Method Statement - Elect. Jerry Shell

1. The document provides a work method statement for an environmental upgrade project by Henmak Technical Services Limited for Belema Oil. 2. The general work sequence includes carrying out surveys, mobilizing to site, installing new cable trays and routing earth cables, reinstalling and terminating cables, installing control panels, testing and commissioning, and demobilizing from site. 3. Safety precautions like using approved scaffolding and safety harnesses for high works, obtaining isolations and authorizations, attaching danger notices, and wearing PPE are described. Testing of cables, earth connections and equipment is required before and after installation.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
187 views5 pages

Method Statement - Elect. Jerry Shell

1. The document provides a work method statement for an environmental upgrade project by Henmak Technical Services Limited for Belema Oil. 2. The general work sequence includes carrying out surveys, mobilizing to site, installing new cable trays and routing earth cables, reinstalling and terminating cables, installing control panels, testing and commissioning, and demobilizing from site. 3. Safety precautions like using approved scaffolding and safety harnesses for high works, obtaining isolations and authorizations, attaching danger notices, and wearing PPE are described. Testing of cables, earth connections and equipment is required before and after installation.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

WORK

METHOD
STATEMENT

HEN/BEU/WMS/02

1
HENMAK TECHNICAL SERVICES LIMITED
WORK METHOD STATEMENT FOR BELEMA
ENVIRONMENTAL UPGRADE.
CONTRACT NO,NG 01019281

ACTION BY NAME TITLE SIGNATURE DATE

PREPARED ANTHONY PROJECT


BY EKEKE ENG.

AUTHRIZED HENRRY MANAGING


BY HALUEDE DIRECTOR

AGREED BY NWOSU SPDC QA/QC


JEREMIAH ENG

APROVED JUDE CONTRACT


BY ORUOGHOR OWNER
SHELL PETROLEUM DEVELOPMENT COMPANY OF
NIGERIA LIMITED

INTRODUCTION
This document provides a description of the things expected of HENMAK
TECHNICAL SERVICES LIMITED as related to this project and outline the
general requirement for the project .This document also presents precautions and
methods to be followed in other to achieve expected success.

GENERAL WORK SEQUENCE


The general work sequence shall include but not limited to the following.

1. Carry out measurement and detail work survey.


2. Shipment of deliverable of materials to site
3. Mobilization to site and HSE site workshop
4. HSE induction, rising of PTW and all complementary documents
5. Isolation of supply line to closes drains, decommissioning of old cable
traydecouple and coupling of fittings and installations of new tray.
6. Construction of cable tray base plate, earth cable route survey and
installation.
7. Earth cablelaying, reinstallation of cables on the installed new trays.
8. Termination of cables, joint boxes, risers, fittings and all accessories.
9. Installation of control panels, photo control for fluorescent fittings etc
10. Testing and commissioning

11. Site clearing and demobilization.


A visual inspection will be carried out to understand the cable route before work
commence.
Disconnect and dismantle the old obsolete and disused cables.
All cables removed during construction to be reinstalled and test to confirm properly in other.
All reconnected lamps should be properly tested with meter tester.
Test all installation and commission
Confirm that the circuit is dead using multimeter to check.

HEIGHT WORKS.
All height works shall be by means of approved equipment such as scaffolding using safety
harness as specified in the contract document.

HENMAK shall ensure that the scaffolding operational mechanisms are in good working
condition.

EARTH CABLE CONNECTIONS.


HENMAK shall ensure that all parts of the working areas equipment outages are obtained and
that SPDC authorized person shall authorize the switching operations.

Connection to earth at all point of disconnection includes line voltage to check for leakage where
necessary to prevent shock and DANGER notices attached.

Clarify the extent of work and obtain relevant certificates for test.

Test all cables for continuity before installation is carried out.

Test all equipment before installation.

Report all defects if any to the supervisor for immediate action and replacement.

All personal protective equipment (PPE) must be worn at all times during operations.

All earth leads must be properly terminated.


SETTING UP OF SCAFFOLDING
HENMAK TECHNICAL SERVICES LIMITED shall ensure that all height work above
1.8meters shall be by use of pre-mobbed and certified functional scaffolding system.

Ensure that the setting of scaffolding is manned by the experienced personnel, stands at level and
stopper is firm on the ground and that the safety harness is in good working conditions.

Use of safety harness is mandatory (safety belt).

TESTING AND COMMISSIONING


All cables, Earth electrodes and installed equipment must be confirmed ok.