Project Management Systems and Techniques
Project Management Systems and Techniques
PGP-CM-MODULE-12
ASSIGNMENT NO: 01
COURSE TITLE:
PROJECT
MANAGEMENT
SYSTEMS AND
TECHNIQUES
i. Identification of project
ii. Stages in development of project
iii. Work break down structure to undertake the project
iv. Milestones & CPM chart for corporate control
v. Cost of project
1) Project Identification:
The primary thing about any project is its necessity as well as its feasibility.
The necessity of the project – cricket stadium is created by the people of the
city as well as a mega city demands a cricket stadium in its vicinity. The
feasibility demands a deep thought like for a location of stadium
Project Report:
It is a basis for communicating what has been planned for the project.
Architects and design engineers primarily handle these phases. The client
operation and utilization of knowledge and field constructors experience are
more strongly injected at this stage through direct participation and
stringent review procedures. There are two phases of engineering and
design
Procurement:
Construction:
Commission:
Maintenance:
This is the phase where we need maximum attention and here we lack
which is the main cause for the failure of the project. Whenever the project
is handed over to the owner to either operate or utilize where he takes
services of all production engineers, maintenance engineers, service people
and people of different trades as required to have a smooth functioning of
the project over its lifetime.
i. Analysis
ii. Anticipation
iii. Scheduling process
iv. Co-ordination and control
v. Production of data
All effectively managed projects involve the preparation of the project plan.
This is the fundamental document that spells out what is to be achieved and
what resources will be necessary. The basic project document is the project
plan. The project lives and breathes and change as the project progresses or
fails.
The operation and maintenance cost in subsequent years over the project life
cycle includes the following expenses:
1. Construction cost
From the data provide, it is assumed that construction of new
stadium cost Rs. 10000/- per spectators. Including all facilities
2. Operating costs
3. Income
Income is achieved in the mode of ticket sales, broadcasting rights,
advertising, sponsorship.
Income through ticket sales
Capacity of separators = 80,000
Average cost of ticket = Rs. 100
Per year matches =4
Assuming one match average spectators = 65000
Earnings from match tickets = Rs. 100*65000 = Rs. 65 lakhs
Per year earning through matches = 65L * 4 = Rs. 260 lakhs
Income through broadcasting rights:
It is assumed 2000 lakhs per match
One year income: = 4 matches * 2000 = 8000 lakhs
Income through sponsorship rights
It is assumed 300 lakhs per match
One year income : = 4 matches * 300 = 1200 lakhs
Income through advertisements
It is assumed 100 lakhs per match
One year income = 4 matches * 100 = 400 lakhs
Total income per year
Income through ticket sales : 260 lakhs
Income through broadcasting rights : 8000 lakhs
Income through sponsorship rights : 1200 lakhs
Income through advertisement : 9860 lakhs
Cost summary:
Cost for construction of new stadium : 20000 lakhs
Total expenditure for 5 years : 16500 lakhs
Income expected in 5 years : 49300 lakhs
Net profit : 12800 lakhs
Hence the construction cost shall be recovered in the span of 5 years and
the project will make the profit of 12800 lakhs in 5 years.
There may be more than one critical path among all the project activities, so
completion of the entire project could be delayed by delaying activities
along any one of the critical paths. For example, a project consisting of two
activities performed in parallel that each require three days would have each
activity critical for a completion in three days.
Formally, critical path scheduling assumes that a project is divided into
activities of fixed duration and well defined predecessor relationships. A
predecessor relationship implies that one activity must come before another
in the schedule. No resource constraints other than those implied by
precedence relationships are recognized in the simplest form of critical path
scheduling.
To use critical path scheduling in practice, construction planners often
represent a resource constraint by a precedence relation. A constraint is
simply a restriction on the options available to a manager, and a resource
constraint is a constraint deriving from the limited availability of some
resource of equipment, material, space or labour. Most of the critical path
scheduling algorithms impose restrictions on the activity relationships or
network geometries which are used. In essence these restrictions imply that
the construction plan can be represented by a network plan in which
activities appear as nodes in a network or designation. Two nodes are
introduced to represent the start and completion of the project itself.
The actual computer representation of the project schedule consists of a list
of activities along with their associated durations, required and predecessor
activities. Graphical network representation rather than a list are helpful for
visualization of the plan and to insure that accomplished by filling in blanks
on a screen menu, reading an existing data file, or typing directly to the
program with the identifiers for the type of information bring provided.
5) Recommendations / Conclusions:
This cricket stadium will be profitable for all the parties say spnsors,
spectators, cricket association etc.
6) Bibliography References:
NICMAR study material
Internet