Project Development and Construction Management
Project Development and Construction Management
J Luxford1
1. engaging a project management or engineering, procurement contractors and the issues and most importantly, knowing
and construction management (EPCM) contractor to manage what the contractors are, and conversely are not entitled to
all of the engineering, procurement, and construction; contractually; and
2. dividing the project into areas, with some managed by the • mining project management – knowing how to plan and
owner’s team and other areas managed by an EPCM manage mining projects, especially the eternal triangle of
contractor; or time, cost and quality.
3. managing the entire EPCM process with the owner’s team. Critical situations will inevitably arise where the project
manager must bring all three of the above skill sets to bear in
The EPCM option is currently the most common project order to make effective decisions that minimise the:
implementation approach taken by major mining companies in
Australia. • time and costs of delays,
According to Manchanda (2006), Newcrest took the Option 2 • risks of contractual disputation, and
approach recently with the construction of the Telfer project. The • risks of compromising the quality expected of the project.
Telfer project involved a very large process plant which was
In situations where the project manager lacks skills and
managed by an EPCM contractor while Newcrest managed the
experience in one or more of these critical areas, it is vital that
mine development and various infrastructure packages.
appropriate support and coaching is available to the project
The best example of Option 3 was Placer Development who manager. If this support is not available when needed, the
developed one of the best ‘in house’ major mining project probability of time and cost overruns are very high.
development teams that the author is aware of. This team
managed all aspects of Placer’s project development around the In addition to the above management, technical and practical
world over a long period of time and had one of the best records skills, there are a wide range of ‘people management’ skills and
in the industry for delivering projects on time and budget. attributes that a project manager must possess. These will
normally develop as a successful manager progresses through
BHP Billiton’s Cannington mine development project in the
operational and project management roles.
late 1990s is another example of the Option 3 approach. In this
case, there were separate teams managing the underground mine The author observed one particular mine development project
development and the surface construction areas, albeit with where the project manager came from a project engineering
teams comprised of individuals or small teams on contract to background with no experience in, or understanding of, mine
Cannington. development. When geotechnical problems arose, they were not
In the past, most Australian mining companies managed their effectively dealt with, which resulted in years of litigation.
mining projects with their own salaried employees. The current
trend is for mining companies to employ the project director as a Selecting the project owner’s team
salaried staff member and also the statutory mine manager if it is The project owner’s team members may be employed or
a mine development project. Other than these key positions, contracted directly by the mining company or through a labour
many of the other key project team roles will be filled by hire company or a project management or engineering service
specialists from outside the mining company. providing company. If the project does not have a mining
component and only involves civil, mechanical and electrical
Creating the owner’s team work, the entire project team, except for the project director, may
be provided by a specialist project management company.
There are a number of common threads in all the successful
projects observed by the author over time. They all revolve Requirements for project team selection include:
around people and include: • knowledge and experience in what is to be designed and built,
• a strong project director, or project managers reporting to the • demonstrated track record in similar projects,
director, with extensive project management experience who • honesty and integrity,
understand what is being designed and constructed and
provide effective leadership to the project; • intellectual and practical ability, and
• simple team structures and clear authority and accountability • ability to work well in a team.
for all team members; While many project management texts specify an extensive
• competent engineers and supervisors on both the mining range of criteria that team members should possess and how they
company’s and the contractors’ teams; and should be recruited, the reality is that many successful project
• good working relationships based on mutual respect and trust managers have a loyal team that follow the manager from one
between the project team and the contractors to the project. project to the next. While the individuals within this team may
sometimes not be of the highest calibre, they have collectively
demonstrated over time that they can work together to
Selecting a project manager successfully deliver projects.
Anyone who manages major mine development and construction
projects, especially in the underground environment, will be Owner’s team size
called up to exercise judgment in the following areas:
The owner’s team size required to successfully deliver a mining
• mining and mine management – knowing how things get project will vary with the size of the owner and the project. Large
done in the mining environment, understanding the culture, mining companies can sometimes create large project
knowing what can go wrong, especially in the geotechnical, management bureaucracies that impede rather than assist project
groundwater and ventilation areas and especially management. Conversely, companies of all sizes can fall into the
understanding the safety and statutory requirements, issues trap of under-resourcing project management teams. This is most
and how to manage them; often seen in the management of mine development projects,
• contract administration – knowing how both mining and especially single entry declines where the owner’s team may
construction contractors work in the mining environment, the consist of as few as one engineer and a clerk. The author visited
issues they face and how to manage the relationship with the one major overseas underground mining project where the
owner’s team managing the mine development project consisted While most of the front end loading process occurs within the
of a manager and a contracts engineer. That particular project feasibility study process, it culminates with the project execution
subsequently experienced major cost and time overruns and plan (PEP). The PEP links all aspects of project implementation
quality management problems. together in one document that explains how the project scope,
While there is no hard and fast rule for the optimum size of an specifications, budgets and schedules will be delivered without
owner’s project management team, it must have sufficient harm to people or the environment.
members to address the following issues: The PEP is the ‘what, why, how, when and who’ of the project
• work planning and budgeting; that explains to those outside the project team how the project
will be managed. Owner’s team members must be able to refer to
• tender preparation and contract awarding; it and understand the performance requirements, what they need
• scope, cost, time and quality control; to do and how their role supports the overall team objectives.
• reporting at all levels; A typical PEP would address the following issues:
• engineering management; • project objectives;
• construction supervision; and • user requirements specification;
• safety and risk management. • definitive estimate that includes:
An EPCM contractor, when employed, will have direct • scope of work;
contractual responsibility for these functions. However, the • work breakdown structure;
owner’s team must still possess sufficient resources to adequately • schedule;
monitor the functions in order to ensure that the project is on
time and budget. • budget;
• procurement;
Need for a separate team on brownfields projects • logistics;
Owners occasionally fall into the trap of using their operational • contract administration;
managers to manage projects in addition to their ongoing • licenses, permits and approvals;
production responsibilities. The author can vouch from personal
experience that this approach is fraught with danger. The reality • organisation charts for the owner’s team and contractors;
is that, despite what ever edicts come down from top • authority levels for owner’s team members;
management, production will always come before project work. • position descriptions for owner’s team members;
Therefore, it is far safer to establish a separate team dedicated to
managing the project and provide them with their own labour • contractors project management plans;
and equipment resources with which to execute the project. • engineering and constructability;
• construction;
Single point accountability • commissioning;
Owners must ensure that one person is accountable for the • project controls:
direction of the project. This person should then be responsible
for decisions on implementation and fulfilling the submission • quality assurance (QA);
promises upon which the project was approved in the first place. • scope, cost and schedule;
When accountabilities and responsibilities are not clear, it is very • change management;
likely that important tasks will be overlooked – with costly
consequences to the project. • document control;
• progress reporting;
Continuity of key people • key performance indicators (KPIs);
Continuity of key people is an important factor in successful • temporary facilities;
mining projects, preferably with involvement in both the study • health, safety, environment and community relations (HSEC);
and implementation phases. Where turnover in key project staff
occurs, projects can be disrupted while new people take time to • site security;
understand the project. Sometimes, when a project is in • risk management;
difficulty, changing direction is necessary. However, unless the • insurances;
change in direction is carefully managed, more problems and
delays can be created that far outweigh the originally intended • external relations management;
saving. • financial administration;
• project review and auditing; and
Front end loading by creating the project • project close-out (the end).
execution plan
Each of these topics within the PEP would address or
Front end loading is the process of scope definition and planning reference the following documents as appropriate:
carried out prior to commencing the project implementation
• board approval conditions,
phase. The period prior to implementation is when the greatest
influence can be made upon, and benefit received from, • feasibility study,
optimising the strategy for executing the project and the • company project standards,
associated plan and schedule for delivering this strategy. Once
project implementation has commenced and contractors have
• company HSEC policies and procedures, and
been mobilised, changes become very costly. • detailed execution plans and procedures to be adopted.
• general arrangement drawings, expended plus fixed overheads and margins. In boom conditions
when contractors are in great demand, cost plus arrangements
• detailed drawings, tend to be used widely.
• bills of material,
• standard and detailed specifications, Fixed price
• risk assessments, Fixed price contracts are used for equipment supply and may be
• hazard and operability studies, used for plant construction where the owner provides the design
if contractors are willing to tender on that basis. Many owners
• hazard analysis studies, are finding that contractors will not bid for construction work on
• as-built drawings, and fixed prices and will only accept cost plus arrangements.
• maintenance manuals.
Schedule of rates
Project – operations interface Schedule of rates contracts were the most frequently used form
It is the owner’s team’s responsibility to ensure that all interested of contract for surface and underground mining prior to the
parties, ie, operations personnel, area project managers, etc are current boom. As with construction contracting in the current
involved in the design process throughout the various phases of boom, mining contractors are increasingly unwilling to enter into
concept, prefeasibility and feasibility. This input for operability fixed prices or schedule of rates contracts.
should be downgraded at the completion of the feasibility study
and should not be allowed to continue into the project Contracting strategy and management
implementation phase as this may lead to serious time and cost
The contracting plan prepared as part of the project execution plan
overruns on the project.
will have detailed the contractual strategies and structures to be
employed to deliver the project. In particular, it will have defined
PROCUREMENT AND CONTRACTING the scope of work for the owner, implementation contractor(s),
vendors, construction contractors, and the contractual and
Contracting options commercial interrelationships between each participant.
Within the project delivery strategies previously discussed, there The contracting plan must take account of the following
are a range of options available to both EPCM contractors and project aspects:
owners for procuring individual parts of a major project. The • scope of work for the project and identifiable work packages;
most popular options are described below. • level of accuracy of the design criteria and existing engineering
information;
Build, own and operate (BOO) and transfer (BOOT)
• overall risk profile of the project;
The supplier totally funds, designs, constructs, commissions and • key commercial terms that are important to the owner (eg
operates the asset. In BOO contracts, the supplier retains lump sum, cost reimbursable, unit rates, indemnities and
ownership of the asset and in BOOT contracts, the supplier warranties, performance testing);
typically will own and operate the asset for ten to 20 years then
transfer title to the owner. Such contracts are usually based on • time frame for the project and the need for ‘overlap’ between
take or pay for the product. This arrangement has been used for engineering, procurement, construction and commissioning;
power stations on remote mine sites with payment based on unit • method required to finance the project during the execution
rates for electricity supplied. and operations phases; and
• skills and experience of the owner’s team (eg managing
Turnkey interfaces).
The implementation contractor provides total process and At a detailed level, the contracting plan must specify criteria to
engineering design, construction and commissioning of the guide the owner’s team in deciding whether commitments should
project to requirements specified by the owner. This arrangement be made by way of:
has been used for process plants where the process risk is low. To • purchase orders,
the author’s knowledge, it has only been used once for the
delivery of a base metals mine and process plant. The contractor • services agreements,
is paid a fixed amount subject to satisfactorily completing • formal contracts for:
performance tests. • equipment supply,
Engineering procurement and construction (EPC) or • equipment supply and install, and
design and construct (D&C) • construction or mine development.
EPC and D&C contracts are similar in that the owner provides If the owner does not have company standards for each of
the process design and the implementation contractor undertakes these documents, then the owner’s team must compile them prior
the design, procurement and construction of the project. The to commencing project implementation, along with defining the
contractor is paid a fixed price progressively for work completed; criteria under which each will be used.
with final payment on satisfactory completion of performance
tests. Risk allocation
Allocating contractual risk between the owner and the
Cost plus – partnering and alliancing contractors has been a difficult task for many projects – which is
The contractor provides some or all services required to deliver reflected in contractual disputes. Owners are well advised not
the project and is paid for all personnel and equipment hours place contractual risk on a contractor unless they are sure that:
In the case of underground mine development and construction • civil work – cubic metes poured, and
projects, the process involves stepping through the mine
development and construction program week by week to identify • mechanical and electrical work – incremental milestones.
conflicting activities, flaws in the mine design, problems with It is vital that these activities are tracked on a regular basis,
drainage, ventilation or vehicle movements and any other usually weekly, and that the overall project schedules are updated
constructability issues. When done properly, this process monthly so that any slippage in completion dates can be
minimises the likelihood of encountering unexpected problems identified and corrective action implemented. The great danger
during the project which would otherwise cause delay and extra in this process is using subjective assessments of progress based
cost. The same process is equally applicable to other forms of on ‘gut feel’. Hard verifiable physical quantities or deliverables
construction projects. must be used to input actual progress to the schedule updates.
Major underground mine development projects may involve Underground mine development is notoriously difficult to
the development of say ten levels, several shafts, numerous bored accurately and realistically schedule: usually because of the
raises for ventilation and ladderways, multiple service and assumptions made or the tools used to update the schedule. In the
drainage hole networks and major excavations for ore crushing author’s experience, once the baseline schedule has been
and handling, workshops, pump stations, etc along with the optimised, the schedule is then best tracked in a spreadsheet that
construction of infrastructure in those excavations. Mine is manually updated with actual advances each week.
production activities may be commencing at the same time. With In addition to tracking actual against forecast progress in
all this activity, very detailed planning and scheduling is critical spreadsheets, it is very useful to plot lateral development advance
to establishing realistic baseline schedules and budgets that can cut by cut on large scale wall plans in a central part of the site
be used to control the project. project office. Lateral development is the one activity over all
The recent development of powerful, user-friendly 3D mine else that will determine whether or not a project finishes on time
planning and mine scheduling software has made the mine and budget because everything else is usually dependent upon it.
development scheduling process much faster, but has not reduced Scheduling is probably the most difficult and poorly executed
the need for careful analysis of all the interactions and issues task undertaken by projects, especially underground mining
mentioned above. projects. It is critical that the project manager pays particular
There are a number of powerful scheduling packages available attention to the schedule and drives key staff to familiarise
for developing the detailed project construction schedules, to themselves with, and contribute to the schedule development.
which the mine development schedules can be linked. These
scheduling tools allow all the resources required for the project Cost forecasting and control
activities to be included – from which they can generate detailed
The forecasting component of the cost control process is to
cost estimates for every aspect of the project.
regularly recalculate the final cost of each activity and of the
total project. This will allow corrective action to be taken in a
Scope control timely manner should it become apparent that costs are
The first step in the planning process was to define the scope and increasing above what has been approved for the project.
it is also the first vital step in the project control process. The cost control component involves controlling commitments
It is important to ensure that both the schedule and budget for by ensuring they do not deviate from what has been approved for
each activity incorporated into the project baseline control that activity, purchase or contract relating to the commitment.
document include contingency appropriate to the amount of It is vital for cost control to employ project orientated cost
engineering completed for that activity. Following compilation of control software rather than the common financial accounting
the baseline, it is then important to ensure that engineering is systems used by mining companies. The dedicated project
then sufficiently advanced prior to commencing that activity to control systems used by the construction industry allow
ensure that the scope is adequately fixed. If there is insufficient commitments to be tracked and costs to be related to project
contingency to start with or the scope is not fixed prior to activities. These systems are well integrated with the project
commencing work, then overruns are likely. schedules and budgets and link all components into the project
reporting process.
Once the project is underway, it will be a constant challenge to
prevent scope creep. Typical examples are metallurgists looking Escalation is one element of cost forecasting that has not been
for more bells and whistles in the process plant or mining an issue in the low inflation environment applying prior to the
engineers adding more excavations to the mine design. Scope current boom. However, it is now rapidly increasing and must be
creep can be prevented by implementing a strict change control considered separately to contingency when setting project base
process where the scope cannot be altered without formal line budgets. It will be a matter of judgement at the time as to
approval from the project manager. The project baseline should what is allowed. The author has heard anecdotally that some
then be updated with approved scope changes. projects are currently experiencing annual rates of ten to 15 per
cent escalation.
Schedule control
Progress reporting
Controlling time, ie the schedule, is the single most important
thing a project manager can do to bring a mining project in on Mining projects will usually issue daily, weekly and monthly
time and budget. In the author’s experience over numerous mine progress reports. Daily reports are one page documents
development and construction projects, if time is controlled then summarising safety and physical performance numbers.
costs will usually be within budget. Ongoing schedule control over Weekly reports will include the key performance data along
the course of a project is based on tracking actual physical with explanations and comments on progress, major issues,
quantities of work achieved on a weekly basis against the baseline highlights and a look ahead for the following week.
schedule. Typical physical quantities to be tracked may be:
The monthly report will be a comprehensive document
• mine development – linear metres, including sections on all key areas of the project summarising
• vertical development – linear metres, progress to date together with deviations from budget, issues,
concerns and corrective actions and a look ahead to the next
• major excavations – cubic metres, month. In addition to tables that summarise key data, the
• pipelines – linear metres, monthly report will include a range of S curves that graphically
depict committed and actual costs and progress to date against The construction phase involves managing:
their baseline budgets and schedules. • planning, scheduling and reporting;
The project reporting process must ensure that:
• safety and security;
• there are no surprises,
• QA non-conformances;
• the current status is validated,
• site establishment;
• trends are explained, and
• construction execution;
• final costs and completion date forecasts are updated.
• cost control and reporting;
Contingency • procurement and logistics;
THE END – HANDOVER TO OPERATIONS • the owner’s team is well led and adequately resourced;
Once construction and commissioning are finished, all that • competent staff, consultants and contractors are engaged who
remains is to complete the project close out activities. These will know the industry and understand what is being designed and
include: constructed;
• verifying that the project complies with the user requirement • the baseline budget and schedule is realistic;
specifications, • the levels of contingency and escalation are realistic;
• completing all QA checks, • the degree of front end loading is sufficient;
• ensuring warranty claim procedures are in place, • a thorough project execution plan is prepared;
• completing as-built drawings, • construction and commissioning plans are in place;
• completing operating and maintenance manuals, • effective project procedures are in place;
• settling and closing final accounts and all cost codes, • project control systems are appropriate;
• compiling the as-constructed schedule, • procurement is based on fair contracts;
• completing punch list items, • competent contractors are engaged;
• completing contractual obligations, • contracts are managed firmly but fairly;
• completing commissioning documentation, • thorough site investigation is done;
• completing operations acceptance documentation, • temporary facilities are adequate; and
• completing compilation into one final report of: • if contractors are in JVs, their systems are compatible.
• monthly reports,
• drawings and specifications, REFERENCES
• close-out activity description, Manchanda S, 2006. Presentation to AusIMM Perth Branch, 11 September.