100% found this document useful (1 vote)
175 views

Yolanda Alaniz Lab Week 7

The document provides processing times, due dates and other information for 5 jobs (A, B, C, D, E). It evaluates 4 sequencing methods: First Come First Serve (FCF), Shortest Processing Time (SPT), Earliest Due Date (EDD) and Critical Ratio (CR) based on average flow time, tardiness and number of jobs in the system. EDD results in the lowest average tardiness of 4.6 hours and average of 2.88 jobs in the system, making it the best sequencing method based on the criteria provided.

Uploaded by

ashibhallau
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
175 views

Yolanda Alaniz Lab Week 7

The document provides processing times, due dates and other information for 5 jobs (A, B, C, D, E). It evaluates 4 sequencing methods: First Come First Serve (FCF), Shortest Processing Time (SPT), Earliest Due Date (EDD) and Critical Ratio (CR) based on average flow time, tardiness and number of jobs in the system. EDD results in the lowest average tardiness of 4.6 hours and average of 2.88 jobs in the system, making it the best sequencing method based on the criteria provided.

Uploaded by

ashibhallau
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 14

Determine the number of cycles per day and the production quantity pe

4 cycle for this set of vehicles: Use the sequence A-B-C-D.

Answer: Product Daily Quantity Daily unit per cycle Units short (3 cylces)
A 21 21/3= 7 0
B 12 12/3=4 0
C 3 3/3=1 0
D 15 15/3= 3 0

Cycle 1 2 3
Pattern CBDA ABCD ADBA
Extra unit(s)
uction quantity per
ce A-B-C-D.
Determine the number of cycles per day and a production quantity per
6 fairly level production:

Answer: Product
F
G
H
K

Assume the production sequence will be F-G-H-K.


Answer:
Cycle 1 2 3 4 5
Pattern F(2)-G-H-K F(2)-G(2)-H-K F(2)-G(2)-H-K F(2)-G(2)-H-K F-G-H-K(2)
Extra unit(s) F FG FG FG K
nd a production quantity per cycle for this set of products that achieves
fairly level production:

Daily Quantity Daily unit per cycle Units short (5 cycles)


9 9/5=1 4
8 8/5=1 3
5 5/5=1 0
6 6/5=1 1
3 Assign trucks to delivery routes so that total costs are minimized, given the cost data shown. What is the tot

Row
Truck A B C D E minimun
1 4 5 9 8 7 4
2 6 4 8 3 5 3
3 7 3 10 4 6 3
4 5 2 5 5 8 2
5 6 5 3 4 9 3

Subtract
Substract row column
minimun Truck A B C D E minimun
1 0 1 5 4 3
2 3 1 5 0 2
3 4 0 7 1 3
4 3 0 3 3 6
5 3 2 0 1 6
Colum minimun 0 0 0 0 2

Answer :my minimun cost= 4+3+6+2+3= $18.00


cost data shown. What is the total cost?

Truck A B C D E
1 0 1 5 4 1
2 3 1 5 0 0
3 4 0 7 1 1
4 3 0 3 3 4
5 3 2 0 1 4 small uncovered

Truck A B C D E

1 0 2 5 3 0
2 4 2 6 0 0
3 4 0 7 0 0
4 3 0 3 2 3
5 3 3 0 0 3
Using the information presented in the following table, identify the processing sequence that would result u
job tardiness, and (3) average number of jobs in the system. Jobs are listed in order of arrival. (Hint: First dete
7 setup time. All times an

Operation time Flow Hours


FCFS Job hrs time Due Date Tardy
a 7 7 4 3
b 4 11 10 1
c 2 13 12 1
d 11 24 20 4
e 8 32 15 17
Total = 5 jobs 32 hours 87 26

Operation time Flow Hours


SPT Job hrs time Due Date Tardy
c 2 2 12 _
b 4 6 10 _
a 7 13 4 9
e 8 21 15 6
d 11 32 20 12
Total= 5 jobs 32 hours 74 27

Operation time Flow Hours


EDD Job hrs time Due Date Tardy
a 7 7 4 3
b 4 11 10 1
c 2 13 12 1
e 8 21 15 6
d 11 32 20 12
Total= 5 jobs 32 hours 84 23

Operation time Flow Due Date Hours


CR Job hrs time Hours Tardy
a 7 7 4 3
b 4 11 10 1
c 2 13 12 1
d 11 24 20 4
e 8 32 15 17
Total = 5 jobs 32 hours 87 26

Operation time Flow Due Date Hours


CR Job hrs time Hours Tardy
a 7 7 4 3
e 8 15 15 0
c 2 17 12 5
b 4 21 10 11
d 11 32 20 12
Total = 5 jobs 32 hours 92 31

4) EDD
Sequence= a-e-c-b-d
Average flow time= 92/5= 18.4
Average job tardiness=31/5= 6.2
Average jobs in the system=92/32= 2.88
entify the processing sequence that would result using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, determine (1) average job fl
. Jobs are listed in order of arrival. (Hint: First determine the total job time for each job by computing the total processing time for the job a
setup time. All times and due dates are in hours.)

Operation time

A=45*.14+.7=7hrs
B=14*.25+.5=4hrs
C=18*.10+.2=2hrs
D=40*.25+1=11hrs
E=75*.10+.5=8hrs

1) FCFS
Sequence= a-b-c-d-e
Average flow time= 87/5= 17.4
Average job tardiness=26/5= 5.2
Average jobs in the system=87/32= 2.72

2) SPT
Sequence= c-b-a-e-d
Average flow time= 74/5= 14.8
Average job tardiness=27/5= 5.40
Average jobs in the system=74/32= 2.31

3) EDD
Sequence= a-b-c-e-d
Average flow time= 84/5= 16.8
Average job tardiness=23/5= 4.6
Average jobs in the system=84/32= 2.63

Critical Ratio Critical Ratio Critical Ratio


Calculations Calculations Calculations
4-0/7=.57 lowest completed a completed
10-0/4=2.50 10-4/4=1.5 10-4/4=1.5
12-0/2=6 12-4/2=4 12-4/2=4
20-0/11=1.82 20-4/11=1.45 20-4/11=1.45
15-0/8=1.88 15-4/8=1.38 lowest completed

Critical Ratio Critical Ratio Critical Ratio


Calculations Calculations Calculations
completed a,e completed a,e, c completed a,e, c,b,d
10-19/4=-2.25 10-31/4=-5.25 lowest Completed
12-19/2=-3.5 lowest Completed Completed
20-19/11=0.09 20-31/11=-1 20-41/11=-1.9
completed completed completed

92/5= 18.4
ss=31/5= 6.2
system=92/32= 2.88
od, determine (1) average job flow time, (2) average
tal processing time for the job and then adding in the
8 The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have differen
a. Determine the processing sequence at the first work center using each of these rules: (1) FCFS, (2) S/O.

b. Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average num
Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.
s: (1) FCFS, (2) S/O.

ompletion time, (2) average number of jobs at the work center.


sted in order of arrival.

You might also like