EI6602 Process Control
EI6602 Process Control
DEPARTMENT OF
ELECTRONICS AND INSTRUMENTATION ENGINEERING
QUESTION BANK
VI SEMESTER
EI6602–Process Control
Regulation – 2013
Prepared by
QUESTION BANK
SUBJECT :EI6602 –PROCESS CONTROL
SEM / YEAR : VI Semester / III Year EIE
2. Derive the transfer functions H2(s)/Q(s) and H3(s)/Q(s) for the three- BTL 1 Remember
tank system shown below, where H2, H3 and Q are deviation
variables. Tank 1 and Tank 2 are interacting. (13)
3. Derive the mathematical model for the given process C1, C2 BTL 1 Remember
capacitances of the tank I and tank II respectively, h1, h2 and A1, A2
heights of liquid level and areas of the tanks tank I and tank II
respectively, q1, q2 inflow and outflow of tank I and q3 is the outflow
of tank II. (13)
4. Evaluate the material balance equation for the two tank hybrid system BTL 5 Evaluate
shown below and determines the transfer functions h1(s) / F1(s) and
h2(s) / F2(s) (13)
5. Differentiate the following with the help of suitable examples: BTL 2 Understand
(i) Servo and Regulatory operations. (7)
(ii) Interacting and Non-interacting processes. (6)
6. Obtain the mathematical model of a process comprising two non- BTL 3 Apply
interacting tanks. Assume that the area of cross section of tank 1 is
A1 ft2 and tank 2 is A2 ft2. The inlet flow to tank 1 and tank 2 is F1
and F2 ft3/min respectively and outflow of tank 2 is F3 ft3/min. The
level of liquid in tank 1 and tank 2 are h1 and h2 respectively. (13)
7. (i) Obtain the mathematical model of first order thermal process. BTL 3 Apply
(7)
(ii) For the above thermal process, identify the process variables,
BTL 1 Remember
including the disturbance variable and obtain the degrees of
freedom of the process. (6)
8. (i) Distinguish between the continuous and batch process with the BTL 2 Understand
help of neat diagram. (7)
(ii) Give the merits and demerits of the continuous and batch process.
(6)
9. (i) Describe with neat diagrams the CSTR and its characteristics in BTL 1 Remember
detail. (7)
(ii) Discuss the instrumentation and controls in CSTR. (6) BTL 2 Understand
10. (i) Explain heat exchanger with a neat sketch. (7) BTL 4 Analyze
(ii) Explain the instrumentation and controls in Heat Exchanger. (6)
11. (i) Discuss the need for mathematical modeling. (6) BTL 2 Understand
(ii) Obtain the mathematical model of a first order pneumatic BTL 3 Apply
process. (7)
12. (i) What is inverse response? Explain the inverse response noticed BTL 4 Analyze
in level control of feed water in boiler. (6)
(ii) Explain the self-regulation process with an example. (7)
13. Develop a mathematical model for the system shown in figure. BTL 6 Create
Assume that the effluent stream from a tank is proportional to the
hydrostatic liquid pressure that causes the flow of liquid. Cross-
sectional area of tank 1 is A1 (ft2) and of tank 2 is A2(ft2). The flow
rates F1, F2, F3are in ft2/min. take necessary assumptions. (13)
14. Explain any one method for linearization of non-linear system with BTL 4 Analyze
example. (13)
PART – C
1. A temperature having a time constant of 0.5 min is placed in a BTL 5 Evaluate
temperature bath and after thermometer is placed in the temperature
bath the temperature comes to equilibrium the temperature of the bath
Ti increased linearly at the rate of 10 C/ min. what is the difference
between the indicated and bath temperature. (15)
(a) 0.25 min after the changes in temperature begins
(b) 3 min after the changes in temperature begins
2. Develop a jacketed coolers as a multi capacity process with BTL 6 Create
appropriate block diagram. (15)
3. Develop a continuous stirred tank reactor with cooling socket and BTL 6 Create
explain the operation. (15)
4. Explain storage-vessel control of continuous process. (15) BTL 5 Evaluate
UNIT II - CONTROL ACTIONS
Characteristic of on-off, proportional, single speed floating, integral and derivative controllers – P+I,P+D
and P+I+D control modes – Electronic PID controller – Auto/manual transfer - Reset windup – Practical
forms of PID Controller.
PART – A
11. Describe the electronic circuit for realizing the P, PD, PID controller BTL 1 Remember
modes. (13)
12. (i) Design an electronic PI controller with PB=50% and Ti=0.5min. BTL 6 Create
(7)
(ii) Discuss the reset windup problem and explain any one scheme
BTL 2 Understand
to avoid the same. (6)
13. (i) Design an electronic PI controller with PB = 50% and Ti = BTL 6 Create
0.5min. (7)
(ii) Describe electronic controller to realize Proportional and Integral BTL 2 Understand
control actions with neat sketch. (6)
14. Compare the practical forms of P, I and D controllers available BTL 3 Apply
commercially. (13)
PART – C
1. Develop a pneumatic PI controller and explain its functions. (15) BTL 6 Create
2. Explain the representation of feedback controller for various BTL 5 Evaluate
processes. (15)
3. Develop an electronic PI controller with proportional gain = 10 and BTL 6 Create
integral gain = 0.1 s-1 (15)
4. Explain the basic hardware components of process control system. BTL 5 Evaluate
(15)
UNIT III - FINAL CONTROL ELEMENTS
I/P converter - Pneumatic and electric actuators – Valve Positioner – Control Valves – Characteristicof
Control Valves:- Inherent and Installed characteristics – Modeling of pneumatic control valve –
Valvebody:-Commercial valve bodies – Control valve sizing – Cavitation and flashing – Selection criteria.
PART – A
12. (i) Explain the model reference adaptive control with neat sketch.(7) BTL 4 Analyze
(ii) Order the hierarchal level of control in detail with their functions
and interfaces. (6)
13. Draw and discuss the P&ID diagram of the following: BTL 2 Understand
(i) Boiler. (7)
(ii) Distillation column. (6)
14. Describe the functions of IMC with block diagram. (13) BTL 1 Remember
PART – C
1. Explain relative gain array and the methodology to find relative gain BTL 5 Evaluate
array. (15)
2. Design a cascade control system for a distillation column and furnace BTL 6 Create
process. (15)
3. Explain self-tuning regulator and develop a rolling mill system with a BTL 5 Evaluate
self-tuning regulator. (15)
4. Design a temperature control model for batch reactor process. (15) BTL 6 Create