Conceptual Design of Plem Structure Labuhan Deli

This document summarizes the conceptual design of a PLEM structure based on a piping arrangement. Key results include: - The maximum steel beam stress of 134.26 MPa is below the allowable limit of 198 MPa. - The maximum principal stress and Von Mises stress in steel plates are both below the limit at 7.991 MPa and 7.233 MPa respectively. - The maximum bearing pile force is 19.689 tons with negligible tension or lateral forces. Vertical displacement is 19.697 mm and lateral is 17.917 mm. - Stresses in 12", 24" and 28" pipes are all below the allowable limit of 198 MPa.

Uploaded by

Fandy Sipata
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
125 views

Conceptual Design of Plem Structure Labuhan Deli

This document summarizes the conceptual design of a PLEM structure based on a piping arrangement. Key results include: - The maximum steel beam stress of 134.26 MPa is below the allowable limit of 198 MPa. - The maximum principal stress and Von Mises stress in steel plates are both below the limit at 7.991 MPa and 7.233 MPa respectively. - The maximum bearing pile force is 19.689 tons with negligible tension or lateral forces. Vertical displacement is 19.697 mm and lateral is 17.917 mm. - Stresses in 12", 24" and 28" pipes are all below the allowable limit of 198 MPa.

Uploaded by

Fandy Sipata
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

CONCEPTUAL DESIGN OF PLEM STRUCTURE

(BASED ON DESIGN PIPING ARRANGEMENT)

ISOMETRIC OF STRUCTURE MODEL

DESIGN ASSUMPTION :
- WAVE HEIGHT : 4 M (BASED ON 100 YEARS R.P OPEN SEA WAVE AT JAMBI)
- WAVE RETURN PERIOD : 10 S
- SEA CURRENT VEL. : 1.5 M/S
- SEABED DEPTH : 17 M
- WAVE THEORY : AIRY WAVE THEORY
- SOIL CONDITION : SOFT CLAY (SOIL SPRING CONSTANT 8,140 KPA/M)
- DESIGN LIFE : 30 YEARS (ALLOWABLE STRESS IS 198 MPA → ABS WITH SF 3.0)
- DESIGN CODE : AISC 360, API WSD, DNV, ABS & SNI FOR SEISMIC REQUIREMENT

Page 1 of 4
CONCEPTUAL DESIGN OF PLEM STRUCTURE
(BASED ON DESIGN PIPING ARRANGEMENT)
SUMMARY OF DESIGN RESULTS OF STRUCTURE ELEMENT :
- MAX. STRENGTH RATIO : 0.852
- MAX. BEAM STRESS : 134.26 MPA < 198 MPA (OK)

MAXIMUM STEEL BEAM STRESS AT DESIGN LOAD COMB

- MAX. PLATE STRESS : - PRINCIPAL STRESS = 7.991 MPA (SHEAR & BENDING)
- VON MIS STRESS = 7.233 MPA (DISTORTION)

Max Top
(Principal Major Stress)
Stress)
N/ mm2
<= 0.155
0.645
1.13
1.62
2.11
2.6
3.09
3.58
4.07
4.56
5.05
5.54
6.03
6.52
7.01
7.5
>= 7.99

Y
X
Z
Load 1087

MAXIMUM PRINCIPAL STRESS OF STEEL PLATE (7.991 MPA< 198 MPA (OK))

Max Von Mis


N/ mm2
<= 1.61
1.96
2.32
2.67
3.02
3.37
3.72
4.07
4.42
4.77
5.13
5.48
5.83
6.18
6.53
6.88
>= 7.23

Y
X
Z
Load 1087

MAXIMUM VON MIS STRESS OF STEEL PLATE (7.233 MPA < 198 MPA (OK))

Page 2 of 4
CONCEPTUAL DESIGN OF PLEM STRUCTURE
(BASED ON DESIGN PIPING ARRANGEMENT)
- MAX. PILE FORCE : - BEARING FORCE = 19.689 TON
- TENSION FORCE = 0 TON
- LATERAL FORCE = 2.570 TON
- MAX. DISPLACEMENT : - VERTICAL DISPL. = 19.697 MM
- LATERAL DISPL. = 17.917 MM
- MAX. WEIGHT : ≈ 38.97 TON

ISOMETRIC DRAWING OF CONCEPTUAL DESIGN RESULT

PROPOSE PILE SHOE (OPEN END WITH REINFORCEMENT RING)

Page 3 of 4
CONCEPTUAL DESIGN OF PLEM STRUCTURE
(BASED ON DESIGN PIPING ARRANGEMENT)
SUMMARY OF DESIGN RESULTS OF PIPE ELEMENT (3 MM INTERNAL CORROSION ALLOWANCE) :
- MAX. PIPE STRESS : - 12” PIPE = 72.822 MPA < 198 MPA (OK)

- 24” PIPE = 31.228 < 198 MPA (OK)

- 28” PIPE = 30.402 MPA < 198 MPA (OK)

All actual combined stress of the pipe have been below the allowable combined stress as per
ASME B31.4 Sect. A402.3.5 (322.67 MPa)

Page 4 of 4