100% found this document useful (1 vote)
375 views

F01T300 Quick Installation Guide

Huawei Outdoor Access Cabinet F01T300 Quick Installation Guide

Uploaded by

MohammadBakir
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
375 views

F01T300 Quick Installation Guide

Huawei Outdoor Access Cabinet F01T300 Quick Installation Guide

Uploaded by

MohammadBakir
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 46

F01T300

Quick Installation Guide

Issue: 01
Date: 2017-04-30

HUAWEI TECHNOLOGIES CO., LTD.


About This Document

Intended Audience
This topic describes how to install the F01T300 cabinet, including installing the cabinet, routing
cables, and powering on the system.
The intended audience is hardware installation engineers.

Symbol Conventions
This following table describes symbols used in this document.

Symbol Description
Indicates an imminently hazardous situation which, if not avoided,
will result in death or serious injury.
Indicates a potentially hazardous situation which, if not avoided,
could result in death or serious injury.

Indicates a potentially hazardous situation which, if not avoided,


may result in minor or moderate injury.
Indicates a potentially hazardous situation which, if not avoided,
could result in equipment damage, data loss, performance
deterioration, or unanticipated results.
NOTICE is used to address practices not related to personal injury.
Calls attention to important information, best practices and tips.
NOTE is used to address information not related to personal injury,
equipment damage, and environment deterioration.

Change History
Changes between document issues are cumulative. Therefore, the latest document issue
contains all updates made in previous issues.
Updates in Issue 01 (2016-04-30)
This is the first release.

i
Content

1 Precautions…..…………………………………………………………………………………………………………...........................1
2 Tools for Installation.………………………………………………………………………….............................…………………..2
3 Outline and Structure……………………………………........………………………….………..........................……………...3
4 Installing the Lifting eyes………………..…….…………………………….………………………...............................……...6
5 Installing the Cabinet on a Concrete Pedestal…………...…………….………………….……………………………...........7
5.1 Construct the Concrete Pedestal.……….…………..………………………………………………………………………………7
5.2 Fastening the Cabinet...……….................…..........…...............................................................................8
6 Installing the Cabinet on an Elevated Platform………………………………………………………………..………………9
6.1 Construct the elevated platform.…………………………………………………………………………………………………9
6.2 Fastening the Cabinet.......…..........…..................................................................................................10
7 Routing Cables………………….…………………………………………………………………….............................…………….11
7.1 Connecting AC Power Cables and PGND Cable-TT mode ...... ……………………....................................11
7.2 Connecting AC Power Cables and PGND Cable-TN-S mode ..... ………………………...............................12
7.3 Connecting the RPS Power Cable(RPS Power Supply)............. ……………………………...........................13
7.4 Diagram of Cable Connections Between the RPS and MDF (RPS Power Supply)……………………………16
7.5 Connecting External Subscriber Cables (DSLAM) ............... …………………..........................................17
7.6 Connecting Optical Cable and Optical Fibers (MA5800-X7-Optical Only) ………………………………………18
7.7 Connecting Optical Cable and Optical Fibers (MA5603T-Optical/Copper Hybrid Configuration) …. 19
7.8 Connecting Optical Cable and Optical Fibers (MA5603T Upstream) ……………………………………………. 20
8 Installing Batteries ……………………………………………………………………………………………..............................21
8.1 Installation Requirements…..……..…………………………………………………………………………………………………21
8.2 Pre-installation Check……….………………………………………………………………………………………………………….22
8.3 Connecting Batteries…..……………………………………………………………………………………………………………….23
8.4 Installing The enhanced anti-theft door of the battery compartment (optional) ……………………25
9 Installing the Electronic Door Lock System.............................…………………..............................………..27
9.1 Appearance and Structure...............................................................................................................27
9.2 Installing the CCU.............................................................................................................................28
9.3 Installing the Door Lock (BOM: 02070080)……….............................................................................30
9.4 Connecting the Power Cable of the CCU(ETP4830 Power System)........................................32
9.5 Connecting the Power Cable of the CCU(ETP4890 Power System).......................................33
9.6 Connecting the Power Cable of the CCU(RPS Power System )..............................................34
9.7 Installing the Anti-Theft Screw…........................................…………...................................................35
9.8 Post-Installation Check…..................................................................................................................36
10 Checking the Cabinet Installation.………………………………….…………………............................………………..37
11 Powering On the Device………………………………………………………….……….............................…………………38
12 Sealing the Cabinet………………………………………………………………….............................……………...……..…41
13 FAQs for Installation.………………………………………………………………............................……….........…………42

iii
1 Precautions

• This document aims to provide simple and distinctive guidelines for hardware installation.
• This document does not describe operations for the pre-delivery installation. Instead, this
document describers only the operations for on-site installation.

Electrostatic Discharge
Before touching the device, or holding the boards and IC chips, wear the ESD gloves or the
ESD wrist strap to prevent the electrostatic discharge of the human body from damaging the
sensitive components. Ensure that the other end of the ESD wrist strap is properly grounded.

ESD gloves ESD wrist strap

Bundling cables
• The distance between cable ties or binding straps inside the cabinet must be within 250 mm.
(For subscriber cable, the distance must be within 200 mm.)
• Use a diagonal pliers to cut off the extra part of the cable tie to the end, and ensure that the
cable tie is neat without sharp edges to prevent hand injury.

Affixing labels / tags


• After routing the cable, attach the label or fasten the tag to the cable 20 mm away from the
connector.
• After the label for the signal cable is attached to the signal cable, the rectangular text area of the
label must face rightwards or downwards.
• After the identification plate for the power cable is attached to the power cable, the text area of
the plate must face rightwards or upwards. Ensure that the side attached with the label faces
outwards.

Using the desiccant


After removing the packing case of the cabinet on the site, take out the desiccant packages
from the corresponding paper bag (Note: Do not tear the own packages of the desiccant). Then,
put the desiccant packages at proper places of the cabinet. After powering on the cabinet, the
desiccant packages must be removed and disposed of as an industrial waste.

Copyright © Huawei Technologies Co., Ltd. 2017.


1 All rights reserved.
2 Tools for Installation
Before you begin, get the following tools ready.

Wire stripper Flathead screwdriver Philips screwdriver Diagonal pliers

Adjustable wrench Socket wrench Tape measure Claw hammer

Percussion drill Impact tool Hydraulic crimper Cable cutter

Network cable
ESD gloves Multimeter ESD wrist strap
crimping pliers

2
3 Outline and Structure

Cabinet appearance Cabinet structure


Unit: mm
Configured With the
MA5603T+ETP4830 power system
Heat exchanger

MA5603T

MDF

ODF(Upstream)
1350
CCU(optional)
TCU
DC PDU
ETP4830
power system

Battery
AC PDU
compartment
450

Configured With the Configured With the


MA5616+ETP4830 power system MA5603T+ETP4890 power system

Heat exchanger Heat exchanger

MA5616
MA5603T

MDF
MDF

ODF(Upstream)
ODF(Upstream)
CCU(optional)
TCU TCU
DC PDU AC PDU
ETP4830 ETP4890
power system power system

Battery
compartment

Battery
compartment
AC PDU

3
3 Outline and Structure

Configured With the Configured With the


MA5616+ETP4890 power system MA5800-X7+ETP4890 power system

Heat exchanger Heat exchanger


MA5800-X7
MA5616

MDF ODF(Downstream)

ODF(Upstream) ODF(Upstream)
TCU TCU
AC PDU AC PDU
ETP4890
Power system ETP4890
Power system
Battery
Battery
compartment
compartment

Configured With the Configured With the


MA5603T+RPR power system MA5616+RPR power system

Heat exchanger
Heat exchanger
MA5603T MA5616

MDF
MDF

ODF(Upstream)
CCU ODF(Upstream)
Fan Control CCU
board
Fan Control
DC PDU board
DC PDU
RPR RPR
RPR MDF RPR MDF

4
3 Outline and Structure
Dimensions of installation interfaces

Unit: mm
Top view 276.3

50 123.3

101
11

63
Cabinet bottom 32
450
119
300 76
45.5
63
45.5

98.5
75

Front door side of the cabinet


75 700
850

Cabinet installation hole 4 x Ø18 Cable hole for user cable and optical fibers
(optical only) 4 x Ø47.8
Cable hole for PGND cable and AC Cable hole for the upstream optical fiber Ø33
power cable Ø33
Cable hole for copper/optical cables
Reserved hole

5
4 Installing the Lifting eyes

The cabinet is configured with lifting eyes. Before installing the cabinet, remove the waterproof
screws and install the lifting eyes properly so as to carry the cabinet.

Waterpro
of screw
Washer

Lifting eye

Washer

After installing the cabinet, remove the lifting


eyes and install the waterproof screws.

6
5 Installing the Cabinet on a Concrete Pedestal
5.1 Construct the Concrete Pedestal

• Face the cabinet front door towards south or north if possible. This ensures that the cabinet receives the
minimum solar radiation.
• It is advisable to deploy bolts on the ground to prevent improper drilling operations from damaging the
installation holes.

Plan space for the cabinet. Constructing the concrete pedestal.

Top view Unit: mm


During the construction, ensure that
the constructed concrete pedestal is
Cabinet horizontal. The horizontal deviation
must be within 4 mm.
Outline of the concrete pedestal
Unit: mm
Installation Concrete
hole position pedestal Cabling aperture
Concrete
pedestal Ground ≥300

≥500

Plan space for the concrete pedestal. Top view


Unit: mm
Cabinet position 950

50 205 45 150

50
115
45

300 230
550

125
50

125 700
Expansion bolt installation
hole 4 x Ø16 Front door side of the cabinet

7
5 Installing the Cabinet on a Concrete Pedestal
5.2 Fastening the Cabinet
Drill holes and install four M12 × 60 expansion bolts. Unit: mm

Expansion bolt
16 Spring washer
90° Flat washer
Expansion tube
52 ~ 60
Guide through
Expansion nut

Carry the cabinet onto the concrete Open and fasten the door, and then use four M12
pedestal. × 60 expansion bolts to fasten the cabinet.
Bearing capacity
<90° of the steel cable >
555 kg
Support
lever Support lever

Cabinet
Concrete pedestal position

Install the Unit: mm


protection fence.

Construct the protection fence after


installing the cabinet.

8
6 Installing the Cabinet on an Elevated Platform
6.1 Construct the elevated platform

When installing the cabinet onto the elevated platform, ensure that the cable inlets are not
blocked by steel channels.

The following construction plan for the elevated platform is only for reference. You can prepare a
plan based on the actual requirements.

Plan space for the cabinet. Top view Unit: mm

Cabinet

Elevated
platform

Construct the elevated platform. Unit: mm

75
Bolt installation
300 hole 4 x Ø16
>75
<25
75
300

>75

9
6 Installing the Cabinet on an Elevated Platform
6.2 Fastening the Cabinet
Carry the cabinet onto the elevated Open and fasten the door, and then fasten the
platform. cabinet on the elevated platform.

Bearing capacity of the


steel cable > 555 kg
<90° Support lever Support lever

Cabinet position

Set Up the Workbench.


Unit: mm

180

1000
1000 1000

10
7 Routing Cables
7.1 Connecting AC Power Cables and PGND Cable-TT mode

This section uses ETP4830 power system as an example. Cable connection for the ETP4890
power system is the same as that for the ETP4830 power system.

• An all-polarity disconnection device is installed on the power supply side of the site. Shut off the
AC input, and attach labels on the switches that will be set during the cabling work.
• Insulate the AC terminals and all unnecessary bare parts.
• Ensure that the cabinet is grounded properly, and the cabinet is safe and reliable; in addition, it
is recommended to install an electrical leakage protective device on the power supply side of
the site to protect personnel against the injury caused by the accidental electric shock on the
device side.
• The cross-sectional area for the core wire of the PGND cable is 25 mm²and the cross-sectional
area for the core wire of the AC power cable must be at least 4 mm².

PGND
cable
Cable hole for PGND cable
and AC power cable AC power
cable

PGND cable
Philips screwdriver

11
7 Routing Cables
7.2 Connecting AC Power Cables and PGND Cable-TN-S mode

• An all-polarity disconnection device is installed on the power supply side of the site. Shut off the
AC input, and attach labels on the switches that will be set during the cabling work.
• Insulate the AC terminals and all unnecessary bare parts.
• Ensure that the cabinet is grounded properly, and the cabinet is safe and reliable; in addition, it
is recommended to install an electrical leakage protective device on the power supply side of
the site to protect personnel against the injury caused by the accidental electric shock on the
device side.
• The cross-sectional area for the core wire of the PGND cable is 25 mm²and the cross-sectional
area for the core wire of the AC power cable must be at least 4 mm².

N
PE cable of
L
the AC
power
cable

PGND
cable
Cable hole for PGND
cable and AC power cable

PGND cable Philips screwdriver

12
7 Routing Cables
7.3 Connecting the RPS Power Cable (RPS Power Supply)

This section uses the MA5603T service subrack as an example. Cable connection for the
MA5616 service subrack is the same as that for the MA5603T service subrack.

• Power off the central office (CO) RPS before connecting the RPS power cable, and power on
the CO RPS after cable connection.
• After the external copper cable is routed from the RPS into the cabinet, connect the ground
cable to the ground bar of the cabinet.
• After wiring, install the protective units and short-circuiting plugs on the exchange-side terminal
blocks for remote power supply (also called protective terminal blocks) and cable-side terminal
blocks for remote power supply (also called multiplexing terminal blocks). Otherwise, the
cabinet cannot be powered on.
• The exchange-side terminal blocks and cable-side terminal blocks described in this section are
specially used for remote power supply.

13
7 Routing Cables
7.3 Connecting the RPS Power Cable (RPS Power Supply)

Loose captive screws to remove the cover. Use jumpers to connect exchange side terminal
blocks and cable side terminal blocks. For
details about the connections, see “Diagram of
Cable Connections Between the RPS and MDF”.

Exchange side Cable side


terminal block terminal block
Lead the RPS power
cable (copper cable) Grounding bar
into the cabinet, connect PGND cable
of the RPS
the PGND cable in the
power cable to the
ground bar in the
cabinet, and the rest of
the wires to the device Exchange side
compartment of the terminal block
cabinet.
Cable side
External copper cable terminal block
of the RPS

14
7 Routing Cables
Use the impact tool to wire the wires from the external copper cable into the cable side terminal
block on the cord patching side according to “Diagram of Cable Connections Between the RPS
and MDF”. (The following figure uses 3- to-1 wire pair connection as an example. )

Exchange side
terminal block
-190 V
+190 V
Cable side
terminal block
Wires of the RPS external copper cable
-190 V

Wires of the RPS external copper cable +190 V

Install short-circuiting plugs on the cable side terminal Place the cover back and fasten
blocks and protective units on the exchange side captive screws.
terminal blocks.

Short-circuit plug Protective unit

15
7 Routing Cables
7.4 Diagram of Cable Connections Between the RPS and MDF
(RPS Power Supply)

16
7 Routing Cables
7.5 Connecting External Subscriber Cables (DSLAM)

• After routing external user cables into the cabinet, reserve an extra length so as to clamp the
cables to the cable side terminal block on the MDF.
• After the every external subscriber cable is routed, ground the metal shielding layer of the
cable.
• When an external splitter board or a VDSL2 board is used, directly clamp the external
subscriber cable to the JPX658-BLK2-E10V cable distribution terminal block.
• When the service is enabled in the future, the protective unit must be installed for the cable side
terminal block correctly.

JPX658-FA8-239X JPX658-BLK2-
cable side terminal E10V
block cable distribution
terminal block

Protective unit

Labeling block

External subscriber cable

Protective unit Grounding bar

Impact tool

17
7 Routing Cables
7.6 Connecting Optical Cable and Optical Fibers (MA5800-X7-
Optical Only)

Do not look into the optical port without eye protection.

• You must use protection pipe to protect core wires of optical cables in the cabinet, and use the
binding strap to bind optical fibers; do not drag or bind the optical fiber too tightly.
• The bending radius of the optical cable core or optical fiber must be 20 times larger than the
diameter of the optical cable core or optical fiber. Generally, the bending radius is larger than or
equal to 40 mm.
• Only the qualified personnel are allowed to splice the optical fiber. Ensure that the optical fiber
is spliced according to the on-site requirements and local practice.

ODF

Protection
pipe
Reinforcing core

Optical cable

18
7 Routing Cables
7.7 Connecting Optical Cable and Optical Fibers
(MA5603T-Optical/Copper Mixed Configuration)

This section uses ETP4830 power system as an example. Cable connection for the ETP4890
power system and RPS power system is the same as that for the ETP4830 power system.

Do not look into the optical port without eye protection.

• You must use protection pipe to protect core wires of optical cables in the cabinet, and use the
binding strap to bind optical fibers; do not drag or bind the optical fiber too tightly.
• The bending radius of the optical cable core or optical fiber must be 20 times larger than the
diameter of the optical cable core or optical fiber. Generally, the bending radius is larger than or
equal to 40 mm.
• Only the qualified personnel are allowed to splice the optical fiber. Ensure that the optical fiber
is spliced according to the on-site requirements and local practice.

Protection
Reinforcing core
pipe

Optical cable

19
7 Routing Cables
7.8 Connecting Optical Cable and Optical Fibers
(MA5603T upstream)

Do not look into the optical port without eye protection.

• You must use protection pipe to protect core wires of optical cables in the cabinet, and use the
binding strap to bind optical fibers; do not drag or bind the optical fiber too tightly.
• The bending radius of the optical cable core or optical fiber must be 20 times larger than the
diameter of the optical cable core or optical fiber. Generally, the bending radius is larger than or
equal to 40 mm.
• Only the qualified personnel are allowed to splice the optical fiber. Ensure that the optical fiber
is spliced according to the on-site requirements and local practice.

Reinforcing
Protection pipe core
Upstream optical port

Optical cable

20
8 Installing Batteries (AC Power Supply)
8.1 Installation Requirements

• Before powering on the cabinet, do not connect the batteries and power module; otherwise, the
batteries will discharge to the power module, affecting the battery service life.
• Record the last charging time (The last time charged at __) and required next charging time
(Refresh Charging No Later than __) marked in the package container to ensure timely
charging. If the batteries are stored overtime without any recharging, the batteries will bulge
and their capacity will decrease, resulting in a shorter service life.
• Unpack the package batteries only after they arrive at the installation site. Install batteries
grouped in the package container. Do not use together batteries of different types,
specifications, capacities, and batches in a group.
• Before powering on the batteries, perform the pre-installation check.

Package container of
the batteries

Install the batteries according to the field installation environment:

• If the cabinet is powered on within the day when it is installed, place the batteries into the
battery compartment and connect them.
• If the cabinet is not powered on within the day when it is installed, store the batteries in an
appropriate environment (battery storage environment: temperature 5°C-45°C and
relative humidity ≤ 90% RH) for proper maintenance and management. Otherwise, the
batteries will have unrecoverable damages. If the cabinet is not planned to be powered on
for a short period
(1-2 months), it is recommended that the batteries be stored in the warehouse for
subsequent maintenance and management.

21
8 Installing Batteries (AC Power Supply)
8.2 Pre-installation Check
Check Item Requirement
Battery outline • No distortion, flaw or disrepair is detected in the appearance
of the battery.
• The terminals are protected properly.
• There is no stain or acid liquid on the surface of the battery .
• The battery terminals are protected against erosion.
Battery structure • The positive and negative leads on the battery are marked to
facilitate connections.
• The polarities, terminals and visual dimensions of batteries
must be consistent with the sample product picture.
• Spare parts, such as bolts, nuts, washers, and connection
cables that are delivered should be consistent with the
delivery list.
Battery storage period If the batteries are stored overtime, make a record and consult
(overtime or not) professional personnel for processing. Perform the following
(The storage period indicates operations by referring to Maintenance Guide of Outdoor
the period since the last Cabinets:
charging.) • If the storage period of the batteries is 8-12 months, recharge
the batteries.
• If the storage period of the batteries is 12-18 months, activate
the batteries.
Battery usability check A battery must be replaced if one of the following situations
occurs:
• The battery has been stored for more than 18 months without
any processing (battery recharging is required when the
storage period of the batteries is 8-12 months, and battery
activation is required when the storage period of the batteries
is 12-18 months).
• The small-current discharge time (when the power module is
connected to the batteries but is not powered on) is over two
months.
• The open circuit voltage is lower than 12 V.
Battery maintenance record The power-on time must be recorded.

22
8 Installing Batteries (AC Power Supply)
8.3 Connecting Batteries

• Follow exactly the installation procedure to install the batteries. Wrap the metal installation
tools, such as wrench, with insulation tape for insulation. Any short circuit may hurt personnel
and damage the equipment.
• Before laying out the battery power cable, ensure that the battery switch is in the OFF state.
• Ensure that the polarity position of each battery is correct. The connection between two
batteries, or the connection between batteries and the power system must be firm and correct.
• If the battery is installed first and battery compartment heater, before the installation, place the
battery right slightly. After the installation, restore the battery space. Ensure that batteries have
about 10 mm space between each other.
• After the batteries are installed, the battery parameters must be configured during software
commissioning. Otherwise, the battery life may be shortened.

• The F01T300 cabinet can be configured with one set of 50 AH or 100AH batteries.
• When the cabinet is configured with the 100 AH battery, the charging coefficient of the battery
must be set to 0.1.

23
8 Installing Batteries (AC Power Supply)
8.3 Connecting Batteries (ETP4830 power supply)

Fasten battery cables with M6 screws


(fastening torque: 48 Kgf·cm).

Blue cable

"LOAD 00" on the DC PDU


Black cable

Connect the four batteries in series according to the wiring diagram. Then, connect the
battery sets to the "LOAD 00" on the DC PDU; Battery monitor alarm cables connect
to the second battery `s “+” of each battery set.

• Before connecting to the DC PDU, ensure that the


MCB of the DC PDU is off.
• The batteries should be connected from the positive
pole to the negative pole in series.
• Before turning on the MCB of the DC PDU, ensure
that all the connections are correct.

24
8 Installing Batteries (AC Power Supply)
8.3 Connecting Batteries (ETP4890 power supply)

Fasten battery cables with M6 screws


(fastening torque: 48 Kgf·cm).

Blue cable

BATT-
BATT+
Black cable

Connect the four batteries in series according to the wiring diagram. Then, connect the
battery sets to the BATT- and BATT+ terminal of the power supply; Battery monitor
alarm cables connect to the second battery `s “+” of each battery set.

• Before connecting to the DC terminal block of the


power supply, ensure that the BATT MCB of the
power supply is off.
• The batteries should be connected from the positive
pole to the negative pole in series.
• Before turning on the BATT MCB of the power
supply, ensure that all the connections are correct.

25
8 Installing Batteries (AC Power Supply)
8.4 Installing The enhanced anti-theft door of the battery
compartment ( optional )

• The enhanced anti-theft door of the battery compartment is optional.


• The supported maximum dimensions (H x W x D) of the lock of the battery enhanced anti-theft
door is 65 mm x 40 mm x 20 mm.

Unit: mm

7
65
30

40 20

During lock installation, do not push the


battery. If any batteries are removed, place
them back after lock installation. Ensure that
batteries have about 10 mm space between
each other.

26
9 Installing the Electronic Door Lock System
9.1 Appearance and Structure
Appearance of the CCU Unit: mm
Main control board

220

43.6

442

Layout of the CCU

CCU

1 3
Extended board Extended board
(optional) (optional)
Main control board
2 4
Extended board Extended board
(optional) (optional)

Components of the SPS system

Item Component
CCU module
Security & protection system (SPS)
Electronic lock

27
9 Installing the Electronic Door Lock System
9.2 Installing the CCU

This section uses the MA5603T service subrack as an example. Electronic door lock system
installation for the MA5616 service subrack and MA5800-X7 service subrack is the same as
that for the MA5603T service subrack.

Install floating nuts on the mounting bars of the cabinet.

Fix the CCU to the mounting bars in the cabinet. Use a Phillips screwdriver to tighten
screws on the CCU.

Configure the MA5603T+ETP4830 power system

CCU

28
9 Installing the Electronic Door Lock System
Connect one end (labeled as MA56T:ETH) of the 2 communication cables to the ETH ports of
the service device.
(Ports with silkscreen ETH are ETH ports. You are advised to connect the 2 cables respectively
to 2 ETH ports with the same silkscreen on the active/standby boards.) Then, connect the other
end (labeled as CCU:FE0/FE1) of the 2 communication cables to the FE0 and FE1 ports of the
CCU.
Electronic door Electronic door
Configured With the MA5603T lock of lock of
the equipment the MDF
compartment compartment

ETH

ETH

D-COM0

FE0

FE1 D-COM1

Electronic door Electronic door


lock of lock of
Configured With the MA56800-X7
the equipment the MDF
compartment compartment

ETH

D-COM0
FE0

FE1 D-COM1
29
9 Installing the Electronic Door Lock System
9.3 Installing the Door Lock (BOM: 02070080)

• Connections between the communication cables of the door locks and the CCU depend on actual
installation conditions. The table of connection mappings in the next slide is for reference only.
• When installing an electric lock on a cabinet, adjust the door handle based on the direction in which the
door is opened so that the door can be easily opened.
• The lock cylinder and lock body of an electronic lock are delivered together. Decide whether to replace
the lock cylinder based on site conditions. If you decide to replace the lock cylinder, refer to to
replace the lock cylinder and keep the mechanical key properly.

When you open or close the cabinet door using the electric lock, the following may occur if the lock handle
lever is not in position (abutting the lock handle), as shown in figure B . In this case, you need to press
the lock handle lever until it is in position and then swipe the access card again, as shown in figure A .
Open the cabinet door.
Wear the ESD wrist strap and connect its Lock handle
grounding end to the ESD jack on the cabinet,
or wear ESD gloves.
Remove the HW-2802 lock from the cabinet. For
details, see Common Maintenance Guide for
Outdoor Cabinets.
Take out the electronic lock and disassemble the
lock to facilitate subsequent installation.
(Optional) Install the restraint part and jumpring.
A B

The restraint part must be correctly assembled so that the


lock handle moves in the same direction (clockwise or
anti-clockwise) as the opening direction of the door.

Assembled and
delivered together
Lock Lock Delivered Left-right Up-down
cover separately
Block

M6 screw

Restraint part
Anti-clockwise
M5 screw Clockwise
Control module

30
9 Installing the Electronic Door Lock System
Remove the lock tongue from the lock rod. Then, install the lock tongue removed in step on the lock rod,
as shown in figure in reverse order.
Clear foreign materials on the position where the new door lock is to be installed, and install the door lock on
the door lock position of the cabinet.
Install the cover on the inner side of the cabinet door, and use a Phillips screwdriver to tighten the 3 screws
clockwise on the cover.
Install the control module removed in step on the lock body.
Use a Phillips screwdriver to tighten the screws that fix the lock tongue.
Connect the communication terminal of the door lock to the communication cable of the CCU. For details on
Connections between the 2 compartment door locks and the CCU, see "Table 1".
Verify that the cable of the electric lock does not interfere with the lock rod when the lock rod moves.
(Optional) Use a Phillips screwdriver to loosen the screws that fix the lock core and take out the lock core.
Then, install the new lock core by following the installation procedure in a reverse order.
Use a box-end anti-theft wrench to clockwise fasten the anti-theft screw on the lock handle.

Lock tongue

Lock core
CCU

Communication cable on Communication cable


the electronic lock side on the CCU side
Table1 Connecting cables
CCU Port Silk Screen CCU Label Connected Component Component Label
D_COM0 CCU:D_COM0 Door of the device compartment Lock1
D_COM1 CCU:D_COM1 Door of the MDF compartment Lock2

31
9 Installing the Electronic Door Lock System
9.4 Connecting the Power Cable of the CCU

• To ensure personnel and equipment safety, before powering on the device, check whether
condensation exists in the cabinet. Power on the device only after you ensure that no
condensation exists. For how to remove condensation, see the related label on the cabinet
front door.
• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (normal DC voltage range: –36 V DC to –72 V DC).

Turn off the SW20 circuit breaker of the DC PDU.


Connect one end of the CCU power cable to the RTN(+)\NEG(-) port on the CCU control board,
and connect the other end to the power system or the output terminals of the DC PDU.

LOAD20-1

Turn on the circuit breaker on the power system that controls the power supply to the CCU.

32
9 Installing the Electronic Door Lock System
9.5 Connecting the Power Cable of the CCU

• To ensure personnel and equipment safety, before powering on the device, check whether
condensation exists in the cabinet. Power on the device only after you ensure that no
condensation exists. For how to remove condensation, see the related label on the cabinet
front door.
• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (normal DC voltage range: –36 V DC to –72 V DC).

Turn off the SW20 circuit breaker of the DC PDU.


Connect one end of the CCU power cable to the RTN(+)\NEG(-) port on the CCU control board,
and the other end is divided into two channels and respectively connect to "LOAD2+" and
"LOAD2-" output terminals.

LOAD20-1

LOAD2- LOAD2+

Turn on the circuit breaker on the power system that controls the power supply to the CCU.

33
9 Installing the Electronic Door Lock System
9.6 Connecting the Power Cable of the CCU

• To ensure personnel and equipment safety, before powering on the device, check whether
condensation exists in the cabinet. Power on the device only after you ensure that no
condensation exists. For how to remove condensation, see the related label on the cabinet
front door.
• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (normal DC voltage range: –36 V DC to –72 V DC).

Turn off the SW20 circuit breaker of the DC PDU.


Connect one end of the CCU power cable to the RTN(+)\NEG(-) port on the CCU control board,
and connect the other end to the power system or the output terminals of the DC PDU.

LOAD20-1

Connect the positive and negative leads of the DC PDU to those of the RPS power system.

Turn on the circuit breaker on the power system that controls the power supply to the CCU.

34
9 Installing the Electronic Door Lock System
9.7 Installing the Anti-Theft Screw

• The anti-theft screw can be replaced only after the electric lock is powered on. Before replacing the
anti-theft screw, use the access card or user identity card to check whether the door can be unlocked.
• The electric lock core and anti-theft screw must be properly installed. Otherwise, the electronic door
cannot protect the cabinet.

• Before completing the site deployment, configure CCU information such as the IP address, mask, NMS,
and authority. In addition, record the name of the site where the cabinet is installed, serial numbers of the
SPS security keys, and serial numbers of the electric lock cores.
• Steps and are recommended steps and you can perform these 2 steps based on the site
requirements.
Deliver the SPS security keys to the Security Department, and deliver the electric lock cores to
each site together with the cabinet based on the allocation rule.
Replace the electric lock cores at a site based on either of the following scenarios.
Scenario 1 If the power supply of the site has been set up and the cabinet can be powered on and
work normally, replace the electric lock cores and anti-theft screws. Then, the customer can open
the cabinet doors using the authorized access card and install and maintain service devices in the
cabinets.
Scenario 2 If the power supply of the site has not been set up and the cabinet cannot be powered
on, hand over the electric lock cores, anti-theft screws, and universal keys to the customer. When
the power supply of the site is available, the customer can assign an engineer to the site to replace
the electric lock cores and anti-theft screws.
Use a box-end anti-theft wrench to anti-clockwise loosen the anti-theft screw on the lock.
Use an authorized access card or a universal key to open the electric lock.
Take out the special anti-theft screw component, and secure it on the lock handle.
Use a box-end anti-theft wrench to anti-clockwise fasten the screw on the anti-theft screw component.
Lock the cabinet door, and verify that the cables of the electric lock do not interfere with the lock
rod when the lock rod moves.

Box-end
anti-theft wrench
Universal key

35
9 Installing the Electronic Door Lock System
9.8 Post-Installation Check

No. Check Content Check Method


1 Boards support easy removal and reinstallation. Check by trial use.

Check the exterior of the CCU. If


2 The exterior of the CCU has no paint peeling. any paint peeling is found, repaint
the CCU to avoid rusting.
The CCU is securely installed in the cabinet and
Check whether the bolts are
3 meets the anti-quake requirements specified in
tightened.
engineering design documents.
The CCU is installed in the left of the cabinet,
4 which meets the requirement specified in Check the installation position.
engineering documents.

5 The ELU port is connected correctly. Check the port connection.

The door locks are correctly installed, and cables Check the door locks and their
6
are correctly connected. connections.
Monitoring cables and AC power cables are not
7 bundled together, and the cables are neatly and Check cable routing.
securely routed.
All power cables must use jointless copper cores
Check all power cables and power
8 and correctly connected according to operation
cable connections.
standards.
All cables are intact without joints between two
9 Check all cables.
ends.
The cabinet interior is clean without foreign
Check the interior of the cabinet and
10 materials, and the air intake/exhaust vent is not
air vents.
blocked.

36
10 Checking the Cabinet Installation
No. Requirement Method
1 The structural parts of the cabinet are installed correctly and Observe and try
properly. The cabinet door is not distorted during the out
transportation. The board can be inserted or removed easily.
Customized parts are installed according to the requirements.
2 There is no paint drop on the surface of the cabinet. Otherwise, Observe
repaint the part where the paint is dropped.
3 The cabinet is fastened reliably and meets the quakeproof Observe
requirement specified in the engineering document.
4 The cabinet installation site meets the requirement specified in the Observe the
engineering document. installation site
5 All cable holes, including those for the power cable, ground cable, Observe
optical cable, and external user cable, are properly sealed.
6 The external positive and negative terminals of the battery are Test with a
correctly and reliably connected to the power system. multimeter
7 The protective cap on the wiring terminal of the battery is intact. Observe

8 All cables are free of damage, fracture, or joint in the middle of the Observe
cable.
9 All power cables and ground cables are made of an entire section Observe
of copper wire. The cables are free of joint in the middle, and are
reliably connected based on requirements.
10 The radiuses of the power cable and the ground cable meet the Observe
requirement specified in the engineering document and the power
distribution requirement of the device.
11 The optical fiber connector and the board optical port to be used Observe
are protected with protective caps. If necessary, clean the
connector and the port in compliance with Huawei regulations.
12 Bury the cable outside the cabinet underground if possible. If the Observe
cable is routed in the aerial mode, take lightning protection
measures.
13 The cabinet is grounded properly and the ground resistance is Measure with
smaller than 10 ohms. the earth
resistance meter

14 An electrical leakage protective device is installed on the power Observe


supply side of the site. If such a device does not exist, it is
recommended to install this device.
15 An all-polarity disconnection device is installed on the power Observe
supply side of the site. If such a device does not exist, it is
recommended to install this device.
16 The inner cabinet is clean and neat, and free of redundant sundries. Observe
Ensure that the air intake vent and air exhaust vent of the device
are not blocked by any object.

37
11 Powering On the Device
11.1 Powering On the Device (AC-powered)

This section uses ETP4830 power system as an example. Check for the ETP4890 power
system is the same as that for the ETP4830 power system.

• The cabinet must be powered on within seven days after installation.


• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (AC ranges: 200 V AC to 240 V AC; DC range: –42 V DC to –58 V DC).
• After installing the cabinet and powering on the device, ensure that the battery switch is in the
ON state. If the device needs to be powered off, you must first turn off the battery switch and
then turn off the AC switch.

AC
PDU

ON

OFF
OFF ON

Green: On for 1s Green: On


and off for 1s
repeatedly

Fan tray
Green: On for 1s
and off for 1s
repeatedly

38
11 Powering On the Device
11.2 Powering On the Device (AC-powered)

• The cabinet must be powered on within seven days after installation.


• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (AC ranges: 200 V AC to 240 V AC; DC range: –42 V DC to –58 V DC).
• After installing the cabinet and powering on the device, ensure that the battery switch is in the
ON state. If the device needs to be powered off, you must first turn off the battery switch and
then turn off the AC switch.

AC
PDU

ON

OFF
OFF ON

Green: On for 1s Green: On


and off for 1s
repeatedly

Fan tray

Green: On for 1s
and off for 1s
repeatedly

39
12 Powering On the Device
11.3 Powering On the Device (AC-powered)

This section uses the MA5603T service subrack as an example. Check for the MA5616
service subrack is the same as that for the MA5603T service subrack.

• The cabinet must be powered on within seven days after installation.


• During the power-on, before and after turning on each circuit breaker for the first time, you
must use a multimeter to check the input and output voltages and ensure that the voltages are
normal (AC ranges: 200 V AC to 240 V AC; DC range: –42 V DC to –58 V DC).
• After installing the cabinet and powering on the device, ensure that the battery switch is in the
ON state. If the device needs to be powered off, you must first turn off the battery switch and
then turn off the AC switch.

OFF
OFF ON

Green: On

Fan tray
Green: On for 1s
and off for 1s
repeatedly

40
12 Sealing the Cabinet

• Covering the sealing material (such as silica gel and grease) onto the inlets at the bottom of
the cabinet.
• After the engineering installation of the cabinet is completed and before the device is powered
on, to avoid the condensation in the cabinet, you must remove the packaging bag from the
desiccant (2 packages) that is attached to the cabinet. Place 1 packages at the bottom of the
device compartment and place the other 1 packages at the bottom of the MDF compartment.
Remove the desiccant packages only when the device is powered on next time.
• After installing the cabinet on a concrete pedestal, use silicon gel to seal the cabinet bottom
properly.
• You must seal the apertures on the bottom of the device compartment. Otherwise, hydrogen
generated in the battery compartment may cause the device compartment to explode.
• You are advised to install an external padlock on the cabinet door to improve the cabinet
security.

Sealing grease

41
13 FAQs for Installation

Cable apertures of the cabinet should The bottom of the cabinet


Keep off electromagnetic
be properly sealed to prevent dust or
interference. should be properly sealed.
insects from entering the cabinet.

After fastening the cabinet, install It is recommended that you install Repaint the place that is collided.
the anti-theft parts and directly use a filler panel in a slot without a
the silica gel or cement to seal the board to ensure a better cooling
anti-theft parts. effect and prevent short circuit.

Each port of the cable side Ensure that parts are not piled Use an ESD bag or board
terminal block should be up on the board. box to store and transport a
installed with a protective unit. board.

When installing and removing a When installing and removing a


Do not remove or install a
board, align the board with the board board, use proper force to avoid any
tracks and prevent the board from board with bare hands. damage to the parts or any scratch
colliding with the other parts. on the PCB.

42
14 FAQs for Installation

43

You might also like