SOP
DOC REF NO APNRL/IMS/SOP/OP/001/ REV 0 DATE OF ISSUE
RESPONSIBILITY MECHANICAL-OPERATION
PURPOSE CEP CHANGEOVER PAGE 0
CEP Changeover
Initial condition
Procedure
1. Withdraw CEP-B from S/B and close its discharge valve.
2. Check that all starting permissive are available. Put recirculation valve opening> 75 %
and ensure minimum flow > 240 TPH.
4. Start CEP-B and give open command of its discharge valve within one minute.
(Within one minute if close limit of its discharge valve does not go then pump will trip
)
10. Select CEP-A S/B, its discharge valve will open automatically