Design For Manufacturing and Assembly (DfMA)
Design For Manufacturing and Assembly (DfMA)
Manufacturing and
Assembly (DfMA)
Prefabricated Prefinished
Volumetric Construction
Contents
Chapter 1
Introduction 6
Chapter 2
PPVC Considerations and Key Factors 10
2.1 Early Involvement of Contractors
2.2 Types of PPVC Modules
2.3 Transportation
2.4 Configuration of PPVC Modules
2.5 Type of Hoisting Machinery
2.6 Comparison of Reinforced Concrete (RC) Module and Steel Module
Chapter 3
Design Considerations 18
3.1 Architectural Design Considerations
3.1.1 Modularisation
3.1.2 Early Coordination
3.1.3 Dimension on Plan
3.1.4 Dimension on Section
3.1.5 Vertical and Horizontal Alignment
3.1.6 Water-Tightness Between Modules
3.1.7 Consideration of Construction Tolerance
3.2 Structural Design Considerations
3.2.1 Structural Modelling
3.2.2 Vertical Modules Connection
3.2.3 Horizontal Modules Connection
3.2.4 Structural Robustness
3.2.5 Modules Connection to Civil Defense Shelter Wall
3.2.6 Structural Design of Modules
3.2.7 Periodic Structural Inspection (PSI)
3.3 Mechanical, Electrical and Plumbing (MEP) Design Considerations
3.3.1 Electrical
3.3.2 Lightning Protection
3.3.3 Water
3.3.4 Sanitary
3.3.5 Air-Conditioning & Mechanical Ventilation
3.3.6 Town Gas
3.4 Compliance with Fire Safety Requirements
3.4.1 Compliance of Fire Compartmentation
3.4.2 Compliance of Use of Material
Chapter 5
Protection, Transportation and Lifting 56
5.1 Transportation Plan
5.2 Packaging, Protection and Labelling
5.3 Module Cover (Temporary or Permanent)
Chapter 6
Construction and Project Management 58
6.1 Location of the Project and Adjacent Areas
6.2 Access and Traffic Management for Trailers with Heavy Cargo
6.3 Consideration of Just-In-Time (JIT) Operation
6.4 Types of Cranes
6.5 Safety
Chapter 7
Installation 62
7.1 Access and Egress
7.2 Vertical and Horizontal Alignments
7.3 Sequencing of the Modules Installation
7.4 Safety
Chapter 9
Maintenance, Replacement and Renovation 72
9.1 Renovation
9.1.1 Homeowner User Manual
Chapter 10
Regulations 74
10.1 List of Regulators
10.2 Minimum Level of Off-Site Work for PPVC
10.3 Building Innovation Panel (BIP) and PPVC Manufacturer Accreditation Scheme (MAS)
10.4 Code of Practice and Good Industry Practice Guidebooks (References)
10.5 Design for Safety
10.5.1 Access/Egress
10.5.2 Choice Between Fall Prevention, Fall Restraint and Fall Arrest System
10.5.3 Module Installation and Alignment
10.5.4 Useful Resources
Appendix
Some PPVC Projects References in Singapore (completed and ongoing)
This guide may be used for reference purposes only. The contents of this guide are protected by copyright and other
forms of proprietary rights owned by, licensed to or controlled by BCA and shall not be reproduced, republished,
uploaded, posted, transmitted or otherwise distributed in any way, without the prior written permission of BCA.
Modification of any of the contents or use of the contents for any other purpose will be a violation of BCA’s
copyright and other intellectual property rights. Any reference herein to any specific commercial products, process,
or service by trade name, trademark, manufacturer, or otherwise, does not constitute or imply BCA’s endorsement
or recommendation.
“All content used herein is for non-profit educational purposes. Where possible, all credit has been given to the
respective owners or creators of the content.”
This guide provides simple and practical tips to practitioners on how PPVC is designed, fabricated, inspected,
delivered and installed to achieve its functional requirements and workmanship standards. Good practices
such as upfront planning and design to incorporate PPVC adoption will also be covered. When constructed,
such PPVC buildings would be no different from conventional buildings and can have creative design and
interesting facades.
As this is an evolving technology, this guide is not meant to be a definitive publication on how PPVCs must
be designed and installed. Practitioners are encouraged to use this guide to innovate and improve further
on PPVC design, fabrication and installation. To obtain more comprehensive information and guidance,
readers should seek professional advice from designers and suppliers of PPVCs. We gratefully acknowledge
the contributions of key technical agencies and practitioners in the production of this guide and trust
that the industry will find this publication useful. We welcome any contributions from readers to improve
subsequent editions of this guide.
A Technical Committee, comprising members from various industry associations and organisations, was
formed to review the contents.
We wish to thank all members of the technical agencies as well as the Technical and Working Committee
for their valuable contributions.
TECHNICAL COMMITTEE:
Mr Ramamoorthy Rajendran Building and Construction Authority (Chair)
Er Siew Hoong Kit Nanyang Technological University (Co-Chair)
Ms Tay Seok Cheng REDAS (Co-Chair)
Er Chee Kheng Chye Housing and Development Board
Er Chan Ewe Jin Institute of Engineers
Mr Kenneth Loo SCAL
Ar Richard Lai Singapore Institute of Architects
Ar Yeo Eng Choon Singapore Institute of Architects
Mr Tan Chin Hock ACES
Mr Wong Soon Tuan Dragages Singapore Pte Ltd
Mr Eddie Kua Tiong Seng Contractors Pte Ltd
Mr John Mo Moderna Homes Pte Ltd
TECHNICAL AGENCIES:
Ministry of Manpower Jurong Town Corporation
Singapore Civil Defence Force Urban Redevelopment Authority
Public Utilities Board Housing and Development Board
National Environmental Agency Land Transport Authority
Introduction
To raise construction productivity and fundamentally change the design and construction processes, the
industry is encouraged to embrace the concept of Design for Manufacturing and Assembly (DfMA), where
construction is designed and detailed for a substantial portion of work to be done off-site in a controlled
manufacturing environment.
DfMA is a new approach in the construction industry. By planning more works offsite, manpower and time
needed to construct buildings are reduced, while ensuring work sites are safe, conducive and have minimal
impact on the surrounding living environment. The use of prefabrication methods in construction has been
promoted as a way to improve productivity in a traditionally manpower-intensive industry.
In this book, the DfMA methodology on PPVC and the benefits reaped will be discussed so that there
is better knowledge and capability in the adoption and implementation of PPVC.
Prefab Components Advanced Prefab Systems Integrated Sub-Assemblies Fully integrated Assemblies
Structural
Manpower Savings
(Project Level) 10% 20% 35% 40%
Architectural
Engineered
Wallpaper timber floor
On-site Dry Applied Finishes Prefinished Surfaces PBUs PPVC
Manpower Savings
(Trade Level) 30% 45% 60% 70%
MEP
Flexible Water Pipe/ Prefab Ceiling Module/ Prefab Module with PPVC
Sprinkler Dropper Prefab Plant Platform/Catwalk
Other major factors will involve logistics of transportation, site layout and holding area, crane or
hoisting position.
Material
1 2
Characteristic of module Concrete Steel
2.3 Transportation
Logistics for modules transportation from factory to site will determine the maximum size and volume of
each module design, which in turn affects the number of modules to complete the layout design.
The size of a single module should be limited to the dimensions allowed to be transported on public road
without requiring special measures such as police escort. Height consideration has to be factored in if the
route involves passing through overhead bridges.
In compliance to LTA‘s traffic regulatory requirements, Police Escort will not be required, when the
parameters are controlled.
Width
Height
The number of modules will vary, depending on the residential unit typology (Studio, 1 to 5 rooms). Total
number of modules can typically range from 1 to 8 numbers per unit.
Module A
LRDIN
Module D
KIT
Module B
B2-IBB
Module C
MB-IBB
B: B2-IBB A: LRDIN
C: MB-IBB
Module A
Bed Bed
1MA
Module B
Bed Bed
1MB Figure: Example of Woodlands Nursing Home PPVC
modules (3D View), combined to form a bedroom
3D Courtesy of Dragages (Singapore) Pte Ltd
Module C
Bed Bed
1MC
Module D
Bed Bed
1MD
Characteristic of
Crane
Tower crane Mobile crane Crawler crane
Note: Actual crane requirement and capacity shall vary according to the
site condition and to be obtained from the crane specialist accordingly.
1 2
Installation
Stacking method Stacking method
Method
Familiarity to
Renovators in
To include information of
Maintenance, Similar to conventional construction
supplier manual
Replacement /
Renovation Works
Fire
Compartmentation and use of materials
Compartmentation Similar to conventional construction
shall comply with the applicable Code
/ Rating
Provision for
Barrier-Free
Similar to conventional construction Similar to conventional construction
Accessibility
Requirements
Design Considerations
3.1 Architectural Design Considerations
3.1.1 Modularisation
• At the unit layout planning and design stage, the PPVC modularisation must be undertaken in tandem
with the unit layout design as early as possible. Early PPVC vendor’s and engineer’s involvement will be
beneficial to the project. The modularisation is largely affected by the configuration, sizes, dimensions,
weights of PPVC modules and ease of transportation.
• The weight of module in turn depends on the choice of PPVC material type, level of finishing, etc.
The transportability of modules would be influenced by the planned delivery routes (i.e. from off-site
prefabrication plants to the construction site) and types of trailers available in the industry.
Figure: Example of PPVC modularisation during planning stage (Residential Block Plan)
• Early coordination among Developer, Architect, Structural Engineer and MEP Engineer, Builder and PPVC
specialist are essential as this will allow the team to look into the key design aspects upfront including
layout design, floor and ceiling height, etc.
• With proper upfront planning to integrate PPVC into the design layout, unique designs and different
building features such as curved facade and non rectangular layout can be achieved.
• To consider the removable of non-structural partitioning wall in design for future renovation.
Length of Module
LRDIN
Width of Module
KIT
B2-IBB
Demountable non-structural
partitioning wall
MB-IBB
False ceiling
Floor slab
MODULE 1 MODULE 2
• To consider the possible misalignment of floor, wall, ceiling at joints between modules.
• To consider the interfacing details between PPVC modules and in-situ construction such as
core walls, staircases, corridors, and other portions of buildings.
LRDIN
Possible vertical /
horizontal
KIT misalignment of
floor and wall
finishes at joints
B2-IBB
between modules.
MB-IBB
Possible misalignment of
ceiling finishes at joints
between modules.
Possible misalignment of
floor and wall finishes at
joints between modules.
MODULE 1 MODULE 2
LRDIN
Vertical /
KIT horizontal
joints between
modules
B2-IBB
MB-IBB
• To consider and allow construction tolerance on vertical and horizontal joints of modules and in-situ part.
Vertical
Joint
Horizontal
Joint
The vertical modules connection is crucial for the structural behaviour especially for high rise buildings.
They have a direct effect on the building stiffness and its corresponding response under the wind, seismic
(if applicable) and lateral design action conditions. Hence, the detailing of the PPVC vertical connection
must satisfy the design intent.
Vertical joints are to be designed for eccentricity or imperfection in accordance with the Building
Code Requirement.
The horizontal modules connection forming the floor diaphragm, are equally important, contributing to
the overall building stiffness. In particular, the peripheral ties and internal ties shall be provided as per
the Building Code Requirements. The PPVC modules and layout shall be laterally connected and designed
such that the horizontal forces (e.g. wind load) can effectively be transferred to the building’s lateral load
resisting system.
Due to the repetitions, and as far as practicable, the horizontal joints should be designed in a manner that
the implementation at site would be speedy and simple. A classic example for steel PPVC module joints is
the bolting system, whereas in concrete PPVC on-site grouting of joints is common.
The design of PPVC building shall give due consideration to the scenario of sustaining an extent of localised
failure without disproportionate collapse. The inter-connected volumetric system must be capable of
redistributing the internal forces to the nearest load bearing elements such that progressive collapse is
totally prevented.
Provisions for structural robustness may involve providing effective horizontal and vertical ties, notional
removal of one column / nominal section of wall or designing such elements as a “key element” or systematic
risk assessment in accordance with the building’s Categorisation of Consequences Classes as per relevant
EN 1991-1-7 provisions.
It is mandatory for residential building projects to incorporate either Household Shelters (HS), Storey
Shelters (SS) or Staircase Storey Shelters (SSS) as Civil Defence (CD) Shelter. In situation where PPVC
modules are abutting the CD shelter, effective connection for load transfer between the abutting PPVC
modules and CD shelter walls at each storey level is to be provided. The connection details should take into
account the construction sequence of shelter walls, launching of precast staircase flights (for SSS), casting
of shelter floor slab and installation of abutting PPVC module(s), hollow cores formed in the precast hollow
core shelter walls, as well as the installation of steel reinforcement cages inside the hollow cores at site.
PPVC Modules
In addition to the normal elemental design under the permanent design actions, it is necessary to carry
out structural analysis of transient design situation (e.g. during handling in the prefabrication plant) to the
PPVC modules considering the designated lifting points during hoisting and erection. Serviceability limit
checks should be performed to prevent cracks to the concrete slab, walls or steel frame distortion during
handling and transporting.
The lifting points must be strategically positioned such that sufficient bond anchorage can be developed
to hoist the entire module safely and that the load distribution to all lifting points is reasonably uniform. It
is a good practice to hoist PPVC module with the aid of steel collar frame so that the module would not be
subject to inclined forces from the lifting wires.
Broadly there are two types of framing system for concrete PPVC modules, namely:
a. Beam-Column system, in which the beam profiles may be visible without false ceiling.
b. Slab-Shear wall system, in which no beam is required for the module framing
Lifting Hooks
Lifting Collar Frame
Periodic Structural Inspection (PSI) is a requirement for all buildings, be it steel or concrete. However, for
Steel PPVC modules, there is an additional access panels with inspection points required to conduct the
inspection on critical structures such as steel beams and column joints. These inspection points and the
proposed inspection methodologies shall be identified at the onset and be included in the structural plans
for fabrication and for authority submission.
To minimise the inconvenience to the building occupiers when the Structural Inspector conducts the
inspection in future, these inspection points shall be strategically planned and located at areas that are
discreet such as balconies, ac ledges, kitchens or common corridors.
Photographs Courtesy of Surbana Jurong Pte Ltd and Moderna Homes Pte Ltd
Sanitary discharge
Refrigerant
pipe for air-
conditioning
PLAN
PPVC
MODULE 1
Penetration between PPVC modules
Junction box
PPVC
MODULE 2
PPVC
MODULE 1
UPPER
PPVC Hot / Cold
MODULE water supply
pipe
Penetration
between
Lightning modules
conductor
PPVC
MODULE 2
LOWER
PPVC
MODULE
• All sanitary discharge pipes and ventilating pipes shall be laid in accordance with PUB and Code of
Practice requirements.
• All gravity discharge pipes shall have suitable gradient to maintain self-cleansing velocity to ensure
smooth flow.
• All joints of pipes shall be tested to ensure water-tightness and air-tightness.
• Shallow floor trap shall be of the suitable type and comply with the performance standards prescribed by
PUB. For shallow floor trap requirements, please refer to Code of Practice on Sewerage and Sanitary Work.
• Shallow floor trap shall not be used if there are connections from kitchen sink or dishwasher.
• To consider potential slab thickening factor for use of shallow floor trap (subject to regulatory compliance
and approval), including impact on weight, transportation and storage requirements.
• Proper protection to all protruding and exposed pipeworks from mechanical damage during transportation,
storage and shifting of modules.
• To protect pre-installed pipeworks from heat, ultra-violet radiation and other possible detrimental factors.
• Concealed components embedded in structural elements shall be taken into consideration for structural
strength design.
• To ensure suitable access and working space provided for pipe connection between modules.
• Method for future repairing works for clogging or leakage shall be taken into consideration in the design.
• To consider mounting type of WC (floor-mounted or wall-mounted).
• Connection of air-conditioning components including refrigerant pipe, condensate drain pipe, respective
insulation layer, and wiring.
• Joints of refrigerant pipe, if required, shall be able to withstand operating pressure and not be
eroded easily.
• Maintenance and repairing measures shall be taken into consideration.
• Connection of mechanical ventilation components including mechanical fan, air-duct and wiring.
• Inspection and replacement access for equipment such as mechanical fan shall be reserved.
Fan Coil
Unit (FCU)
Condensate
Drain
discharge
to Floor
Trap (FT)
• Connection of town gas supply shall be able to withstand town gas supply pressure and free from leakage.
• Joints shall be treated as necessary to prevent corrosion.
• Concealment, if any, shall be subject to regulatory approval.
• To comply with fire resistance rating required for the elements of structure of the building.
• The typical compartment floor between floor levels shall comply with the required fire resistance rating in
accordance with the Fire Code requirements for the compartment floor which is an element of structure.
• The compartment walls segregating the dwelling units as well as segregating the dwelling units and
fire fighting lobby shall comply with the required fire resistance rating in accordance with the Fire
Code requirements.
• Provision of documentary proofs and detail drawings to illustrate compliance of Fire Code requirements
of the proposed system in terms of compartmentation, material usage, etc. is required.
Compartment wall
segregating dwelling units
Moulds are fabricated in steel with comprehensive design to withstand the handling and production
process for the lifetime required in production. These moulds are three-dimensional and may be adjusted
to cater for several combinations of dimensions. The factors that influence the concept of mould design are
as follows:
Mould design
1
(Adjustable Mould)
Mould fabrication
2
Reinforced Concrete modules can be produced by integrating structures like column, beam, wall and slab as
a single module. The production process comprises of the following steps:
The architectural works shall be executed under the sheltered environment, by trained specific trades off-
site. The works shall comprise the following in the sequence of execution and on levelled platform.
MEP Installations
Wall Tiling
Cabinets
Sanitary Fixtures
Waterproofing and
Floor Tiling
Window Switches Wall Plastering Door
and Glazing and Power or Skim Coat Frame
Installation Points
False Ceiling
Railing Installation
Wardrobe
MEP installation
3
Installation of wardrobe
14
Installation of cabinets
15
Painting works
19
Whenever possible, customised welding robots could be used in place of manual welding to reduce the
reliance on manpower and to increase productivity.
The jigs used in the fabrication work are designed and fabricated to withstand additional force caused by
heat transmitted between and within the steel sections to ensure the accuracy of the 2D frame and 3D shell
remain unchanged during and after welding work.
The total number of jigs required for each project is determined by the design and type of modules, the
fabrication schedule/rate and the flexibility of the jigs. It is different from project to project.
Overseas Factory
ICA Checkpoint
Delivery to Site
for Installation
Temporary safety
railings
Temporary or
permanent roofing
Completed module
6.2 Access and Traffic Management for Trailers with Heavy Cargo
• The access to and within the site must be able to accommodate trailers with heavy cargo. Slopes and
undulating terrain might prove to be a challenge for heavy vehicles. The turning radiuses of the trailers
has to be considered during the planning stage of the site to avoid choking of vehicle access.
• Trailers with heavy cargo pose potential hazards upon entering while navigating the site. Traffic controller
has to be employed to ensure smooth traffic management within the site.
A comprehensive risk assessment shall be A comprehensive Fall Prevention Plan with Safe
established to identify all potential hazards. Work Procedure and appropriate control measures
Appropriate control measures must then be set have to be established. Control measures such as
up, communicated and implemented before the safety barricades shall be provided for all open
commencement of works. sides where a person may fall. Such barricades
can only be removed during installation when
the precast component is hoisted near its
designated position.
All workers who are carrying out work at height All lifting gears and equipment are to be
shall be provided with the appropriate Personal in serviceable condition. Checks have to be
Protective Equipment such as a personal fall arrest conducted by Accredited Checkers periodically
system. They shall be trained in the proper use of to ensure workers are working with safe and
the system and ensure that the system is in place functional equipment.
at all times.
Installation
7.1 Access and Egress
• An access has to be provided for workers to move in and out during an installation. Any open area
will have to be covered with safety barricade to prevent any worker from falling from height. A clearly
demarcated egress has to be provided as well to allow workers to exit the work area in the case of
an emergency.
• For MEP services that require installation works horizontally crossing modules, (including wiring,
pressurized pipeworks, gradient pipeworks), the method of connection, if required, shall not compromise
the level of continuity. All point of connections shall be properly secured by proper support. Method of
connections shall not compromise the gradient required for gradient-pipeworks. Proper protection to
finishes to be provided if hot work is required for connections. Installation works shall be done via the
space allocated for installation works.
7.4 Safety
• Workers are prone to high-risk activities such as Lifting Operation and Fall from Height. Proper safety
equipments are be provided to ensure the well being of the workers are taken care of.
• Safety documents such as Risk Assessment and Safe Work Procedure are to be submitted and vetted
thoroughly by the site safety officer. Safety Instruments are to be checked regularly. Daily Permit to work
has to be submitted dutifully to ensure workers work in a safe environment.
QC inspection on concrete
Casting
remain within the tolerance its verticality not greater than the elements, as this will decrease
limits. stipulated tolerance for PPVC. the stability of the structures.
water-tight before and after the pressurised pipe works. cable and wiring condition.
architectural finishing works.
LEVELLING
To ensure that the module is levelled and set before
the start of the finishing works.
SPRAY TEST
Shall comply with the approved method statement.
Figure: WC Installation
Besides engaging a trained renovation contractor, homeowners should have a ready reference of the PPVC
system used in the unit. It is good practice for developers/builders to provide a homeowner user manual
of the PPVC upon completion of the project. The homeowner and subsequent buyers of the unit should
obtain a copy of the homeowner user manual after taking over the unit and follow the recommendations
on maintenance and renovation to PPVC units provided in the manual.
The information in the homeowner user manual could include (but not limited to) the following:
Regulations
10.1 List of Regulators
Fire Safety Act and Regulation ”Code of Practice for Fire Safety
Precaution in Buildings”
Singapore Civil
Fire Safety Requirements for the use of Plastic in Building
3 Defence Force
Construction, SCDF’s circular dated 1 Oct 2014.
(SCDF)
Permitting Services within Fire-Rated Dry Construction in Buildings,
SCDF’s circular dated 13 Nov 2014.
Code of Practice on Environmental Health, Singapore Standard SS593,
National COP on Pollution Control, Code of Practice on Sewerage and Sanitary
4 Environment Agency Works, Environmental Protection and Management Act, and their
(NEA) Regulations, including the Environmental Protection and Management
(Control of Noise at Construction Site) Regulation
Singapore Standard CP 48: Code of Practice for Water Services
1. Sewerage and Drainage Act
2. Sewerage and Drainage (Sanitary Works) Regulations
3. Code of Practice on Sewerage and Sanitary Works
4. Code of Practice on Surface Water Drainage
5. Public Utilities (Water Supply) Regulations
BS EN 1253-1, in event, if client preferences for shallow floor trap
Public Utilities (SFT) all relevant test shall comply with BS EN 1253-1 as follows:
5
Board (PUB) 1. Anti-Blockage Test
2. Water Tightness Test
3. Flow Rate Test
4. Resistance to water seal to pressure
5. Odour Tightness Test
6. Depth of water seal
7. Access for Cleaning
8. Side Inlet
Workplace Safety And Health Act 2014
Ministry of
6 WSH (Exemption) Order 2011
Manpower (MOM)
Workplace Safety and Health (Design for Safety) Regulation 2015
MEP including water and sanitary pipes, 100%, only equipment to allowed
electrical conduits and ducting for on-site installation
Things to note:
• For onsite installation, please pay special attention to activities related to Lifting, Access/Egress and
Working at Height.
• The design should cater adequate provisions for safe PPVC building maintenance and repair.
• User/ installer manual should include safe demolition sequences and special precautions.
• PPVC suppliers/ designers shall control the design risks based on the Hierarchy of Control Measures.
PPE shall be adopted as a last resort.
10.5.1 Access/Egress
As part of the design review, the entire process of which the PPVC units are to be installed should be
reviewed. This should include how workers would gain access to and egress:
1. from the ground to the top of the modules loaded on a trailer;
2. from the ground to the top of the modules in the holding/ storage area;
3. from the working level to the top of a PPVC module that had just been installed;
4. from point A to point B of the same level of the installed PPVCs, or cast in-situ areas or working platforms.
5. from point A to point B of the different level of the installed PPVCs, or cast in-situ areas or
working platforms.
Such access provisions include the use of MEWP, mobile tower scaffolds with appropriate height, fixed
ladders with proper fixtures that are cast-in during the fabrication of the modules or use of permanent/
temporary staircase. If a vertical access ladder (see figure 2) is proposed, it should be secured in place at
its top & bottom and extended 1 meter above the landing. Such ladder will not be suitable if the user is
unable to maintain 3-points of contact. In general, a step platform ladder (see figure 3) would provide a
safer access and more stable work surface than the vertical access ladder or A-frame ladder. If the ladder
leads to a barricaded area, a proper access point should be catered for in the design.
(Fig. 2) vertical access ladder with both stiles tied. (Fig. 3) Step platform ladder (Mobile).
Before choosing a fall prevention or protection system, one should first consider elimination of working
at height.
Fall Restraint Systems prevent a person from falling and includes the use of:
i) Work-Positioning and
ii) Travel Restraint systems
Fall Arrest Systems protect a person after the person falls a certain distance by stopping the fall before the
person hit the surface below. It includes the use of:
i) Full body harness, shock absorber and Anchor
ii) Safety nets
Please also refer to the prevailing codes including SS 570, S541 and SS607.
During the PPVC installation, it is important to avoid the need to align too many connecting bars as this
will increase the installation duration and the likelihood of installers being exposed to risks of crushing
and being caught-in-between objects. In the event of misalignment/ bent bars, there should be established
measures to ensure no worker shall go underneath the PPVC unit to realign the bars.
WSH Council’s Website MOM’s Website WSHC-Approved COP WSH Act and
Regulations