SCHEDULE Level 2 New

This document provides a schedule for the PKI PFM PROJECT located in Jasaan, Cagayan de Oro. It outlines the civil works, structural, mechanical, and piping works to be completed each month from September 2018 through March 2019. The project involves steel structure installation, equipment installation including reactors and heat exchangers, piping fabrication and installation, and testing of the piping system. The schedule is broken down by area (M3 Production, ITY Tank Yard, and UC3 Cooling Tower) and lists the start date and key activities for each item.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
179 views24 pages

SCHEDULE Level 2 New

This document provides a schedule for the PKI PFM PROJECT located in Jasaan, Cagayan de Oro. It outlines the civil works, structural, mechanical, and piping works to be completed each month from September 2018 through March 2019. The project involves steel structure installation, equipment installation including reactors and heat exchangers, piping fabrication and installation, and testing of the piping system. The schedule is broken down by area (M3 Production, ITY Tank Yard, and UC3 Cooling Tower) and lists the start date and key activities for each item.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 24

Aboitiz Construction Inc.

Project :PKI PFM PROJECT


Client: JGC Phils.
Location: Jasaan, Cagayan de Oro
SCHEDULE
Description Qty Unit M1 M2 M3 M4 M5 M6 M7 M8 M9 M10
CIVIL WORKS
CLEARING AND GRUBBING 11,380.00 sq.m.
EXCAVATION 8,027.78 cu.m.
BACKFILLING 2,237.71 cu.m.
FILL AND COMPACTION 11,578.00 cu.m.
DISPOSAL 8,312.17 cu.m.
GRAVELLING (ROADWORKS) 830.10 cu.m.
SUBGRADE COMPACTION 5,760.00 sq.m.
DEMOLITION 11.00 sq.m.
EARTHWORKS 8,027.78 cu.m.
CONCRETE WORKS 3,655.88 cu.m.
REBAR WORKS 350,048.24 kgs.
FORMWORKS 6,665.44 sq.m.
ROAD CONCRETING/GRAVELLING 5,760.00 sq.m.
LANDSCAPING 398.00 sq.m.
FABRICATION & INSTALLATION 20,113.75 kgs.
MASONRY WORKS 2,950.93 sq.m.

STRUCTURAL, MECHANICAL, PIPING WORKS


SITE DEVELOPMENT 2,400.00 IM
STEEL STRUCTURE 558.36 ton
EQUIPMENT 265.19 ton
PIPING 51,713.46 ID
INSULATION 8,891.70 sq.m.
PAINTING 5,488.68 sq.m.
SURFACE PROT. & FIREPROOF 1,563.18 sq.m.
SCHEDULE
M11 M12 M13 M14 Remarks
Aboitiz Construction Inc.
Project :PKI PFM PROJECT
Client: JGC Phils.
Location: Jasaan, Misamis Oriental

Item Description Start


A100 : M3 Production Area
Steel Structure 9/1/2018
A10HB3200 Steel Equipment Support 9/1/2018
Preparartion materials
Steel structure works installation
Ground floor
2nd floor
3rd floor
4th floor
5th floor
Inspection
A10HB3100 Steel pipe Rack 10/1/2018
Preparation
Steel installation
Fix and allignment
Inspection
A10HB3800 Misc. Support Structure 1/19/2019
Preparation
Steel support installation
Fix and allignment
Inspection
Equipment 11/14/2018
A10HB5130 Column Installation (3sets) 11/14/2018
Preparation
Column installation
Fix and allignment
Inspection
A10HB5120 Reactor Installation (3sets) 12/14/2018
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5810 Pumps Installation (24sets) 1/2/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5320 Heat Exchanger (S/T spiral) (20sets) 1/11/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5140 Drum/Vessels (27sets) 1/14/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5520 Filters Installation (5 sets) 1/14/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5A00 Package Equipment Chiller Installation (1set) 1/25/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5530 Hoist Installation (1set) 2/9/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5310 Air Fin Cooler 2/12/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5820 Blower Compressor Inst. (1set) 2/18/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A10HB5510 Agitator Installation (2sets) 3/4/2019
Preparation
Agitator installation
Fix and allignment
Inspection
Piping 9/1/2018
A10HB6100 Piping Shop Fabrication 9/1/2018
Surface Preparation Materials
Painting
Lay-out / cutting spool
Fit-up
Welding
cleaning
Inspection
Delivery
A10HB6900 Piping Tie-in by hot cutting/fitting 9/1/2018
Cutting of tie-in spool area
Installation of tie-in spool
Fullwelding of tie-in spool
Cleaning
Testing
Inspection
A10HB6210 Piping on P/R Installation 11/17/2018
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support at new pipe rack
Cleaning
Insulation and installation of heat tracing
inspection
A10HB6230 Piping Around Equipment Installation 1/10/2019
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support
Cleaning
Insulation and installation of heat tracing
inspection
A10HB6800 Piping Test 3/1/2019
RT test
Hydrotest
Inspection
A200 : ITY Tank Yard Area
Steel Structure 10/2/2018
A20HB3100 Steel pipe Rack 10/2/2018
Preparation
Steel installation
Fix and allignment
Inspection
A20HB3800 Misc. Support Structure 2/2/2019
Preparation
Steel support installation
Fix and allignment
Inspection
Equipment 9/1/2018
A20HB5540 Pig Launder/Reciever Installation (1set) 1/9/2019
Preparation
Pig Launder installation
Fix and allignment
Inspection
A20HB5810 Pumps Installation (1set) 1/22/2019
Preparation
Pump installation
Fix and allignment
Inspection
A20HB5510 Agitator Installation (5sets) 2/18/2019
Preparation
Agitator installation
Fix and allignment
Inspection
Piping 10/9/2018
A20HB6100 Piping Shop Fabrication 10/9/2018
Surface Preparation Materials
Painting
Lay-out / cutting spool
Fit-up
Welding
cleaning
Inspection
Delivery
A20HB6210 AG Piping on P/R Installation 12/5/2018
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support at new pipe rack
Cleaning
Insulation and installation of heat tracing
inspection
A20HB6230 AG Piping Around Equipment Installation 2/2/2019
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support
Cleaning
Insulation and installation of heat tracing
inspection
A20HB6800 Piping Test 3/30/2019
RT test
Hydrotest
Inspection
A300 : UC3 Cooling Tower Area
Steel Structure 11/26/2018
A30HB3100 Steel pipe Rack 11/26/2018
Preparation
Steel piperack installation
Fix and allignment
Inspection
A30HB3800 Misc. Support Structure 2/8/2019
Preparation
Steel support installation
Fix and allignment
Inspection
Equipment 10/9/2018
A30HB5500 Cooling Tower Installation- UC3 (1set) 10/9/2018
Preparation
Cooling Tower installation
Fix and allignment
Inspection
A30HB5810 Pumps Installation- UC3 (2sets) 11/10/2018
Preparation
Pump installation
Fix and allignment
Inspection
A30HB5A00 Package Equipment (Sand Filter) Installation (1set) 12/12/2018
Preparation
Sand Filter installation
Fix and allignment
Inspection
Piping 11/10/2018
A30HB6100 Piping Shop Fabrication 11/10/2018
Surface Preparation Materials
Painting
Lay-out / cutting spool
Fit-up
Welding
cleaning
Inspection
Delivery
A30HB6210 AG Piping on P/R Installation 1/2/2019
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support at new pipe rack
Cleaning
Insulation and installation of heat tracing
inspection
A30HB6230 AG Piping Around Equipment Installation 2/16/2019
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support
Cleaning
Insulation and installation of heat tracing
inspection
A30HB6800 Piping Test 3/28/2019
RT test
Hydrotest
Inspection
A400 : CHO CO Reduction Area
Steel Structure 11/3/2018
A40HB3100 Steel Equipment Support 11/3/2018
Preparation
Steel equipment installation
Fix and allignment
Inspection
A40HB3200 Steel pipe Rack 11/17/2018
Preparation
Steel pipe rack installation
Fix and allignment
Inspection
A40HB3800 Misc. Support Structure 1/28/2019
Preparation
Steel support installation
Fix and allignment
Inspection
Equipment 1/11/2019
A40HB5120 Reactor Installation (2sets) 1/11/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A40HB5140 Drum/Vessels (9sets) 1/14/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A40HB5250 Platform and Ladder Installation 1/21/2019
Surface Preparation Materials
Painting
Lay-out / cutting spool
Fit-up
Welding
cleaning
Inspection
Delivery
A40HB5320 Heat Exchanger (4sets) 1/29/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A40HB5520 Filters Installation (3 sets) 1/31/2019
Equipment Preparation
Equipment installation
Fix and allignment
Inspection
A40HB5810 Pumps Installation (7sets) 2/1/2019
Preparation
Pump installation
Fix and allignment
Inspection
Piping 10/9/2018
A40HB6100 Piping Shop Fabrication 10/9/2018
Surface Preparation Materials
Painting
Lay-out / cutting spool
Fit-up
Welding
cleaning
Inspection
Delivery
A40HB6210 AG Piping on P/R Installation 12/28/2018
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support at new pipe rack
Cleaning
Insulation and installation of heat tracing
inspection
A40HB6230 AG Piping Around Equipment Installation 1/26/2019
Preparation
Installation of spool
Fullwelding of spool
Installation of pipe support
Fullwelding of pipe support
Cleaning
Insulation and installation of heat tracing
inspection
A40HB6500 Piping Steam Tracing 3/23/2019
Preparation
Lay-out / cutting
Fit-up
Welding
Cleaning
A40HB6800 Piping Test 4/6/2019
RT test
Hydrotest
Inspection
B100 : Interconnecting Existing Plant (P/R,S/L,Ditch)
Pre-shutdown Works (STL STR./Piping/Painting) 5/2/2018
B10HBA100 Surface Preparation and Primer Coat (existing P/R) 5/2/2018
B10HB6100 Piping Shop Fabrication (existing P/R) 5/2/2018
B10HB3100 Steel Pipe Rack / Bridge (existing area) 7/21/2018
Works During Shutdown (Piping) 8/11/2018
B10HB6210 AG Piping on P/R Installation(existing P/R) 8/11/2018
B10HB6900 Piping Welding/Tie-in (existing P/R) 9/1/2018
B10HB6800 Piping Test (existing P/R) 9/19/2018
Post Shutdown Works (painting/insulation/surface prot 9/29/2018
B10HBB100 Wrapping Work (existing P/R) 9/29/2018
B10HBA200 Finish Painting (existing P/R) 10/1/2018
B10HBA300 Lettering and Identify Marking (existing P/R) 10/31/2018
B200 : Interconnecting Pier Side
Pre-shutdown Works (Civil/STL STR/Equipment/Pip 5/17/2018
B20HB1240 Piping Demolotion (existing pier side) 6/7/2018
B20HB6100 Piping Shop Fabrication (existing pier side) 5/17/2018
B20HB6A10 Surface Preparation and Primer Coat (existing pier side) 5/17/2018
B20HB3800 Misc. Steel support (existing pier side) 6/22/2018
B20HB5500 Pig Launcher/Reciever Installation(existing pier side) 7/7/2018
Works During Shutdown (Piping) 7/3/2018
B20HB6210 A/G Piping on Piperack Installation (existing pier side) 7/3/2018
B20HB6230 A/G Piping Around Equipment Installation (existing pier side) 7/31/2018
B20HB6800 Piping Test (existing pier side) 9/6/2018
Post Shutdown Works (painting/insulation/surface prot 9/29/2018
B20HB9100 Hot Insullation (existing pier side) 9/29/2018
B20HBA200 Finish Painting (existing pier side) 9/29/2018
B20HBB100 Wrapping Work (existing pier side) 9/29/2018
B20HBA300 Lettering and Identify Marking (existing pier side) 10/15/2018
B300 : Interconnecting Arround Equipment
Pre-shutdown Works (Concrete/Equipment/Piping/Paint 7/30/2018
B30HB2300 Pump Foundation (existing) 6/30/2018
B30HB6901 Pump Installation (existing) 6/30/2018
B30HB6100 Piping Shop Fabrication (existing) 7/13/2018
B30HBA100 Surface Preparation and Primer Coat (existing) 7/13/2018
Works During Shutdown (Piping) 8/13/2018
B30HB6230 A/G Piping Around Equipment Installation (existing) 8/13/2018
B30HB6800 Piping Test (existing) 9/19/2018
B30HB6900 Piping Welding/Tie-in (existing) 9/1/2018
Post Shutdown Works (painting/Lettering/Marking) 10/1/2018
B30HBA200 Finish Painting (existing) 10/1/2018
B30HBA300 Lettering and Identify Marking (existing) 10/31/2018
Finish Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
2/28/2019
2/28/2019

11/17/2018

2/28/2019

4/3/2019
12/6/2018

1/14/2019

3/5/2019

3/14/2019
3/16/2019

2/14/2019

2/9/2019

3/12/2019

3/16/2019

3/4/2019

4/3/2019

5/22/2019
12/20/2018

9/29/2018
2/23/2019

4/26/2019

5/22/2019

2/27/2019
12/5/2018

2/27/2019

4/4/2019
2/1/2019

2/2/2019
4/4/2019

5/6/2019
12/29/2018

2/9/2019

4/5/2019

5/6/2019
4/4/2019
12/29/2018

3/4/2019

1/9/2019
12/12/2018

12/12/2018

1/9/2019

5/3/2019
12/29/2018

2/18/2019

4/3/2019
5/3/2019

2/21/2019
2/9/2019

12/19/2018

2/21/2019

3/14/2019
3/4/2019

2/14/2019

2/21/2019
3/1/2019

3/4/2019

2/16/2019

5/14/2019
12/29/2018

3/2/2019

4/15/2019

5/14/2019
5/14/2019

8/14/2018
5/25/2018
8/2/2018
8/14/2018
9/29/2018
9/6/2018
9/19/2018
9/29/2018
11/16/2018
10/30/2018
10/31/2018
11/16/2018
7/31/2018
6/30/2018
7/18/2018
7/3/2018
7/7/2018
7/31/2018
9/29/2018
9/4/2018
9/17/2018
9/29/2018
11/16/2018
10/30/2018
10/30/2018
10/23/2018
11/16/2018

8/24/2018
7/31/2018
8/24/2018
8/13/2018
8/6/2018
9/29/2018
9/7/2018
9/29/2018
9/19/2018
11/16/2018
10/31/2018
11/16/2018
Feb-19 Mar-19 Apr-19 May-19
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4