Routing Sheet Kursi

This document contains a routing sheet for a manufacturing process. It lists 14 operations to cut, drill, weld and assemble metal and plastic parts into a final product. The operations will utilize circular saws, drilling machines, electric welding, and grinding/painting equipment. Performance metrics like processing time per part, machine efficiency and scrap rates are provided for each operation.

Uploaded by

yourdania
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views2 pages

Routing Sheet Kursi

This document contains a routing sheet for a manufacturing process. It lists 14 operations to cut, drill, weld and assemble metal and plastic parts into a final product. The operations will utilize circular saws, drilling machines, electric welding, and grinding/painting equipment. Performance metrics like processing time per part, machine efficiency and scrap rates are provided for each operation.

Uploaded by

yourdania
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ROUTING SHEET KURSI CHITOSE MANABU

Waktu Produksi Bahan Bahan Efisiensi Kebutuhan


No. Operasi Deskripsi Mesin/Alat Tooling % Scrap
(Detik) Mesin/Jam Diminta Disiapkan Mesin Mesin Teori
100 - DUDUKAN RANGKA
O-101 Pipa besi diukur dan dipotong (Ø20 x 1500 mm) Circular Saw Mata Pisau, mal ukur 15 240 0.00% 84 84 105 0.438
O-102 Pipa besi bulat ditekuk Pipe Roll Bending Roller 40 90 0.00% 84 84 105 1.167
200 - SAMBUNGAN KAKI KANAN
O-201 Besi diukur dan dipotong (35 x 15 x 300 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.00% 85 85 107 0.297
O-202 Besi dilubangi Drilling Machine Mata bor Ø13 mm 10 360 0.08% 84 85 107 0.297
300 - SAMBUNGAN KAKI KIRI
O-301 Besi diukur dan dipotong (35 x 15 x 300 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.00% 85 85 107 0.297
O-302 Besi dilubangi Drilling Machine Mata bor Ø13 mm 10 360 0.08% 84 85 107 0.297
400 - PLAT DUDUKAN SANDARAN KANAN
O-401 Plat strip diukur dan dipotong (3.1 x 100 mm) Circular Saw Mata Pisau 10 360 0.00% 85 85 107 0.297
O-402 Plat strip dilubangi Drilling Machine Dies 10 360 0.03% 84 85 107 0.297
500 - PLAT DUDUKAN SANDARAN KIRI
O-501 Plat strip diukur dan dipotong (3.1 x 100 mm) Circular Saw Mata Pisau 10 360 0.00% 85 85 107 0.297
O-502 Plat strip dilubangi Drilling Machine Dies 10 360 0.03% 84 85 107 0.297
600 - PLAT DUDUKAN
O-601 Plat strip diukur dan dipotong (3.1 x 320 mm) Circular Saw Mata Pisau 10 360 0.04% 84 85 107 0.297
O-602 Plat strip dilubangi Drilling Machine Dies 10 360 0.01% 83 84 105 0.292
700 - KAKI KIRI ATAS
O-701 Besi diukur dan dipotong (40 x 20 x 320 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.04% 85 86 108 0.300
O-702 Besi dilubangi Drilling Machine Mata bor Ø13 mm 15 240 0.01% 84 85 107 0.446
800 - KAKI KIRI BAWAH
O-801 Besi diukur dan dipotong (40 x 20 x 400 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.00% 85 85 107 0.297
O-802 Besi dilubangi Drilling Machine Mata bor Ø13 mm 15 240 0.01% 84 85 107 0.446
700 - SAMBUNGAN ANTAR KAKI
O-901 Besi diukur dan dipotong (Ø10 x 300 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.00% 84 84 105 0.292
1000 - KAKI KANAN ATAS
O-1001 Besi diukur dan dipotong (40 x 20 x 320 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.04% 85 86 108 0.300
O-1002 Besi dilubangi Drilling Machine Mata bor Ø13 mm 15 240 0.01% 84 85 107 0.446
1100 - KAKI KANAN BAWAH
O-1101 Besi diukur dan dipotong (40 x 20 x 400 mm) Circular Saw Mata Pisau, mal ukur 10 360 0.00% 84 84 105 0.292
O-1102 Besi dilubangi Drilling Machine Mata bor Ø13 mm 12 300 0.01% 83 84 105 0.350
SUB-ASSEMBLING 1
Perakitan Komponen Kaki Kiri Atas
O-703 dengan Kaki Kiri Bawah (700 dan Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
800)
SUB-ASSEMBLING 2
Perakitan Sub Assembling 1 dengan
O-704 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Sambungan Antar Kaki (700 dan 900)
SUB-ASSEMBLING 3
Perakitan sub assembling 2 dengan
O-705 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Kaki Kanan Atas (700 dan 1000)
SUB-ASSEMBLING 4
Perakitan sub assembling 3 dengan
O-706 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Kaki Kanan Bawah (700 dan 1100)
O-608 Penghalusan Gerinda Batu gerinda, amplas 120 30 0.001% 83 84 105 3.500
O-609 Pengecatan Spray booth Electric Spray Gun 10 360 0.00% 83 83 104 0.289
Waktu Produksi Bahan Bahan Efisiensi Kebutuhan
No. Operasi Deskripsi Mesin/Alat Tooling % Scrap
(Detik) Mesin/Jam Diminta Disiapkan Mesin Mesin Teori
SUB-ASSEMBLING 5
Perakitan sub assembling 4 dengan
O-709 Electric welding Elektroda 10 360 0.00% 83 83 104 0.289
Plastik Penghubung (700 dan 1200)
SUB-ASSEMBLING 6
Perakitan sub assembling 5 dengan
O-710 Electric welding Elektroda 10 360 0.00% 83 83 104 0.289
Plastik Penutup Kaki (700 dan 1300)
SUB-ASSEMBLING 7
Perakitan sub assembling 6 dengan
O-710 Electric welding Elektroda 10 360 0.00% 83 83 104 0.289
Plastik Alas Kaki (700 dan 1400)
ASSEMBLING 1
Perakitan Dudukan Rangka dengan
O-103 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Sambungan Kaki Kanan (100 dan 200)
ASSEMBLING 2
Perakitan assembling 1 dengan
O-104 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Sambungan Kaki Kiri (100 dan 300 )
ASSEMBLING 3
Perakitan assembling 2 dengan Plat
O-105 Electric welding Elektroda 30 120 0.00% 84 84 105 0.875
Dudukan Sandaran Kanan (100 dan
ASSEMBLING 4
Perakitan assembling 3 dengan Plat
O-106 Benchwork Tools Elektroda 30 120 0.00% 84 84 105 0.875
Dudukan Sandaran Kiri (100 dan 500)
ASSEMBLING 5
Perakitan assembling 4 dengan Plat
O-107 Benchwork Tools Elektroda 45 80 0.00% 84 84 105 1.313
Dudukan (100 dan 600)
O-108 Penghalusan Gerinda Batu gerinda, amplas 60 60 0.001% 83 84 105 1.750
O-109 Pengecatan Spray booth Electric Spray Gun 120 30 0.00% 83 83 104 3.467
ASSEMBLING 6
Perakitan sub assembling 7 dengan
O-110 Benchwork Tools Toolsbox 10 360 0.00% 83 83 104 0.289
assembling 5
ASSEMBLING 7
Perakitan asssembling 6 dengan Papan
O-111 Benchwork Tools Toolsbox 10 360 0.00% 83 83 104 0.289
Sandaran (100 dan 1500)
ASSEMBLING 8
Perakitan asssembling 6 dengan Papan
O-112/I-101 Benchwork Tools Toolsbox 60 60 0.00% 83 83 104 1.733
Alas Duduk (100 dan 1600)

Instruktur Praktikum

Tiradia Ihsan, S.T