Functional testing of a hot water boiler in the commissioning process can be streamlined if
coordinated properly. Much of the Functional Testing Procedure can be accomplished by
coordinating with the start up technician or engineer and the test and balance crew. During start
up the boiler start-up technician should test and verify the proper function of the boiler per
manufacturers specifications. During and after the start up the technician should generate a
report of all start-up work done including adjustments, calibrations, and test data collected
during the start up. The Cx Technician or Engineer can then verify first-hand essential data
needed to complete the Functional Testing Procedure document. The same applies by
coordinating with the Test and Balance crew.
Equipment is clean and free of any physical damage including any debris inside of any control
panels.
All safety devices, including the pressure relief valve, have been tested and tagged according to
local code and national requirements.
All unit identification tags, piping labels, operating manuals, maintenance checklist, and basic
documentation are with the boiler(s).
All pipes have been flushed and strainers cleaned.
Piping insulation is complete (especially for outside piping).
All electrical connections are tight including all ground connections.
All breakers for the boiler system including associated pumps are labeled properly for the
source.
Boiler drain is accessible and can be drained to a sanitary drain near the boiler drain.