Footbridge Over The Bow River in Banff: Gerald Epp President, Structurecraft Partner, Fast + Epp
Footbridge Over The Bow River in Banff: Gerald Epp President, Structurecraft Partner, Fast + Epp
Summary
Set over the Bow River in the mountain setting of Banff is a slender 113m long timber bridge
both serving pedestrian traffic and providing a sensitive sanitary crossing replacement. Its
minimal form was designed to blend into the natural beauty of Canada’s first national park.
Completed in June 2013, the bridge was designed and constructed by StructureCraft Builders in
collaboration with Fast + Epp Structural Engineers for the Town of Banff, under a design-build
contract. Key to success of the project was careful attention to detailing, mitigation of dynamic
behavior, and a high degree of pre-fabrication.
It seemed evident that some form of damping system would be advantageous for user comfort.
Detailed dynamic loading models for each of the potential excitation scenarios were imposed on
the finite element model, and analysis of the time history acceleration response provided the first
estimates of performance under pedestrian excitation and the level of damping required.
Several damping systems were investigated, including
viscous dampers fastened to the bridge diaphragm, and
combined viscous and tuned mass dampers suspended
below the bridge deck. The final system adopted
comprised two asymmetric custom-designed tuned
mass dampers suspended on cables at quarter points
beneath the central span of the bridge. The dampers
were created using a cradle which had the capacity to
hold different numbers of tuning mass plates. This
cradle was suspended from the bridge above with two
sets of cables, of particular lengths and stiffnesses.
Figure 8 - Tuning of mass dampers before erection
4. Fabrication
A parametric 3D solids model of the entire bridge was created early on in the design process,
allowing rapid and detailed investigation of a multitude of design decisions, providing visual
feedback to both
designer and client. The
model grew through the
design process to include
every component of the
bridge – from the
surrounding topography
to the giant glulam
beams to the minimal
guardrails. The
Figure 9- 3D parametric model parametric nature of the
model allowed it to respond seamlessly to changes in global form and reflect them down to the
smallest level of detail.
The model was critical to many parts of the design process, from early visualization and
rendering, to cut-and-fill calculations on the site, trucking viability, and fine tuning the aesthetics
of the tuned mass damper beneath the bridge. Most importantly the model was used to create
detailed fabrication drawings for each piece of the bridge. The link between model and drawings
ensured drawings remained accurate even as the design evolved.
As the Glulam beams are curved, the parametric model contained both ‘states’ of the beams –
pre-bent (straight, prior to cutting) and post-bending (arched and cut to length), allowing
accurate dimensional checks to be performed at each of the manufacturing stages and an accurate
appraisal of erection weights.
Comprehensive part numbering and component scheduling within the model provided accurate
material take-offs and ensured all pieces were assembled correctly on the site.
Fabrication of all timber elements occurred in the shop. The direct proximity of the fabrication
shop and the design team allowed full-scale ‘rapid prototyping’ of many of the key components
of the bridge. Handrails, stanchions, and deck panels all went through several mock-ups and
design iterations before settling on a final design optimised for both form and aesthetic.
Throughout the design and fabrication process, the delivery model led to a natural desire to
create efficiency: similar to the manufacturing industry, conceptualisation, design, modelling,
testing, fabrication, and erection takes place in-house, allowing each step of the process to be
influenced by the other steps.
5. Erection
A tight, remote site, huge structural elements, and harsh winter weather all combined to make the
bridge erection a challenge. This, coupled with a desire to complete the lifts before spring thaw
and a firm arrival date for a large mobile crane put a huge emphasis on ease and accuracy of
assembly in the field.
The main structural elements of the bridge were too large to be transported to the site in modules
ready for installation; and fitting up the pieces over the river with a smaller crane would have
presented significant environmental and safety challenges. In order to accurately assemble and
erect the bridge, the individual elements were prefabricated in the shop and shipped to site as a
kit of parts. All cutting, drilling, sanding and finishing was performed indoors under controlled
conditions so that members were protected from the elements both in transit and on site. Jigs
were built to ensure accurate assembly of the main bridge components in the field. The stepped
glulam girders were paired up and joined by long fully threaded screws through pre-drilled holes.
Once the beams were levelled and squared to each other, the diaphragm webbing was connected
with friction grip bolts to the receiving plates which were fastened to the innermost glulam face.
During the final preparations for the big lift,
temporary walking planks and safety lines were
installed to provide immediate access to the bridge
sections after installation. Additionally, several
survey targets were installed to the girders, both at
the abutment end and at the tips which would
receive the drop-in span. This allowed real-time
verification and placement of the bridge sections and
fine tuning of the hold-down rods at the abutment
ends to compensate for dead load deflection of the
Figure 11 - Erection of south girders girders and the drop-in span.
In all, the entire bridge superstructure was erected
in 3 lifts over 2 days with an additional day spent
relocating the crane to the North bank of the river.
The tapered girder assemblies weighed in at over
50T while the drop-in span, complete with tuned
mass dampers, maxed out the 500T crane at just over
20T and a radius of 45m. The bridge sections rested
within 12mm of their target coordinates and the
drop-in span “fit like a glove,” according to the
erector.
6. Dynamic Testing
The desire for field testing of the bridge arose early in the design
phase and gained traction as the importance of its dynamic behaviour
came into focus. The testing was primarily required to provide
experimental validation of the structure’s natural frequencies; but a
number of additional tests were performed which provided
estimations of modal damping as well as measurements of pedestrian
induced accelerations for comparison with user comfort criteria.
This information allowed for precision tuning of the dampers and
quantification of their effect on user comfort.
A variety of tests are available to determine dynamic properties of Figure 13 - Dropping over tie-down
rods at abutment
structures, however, the Ambient Vibration Test stood out as the
most appropriate and convenient method. Due to the current availability of high precision
sensing equipment and sophisticated data analysis software packages, experimental modal
estimation, which once required extensive equipment, custom software, and precise knowledge
of the input forces and frequencies, can now be performed with a few accelerometers and a
laptop. The test setup involves positioning of accelerometers at locations of maximum estimated
modal displacement which are set to record simultaneous data sets of the accelerations measured
under ambient vibration of the structure.
The testing of the Banff Bridge utilized a commercially available software package for the
determination of the natural frequencies and associated mode shapes. The software applies local
degrees of freedom to the global geometry where accelerometers are to be placed. Higher
accelerations resulting from resonance at the structure’s natural frequencies appear as peaks on a
frequency vs acceleration plot, which made the modal frequencies easily identifiable. Finally, by
selecting the peaks on the graph, the software animates the dominant motion of the structure as
measured by the accelerometers. In this way we were able to visually confirm which mode
shapes we were measuring and compare with the analytical model.
Figure 14 - 2nd torsional mode (from AVT) Figure 15 - 2nd torsional mode (analytical model)
Acceleration (g)
0.035
Acceleration (g)
1.04
1.02 0.03
1 0.025
0.98 0.02 y = 0.0332e-0.416x
0.96 0.015
0.94 0.01
0.92 0.005
0.9 0
0 5 10 15 0 1 2 3 4 5 6
Time (s) Time (s)
Figure 17 - Excitation and free decay of 2nd torsional mode Figure 18 - Fitting of exponential curve to free decay response
Since the two tuned mass dampers were designed to mitigate motions excited by the 2nd vertical
and 2nd torsional modes of vibration, these were of particular interest. The 2nd vertical mode was
predicted to be at 1.9 Hz and the damper’s vertical stiffness & mass were proportioned to have
the same natural frequency with room to add or remove mass for tuning. The measured
frequency of the 2nd vertical mode was significantly lower than anticipated at 1.5 Hz; meaning
the structure was softer than predicted, likely due to uncertainty in modelling the boundary
conditions. Frequency follows equation (2) and being unable to alter the stiffness provided by the
= 2 (2)
cables suspending the carriage, the mass needed to be increased by over 600 kg (or 60% of its
predicted mass) for which we had made sufficient allowance in the damper carriage. By
contrast, the 2nd Torsional mode was predicted to be 3.1 Hz and was measured at 3.3 Hz. This
required an increase of only 50 kg to 375kg total. Once the masses of the dampers had been
calibrated to the bridge’s natural frequencies, an additional set of resonance tests was performed
for both the 2nd vertical and 2nd torsional modes. The accelerations and structural damping were
compared with the baseline tests performed before tuning.
The tuned mass dampers improve the dynamic performance by preventing the accelerations from
reaching unacceptable levels by participating in and out of phase at the natural frequencies; thus
preventing a resonant response. The results of the before and after tuning resonance tests
showed that the damping ratio increased slightly but remained at a relatively low 1.5-2%
depending on the mode under consideration. Vertical accelerations were reduced by over 50% to
less than 1 m/s2 during excitation of the 2nd vertical mode.
In order to calibrate the model to match the field tested frequencies, very small adjustments to
suit the boundary conditions between the drop span and haunched girders as well as the bearing
surface between the girders and the precast pier cap brought the analytical frequencies precisely
in line with measured values. This sensitivity to actual site conditions is a major reason why
there is a continued need for field testing of vibration controlled structures.
7. Conclusion
Footbridges are an excellent opportunity to exploit the use of timber, especially in beautiful
settings. However great care in design and execution must be taken to account for its unique
properties, and to ensure the structure will remain an enhancement to the setting which all can
enjoy for many years to come. Proper credit goes to all involved, including a sympathetic client
with great aspirations!
Figure 19 - Finished bridge south bank Figure 20 - Finished bridge south elevation