Flexible Manufacturing: Faculty of Mechanical Engineering
Flexible Manufacturing: Faculty of Mechanical Engineering
final report:
FLEXIBLE MANUFACTURING
AUTHORS: LECTURER:
b. Simulation results
IV. Conclusions
In our model the main criteria was the cost of operation – not cost of the
machines. We decided to choose new, numerical machines – more expensive,
but faster and more precisely than conventional machines. Because of our
choice, the time of operation was shorter and production quality – better.
REQUIREMENT
OPERATION NAME
(MACHINE-TOOL TYPE, EQUIPMENT)
Rough and medium milling of machining Required CNC milling machine with
1 datum surface
Choice 2
main drive 8,5 kW electric power
REQUIREMENT
OPERATION NAME
(MACHINE-TOOL TYPE, EQUIPMENT)
Rough and medium milling of machining Required CNC milling machine with
1 Choice 2
datum surface main drive 8,5 kW electric power
Nu
Name of m Probe Robo Chip Max Max
t
palle
remo rotati Spind Spindle Tool Price Price
the be system t
avail val onal le orientati warehou
machine r of able
chan
facilit speed Powe on se
Ax ger
tool ? y [rpm] r [kW]
es Tool Object
measur. measur. euro PLN
sensor system
Milling
Wheel -
machine CNC 3 No No No No No 7500 14,9 Vertical 10slots
36995 155379
VF-1.0
Conventional
drilling-
milling 3 No No No No No 2000 7.5 Vertical N/A - 85400
machine BFM
200 Bernardo
Auto
Name of Robo matic Chip Spindle
Tool Object t mode remo max Bar
Tool Price Price
the Ax max rotatio Powe handling
measur. measur. avail val warehou
machine es sensor system
bar nal
able length facilit speed
r [kW] accessor
se
ies
tool ? Lw y [rpm]
[mm] euro PLN
revolving
Lathe CNC X,
No No No 712 No 6000 11,2 No head - 12 33995 142779
ST-10,0 Z positions
Calculation:
TIMES (h) I0
QUANTIT PRICE TOTAL
MACHINE bottom bottom
Y
front cover – front cover – [PLN] PRICE
cover change cover change
d d
Lathe CNC
ST-10,0
0,016 0,012 0,33 0,25 2 142 779 285 558
Conventional drilling-
milling machine 0,023 0,013 0,48 0,28 2 85 400 170 800
BFM 200 Bernardo
QC (PP i PTZ) 0,032 0,026 0,25 0,21 2 1 000 2 000
Equipment actions (mounting in the holder) 8 min = 0,13 h 10 min = 0,17 h 15 min = 0,25 h
FRONT COVER:
1
4. Part symbol 5. Drawing numer 6. Part name 7.
2,40 1/1
18. Material name 19. 20.
EN-GLJ-250
21. Type of primary product 22. 23. 24. 25.
Cast iron
26. Op. number 27. 28. Machine symbol 29. 30. 31. 32. 33. 34. 35. Setup time 36. Cycle time [s] 37. 38. 39.
10 FNC 64
40. Operation name 41. 42. 43.
20 TNC 57,6
30 FNC 261,7
Holes processing
40 FV 83,7
1 hole Ø1,5 drilling
50 QC 115
Quality control
47. Created by: 48. Checked by: 49. Approved by: 50. Date
2
4. Part symbol 5. Drawing numer 6. Part name 7.
2.00 kg 1/1
18. Material name 19. 20.
EN-GLJ-250
21. Type of primary product 22. 23. 24. 25.
Cast iron
26. Op. number 27. 28. Machine symbol 29. 30. 31. 32. 33. 34. 35. Setup time 36. Cycle time 37. 38. 39.
10 FNC 64
40. Operation name 41. 42. 43.
20 TNC 43,6
30 FNC 305,7
Holes processing
40 FV 48
50 FNC 102,3
Holes processing
60 QC 95
Quality control
47. Created by: 48. Checked by: 49. Approved by: 50. Date
Our assumptions:
Number of dimensions in IT8 quality class or better: Number of dimensions in IT8 quality class or better:
n=5 n=1
tQC = 90 + 5*5 = 115 [s] = 0,032 [h] tQC = 90 + 1*5 = 95 [s] = 0,026 [h]
- Hall: 25 m x 45 m = 1 125.00 m2
- R.M. Storage: 15.3 m x 7.65 m = 101.75 m2
- F.P. Storage:13.3 m x 7.65 m = 101.75 m2
● ANOTHER DIMENSIONS:
INPUT:
b. SIMULATION RESULTS
USE OF MACHINES:
Machines that are used the most are milling machines. Use of these machines
determines total time of simulation. Basing on i0 calculation and technological
card produced parts demands most operation exactly on milling machines so
others like lathe 1,2 or Drill 1,2 are working less than 50% of the production time.
Considering fact that in the project front cover and bottom cover changed
are produced on two separate lines, i0 had to be calculated for 100.000 parts
of front cover and 100.000 parts of bottom cover changed. Due to fact that
setup times are eliminated, some of the machines was bought separately for
two produced parts yet use of the machines during simulation time could allow
to realize production plan only on one of them for two parts (eg. Lathe 1 & 2).
USE OF RESOURCES:
COST FROM PROMODEL:
c. ANALYSIS OF THE RESULTS
● EMPLOYEE’S SALARIES:
o Transport workers: 4 x 17 PLN / h = 68 PLN / h
o Operation Workers: 9 x 20 PLN /h = 180 PLN / h
o QC workers: 2 x 15 PLN / h = 30 PLN / h
OPERATING PER
SIM. MACHINES HALL BLANKS EMPLOYEE’S OPERATING INVESTMENT TOTAL
MACHINES HOUR
TIME COSTS COSTS COSTS SALARIES COSTS COSTS SUM
COSTS COST
15290
6 070 1 235 253 1 800 000 1 706 000 1687460 8862200 10549660 3 035 253 1738
913
9=
1 2 3 4 5 6 7=5+6 8=2+3 7/1
4+7+8
IV. CONCLUSIONS
Within a year (about 253 days), we produce 100 080 parts of FRONT
COVER and 108 900 parts of BOTTOM COVER CHANGED. To perfectly fit in the
production plan, which assumed 250 days, we could add 3 working Saturdays
during the year, for for people want to use opportunity of 150% reward for their
work day. Another solution could be to use better the equipment, especially
milling machines with better performance and a shorter working time, because
the whole process is based on them, and also they generate the most time.
In summary, the production plan 100 000 parts of both components has
been completed, all the assumptions of the project have been met. But
certainly we should optimize our process. Introduce more solutions in the field
of lean management and based on the analysis of statistics make changes
and introduce continuous improvement plan.
V. ATTACHED DOCUMENTS AND FILES
4. A3 Layout (pdf)