peg(top level
equals ground level).
concrete
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 21
Transferring levels
The level of the site datum can be transferred to other parts of the site in several ways.
One method is using the straight edge and the spirit level. The straight edge and the
spirit level must be reversed in the next move to cancel out minor errors that may occur.
Requirements of setting out:
1. Should be in the correct position
2. Be at the correct level
3. Be erected vertically
ground line
3.0m straigt edge
straight edge& spirit
level reversed
datum peg
peg
transferring levels-straight edge spirit level method
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 22
Sequence of operation
Note: all setting out is done from a building line.
1. Drive in pegs on the side boundary at the correct distance from and parallel to the
centre line of the road
2. Strain a line between two nails placed at the centre of the pegs
3. Drive two pegs C and D along the building line to indicate the front corners of the
building.
4. Set out lines at right angles to peg C and D and establish pegs E and F. Drive nails
at the centres of the pegs and stretch lines between the four pegs.
5. Measure along lines CE and DF to establish pegs G and H in the far corners of the
building.
6. Check diagonals CH and DG
Note:
Base line is the line on which the building commences
Building line is the an imaginary line drawn from the centre of the road to the base
line
trench
width
wall
width
saw kerf
arrangement for
a corner profile
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 23
Frontage line is the line in front of which no other development is permitted by the
local authority (and can be the building line or the base line).
Setting out Curves
To set out circular shape the easiest method is to determine the centre or striking point
of the curve. Then a trammel or measuring tape is used to mark out the curve by securing
the trammel at the centre point and swinging around in an arc.
Using template
1. This method is applicable if the radius of the curve is short.
2. Mark out the chord AB and rise CD
3. Fix nails at points A B and C.
4. Nail battens together so that the first batten touches points A and C and the
second points B and C
5. Nail the spreader across the two battens
6. Draw the curve by moving the frame so that it keeps in contact with points A and B
with a pencil at the intersection.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 24
Setting out right angles
3:4:5 method
1. Mark out a triangle of sides 3:4:5
2. Measure three and four units respectively on the front and side lines
3. Position the side lines so that the distance between the two marked points is five
units.
Builders’ square
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 25
1. Using a large builders’ square set it up on pickings so that one leg is against the
building line.
2. Position the side line so that it runs parallel to the other leg of the square.
3. Read off the right angle at the corner.
3:4:5 method
builders’ square method
Using the site square
1. Set out the base or building line with pegs at the required distance
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 26
2. Set the site square at the head of nail at the peg marking the corner to be set out
3. Sight onto the nail in the next peg along the base line and obtain the dead on
position
4. Measure the required distance approximately at right angles to the peg from the
peg from which the instrument is set up. Signalthe assistant to move pe sideways
until it is on spot.
5. Place a nail at the top of the peg ensuring that the nail is at the centre and that
the distance is the exact required.
6. Repeat the operations on all pegs to set out the corners of the structure.
Setting out acute angles
To setout 45˚
1. Set out right anles using any known methods
2. Measure equal lenths from the vertex topoints B and C
3. Measure carefully halfway the length BC
4. Pull a line from A through the mid point of BC and this forms 45˚ to either of the
lines forming the right angles.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 27
To setout 60˚
Measure any convenient distance between points A and B
Hammer in pegs at these points
A third point C is driven in from both points A and B
Pull lines from peg A through peg B and from peg A through peg C
The two lines will form 60˚
When this angle is halved 30˚, 15˚ and 7.5˚ can be set out
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 28
Timbering to trenches
Timbering is the method used to support the ground when excavating is done.
Factors to consider when timbering
1. The nature of the soil
2. The pressure to be supported
3. The depth of cutting
4. The water table level
Purpose of timbering
To prevent the sides of the trench from collapsing
To safeguard the operatives working in the trench
To save excessive excavation as in battered trenches
Causes of collapse of timbering
1. Variation of the bearing pressure
2. Changes of angle of repose due to moisture content differences
3. Failure due to heavy loads placed near the edges of the trench
4. Overloading timbering members
Methods of support
1. Timbering
2. Sheet piling
3. Battering
4. Cofferdams
5. Retaining walls
6. Caisson
Safety requirements
1. Must be inspected by competent persons
2. Timbering must be done as the work proceeds
3. Suitable barriers should be provided
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 29
STAIRS
A stair is a series of steps leading from floor to floor, floor to landing or landing to
landing.
A stair case or stair way is the complete system of treads, risers, strings, balustrades,
and other component parts in one or more successive flights of stairs.
The space occupied by a staircase is called a stairwell. The vertical distance between the
floors served by a staircase described as the lift.
Function
The primary functions of any stairway are:
1. To provide the movement of people and goods from one floor level to another
2. To provide a suitable means of escape in case of fire
Types of stairs
i. Straight flight
ii. Dogleg or half space landing
iii. Open well
iv. Geometrical
v. Spiral
vi. Helical
Straight flight
This the simplest form of stair and consists of a straight continuous flight or run of
parallel steps.
Dogleg
A dogleg or half turn stair has one flight rising to an intermediate half-space landing, with
the second flight travelling in the opposite direction to the first.
Open-well or Open newel
This stair contains a central well with newels at each change of direction and two or more
flights of steps around the outside of the well.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 30
Geometrical stair
This is a stair which takes the form of a spiral with the face of the steps radiating from
the centre of a circle which forms the plan of the outer string and incorporates an open
well.
Spiral stair
This is a form of geometrical stair without a well.
Helical stair
This is a stair which contains a helix round a central void.
Regulations and Requirements
1. The pitch of a private stairway must not be more than 42˚.
2. The pitch of a common stairway must not be more than 38˚.
3. The rise per step of a common stairway must not be more than 190mm.
4. Maximum rise per step should be 220mm.
5. Minimum going should not be less than 225mm.
6. Twice the rise plus the going shall not be less than 550mm and not more than
700mm. (2R + G = 550 -700mm).
7. The minimum headroom shall not be less than 2m, measured vertically the pitch line.
8. The nosing of any tread in an open riser stair shall overlap the back edge of the
tread below not less than 16mm.
9. Stairs with open risers shall be constructed such that the spaces between the open
risers do not permit the passage of a 100mm sphere.
10. A stairway should not have more than 16 risers in a flight.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 31
quarter - space landing
open newel stair
dog-leg stair
landing between two straight
flights (fly landing)
Straight flight Dog-leg Open Well Geometrical
sectional elevation
Pre- Cast Concrete Spandrel Stair
(triangular section)
Geometrical
Up
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 32
Terms
1) Tread 2)Riser 3) Nosing 4)Going 5)Rise 6)Margin
7) Closed String 8) Cut (open string) 9) Newel 10) Bearer
11) Brackets 12) Trimmer 13) Blocks 14) Handrail 15) Baluster 16) Wedges
Spiral (helical) Stair
Plan
REGULATIONS FOR COMMON STAIRWAY
going not less than 225mm
rise not less than 190mm
38°
Pitch Line
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 33
420
REGULATIONS FOR PRIVATE STAIRWAY
going not less than 212mm
rise not less than 200mm
Pitch Line
Glue Block
16mm Riser
HousedScotia
METHOD OF FORMING STEPS
22mm Tread
9mm plywood
Riser
Glue Block
HOUSED RISER
Newel Fixing
galvanised
steel dowel
grouted into
concrete floor
Newel
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 34
Guarding of stairway
Setting out the stairs
Assume a lift or total rise of 2400mm
Assume a travel or total going of 2925mm
Assume 14 risers
Thus number of treads = 14 - 1 = 13
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 35
Thus: rise = lift/ total rise = 2.400 = 172mm
Number of risers 14
Going = travel/total going 2.950 = 225mm
Number of treads 13
Check: 2R + G = 550 - 700mm; 2(172) + 225 = 344 + 225 = 569mm, thus the stair is
satisfactory.
Factors affecting the design of stairs
1. Purpose or use of the stair
2. Size and shape of the stairwell
3. Economic factors (type of construction, cost, material type etc.)
4. Total height of the building
Defect in stairs
1. Poor fixing of newels and top nosings
2. Flights not rigidly fixed
3. Handrails not sanded smooth
4. Creaking of stairs resulting from poor securing of treads and risers
Unprotected stairs, damage after installation and loosened items such as Disadvantages
of timber stair
1. The main disadvantage is that it will help to spread fire in case of an outbreak.
2. Few timbers are resistant to decay or insect attack, thus for a prolonged life span,
the timber should be preserved which may automatically increase the cost f
construction.
3. Difficulty in the selection of good quality timber
Advantages of concrete stair
1. Non combustible
2. Strong as compared to timber
3. Hard wearing
4. Obtained in in-situ or pre-cast for ready installation.
Disadvantages of tapered steps
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 36
1. Hazard to the aged and the very young, due to the very small tread length at or
near the newel post.
2. Difficult to carpet
3. Difficult to negotiate with furniture
4. Have little or no aesthetic appeal
5. Expensive to construct
Pre-cast concrete stair construction
Basically there are two methods of fixing stairs into walls:
i. as the work proceeds
ii. after the work has been completed
Fixing after completion of the wall
1. Set out the position of the stairway as the wall proceeds to ensure the correct
placement of the sand courses.
2. Remove the sand courses, brush out the indents and dampen the wall
3. Use a height rod to set out position of stair between two floors this should have
the number of steps required marked on it
4. Measure the total going of the steps and divide into the number of steps
5. Use riser and tread gauges to allow for ease of checking
6. Bed the first step in a cement sand mortar (1:2) across the width of the stair, level
in both directions, check for height and build into the wall
7. Wedge the steps at both ends and level the treads
8. Lay a straight edge against the nosings of the stair to check for accuracy
9. Use a line to check the alignment of the steps at their free ends
Fixing the steps as the work proceeds
1. Set out the position of the stairway as the wall proceeds ( no provision of sand
courses)
2. Use a height rod to set out position of stair between two floors this should have
the number of steps required marked on it
3. Measure the total going of the steps and divide into the number of steps
4. Use riser and tread gauges to allow for ease of checking
5. Bed the first step in a cement sand mortar across the width of the stair, level in
both directions, check for height
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 37
6. Lay a straight edge against the nosings of the stair to check for accuracy
7. Use a line to check the alignment of the steps at their free ends
8. If the steps are cantilevered a temporary support must be provided
not less than 16mm
Square for determining
position of the step ( gauge)
OPEN RISER STAIR WAY
upper part of step
reinforced
Methods of checking the accuracy of the position of the steps
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 38
waist
cut string
treads fixed
to string
open riser stair
Newel
Handrail
String
Fitting Handrail & string
to newel in timber stair
Metal Bracket to wall
Handrail screwed through
bracket to plug
Handrail plugged screwed
Fixing handrails
molten lead caulked into
mortice around standard
End of handrail
flattened and bolted to
side of concrete stair
Metal standard of
balustrade
cement pointing
standard ragged with
saw cuts
nut & washer
nut & washer
baluster bolted tread or
landing
fixng metal standard to
concrete steps
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 39
tension lap
starter bars
distribution bars
main bars
stair waist
distribution bars
In-situ reinforced concrete stair details
Straight egde to
check nosing
cleat
strut
joist
sole plate
wedges
cleat
margin piece
soffit board
strut
props
cleat
struts
outer cut string
to both edges
bracing
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 40
wedges
string
scotia mould
nosing
blocks
riser
tread
line of nosing
section through a string
handrail
top rail grooved
into handrail
plywood panels
bottom rail
capping
string
panelled balustrade
B
B
A
A
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 41
DOORS
A door is a solid barrier fixed in a doorway or opening in a wall or partition to hinge, pivot
or slide open to close for access to and from buildings and between rooms, compartment,
corridors, landings and stairs.
A door is classified by the way it is positioned in a building, by their function or their
method of construction. The recommended size of a door opening is 900mm x 2100mm.
this gives a door size of 800 x 2000in both width and height.
Functional Requirements
The primary function of a door is the means of access. The functional requirements of a
door when closed are
a. Privacy
b. Strength
c. Stability
d. Weather resistance
e. Durability or freedom from maintenance
f. Fire security
g. Resistance to the passage of heat
h. Resistance to the passage of sound
i. Exclusion of wind and rain (external door)
Selection of Doors
The factors affecting the choice of doors are:
a. Position in the building
b. The order of priority
c. Appearance
The order of priority of the performance requirements of a door are:
i. Weather exclusion
ii. Security
iii. Fire
iv. Thermal/sound insulation
v. Privacy
vi. Durability
vii. Method of operation
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 42
The appearance of a domestic bathroom door is of little importance, whereas the doors to
the office of a Managing Director should create a suitable impression on those entering.
External doors
These are used to close the access to the internal of a building and provide a means of
security. They are thicker and more robust in design than internal doors.
Internal doors
These are used to close through internal walls within the building, partitions etc. they are
made thinner than their external counterparts since weather protection is no longer a
requirement.
Classification (types)
Battened doors –(match boarded doors) - ledge and batten doors, ledge, brace and batten
doors and frame ledge brace and batten doors.
1. Panel doors
2. Glazed doors
3. Flush doors
4. Purpose made doors
Ledge and batten doors
The face of the door is made from tongue and groove boarding which has edge chamfers
to one or both faces, forming a vee joint between consecutive boards. Normally three
horizontal members called ledges, clamp the boards together making it a non standard
form of a door. It is cheap to construct but has a disadvantage of dropping at the closing
edge, thus pulling the door out of square. its use is limited to buildings such as sheds,
outhouses, and small units like trap doors.
Ledge brace and batten doors
This is a standard battened door in which braces are incorporated to resist the tendency
of the door to drop out of square. The braces are fixed between the ledges so that they
are parallel to one another and slope toward the hanging edge.
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 43
Frame ledge brace and batten doors
Another standard door in which mortise and tenon frame surrounds the match boarded
panel, giving the door added rigidity. When the doors are wider, the braces become too low
to be of value as an effective restraint and it must therefore be framed as a diagonal
between the top and bottom rails.
Treatment to doors in transit
A door irrespective of the soundness of its construction will deteriorate if improperly
treated during transportation, storage and after hanging.
framed ledged
brace & batten door
ledged brace &
batten door
ledged &
batten door
ledge
match board
top rail
brace
stile
bottom rail
middle rail
hanging edge
1,2,3,or 4 panelled doors
top rail
plywood or glazed
panel
stile
bottom rail
middle rail
skeleton
framing
lightweight
core filling
plywood facing
edge lipping
flush door
Construction Practice for Technician & Diploma Students -Volume One
ANSAH NANA BENYI CIVIL ENGINEERING TECHNOLOGY Page 44
Treatment
1. It should receive wood priming coat of paint before or immediately after delivery,
2. It should be stored in the dry and flat position so that it does not twist before and
immediately after delivery
3. It should also receive finishing coat of paint as soon as practicable after hanging
4. Finished doors should be wrapped in building paper or polythene sheet to prevent
damage to the finished door
purpose made doors
top rail
plywood or glazed
panel
stile
bottom rail
middle rail
purpose made doors
top rail
stile
bottom rail
intermediate rail
frieze rail
solid raised panel

You might also like