0% found this document useful (0 votes)
60 views

Masonry: Ground Floor: Front

The document summarizes the materials needed for masonry work on the ground floor, second floor, wall footings, and mortar for a construction project. It calculates the number of concrete hollow blocks (CHB), cement bags, and sand cubic meters required. The total CHB needed is 4,835 for the floors and 443 for the footings. The total cement required is 588 bags for floors, 279 bags for plaster, and 54 bags for footings mortar. The total sand required is 32.64 cubic meters for floors mortar and 2.99 cubic meters for footings mortar.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views

Masonry: Ground Floor: Front

The document summarizes the materials needed for masonry work on the ground floor, second floor, wall footings, and mortar for a construction project. It calculates the number of concrete hollow blocks (CHB), cement bags, and sand cubic meters required. The total CHB needed is 4,835 for the floors and 443 for the footings. The total cement required is 588 bags for floors, 279 bags for plaster, and 54 bags for footings mortar. The total sand required is 32.64 cubic meters for floors mortar and 2.99 cubic meters for footings mortar.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Masonry

Ground Floor:

Front
20m x 2.6m = 52sq.m – (3) 6.12sq.m – 2.25sq.m – 2(0.20m)(2.6m)

= 30.35sq. m

Right Side
9m x 2.6m = 23.40sq.m – 2(0.30m)(2.6m) + .15m(2.6m)
= 21.06sq.m

Left Side

11.50m x 2.6m = 29. 9sq.m – (2)(0.36 m) – 0.6sq.m – 2(0.30)(2.6m) – 0.15m(2.6m)


= 26.63sq.m

Rear
20m x 2.6m = 52sq.m – 4(6.12sq.m) – [2(0.2m) – (0.3m)]2.6m
= 28.82sq.m

Interior Wall

7.5m x 2.6m – 2(0.3m) (2.6m) – 2(1. 26sq.m) + 3m(2.9m) + 2(1.5m) (2.9m) +


2(1.5m) (2.9m) – 2(1.26sq.m)
= 39.78sq.m

Total Ground Floor Wall Area:


T= Front + Right + Left + Rear + Interior
= 30.35sq.m + 21.06sq.m + 26.63sq.m + 28.82sq.m + 39.78sq.m
= 152.21sq.m

Where:
1sq.m = 12.5 pieces of CHB
Total CHB for Ground Floor :

152.21 x 12.5 = 1902.63 say 1903 CHB


Second Floor:

Front

15.75m(3.2m) + 4.25m (4.15m) = 68.04 sq.m – 1.5(0.20m x 3.2m) – 2.5(0.30m x 3.2m)


– 2. 06sq.m – (3) 5. 61sq.m – 0.2m (4.15m)

= 44.96 sq. m

Right Side

9m x (3.2m) – 2(0.3m x 3.2m) = 26. 88sq.m + 4.5m(4.15m) – 6.11sq.m – 0.3m (4.15m)

= 38. 20sq.m

Left Side

13.50m(3.20m) – 3(0.30m x 3.2m) -2. 97sq.m

= 37. 35sq.m

Rear

20m x (3.2m) – 4(0.30m x 3.2m) – 0.2m(3.2m) – 4(5. 61sq.m)

= 37. 08sq.m

Interior Wall

(3m x 3.2m) + 2 (7.5m x 3.2m) + 2.56sq. m – (2) 1. 68sq.m – 0.4m(3.2)

= 52. 32sq.m

Total Second Floor Wall Area:


T= Front + Right + Left + Rear + Interior

= 37. 08sq.m + 37. 35sq.m + 38. 2sq.m + 44. 96sq.m + 24.6sq.m +52.32sq.m

= 234.51 sq.m

Where:
1sq.m = 12.5 pieces of CHB
Total CHB for Second Floor : 234.51 x 12. 5 = 2931.38 say 2932 CHB

TOTAL CHB = GROUND FLOOR CHB + SECOND FLOOR CHB

= 1903 + 2932

TOTAL = 4835 CHB


Mortar
According to Hundred Block Method:

Total No. of CHB = 4835 CHB

Convert to unit of 100 = 4835/100


= 48.35

Under Class “A” mixture for 15 x 20 x 40 CHB, multiply:

Cement: 48.35 x 12.150 = 587.45 say 588 bags

Sand (cu. m) for 15 x 20 x 40 CHB, multiply:

Sand: 48.35 x 0. 675cu.m = 32. 64cu.m

Mortar plastering
According by Area Method:

Total Wall Area = 386. 72sq.m

 Find the area of the wall (two sides)


= 386.72 x 2
= 773. 44sq.m
 Solve for the cement and sand
Under 20mm thick plaster class “A” mixture:
Cement: 773.44 x 0.360 = 278.44 say 279 bags
Sand: 773.44 x 0.020 = 15. 47cu.m
Wall footing hollow blocks
FRONT:

(3.0m x .40m) + (12.75m x .40m) + (4.25m x .40m) – (.40m x .40m) = 7.84sq.m

LEFT SIDE:

(11.50m x .40m) – 2(.30m x .40m) = 4.36sq.m

RIGHT SIDE:

(11.50m x .40) – 2(.30x .40) = 6.0sq.m

REAR:

(20m x 0.40m) – 4(0.30m x .40m) – (0.2m x 0.4m) = 7.44sq.m

INTERIOR WALLS:

= 2(1.5m x .40) + 2(3.0m x .40m) + (4.25m x .40) + (4.8m x 0.4m) + (7.5m x 0.4m) – 2(.40m x
.40m) – (.30m x .40m) = 9.78sq.m

TOTAL WALL FOOTING HOLLOW BLOCKS AREA:

TOTAL = FRONT + RIGHT + LEFT + REAR+ INTERIOR WALLS


= 7.84sq.m + 4.36sq.m + 6.0sq.m + 7.44sq.m + 9.78sq.m

= 35.42 sq.m

Where:
1 sq. m = 12.5 CHB
TOTAL CHB NEEDED:

35.42sq.m x 12.5 = 442.75 say 443 CHB

Mortar:
According to Hundred Block Method:

Total No. of CHB = 443 CHB


Convert to unit of 100 = 443/100 = 4.43
Under Class “A” mixture for 15 x 20 x 40 CHB, multiply:
Cement: 4.43 x 12.150 = 53.82 say 54 bags
Sand (cu. m) for 15 x 20 x 40 CHB, multiply:
Sand: 4.43 x 0. 675cu.m = 2.99cu.m