This document is a typical inspection plan for a powered in-plant communication systems project in Saudi Aramco. It outlines 8 items to be inspected during various project phases, including receiving inspections for cable and equipment. Inspections include visual checks and testing of materials according to various quality procedures. Responsibilities are assigned to both the contractor and Saudi Aramco personnel.

Uploaded by

sajid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
239 views

SATIP-T-481-01 Rev 7

This document is a typical inspection plan for a powered in-plant communication systems project in Saudi Aramco. It outlines 8 items to be inspected during various project phases, including receiving inspections for cable and equipment. Inspections include visual checks and testing of materials according to various quality procedures. Responsibilities are assigned to both the contractor and Saudi Aramco personnel.

Uploaded by

sajid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Powered In-Plant Communication Systems SATIP-T-481-01 30-Apr-13 Telecommunications
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

DOCUMENT
1.0
REVIEW
Cable and Conduit Seal SAIC-P- To be reviewed and approved prior to public address
1.1
Installation Procedure
SAIC-P-3004
3004 RH R system work at jobsite.
RECEIVING
2.0
INSPECTION

Storage, Handling, and Preservation


2.1 Visual Inspection and Testing SAIC-T-5001 SAIC-T-5001 W S Weekly inspection by Contractor QC
Electronic Equipment

Storage, Handling, and Preservation


SAIC-P-
2.2 Visual Inspection and Testing SAIC-P-3002
3002 W S Weekly inspection by Contractor QC
Electrical Equipment

Cable Material Receiving


Visual Inspection
2.3
Manufacturer's Page-Party
SAIC-T-5201 SAIC-T-5201 H W
Power Cable MR

Cable Material Receiving


2.4 Visual Inspection SAIC-T-5202 SAIC-T-5202 H W
Manufacturer's Speaker Cable MR

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.5
Visual Inspection
SAIC-T-5203 SAIC-T-5203 H W
Speaker SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.6
Visual Inspection
SAIC-T-5204 SAIC-T-5204 H W
Page-Party Station - Indoor SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Page 1 of 4
04/04/2018 17:25:17
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Powered In-Plant Communication Systems SATIP-T-481-01 30-Apr-13 Telecommunications
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.7
Visual Inspection
SAIC-T-5205 SAIC-T-5205 H W
Page-Party Station - Outdoor SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.8
Visual Inspection
SAIC-T-5206 SAIC-T-5206 H W
Speaker Amplifier SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.9
Visual Inspection
SAIC-T-5207 SAIC-T-5207 H W
Line Balance Assembly SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Accessories include telephone interfaces, tone and


Communications Equipment speech alarm generators, radio interfaces, and
Material Receiving acoustic hoods.
2.10
Visual Inspection
SAIC-T-5208 SAIC-T-5208 H W
Page-Party Accessories SA PID shall be notified on delivery of each Item. (by
type or manufacturer)

Cable Acceptance Testing See See


2.11 See SATIP-P-104-01 LV Cable
(On Cable Reel) Remarks Remarks

Page 2 of 4
04/04/2018 17:25:18
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Powered In-Plant Communication Systems SATIP-T-481-01 30-Apr-13 Telecommunications
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

3.0 INSTALLATION

Communications Equipment
SA PID shall be notified on start of this activity for each
3.1 Installation and Identification SAIC-T-5209 SAIC-T-5209 H W plant area.
Visual Inspection

SATIP-P-104-03 Cable Tray


SATIP-P-104-05 A/G Conduit
Conduit / Cable Tray SATIP-P-104-07 B/G Conduit
See See
3.2 Installation & Identification SATIP-P-104-04 Boxes and Wireways
Remarks Remarks
Visual Inspection SATIP-P-111-01 Grounding / Bonding
as applicable. SA PID shall be notified on start of this
activity for each plant area.

SATIP-P-104-01 LV Cable
Cable Pulling / Laying See See SATIP-P-111-01 Grounding & Bonding
3.3
Visual Inspection Remarks Remarks SA PID shall be notified on start of this activity for each
plant area.

SATIP-P-104-01 LV Cable
Cable Gland Installation,
See See SATIP-P-111-01 Grounding & Bonding
3.4 Cable Dressing, Identification, &
Remarks Remarks SA PID to be notified on start of this activity for each
Termination Visual Inspection
plant area.

4.0 PRE-COMMISSIONING

SATIP-P-104-01 LV Cable
Cable Continuity
See See In accordance with manufacturer's instructions. SA
4.1 and Insulation Resistance Testing
Remarks Remarks PID to be notified on start of this activity for each plant
(Installed Cable)
area.

SATIP-P-104-01 LV Cable
Cable Termination See See In accordance with manufacturer's instructions. SA
4.2
Torque Testing Remarks Remarks PID to be notified on start of this activity for each plant
area.

Page 3 of 4
04/04/2018 17:25:18
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 7 COS 03/31/2013
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Powered In-Plant Communication Systems SATIP-T-481-01 30-Apr-13 Telecommunications
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Cable / Conduit
SAIC-P-
4.3 Hazardous Location Sealing SAIC-P-3209
3209 H H Hold point for fiber damming & cement pouring
(where applicable)

Final Visual Inspection See


4.4
(for Energization Certificate) Remarks
EIL H H Review All Associated Quality Records

Quality Document Review Energization


4.5
and Energization Certificate
EIL
Certificate RH RH Review EIL and All Associated Quality Records

Final Visual Inspection See


4.6
for Mechanical Completion Certificate Remarks
FEIL H H Review All Associated Quality Records

Quality Document Review and PMCC


4.7
Mechanical Completion Certificate
FEIL
MCC RH RH Review FEIL and All Assocated Quality Records

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1
adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection