Gantt Chart

This document outlines the planning schedule for an integrated design project from September 2017 through December 2017. It includes 9 main tasks: introduction, define task, conceptual design, embodiment design and analysis, detail design and product simulation, prototyping testing and refinement, sustainability and environmental considerations, economic costing and business plan, and summary. Each task has sub-items with start and end dates assigned to specific team members to be completed over the scheduled months.

Uploaded by

Esabell Olivia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
179 views

Gantt Chart

This document outlines the planning schedule for an integrated design project from September 2017 through December 2017. It includes 9 main tasks: introduction, define task, conceptual design, embodiment design and analysis, detail design and product simulation, prototyping testing and refinement, sustainability and environmental considerations, economic costing and business plan, and summary. Each task has sub-items with start and end dates assigned to specific team members to be completed over the scheduled months.

Uploaded by

Esabell Olivia
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 16

Planning Schedule for I

BDA40804

21-12-2017 Remaining Date (Incl. Fri & Sat.)


ETD

No. Item Sub-item

1 Introduction 1.1 Product Background

1.2 Problem for Existing Product

1.3 Product Significance

1.4 Product Objective

1.5 Project Scope


1.5 Project Scope

1.6 Team Formation

1.7 Design Process

1.8 General Tas Delegation

1.9 Project Planning and Scheduling

2 Define Task 2.1 Related Works/Product-Literature, Patent Search, Ca

2.2 Comparison of Products from Patent Search

2.3 Benchmarking of Product Specification from Comm

2.4 Identification of Market Needs(Market Survey) and

2.5 Clarifying Objectives - Objective Tree

2.6 Weighting of Objective Tree

2.7 Quality Function Deployment (QFD)

2.8 Requirement List (RL)/ Engineering Design Specific


2.8 Requirement List (RL)/ Engineering Design Specific

3 Conceptual Design 3.1 Introduction

3.2 Clarifying Function

3.3 Concept Generation

3.4 Concept Evaluation

4 Embodiment Design and Analysis 4.1 Product Architecture

4.2 Configuration Design

4.3 Parametric Design

5 Detail Design and Product Stimulation5.1 Detail Drawings

5.2 Product Analysis and Simulation by Solidworks Sim

5.3 Bill of Materials (BOM)

5.4 Final Product Design Specification

5.5 Complete Design Checklist


5.5 Complete Design Checklist

6 Prototyping, Testing and Refinement 6.1 Product Prototyping

6.2 Testing Requirement and Checklist

6.3 Testing & Refinement

6.4 Final Prototype Product

7 Sustainability and Environmental Cons

8 Economic, Costing and Business Plan8.1 Introduction

8.2 Cost Evaluation

8.3 Business Plan

9 Summary 9.1 Conclusion

9.2 Recommendations
g Schedule for Integrated Design

Document No.
BDA40804
UTHM/FKMP/WEC
.)

September
Sub-item PIC Start End 1 2
SMTWTFS SM
Patent Search, Catalogue, Commercial Product, Website

t Search

tion from Commercial Product

ket Survey) and Customer Satisfaction- Questionaire;Constru

ree

D)

g Design Specification (EDS)


g Design Specification (EDS)

Solidworks Simulation
Prepared by Checked by

No.
P/WEC Josephine anak Tuan Esther Rami Sikien

Plan Actual
September October November
2 3 4 5 6 7 8 9 10
TWTFS SMTWTFS SMTWTFS SMTWTFS SMTWTFS SMTWTFS SMTWTFS SMTWTFS SMTWTFS
Checked by Revisions
### ###
### ###
### ###
### ###
her Rami Sikien ### ###

DATE: 21 .12.2017

November December
11 12 13 14
SMTWTFS SMTWTFS SMTWTFS SMTWTFS