Punchlist PDF

This document is a punchlist for office renovations across the 10th, 11th, and 12th floors. It outlines 15 items requiring work on specific areas or rooms, including installation of graphics, sensors, tiles, cabinets, and CCTV. The status of each item is provided, with many committed to being completed by March 22-23, 2018. Additional requests are noted as ongoing or requiring purchase order approval.

Uploaded by

izra habla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
328 views1 page

Punchlist PDF

This document is a punchlist for office renovations across the 10th, 11th, and 12th floors. It outlines 15 items requiring work on specific areas or rooms, including installation of graphics, sensors, tiles, cabinets, and CCTV. The status of each item is provided, with many committed to being completed by March 22-23, 2018. Additional requests are noted as ongoing or requiring purchase order approval.

Uploaded by

izra habla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Empire East Corporate Head Office

Alliance Global Tower, Uptown Bonifacio, Taguig City As of March 21, 2018

PUNCHLIST
10TH FLOOR
ITEM NO. AREA PARTY RESPONSIBLE COMMENTS/REMARKS STATUS
-Installation of Graphicote
1 Training Room Pacific Glass/ Triframe Waiting for installation
-Backing (c/o Triframe)
General Storage
2 Razor -Sensor - for checking DONE
Room
3 Pantry Triframe Inc. -Paint on trim DONE
11TH FLOOR
-Rectification of walls near glass door and
4 CNC Area Excell DONE
thermostats

5 Client's Room Excell -Rectification of walls DONE

-Paint on trim
6 Pantry Triframe Inc. -Faucet DONE
-Baseboard
12TH FLOOR
-Alignment of Cabinets - Committed date:
7 OP Excell
Installation of Mohair March 22, 2018
Committed date:
8 Den Excell -Installation of cabinet laminate
March 22, 2018
Committed date:
9 Toilet (ACY) Excell -Change Tiles (wood planks) @ Door
March 22, 2018
-Alignment of Cabinets (installation of hook
and eye) - Committed date:
10 Receiving Area Excell
Installation of tile (near the door) - March 22, 2018
Wire Manager (c/o Triframe Inc.)

11 Lounge Microgen -Door access ID not recognized On-going


Was requested last March
12 Board Room Triframe Inc. -Installation of HDMI Port
29, 2018

EGC Office and


-HR requested for
13 Disbursement Megaworld -Rectification of leak
inspection
Area
Comitted date: March
14 Legal Area Jogging Path -for re-installation
23, 2018
10TH AND 12TH FLOOR
15 Built-in Cabinets Triframe Inc. -Installation of edge bands
ALL FLOORS
For approval of change
16 Razor -Installation of additional CCTV
order
-Supply and Installation of additional
17 Group Perspective Inc. On-process of PR
partition