Interior Installation Productivity

The document lists installation productivity ratios for various construction items at the Grand Millenium Hotel. It provides the item descriptions and expected productivity rates in terms of area covered or number of items installed per person per day or working hours. Productivity rates are given for tasks like plastering, screeding, ceiling installation, flooring, painting, fitting of fixtures and various furnishings.

Uploaded by

rehan840
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
211 views

Interior Installation Productivity

The document lists installation productivity ratios for various construction items at the Grand Millenium Hotel. It provides the item descriptions and expected productivity rates in terms of area covered or number of items installed per person per day or working hours. Productivity rates are given for tasks like plastering, screeding, ceiling installation, flooring, painting, fitting of fixtures and various furnishings.

Uploaded by

rehan840
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 10

Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden


10 Carpenter Day / Room
Box etc.
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Door Shutters & Architrave 1 No / 12 Manhours


Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Door Shutters & Architrave 1 No / 12 Manhours


Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room
Grand Millenium Hotel - Installation Productivity Ratio

Item Description Productivity

Plaster Works Ceiling & Wall 10 m2 / ManDay


Screed Works 9 m2 / ManDay
False Ceiling Suspension Frames 7 m2 / ManDay
Wooden Sub-Frame / Internal Framing Works 5 m2 / ManDay
Installation of Door Frames 1 No / 6 Manhours
Fixing of Wooden/Steel Frame for Bathtub 1 No / 24 Manhours
Fixing of Wooden/Steel Frame for Vanity 1 No / 6 Manhours
False Ceiling Gypsum Board 8 m2 / ManDay
Cut-Outs in Ceiling & Fixing of Access Panels 10 m2 / ManDay
Stone Wall & Floor Finishes 8 m2 / ManDay
Painting (1st coat) 8 m2 / ManDay
Installation of Wardrobe / Kitchen Carcass 1 No / 32 Manhours
Installation of Wall & Ceiling Panels + Feature Wall 3.5 m2 / ManDay
Installation of Vanity Mirror & Glass Door 2 Glass Fixer Day / Room
Fixing of Vanity Top 1 No / 16 Manhours
Fixing of Kitchen Top 1 No / 8 Manhours
Lighting Fittings & Accessories 2 Electrician Day / Room
Sanitary Fittings & Accessories 4 Plumber Day / Room
Installation of Tracks for Curtains & Windows Blinds 1 Carpenter Day / Room
Final Paint To Ceilings & Walls 10 m2 / ManDay
Installation of Door Shutters & Architrave 1 No / 12 Manhours
Grand Millenium Hotel - Installation Productivity Ratio

Installation of Wardrobe/Kitchen Shutters, Headboard, Architrave, Wooden Box10 Carpenter Day / Room
Timber Flooring 8 m2 / ManDay
Carpet Flooring 8 m2 / ManDay
Furniture, Furnishing, Mirrors & Artwork 4 Carpenter Day / Room