Construction Management Notes
Construction Management Notes
CHAPTER NAME
1. Introduction
2. Construction Planning
3. Organization
4. Construction Labour
5. Inspection and Quality Control
6. Contracts
9. Stores
CHAPTER 1
INTRODUCTION
(i) The Government and its agencies, such as the central and state public
works
departments, the military engineering services, municipalities etc.
(ii) Public under takings, such as the Railways, National Building Construction
Corporation etc.
(iii) Private companies.
(iv) Individuals.
Labour: Labour schedule, helps in providing future labour requirements and efficient
and optimum deployment of labour force where ever necessary.
Material: Material schedules helps in providing types of material required along with
their quantities and the actual time by which the materials are kept ready so as to avoid
any delays in completing a construction project.
Equipment: Equipment schedules are prepared to find the type of equipment required,
time and period for which particular equipment is needed. It helps in avoiding the
equipment keeping idle.
Fig 2.1
The planned program is shown by a thick or double line with the planned start
and finish by short vertical lines. The float is shown by a hyphenated horizontal line and
indicates that, lthough the item is scheduled to be completed by a certain date, yet
subsequent items are not likely to be held up in case of delay up to the period
represented by the hyphenated line. A hyphenated vertical line, connecting the start of
the item with the completion of the item on which it is dependant, indicates the
dependency of one work on another. In fig 2.1, item 3 is dependent on item 1 and
cannot be started till item 1 is completed. The actual progress shown in single line
drawn below the line showing planned program.
Bar charts are suitable for determining the resources, such as materials, labour,
machinery and finance, required for construction work. Figure 2.2 shows the resource
aggregation chart for RCC work.
Bar chart is simple, easily understandable and widely used method of scheduling.
However it has certain limitations, firstly it is difficult to depict complicated
interdependencies of various items of work. It does not give actual progress of the work.
It is not possible to know the peak rate of work necessary for timely completion of a
project. The bar chart, there fore, is a static representation and does not respond to the
dynamic happenings on the construction site of a complex project.
2.11 Critical path method of scheduling
Critical Path Method is a network method. In CPM the project is analyzed into
different activities whose relationships are shown on the network diagram. The
limitations of the bar charts can be over come with the Critical Path Method. CPM is
widely used in construction industry by a number of private and public organizations.
The concept of CPM is that only a small number of critical activities take most of
the estimated project time. Speeding up the rest of the activities has no effect on the
completion of work. Only these critical activities need to be speeded up and the rest of
the activities can be allowed to proceed normally. The work can then be completed by
the target date.
2.12 Basic network construction
A network diagram is a graphical representation of the sequence in which various
activities of a project are under taken and the relationship among them. The method of
construction of Network diagram is given below
1) Listing the activities: All the activities of which the work is composed of are listed.
2) Arrow: Individual activities such as excavation, plastering, brickwork, plumbing etc.
which consumes time are denoted by arrows. The direction of the arrow indicates the
general flow of the work, tail representing the start and the head the completion of the
activity. The length of an arrow does not have any significance.
3) Events: The head and tail of an arrow represent events which are represented by a
circle, square or a triangle. An event is just a point of time and it is not a time consuming
element.
4) Activity
Identification: All events are given unique numbers which may or may not be in serial
order. Activity is identified by the event numbers preceding and following it; or by
letters A, B, C etc. The activity, Excavation is identified by number 1-2 or A, ‘Plumbing’ by
8-12 or B.
5) Sequence convention: All activities shown as entering an event must be completed
before those emerging from it can be started. In fig (2.6) the activity emerging from
event 2, i.e 2-3 (laying foundation concrete) can not be started before activity
1-2 (excavation of foundation) entering in
to event 2 has been completed.
6) Net work logic: The following points have to be considered before deciding where
an activity fits.
i) Which activities must be completed before this activity can be started?
ii) Which activities cannot be started before this activity is completed?
iii) Which activities can be started simultaneously?
Some commonly occurring network situations, along with their bar charts are given
below:
2.13 Terms used in CPM method
Dummy Activity: Dummy Activity is an activity, which do not consume any time.
Dummies are used only to ensure separate activity numbers and maintain the correct
logic of the network. This activity is represented by dotted arrow.
Duration: Duration is the estimated time, required to complete an activity and is shown
on or under the activity in the network.
Earliest start time: It is the earliest possible time for the activity to start without
changing the sequence of the activities in the network. It is denoted by E.S.T.
Earliest finish time: It is the earliest time by which the activity can be completed and is
denoted by E.F.T. EFT of an activity = EST + Duration of activity (T).
Earliest event occurrence time: It is the earliest time that the event start can occur. It is
denoted by TE.
Latest start time: It is the latest time by which an activity can be started without
delaying the project. It is denoted by L.S.T.
Latest finish time: It is the latest time by which an activity can be completed without
delaying the project. It is denoted by L.F.T.
Latest allowable event occurrence time (TL): It is the latest time, the event can occur.
Symbolic Representation
Total float: It is the difference between the maximum time allowed for an activity and
its duration time. It is also called total activity slack or spare time and is denoted by (TF).
TF = LST - EST
= LFT - EFT
= TL - EFT
Free float: The free float of an activity is an amount of time by which the activity
completion time can be delayed without interfering with the start of succeeding
activities.
It is denoted by F.F. = TE-EFT
Critical path: The events which have no float or slack are the critical events i.e., If TE =
TL. These events must be completed on schedule, if the project is to be completed in
the minimum total time. The path joining such critical events is called the critical path of
the network.
Critical activities: The activities lying on the critical path are called critical activities.
Critical activity has a zero float
2.14 Steps in Critical Path Scheduling
Before applying the critical path method of scheduling to a construction project,
it is necessary to follow the given steps.
1. Prepare a list of activities for the project.
2. Estimate the durations of each activity.
3. Determine which activity or activities immediately follow each activity.
4. Determine which activity/activities immediately precedes each activity.
5. Draw a network with the activities and events properly interconnected.
6. Assign number to the events and make sure that the number at the head of
each arrow is larger than the number at the tail of arrow.
7. Prepare a chart with vertical columns and horizontal lines on which to list each
activity with an appropriate designation. Duration, earliest start, earliest finish,
latest start, latest finish, and total float are to be mentioned. A column of free
float may be included if this information is required.
8. Determine which activities lay on the critical path.
2.15 Determination of project schedule and Critical Path
After estimating the performance time for each activity, scheduling of activities is
begun to determine the network critical paths. The basic scheduling computations
involve a forward and backward pass through the network. Based on a specified
occurrence for the initial network event, the forward pass computations give the earliest
start and earliest finish times for each activity and also the earliest occurrence time for
each event.
By specifying the latest allowable occurrence time for the terminal network
events, the backward pass computations will give the latest allowable start and finish
times for each activity, and the latest allowable occurrence time for each event. After the
forward and backward pass computations are completed, the float can be computed for
each activity and thereby critical and the sub critical paths through the network are
determined. When an activity has float, there is more time available to do it than it
requires.
In initial stages it is convenient to begin with zero as the starting time of the
initial project event and estimate the activity performance times in working days. Finally
these computational results are converted to calendar dates. It is also assumed that
there is only one initial event and one terminal event. Also the latest allowable finish
time for the project is equal to the earliest finish time computed in the forward pass
computations.
Example 2.1: Draw a Network for the following logic Activities B and C depend upon
activity A; Activity D depends upon Activity B; Activity E depends upon activity C and
activity F depends upon activities D and E.
Solution: Fig.2.8
Example 2.2: Draw a C.P.M. Network diagram for the following logic:
Activity B follows activity A.
Activities C and D follow activity B
Activities E and F follow activity C
Activity G follows activity D
Activity H follows activities F and G
Activity I follows activity E
Activity J follows activities H and I.
Solution:
If event 1 is at work 0 (Zero) then even 2 has an earliest time of 10 days. Event 3 has an
earliest time of 13 days but event 4 has two paths leading into it
(i) 1-2-4 of duration (10+15) = 25 days
(ii) 1-3-4 of duration (13+8) = 21 days.
The earliest time for event 4 is determined by the longest path. In this case 1-2-4 has
maximum continue duration time of 25 days. Hence the earliest time for the terminal
event is 25 days
Example 2.4: Find the Latest allowable time for the events and prepare a time schedule
and calculate float for each activity and show the critical path for the given network
diagram.
Solution:
For the terminal event 4, the latest allowable occurrence time (TL) will be equal to the
earliest occurrence time (TE)
Therefore .TL of event 4 =31
TL for event 3 = TL of event 4 – duration of activity (3-4) = 31-
11 =20
TL for event 2 = TL of event 4 – duration of activity (2-4) = 31-
18 =13
For TL for event 1 has two paths i.e. 2-1 and 3-1 TL for event 1 along path 2-1 = 13-
13 =0
Or TL for event 1 along path 3-1 = 20-16 =4 Least is to be taken i.e., 0.
In the network critical path is (1-2-4) and the duration of the project is 31 on this path
the activities have no float (when TE=TL; then flow is zero)
Example 2.6: The table given below represents the activities of the network of a
construction project. The durations for the activities for the network are also given.
(i) Prepare the network diagram
(ii) Find the Critical Path and time of completion of construction project
(iii) Prepare time schedule indicating total
float and free float.
Solution: Refer Fig.
Finding TL for events: For the terminal event 8, the latest allowable occurrence time
(TL) will be equal to the earliest occurrence time (TE) as calculated from forward pass
and is equal to 84
TL for event 8 = 84
TL for event 7 = 84 – 7 = 77
TL for event 6 = 77 – 11 = 66
TL for event 5 = 66 – 0 = 66
TL for event 4 = (i) 66-15 = 51, (ii) 66-13 = 53 Least value = 51.
TL for event 3 = 51 – 7 = 44
TL for event 2 = (i) 51-35=16, (ii) 77-5=72, (iii) 44-9=35
Least among the above is to be taken, hence
TL for event 2 = 16
TL for event 1 = 16 – 11 = 5
TL for event 0 = 5 – 5 = 0
for activity 7-8 77-77 = 0
Free Float = TE-EFT
Total Float = LST-EST=LFT-EFT Free float for activity 0-1 5-5 = 0
Total float for activity 0-1 0-0 = 0 for activity 1-2 16-16= 0
for activity 1-2 5-5 = 0 for activity 2-3 25-25= 0
for activity 2-3 35-16 = 19 for activity 2-4 51-51= 0
for activity 2-4 16-16 = 0 for activity 2-7 77-21=56
for activity 2-7 72-16 = 56 for activity 3-4 51-32=19
for activity 3-4 44-25 = 19 for activity 3-7 77-34=43
for activity 3-7 68-25 = 43 for activity 4-5 64-64= 0
for activity 4-5 53-51 = 2 for activity 4-6 66-66 = 0
for activity 4-6 51-51 = 0 for activity 5-6 66-64 = 2
for activity 5-6 66-64 = 2 for activity 6-7 77-77 = 0
for activity 6-7 66-66 = 0 for activity 7-8 84-84 = 0
In the diagram 2.15 the critical path is shown by thick line and the activities along critical
path will not have any slack time.
3.1 Introduction
Organization can be defined as the managerial function of fixing the
responsibilities of individuals and establishing good relationships with one another for
effectively achieving a common goal in a group activity.
For medium-sized works, a more elaborate arrangement is called for and the
organization is generally of the line and staff pattern. The engineer in charge may be
assisted by a team of experts, such as architects, design engineers, accountants,
planning engineers and personnel officers. This constitutes the staff portion of the
organization. The staff is usually located at a permanent place, known as the head
quarters. The construction work is carried out by field officers who are organized in a
line form. The field staff receives guidance and instructions from the head quarter staff.
For large projects, the number of people involved may run into thousands and
the staff portion of the organization may be departmentalized. Each departmental head
looks after a particular aspect of the work, such as design, planning, purchase of
materials, personnel, etc. and is assisted by a team of subordinates grouped under the
charge of different heads.
The grouping of work in the field could be on the basis of the type of work, such
as civil works, mechanical works, electrical engineering works, piping or other
specialized types of works. For works such as highways, canals, etc. which extends over
large areas, field work may also be divided on the basis of territory and placed under the
charge of a departmental head, assisted by a subordinate staff organized in a line form.
Masonry:
It is necessary to see that the bricks used are of the specified quality and have the
require bearing capacity when used in load bearing walls. The bond should be
maintained properly. The dimensions and verticality of masonry are also important items
to be controlled.
Water proofing:
Water proofing also needs quality control. The damp proof courses and the
damp proofing of roofs, etc are very important items needing special attention.
Joinery and Timber work:
In this item both the quality of timber used and workmanship are important for
quality control.
Services:
Services include such as electrical, sanitary, water supply, air conditioning etc.
CHAPTER 6
CONTRACTS
6.1 Introduction
Contract is an undertaking by a person or a firm to do any work under certain
terms and conditions, which should invariably be in writing. The work may be for the
construction or maintenance and repairs, for the supply of labour or the transport of
materials, etc.
Contractor means a person or a firm who undertakes any type of contract.
Usually this term is confined to the contractors who are engaged in construction or
execution of works or repairs.
The system through which the works are carried out by the contractors, who
arrange all the materials, labour and equipment required for proper completion of the
works is known as the contract system. The work should satisfy the specifications with
expected quality .It should also be completed within the stipulated time.
6.2 Legality of Contracts
All the contract conditions should be according to the law because the court can
force only those conditions, which are according to the established public policy and
should put up good examples on the morals of the society as a whole.
As per the Indian Contract Act Sections 10, 11, and 68 the parties entering into
the contract should be legally competent. The law relating to contract imposes upon
each party of the contract a legal obligation to observe the terms of the contract and
give the other party the right to enforce fulfillment of these terms or to claim damages
in respect of the loss suffered in consequence of the breach of the contract.
The obligation, which a contractor accepts, which he submits a tender are
determined by the conditions of the tender, such acceptance of tender gives rise legally
to a binding contract.
Some of the legal aspects of contracts are given below.
i) For a contract to complete a definite piece of work, recovery is possible only
after completion.
ii) The impracticality of a work cannot be excuse for nonperformance.
iii) A contractor who refuses to carryout the work before completion can be
subjected for breach of contract.
iv) When an employer makes it impossible for contractor to complete the work in
accordance wth the contract, the contractor can sue for the rate of the completed
work.
v) The penalties described in the penalty clause will not be applicable if the
execution of the contract is delayed because of the fault of the employer.
vi) In case of the contractor’s inability to complete the work, after part execution
the employer can consider the contract as rescinded and take an action for the
damages. The contractor under such circumstances has no lien for the money
spent on the work by the contractor.
vii) When a contractor has finished part of a work and refused to complete the
entire work and the employer without the consent of the contractor takes the
work in his own hands for completion. In this case the law implies that the
employer has to pay for the work, which has done by the contractor.
viii) When a contractor without lawful excuse, refuses to carry on the work after
part performance, the employer may have to pay for the materials delivered on
the site by the contractor as distinguished from the materials, which have
become fixed in to the work.
ix) When a contract is formed and it becomes impossible to perform the work
immediately or at a later date, it may be possible to adjust the rights and
liabilities of the parties.
6.3 Types of Contract Agreements
Contract agreements fall into the following two clauses.
1. Piece-work agreements. 2. Contracts.
6.4 Piece-work agreements.
These are agreements for doing the work at agreed rates, without reference to
the total quantity of work or time. Small works or piecework up to Rs.5000/- are got
done through the contractors by piecework agreement.
Piecework agreements are of the following types.
1. Piece-work. 2. Work Order.
Piece-work: In piece-work, the quantity of work is not mentioned and only the rate is
mentioned. This agreement is used
(i) For small works
(ii) When it is necessary to start work in anticipation of the formal acceptance of
the contract.
(iii) For running contract.
Work Order:
Work order is used for petty works; work orders may sometimes also mention the
time limit within which the work is to be completed. No formal agreement is drawn up
with the contractor as in the case of piece-work when the work is awarded by a work
order.
6.5 Types of Contracts
Contracts are of the following types.
1. Item rate Contracts.
2. Percentage Rate Contracts.
3. Lump sum contracts.
6.6 Item Rate Contract:
In this type of contract, the contractor undertakes the work on the item rate
basis. The payment is done on the basis of quantities of items done and their respective
rates. The quantities of various items are worked out by detailed measurements. This
type of contract is also known as unit price contract.
The approximate quantities of all possible items of work are worked out and are
shown in the tender form. Every contractor quotes his rates against each item are arrives
at the final total amount of the work. This is the most common type of contract system,
which is widely adopted.
Following are the advantages of item-rate contract
1. The additions and alterations in the plan and specifications can be easily made
at any stage.
2. As the contractor gets the payment against the actual quantities of items done
by him, the method is economical. No possibility for excess payment.
3. As the rates are item-wise the contractor is not worried regarding the
uncertainties in the plan and specifications.
4. The work can be started after accepting the tenders without waiting for all the
detailed drawings and specifications.
Disadvantages:
1. The total cost of the work can only be computed after completion of entire
project. In such case the contractor may face financial difficulties if final cost
increases abnormally.
2. Before preparing the bills for payment of money to the contractor, all
measurements of various items of work have to be carefully taken and suitably
entered in the measurement book.
3. Great care shall be taken by the department officers to strictly enforce the
specifications during execution of work to avoid the using of substandard
materials by the contractor.
6.7 Percentage Rate Contract:
This is also known as cost-plus percentage contract. In this type of contract the
contractor agrees to take the work of construction for fixed percentage over the actual
cost of construction. This type of contract is given when no contractor is agreeing to do
work on other types due to uncertainties and fluctuations in the market rates of
materials and labour.
The department keeps the actual up to date records of the expenditure incurred
on the work and pays the fixed percentage as agreed over it to the contractor. The
contractor arranges for the labour, materials required for completion of the work, and
maintains proper account of the construction costs.
The cost plus or percentage contracts can be of the following types:
1. Fixed Percentage of Cost
2. Cost plus a fixed sum
3. Cost plus a fixed sum with profit sharing
4. Cost plus variable percentage.
6.8 Lump sum Contracts:
In this type of contract, the contractor undertakes the construction work or the
execution of the specified work and completes it in all respects for a fixed amount of
money. The detailed specifications of all items of works, detailed drawings, plans etc.,
are supplied by the department to the contractor.
The contractor on the basis of given details, works out the total cost of the
construction and quotes it in lump sum. The design, shape and materials are as per the
choice of contractor, but they have to be got approved before the start of the work.
Following are the advantages of Lump sum Contracts.
1. Due to competition among the contractors, the contractor tries to take the
work even at less profit, resulting in low cost of the work.
2. As the total cost of the work is known before hand, the owner can arrange the
funds in time.
3. The contractor’s profit directly depends on the time of completion; hence for
getting more profit, the contractor tries to complete the work as early as possible.
4. The materials used on te temporary works during construction are relieved
earlier resulting in their effective use in other works also.
Following are the disadvantages of Lump sum Contracts:
1. The owner tries to get the maximum work out of money he spends, where as
the contractor tries to get the maximum profit, this causes conflicting interests.
2. It becomes very difficult to adjust the additions and alterations in the plan and
the specifications at a later stage.
3. If the plans and specifications are not clear, the contractors will quote higher
rates, resulting in high cost of the work.
CHAPTER 7
TENDER AND TENDER NOTICE
7.1 Tender:
A Tender is the contractor’s bid in writing offering to execute the specified work
of construction, supply of materials etc., at the rates and amounts indicated, within the
time limit and under conditions specified and agreed to.
7.2 Necessity of Tenders:
Works, which are to be awarded to contractors, are publicized to enable a
sufficient number of interested parties to bid. The lowest bid is generally accepted,
unless there are good reasons for not doing so. The process of inviting bids and
accepting them is known as tendering. The bid is usually made on the tender forms
specified by the owner. The following tender documents are made available along with
the tender forms to enable contractors to bid for the job.
1. Layout plan.
2. Set of drawings, including working drawings.
3. Detailed specifications or reference to standard specifications for each item of
work
4. Schedule of stores to be issued by the owner indicating the rates and their
place and issue.
5. Schedule of tools and plant and other facilities to be made available by the
owner, indicating the conditions, hire changes and the place of delivery.
6. General conditions of the contract including time limits.
7. Special conditions of the contract that may have to be highlighted.
8. Amount of Security deposits to be paid /deducted.
7.3 Tender Notice:
Whenever works are to be let out on contract, tenders are to be invited from the
registered contractors or both registered and unregistered contractors depending on
the
magnitude and nature of the work by issuing notice in newspapers. The notice that
includes various particulars of work is named as Tender Notice.
7.4. E.M.D:
Earnest Money Deposit is the amount, which the contractor has to deposit with
the department at the time of submitting a tender. This accompanies the tender form
and this is usually 2% of the total estimated cost of the project. This serves as a check to
prevent the contractor from refusing to accept the work when the tender has been
accepted.
The other objects of collecting earnest money are:
1. To reduce unnecessary competition: If no earnest money is collected, heavy
competition may start among the tenderers. The contractors who do not have
sound financial status may also offer their tenders, which increase the
unnecessary competition among the tenderers.
2. To act as a tool for punishment: In case the contractors quote lower without
intention of doing work, the earnest money shall be forfeited by the department
as a punishment to such contractors.
3. To act as compensation: When the lowest contractor refuses to take up the
work, the work can be allotted to the second lowest contractor. The earnest
money forfeited from the first lowest contractor compensates to loss of the
department.
(9) Authority competent to accept tenders. The tender notice may be advertised
in newspapers and issued to registered contractors by post. Copies of the tender
notice are also put up on the notice boards of various offices of the organization.
For very large works or those involving special techniques, which may not
be within the capacity of the construction industry in the country, global tenders
will be issued all over the world inviting bids for the work.
Contractors are given a reasonable period of time, depending upon the
size of the work to prepare and submit their tenders. Tender documents are
usually priced and are issued on payment of the prescribed amount. The sale of
tender papers starts and closes at the time notified in the tender notice.
The lowest tender is generally accepted unless there are good reasons not to do
so, such as poor past performance and limited financial or physical capacity of the
tenderer. If the rates quoted are on the high side, all tenders may be rejected and re-
invited to obtain a reasonable bid. In order to ensure that there is no legal complication
in not accepting any tender, a clause is added in the tender notice reserving the right to
reject any or all tenders without assigning any reason.
The tenderer whose bid is accepted is intimated in writing and asked to sign the
contract documents within a specified period of time. If he fails to do so, the offer is
cancelled; the security deposit forfeited and the work allotted to the contractor whose
tender is the next highest. After signing the contract agreement, the site of the work is
formally handed over to the contractor, then he can start the work. The time for
completion is reckoned from the day the site is handed over to the contractor.
7.9 Work Order
Work order is used for petty works; work orders may sometimes also mention the
time limit within which the work is to be completed. No formal agreement is drawn up
with the contractor as in the case of piece-work when the work is awarded by a work
order.
7.10 Contract Agreement
Contract agreements are fall into the following categories:
1. Contracts
2. Piece work agreements
Contracts are classified as:
1. Percentage Rate contracts.
2. Item Rate contracts.
3. Lump sum contracts.
Piece-work agreements are of following types
1. Piece work 2. Work order
7.11 Conditions of Contract
The Conditions of contracts includes the following
1. Time of completion of work.
2. Volume of work.
3. Specifications of work.
4. Rates of payment.
5. Penalties for default on the part of the contractor etc.
CHAPTER 8
ACCOUNTS
8.1 Necessity of Accounts
The accounts of an organisation are maintained in accordance with a system
which lays down the detailed procedures to be followed in entering into different
transactions involving financial matters and keeping a record of such transactions. The
system of accounts is devised to suit the requirements of the organisation, taking into
consideration the volume and type of transactions entered into at various levels of the
organisation for smooth and efficient functioning.
8.2 Different Methods of Carrying out Works
Public works are carried out either departmentally or through contractors.
Complicated and important works, where a high degree of reliability in the quality of
work is essential, are generally executed departmentally by engaging labour.
This method requires intensive planning and supervision, so that the output of
labour and machines is commensurate with the expenditure incurred. For most works,
however, the contract method is employed, when the department, taking advantage of
competitive bidding by rival contractors, is able to get the work executed at the lowest
possible rates.
Moreover, the risks involved in construction and the day-to-day problems are the
headaches of the contractor and the departmental staff can devote sufficient time to
ensure that the contractor's work is in accordance with the designs, specifications, time
schedule and other conditions laid down in the agreement.
8.3 Public Works Department System of Accounts
The Main features of the system are:
1. The divisional officer obtains money required for disbursement in connection
with the execution of works and contingent charges by cheque on the civil
treasury/bank. He also collects some of the departmental receipts and deposits
them in the treasury /bank.
2. The accounts of all these transactions, as well as transactions of subordinate
officers acting on behalf of the divisional officer are compiled under the
supervision of the divisional accountant and are submitted to the pay and
accounts officer/accountant general.
3. The divisional officer also maintains clear accounts of the stores received by
him and makes these accounts available to the accountant general at the time of
audit.
4. The charges for each project, work or sub-work under each major head of
expenditure are maintained separately in the accounts of the divisional officer.
5. Personal payments of all Government employees of the department are made
on bills presented to the treasury/pay and accounts officer and these are,
therefore, brought to account by the accountant general/pay and accounts
officer himself.
The divisional officer is the primary disbursing officer and maintains a detailed
account of the departmental receipts-and payments kept by him and not at the
treasury/pay and accounts office as in the civil accounting system.
The accountant general audits the accounts maintained by the divisional officer
and, therefore, the accountant general has not only to satisfy himself about the
maintenance of accounts, but also about the audit. The divisional officer should,
therefore, keep the following points in view.
1. That a claim, which has been accepted, is valid and that a voucher is a
complete proof of the payment which it supports and that the account is correct
in all respects.
2. It is necessary that all accounts are so kept and the details so fully recorded
that they can support any enquiry.
3. It is further necessary that the record of all transactions in general are so clear,
explicit and self-contained that it can form convincing evidence in a court of law,
if so required.
4. Every transaction involving the giving and taking of cash, stores, other
properties, rights, privileges and concessions, which have money value, should be
brought to account.
8.4 Definition of some of the terms used in accounts
1. Administrative Approval: This term denotes the formal acceptance by the
Administrative department concerned, of the proposal for incurring expenditure
in the PWD.
2. Technical sanction: It is an order by a competent authority sanctioning a
properly detailed estimate of the cost of a work to be carried out by the PWD.
3. MajorEsimate: An estimate whose sanctioned amount exceeds a certain fixed
limit is known as major estimate. In PWD this limit is fixed at Rs.1 lakh.
4. Minor estimate: An estimate whose sanctioned amount islower than a fixed
limit is known as minor estimate. In PWD this limit is fixed at Rs.1 lakh.
5. Detailed Estimate: An estimate prepared on the basis of the detailed
quantities of all items worked out from the designs and drawings is known as a
detailed estimate.
6. Petty Work: A work, which does not cost more than Rs.7500 is known as a
petty work.
7. Debit and Credit: In simple terms, ’debit’ means expenditure and ‘credit’
means a receipt.
8. Cash: The term ‘cash’ as defined in the CPWD code includes legal coins, notes,
cheques, deposit-at-call receipts of scheduled banks, drafts and payments on
demand.
8.5 Classification of Transactions and Heads of Accounts
The functions of the Government are widely varied and complex and as a result,
the financial transactions are so huge that it needs a system of identifying the various
types of financial activities of the Government to maintain the accounts and to control
the expenditure.
Basically the transactions of the Government are of two types, i.e., receipts and
expenditure. For accounts purposes, receipts and expenditure are divided into a number
of sectors. Each sector is further divided into major heads. Under each major head there
are minor heads, subheads and detailed heads. Each sector has an alphabetical series for
identification.
The last two digits indicate the major heads, the same number representing the
same major head, whether it is in the revenue receipt section, revenue expenditure
section, capital expenditure section, etc.
8.6 Payment to Labour- N.M.R. Format
Except for the regular and work charged establishments, all persons engaged
departmentally for the execution of works are considered as casual labour. Their wages
are drawn on "Muster rolls". Muster rolls are prepared in the prescribed form. The
Nominal Muster Roll (N.M.R) form consists of two parts.
Part I of N.M.R. form consists of necessary columns for entering the names of
labour, designation, father's name, their attendance particulars, rates of wages and the
total amount payable for each labour. N.M.R form has the provision for entering the
total amount of the muster, signature or left hand thumb impression of the labour as a
receipt. At the bottom of this form, the person preparing such N.M.R form should sign
before submitting to A.E / D.E.E who in turn verifies the details entered and makes the
payment.
Part II of the muster roll is used for recording the name of work, amount of work
done in cases in which the work is susceptible to measurements. Other details like the
number of measurement book, pages in which the measurements are recorded will also
be entered in this part. If the work is not susceptible to measurement, a remark to that
effect is recorded. Some important instructions regarding the preparation of Muster
rolls are:
1. Duplicate copies of muster rolls should not be prepared.
2. Separate muster rolls are prepared for each period of payment. Labour may be
paid more than once a month depending upon local conditions and practices.
3. The daily record of attendance and times should be recorded in such a way as
to leave no possibility of tampering or making unauthorized entries.
4. After the muster roll has been passed, payment should be made as early as
possible.
5. A record of wages that remains unpaid must be kept in a register of unpaid
wages.
6. Subsequent payment of unpaid wages is recorded in the hand receipt. A note
of the same is recorded in the register of unpaid wages as well as in the muster
roll.
7. Wages that remain unpaid for three months must be reported to the divisional
office.
8. Progress of work done by the labour is recorded and is to be compared with
departmental rates.
9. Muster rolls are checked with reference to entries in the measurement book to
the extent of 50% in the sub-divisional and 50% in the division office, when the
divisional engineer makes payments.
8.7 Measurement Books (M-BOOKS)
The measurement book, (common Form No. 298) is a most important record
since it is the basis of all accounts and quantities whether the work is done by daily
labour, piece work, Schedule contract, lump-sum contract or of materials received. It is
the original record of actual measurements or accounts and forms a reliable record as it
may have to be produced as evidence in court of law. All the books belonging to a
division should be numbered serially and the pages of each book should be machine
numbered. A register of M-Books should be maintained in Form PWD VI-20, in the
divisional office showing
(a) The serial number of each book,
(b) The names of sub-divisions to which issued,
(c) The date of issue and the date of its return, so that its eventual return to the
divisional office may be watched.
A similar register should be maintained in the sub divisional office showing the
names of the sub-divisional officer and section officers to whom measurement books
are issued. Books no longer in use would be withdrawn promptly even though not
completely written up. All completed measurement books containing measurements of
the works executed by contractors, having running accounts should be sent to the
Divisional Office for final record after final bills have been paid to the contractors.
1. The full description of the materials to be supplied by the Government for use
on works.
2. The place of delivery.
3. The rate including the storage rate, to be charged to the contractor for each
item.
4. The contractor shall be responsible for obtaining the items and making
payment there of at the rates specified, by deduction from bills.
5. No carriage or incidental charges are to be borne by the government beyond
the place of delivery.
The cost of material issued to the contractor for use on a work should ordinarily
be recovered by deduction from the first bill authorising payment for the work. The
divisional officer may, however, permit recovery in phases to the extent the material is
actually used in the construction at the time of payment.
Moreover stores should not be issued to contractors in bulk long before they are
atually required due to the risk of pilferage and misuse. The issue of stores to the
contractors should therefore, be regulated and restricted to the actual requirements
over a reasonable period of time.
9.12 Issue of Machinery and Equipment
Construction Machinery like road rollers, concrete mixers, vibrators, etc., can be issued
to contractors for use on works of the department. A provision for the supply of such
items is made in the notice inviting tenders and in the contract documents, clearly
indicating the rates of recovery. The recovery of charges should cover the following
1. Direct charges:
i) Running expenses, i.e., the charges that would be incurred when the machinery
is actually utilized.
ii) Maintenance charges which include
a) Supervision charges b) minor repairs
c) Special repairs d) other miscellaneous charges
2. Indirect Charges
i) Yearly depreciation, which is calculated by dividing the value of the article by
the life of the machine in years.
ii) Interest on capital investment, i.e., the cost of the machine.
iii) Departmental charges on direct charges.
When the supply of materials and equipment is envisaged in the contract, for
Government or contribution work, only the direct charges are recovered from the
contractors. When such a supply of articles is not stipulated in the contract, or when the
items are provided to commercial departments and private bodies for use on works
under their supervision, full hire charges including both the direct and indirect charges
are recovered.
9.13 Receipts
Materials are received on stock from the following sources:
1. Suppliers or Contractors: Most supplies are procured by direct purchase from
suppliers and contractors.
2. Other Subdivisions, Divisions or Departments: Supplies are obtained from
these sources when the materials available exceed their requirement.
3. Departmental Manufacture: Items like bricks, charcoal, etc., may be
manufactured departmentally.
4. Works Buildings etc.: Some items may be obtained by recovery from
works/buildings, etc. that are dismantled.
9.14 Record of Receipt of Stock
All materials, when received, must be examined and weighed, counted, or
measured, as the case may be and an entry made in the 'goods received sheets’ in Form
8-A. The goods received sheets’ are printed in booklet form in triplicate or quadruplicate
and the pages are machine numbered. These are fitted in triplicate with the help of
carbon paper. The storekeeper retains one copy and the other two are sent to the sub-
divisional officer, who passes on one of the copies to the divisional office for record and
payment.
9.15 Receipt of Machinery and Equipment
When articles of machinery and equipment are received, they should be
examined and counted. A record of these is kept in the tools and plant received sheet.
Form 13, which are prepared in triplicate. The storekeeper retains one copy and the
other two sent to the sub-divisional officer, who retains one copy for his record and
sends the other to the divisional office for making payment.
9.16 Materials at Site Account
In the case of minor works in which transactions relating to the materials at site
are not likely to be heavy, an account in form P.W.D VI-83 should be maintained of all
departmental materials brought on to the site of a work. This should clearly show the
sources and quantities of all receipts and of their issues to the work as the transactions
occur.
The detailed account of the material issued to the work is known as the
'materials-at-site account’. All departmental materials brought on to the site of work for
use on that work, from any source, should be entered as receipts in the ‘Materials-at-site
accounts’, immediately on their receipts giving a reference to the measurement book.
The register of material-at-site account should show separately for each material:
(i) The estimated requirement.
(ii) The issue rate.
(iii) Receipts, issues and balances, month to month
(iv) Net issues at the end of each month.
After completion of work, a theoretical calculation of the quantities of materials
used on each subhead is made on the basis of the magnitude of work executed. These
are recorded in Part I and Part II indicating the surplus or deficit as per actual
consumption and the theoretical calculations, together with an explanation of the
difference. Part III of the form is a statement showing the disposal of material remaining
unused as per 'Material-at-site accounts'. The unused material is disposed off in the
following manner.
(i) Transfer to stock, provided the items are serviceable and are likely to be
required for other works.
(ii) Transfer to other works in progress, if required.
(iii) Sale of the items those are no longer required.
9.17 Indent
Material should issue only on receipt of an indent, form 7 signed by the divisional
or the sub-divisional officer. These indents on stores are demands on store keeper
signed by authorised persons to issue to bearer to be charged to a particular job or
department and signified there in.
9.18 Invoice
The store keeper will prepare and sign the form of the invoice attached to the
indent according to the supply as actually made. Simultaneously an entry should be
made in the register of stock issues Form 8.
9.19 Bin Card
This is a card, which is attached to each Bin, or the container for stores a record
of all materials entering or leaving the bin and the balance of materials in hand is kept in
this card.
9.20 Stock Register
The accounts branch of the divisional office maintains day- to- day record of both
the quantity and value of transactions relating to each item of stock. Separate ledgers
are maintained for articles falling under each subhead of stock. The register has different
sets of pages for different articles. The value of items posted on ‘goods received sheet’
on the basis of bills. The ‘goods received sheets’ are then posted in the priced stores
ledger. The pages of the register are machine numbered.
9.21 Issue Rate
The issue rate is the unit rate at which the item is issued from the stock. It covers
the cost of the procurement and storage of the article. The issue rate for each article
should be fixed at the beginning of each year.