δωγδγχφ
δωγδγχφ
ËËËËËË
STATUS OF INTERVIEWS:
OPEN FOR RESEARCH
ËËËËËË
Table of Contents
Table of Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xxix
Blasting Work . . . . . . . . . . . . . . . . . . . . . . . . . 28
How Reclamation Passed Information from Shift
to Shift . . . . . . . . . . . . . . . . . . . . . . . . . 30
Getting Around the Damsite . . . . . . . . . . . . . . 30
Inspection Crew at Flaming Gorge . . . . . . . . . 33
“. . . as the work progressed, the size of the
crews would go up to significantly more
than . . . in the early stages. . . .” . . . . . 33
Roscoe Granger . . . . . . . . . . . . . . . . . . . . . . . . 34
“He trusted me, and I got by with some things,
working for Roscoe Granger, that he’d
have fired anybody else on the spot, but I
did what I thought I had to do. . . .” . . 35
The Staff Stationed at Grand Coulee Wasn’t
Thrilled to Have a Big Construction
Project like the Third Powerhouse on the
Doorstep . . . . . . . . . . . . . . . . . . . . . . . 37
Setting up Coordination among the Contractor,
Construction Staff, and Local Operations
Staff at Grand Coulee . . . . . . . . . . . . . 37
“For years and years, the Bureau of Reclamation
had a superior position to the
Department. . . .” . . . . . . . . . . . . . . . . . 39
“I just know that Reclamation occupied the
seventh floor of the Interior Building, and
Interior just did not mess with
Reclamation in those years. . . .” . . . . . 39
Another Coordination Incident During
Relocation of the Switchyard . . . . . . . 39
“And that was the end of the coordinator. . . .”
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
“. . . there was a hell of a friction between the
Ephrata office, who I think had
somebody that they thought should have
Roscoe Granger’s job. . . .” . . . . . . . . . 40
Accident While Dismantling the Old Switchyard
Towers . . . . . . . . . . . . . . . . . . . . . . . . 41
Roscoe Granger Retired from the Grand Coulee
Job . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
“When Ellis Armstrong came in as
Commissioner, he did away with the title
Chief Engineer . . . and there was an
effort to de-emphasize the control . . . of
the Denver Office . . .” . . . . . . . . . . . . 43
“. . . the way the field worked with the Denver
office didn’t change at all. . . .” . . . . . 43
Ted Mermel . . . . . . . . . . . . . . . . . . . . . . . . . . 44
“The nearest thing that I remember about Ted
was his involvement in moving to those
big units at Grand Coulee. I think he had
significant influence . . .” . . . . . . . . . . 45
Oil-filled Transmission Cable at Grand Coulee
Later Replaced . . . . . . . . . . . . . . . . . . 45
Gene Walton Came to Flaming Gorge from
Davis Dam . . . . . . . . . . . . . . . . . . . . . 46
“Gene was, I guess, more of a perfectionist than
most anybody that I’ve worked for, as far
as heavy construction was concerned. . .
.” . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
“Flaming Gorge has a number of, looked like
miniature dams, downstream from the
dam, that were a product of Gene
Walton’s concern about those shale
seams. . . .” . . . . . . . . . . . . . . . . . . . . . 47
“. . . at Flaming Gorge we had a number of
Australian engineers that were assigned
up there, in training. . . .” . . . . . . . . . . 48
“. . . Gene [Walton] came out of that Snowy
Mountain [Project] . . . Then Davis Dam,
then Flaming Gorge. . . .” . . . . . . . . . . 49
Meets Roscoe Granger at Dutch John . . . . . . 50
Russell Borden Was Chief Inspector at Flaming
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
The Third Powerhouse Was Being Contracted at
the Time of Arrival on the Project . . 104
Preliminary Site Clearing Had Begun, but No
Construction Contract Work . . . . . . 104
“We had the switchyards to move– without
taking them out of service . . .” . . . . 104
“Had to remove the end of the dam, and there
was a significant amount of planning that
went into that. . . .” . . . . . . . . . . . . . . 105
Drove a Tunnel Through the Dam to Provide
Cable Access to the New Switchyard
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
Laying Oil-insulated Cable up a Substantial
Change of Elevation to the New
Switchyard Had Not Been Done Before
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
“Again, those kind of things. Designers think
they’ve got it figured out, and you go
build them, and then you modify them if
it doesn’t work. Nothing unusual about
it, as far as I’m concerned. . . .” . . . . 106
Third Powerhouse at Grand Coulee Was a Joint
Venture of Vinnell, Dravo, Lockheed,
and Mannix . . . . . . . . . . . . . . . . . . . . 107
“. . . Vinnell, went through, if I’m not mistaken,
three managers in less than a year . . “
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
“Everything got behind real quick. . . .” . . . . 108
Serious Problems Because of Political
Commitments for Completion of the
Project . . . . . . . . . . . . . . . . . . . . . . . . 109
Cure Notice Sent to Contractor . . . . . . . . . . . 111
Contractor Was Using Two Rather than Three
Shifts . . . . . . . . . . . . . . . . . . . . . . . . . 112
“. . . a good part of them came from the West
Coast. They called a lunch recess at ten
o’clock in the morning, Denver time. . .
.” . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
Sponsorship Shifted from Vinnell to Dravo
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
Decline of the Heavy Construction Industry
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114
Howard Latham Became Reclamation’s Safety
Officer . . . . . . . . . . . . . . . . . . . . . . . . 116
Howard Latham Affected the Construction
Program for the Third Powerhouse . . 116
The specifications required taking down the
concrete in the dam in five foot lifts
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117
“. . . they proposed that we just knock the rock
out from under . . . those blocks, and tip
Government . . . . . . . . . . . . . . . . . . . . 151
Believed the Civil Service Reform Act Opened
the Government to More Politicization
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151
“Carter’s water project “hit list.” The
handwriting was on the wall, as far as I
was concerned. . . .” . . . . . . . . . . . . . 152
NEPA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152
Design of the Third Powerhouse Exterior by
Marcel Breuer . . . . . . . . . . . . . . . . . . 153
A Bald Eagle Nesting Tree Was Affected by
Spoil from the Third Powerhouse . . . 153
Thinking about Leaving Government . . . . . . 154
“I dealt an awful lot with contractual problems,
with contractors, and money problems,
and settling disputes on whatever project
was out there. . . .” . . . . . . . . . . . . . . . 155
“We had a lot of underground construction going
on, and . . . there are always problems
with underground construction. . . .”
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
Contractors Were Losing Money . . . . . . . . . 156
“In my view, it was really a good time for
owners–purchasers of projects. . . .”
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
Third Powerhouse Was One of the Contract
Issues Handled in the Denver Office
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
“I mentioned that Vinnell, Dravo, Lockheed,
Mannix. None of them are in the heavy
construction business anymore. . . .”
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
In Process of Negotiating Claims with M-K
When Teton Dam Failed . . . . . . . . . . 158
At That Time about 90 Percent of Claims Were
Negotiated and 10 Percent Went to
Litigation . . . . . . . . . . . . . . . . . . . . . 158
“Bizz” Johnson . . . . . . . . . . . . . . . . . . . . . . 159
Cecil Andrus and Keith Higginson . . . . . . . 159
After the Failure of Teton Dam, Harold Arthur
Was Busy with Reviews of the Failure,
and Duck Was Doing Other Work of the
Office . . . . . . . . . . . . . . . . . . . . . . . . 159
Harold Arthur Fired after the Failure of Teton
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 160
Bob Jansen Brought in from the California
Department of Water Resources to Run
the Office . . . . . . . . . . . . . . . . . . . . . 160
Review of Internal Procedures at Reclamation
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 160
Decided He Wanted an Internal Review . . . 161
Reclamation’s Study Argued for Centralized
Design and Construction Responsibility
in Denver . . . . . . . . . . . . . . . . . . . . . 162
“It got to be a kind of a tug-of-war between the
regions then and the Denver office . . .”
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162
The Development Part of Reclamation’s
Program Has Ended . . . . . . . . . . . . . 164
Reclamation Has Very Deliberately Killed off
the Planning Process . . . . . . . . . . . . 164
Some Operation and Maintenance Has to Be
Done by Reclamation . . . . . . . . . . . . 164
“My opinion is that the [environmental] zealots
have gotten control of the program, and
the purpose is to make everything so
expensive, or costly, whatever, that you
just don’t build projects, you do studies. .
. .” . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
The Denver Office Before and after the Failure
of Teton Dam . . . . . . . . . . . . . . . . . . 165
Dealing with Auburn Dam and the Oroville
Earthquake . . . . . . . . . . . . . . . . . . . . 166
Yuma Desalting Plant . . . . . . . . . . . . . . . . . . 166
We Contracted for Review of All Major
Contracts under Construction . . . . . . 167
Auburn Dam . . . . . . . . . . . . . . . . . . . . . . . . . 168
Robert Jansen Replaced Harold Arthur . . . . 168
Jansen and Higginson Disagreed over
Implementation of the Internal
Recommendations . . . . . . . . . . . . . . . 169
The Work of the Denver Office Proceeded as
Reorganization Progressed . . . . . . . . 170
Robert Jansen Moved into the Office of Dam
Safety . . . . . . . . . . . . . . . . . . . . . . . . 170
Rod Vissia Brought in to Run Denver Office
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171
Position Abolished So He Could Retire Early
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171
Decentralization of the Contracting Process
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171
“My view was, we couldn’t even keep a fully
competent [procurement] staff in one
location in Denver, and then we were
going to disperse it to seven other . . .
regions . . .” . . . . . . . . . . . . . . . . . . . . 172
Pacheco Tunnel . . . . . . . . . . . . . . . . . . . . . . . 172
Billy Martin . . . . . . . . . . . . . . . . . . . . . . . . . . 172
Indexing Both the Costs and Authorization for
the San Felipe Division of the Central
Valley Project . . . . . . . . . . . . . . . . . . 173
Cost Reductions on the San Felipe Project . . 173
Auburn Dam Studies . . . . . . . . . . . . . . . . . . . 174
The First Pacheco Tunnel Had Serious
Difficulties, Including “Squeezing
Ground” . . . . . . . . . . . . . . . . . . . . . . . 174
In Pacheco Two the Engineering Problems Were
Anticipated, and There Was Little
Difficulty . . . . . . . . . . . . . . . . . . . . . 175
“. . . we sure handed them the hammer to beat us
about the head and ears with Teton. We
would have built Auburn, . . . but for
Teton. . . .” . . . . . . . . . . . . . . . . . . . . 177
Had it Not Been for the Teton Dam Failure, We
Would Have Built Auburn Dam as a
Thin-arch Concrete Dam . . . . . . . . . 177
Significant Work Was Completed on
Construction of Auburn Dam . . . . . . 178
Even today “. . . we don’t know, exactly what the
failure mechanism was. . . .” . . . . . . 179
“. . . you certainly felt a sense of responsibility
for everything that was going on,
including Teton. I sure as hell didn’t feel
the need to take any blame for it. It’s an
engineered project. Something didn’t
work. . . .” . . . . . . . . . . . . . . . . . . . . . 180
The Big Thompson River flood drew some
attention away from the failure of Teton
Dam . . . . . . . . . . . . . . . . . . . . . . . . . 180
“. . . there isn’t anything that’s going to dampen
that feeling, that ego, that goes along
with having been a part of some very
successful projects. . . .” . . . . . . . . . . 181
“That failure [at Teton Dam] did not impact and
affect the international reputation of the
Bureau at all. . . .” . . . . . . . . . . . . . . 181
“Failures are a part of the engineering
construction process. . . .” . . . . . . . . 182
Talk at the National Society of Professional
Engineers on the Failure of Teton Dam
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
The Tendency after a Disaster Is to Guard
Information . . . . . . . . . . . . . . . . . . . 183
The media want fast information and often
Statement of Donation
1999–Died
Introduction
Duck: Yeah.
Duck: No.
letter.
Duck: No.
Duck: Yes.
Storey: At a time.
Duck: Yeah.
Blasting Work
Duck: Again, more related to arch dam work–the
loading, the hole spacing, drilling.
Shift to Shift
Duck: Well, we had what we called a pass-on book.
Significant items–and the principal inspectors, it
was kind of our book, we passed on information
in that pass-on book, and then there were shift
reports from all the inspectors. Whatever they
were inspecting, whatever they were doing, they
gave the status of it– what they’d done, what
they’d approved, what they had turned down,
maybe, or what needed to be done. And those
reports always were reviewed by the principal
inspector and passed on to the inspector.
Duck: Uh-huh.
Duck: Yes.
Duck: Well, not all the time. There was the sequence:
drill, blast, clean up. Clean up, in the sense–the
arch dam jobs was a matter of working a
bulldozer into the keyway and then pushing the
material into the bottom of the river. Then
other equipment would be picking up out of the
bottom of the river. Well, as you can guess,
4. (...continued)
was 27 feet while the maximum base thickness was 131
feet.
Roscoe Granger
Duck: Well, he was pretty tough. I always found him
to be fair. He had a reputation for being
hardnosed. He was a favorite of mine, and I
was a favorite of his. Moved on to Yellowtail
with him, and then over to Third Powerplant at
Grand Coulee. He was a rather small, slight-
built man, gray hair. Lot of people had a lot of
fear of Roscoe Granger. He could unload about
as quick on anybody as anyone I ever knew, and
it stuck.
Duck: Yep.
Storey: Sure.
understand.
Ted Mermel
Storey: Did you ever run across a guy named Ted
Mermel while you were there?
Duck: Yeah.
Born in 1930
Duck: That’s typical. August the 8th, 1930.
Storey: Sure.
Duck: Yeah.
Duck: Sure.
Concrete Sampling
Storey: So am I hearing correctly that there would be
concrete samples taken at the batch plant, and
then concrete samples when it was placed?
Checking Aggregate
Duck: Walk.
Storey: No.
Duck: They knew that’s the risk they were taking, that
we would have had them remove it. Go in and
chip it out and redo it.
Duck: No. I had a drill crew come in, with a core drill
bit.
Duck: Had the contractor take it. They took the cores;
Duck: Yes.
Duck: Yes.
Storey: T-R-A-N-S-A?
Duck: Right.
Storey: What grade did you start out at when you came
to Reclamation in [‘59] ‘64?
Duck: GS-7. GS-7, which was because of my age. I
was twenty-nine when I graduated, and that
interviewing group told me they were sure that
they could get me in at–usually, entry-level
engineering positions, at that time, right out of
school, were GS-5.
Roscoe Granger
I think [Floyd] Dominy had significant
call on bringing the Assistant Construction
Engineer in, Howard Fink, who was finishing
up, or had finished up, down at Glen Canyon,
because of Roscoe’s age and health, etc., and he
lived on the edge for a lot of years, but lived to
be 83-, 84. He looked like he had one foot in
the grave when I was at Flaming Gorge, you
know. He was a frail–and at Yellowtail, he was
taking bromine, some bromine product,
anyway, and, you know, packed him out to the
hospital in Billings, you know, out cold. His
stomach, whatever it was. The doctor told him
positively not to take any more of that stuff.
Storey: S-
Duck: Oh, he lived for a long time after they told him
to quit. It would’ve been ‘64.
Duck: Yeah.
Duck: For the most part, no. You know, you had the
other supervisory inspectors that were moved
into those positions, and so forth. The day shift
thing, for me, was– Phil Soukup had his craft
superintendents, his superintendents for the
concrete, or excavation, or the powerplant
superintendents, and so forth, but he dealt with
me a heck of a lot of the time, and then I dealt
with his supervisory people. He had his finger
or thumb on everything that was going on, knew
what was going on. He’d be out there in the
middle of the night. It wasn’t unusual to see
Yellowtail?
Duck: Sure.
Duck: Yes.
Duck: Yes.
big difference. . . .”
Duck: I’m not sure–well, it had been authorized, I’m
sure. I’m not sure that it had been funded. And
there’s a big difference. You know, there was a
Construction Engineer on Yellowtail in 1947.
Storey: But you knew from talks with Mr. Granger that
you were going to be over there? Is that what
I’m understanding?
Duck: And you fully expect to. You fully expect to. It
doesn’t always work.
Duck: Yeah.
Duck: Sure.
Duck: Yes.
11. (...continued)
1959; member of the U.S. Congress 1959-1981; not
reelected in 1980; and died in Roseville, California in
1988.
12. Manuel Lujan, Jr., born in 1928, served New
Mexico in the U.S. Congress 1969-1989; Secretary of
the Interior 1989-1993; is a resident of Albuquerque.
13. Was a California representative to the U.S.
Congress 1963-1983, not reelected in 1982.
Subsequently served as director, special programs,
Federal Aviation Administration.
14. Born in 1938, Symms served in the U.S.
Congress 1973-1981 and than in the U.S. Senate 1981-
1993. Subsequently stayed in Washington, D.C., in
various lobbying capacities.
Storey: And what did he want you to do? What did the
deputy do at that time?
field”?
Duck: Yes.
concerned. . . .”
Carter’s water project “hit list.” The
handwriting was on the wall, as far as I was
concerned. Doesn’t really make a lot of
difference which President you look at. The
idea and the practice, in those very active years
of dam building, the constituents, the water
users, the power users, the subcommittees of
Congress, and the Commissioner of
Reclamation, the so-called iron triangle, the
Bureaus. You don’t necessarily need to look at
just the Commissioner of Reclamation. But I
think I first heard “breaking the iron triangle”
under the [Richard M.] Nixon Administration.
But that effort to break up that successful
bringing-to-fruition projects that the
constituents, the people, the water users,
whether you’re talking agricultural or M&I,
whatever, anyway, the success with which those
projects had been accomplished over a long
period of years was going to come to an end.
While Nixon didn’t have anything to do with
the breaking of the so-called iron triangle, the
evolution of the process certainly did. Different
mentality of politicians. The NEPA [National
Environmental Policy Act] Act passed in, what,
‘72, I believe.
NEPA
Storey: ‘69. 1969.
15. Marcel Lajos Breuer was born May 21, 1902, in Hungary and
died in New York City on July 1, 1918.
Reclamation.
“Bizz” Johnson
Duck: Well, at the time of the Teton failure, as I
indicated, I think, before, that we had the
“Bizz” Johnsons still in Congress. Manny
Lujan, Steve Symms from Idaho, Jim McClure,
people like that, that were interested in
development.
Storey: Control.
Duck: Sure.
Auburn Dam
So that environment started from day one,
after the dam failed, until I left. It’s still going
on. Same way with the design process, outside
reviewers looking at what was being considered
and designed. Auburn, of course, fell in the
middle of this. We were dealing with the
earthquake problem before the dam failed.
After the dam failed, it just escalated. That was
further evidence, in a lot of critics’ minds,
anyway, that they’d picked the wrong structure
type, and it just evolved into the tremendous
amount of foundation work that was done at
Auburn, and, ultimately, losing the project. The
project failed to go forward. Anyway, that was
part of the environment in that post-‘76 year.
the regions.
Pacheco Tunnel
You were asking about Pacheco Tunnel.
Billy Martin
Some of these guys, believe me, regional
directors like Bill E. [pronounced “Billy”]
Martin, to a certain extent, Joe Hall–that’s kind
Storey: Auburn?
Duck: Yes.
Duck: Yes.
Duck: Yes.
Storey: But Auburn was going hot and heavy while you
were there.
Duck: Yes.
Storey: How long did you stay with Harza after you
were made President?
Duck: Absolutely.
Duck: Okay.
Storey: Hickel?