Sample Re-Entry Osh Plan

This document outlines an occupational safety and health (OSH) re-entry plan for a construction company. The plan identifies 7 areas of concern: lack of an OSH policy; safety officer without proper accreditation; no OSH committee established; lack of emergency preparedness procedures; no inspection procedures for workplaces, equipment, and tools; no inspection and tagging of scaffolding; and lack of safety data sheets for site chemicals. For each concern, the plan lists action steps to address the issue, assigns responsibilities, and establishes target timelines. The overall goal is to develop the necessary OSH programs and procedures to ensure workplace safety and compliance with Department of Labor and Employment regulations within 2 months.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
67% found this document useful (6 votes)
16K views

Sample Re-Entry Osh Plan

This document outlines an occupational safety and health (OSH) re-entry plan for a construction company. The plan identifies 7 areas of concern: lack of an OSH policy; safety officer without proper accreditation; no OSH committee established; lack of emergency preparedness procedures; no inspection procedures for workplaces, equipment, and tools; no inspection and tagging of scaffolding; and lack of safety data sheets for site chemicals. For each concern, the plan lists action steps to address the issue, assigns responsibilities, and establishes target timelines. The overall goal is to develop the necessary OSH programs and procedures to ensure workplace safety and compliance with Department of Labor and Employment regulations within 2 months.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SAMPLE

NAME: LOCATION: DATE:


ENGR. ALEX TRILLANA
RE-ENTRY OSH PLAN MALOLOS CITY 7TH AUG 2016
CONCERN (PROBLEM) ACTION PLAN RESPONSIBLE TARGET TIME STATUS
1. OHS policy not yet establish  Develop OHS policy and approval GM/PM/SM Within 2 weeks In Progress
 Roll-out [dissemination] and displays GM/PM/SM Within 2 weeks and In Progress
onward
2. Safety Officer in-charged no DOLE  Comply to DOLE training requirements for Safety GM/PM/SM Within 2 months In Progress
accreditation Officer
 Submit CV and credentials to DOLE for evaluation GM/PM/SM Within 2 weeks In Progress
 Establish OHS Committee GM/PM/SM Within 2 weeks In Progress
3. OHS committee not yet develop  Conduct OHS meeting and record minutes of meeting GM/PM/SM Monthly In Progress
 Submit to DOLE for compliance GM/PM/SM Monthly In Progress
 Develop emergency preparedness procedure [for fire, GM/PM/SM Within 2 weeks In Progress
4. Emergency preparedness procedure earthquake, typhoon, flood, lightning, spills, etc.] and
not yet develop approval
 Conduct training to all ERT members GM/PM/SM Within 2 weeks In Progress
 Carry-out drills as per the procedure PM/SM Monthly In Progress
 Develop inspection procedure and approval GM/PM/SM Within 2 weeks In Progress
5. Workplace and  Carry-out quarterly inspection [tagging/sticker PM/SM Quarterly In Progress
equipment/tools/devices Inspection system] to all equipment/vehicles/tools/devices
not yet develop  Carry-out weekly workplace inspection PM/SM Monthly In Progress
 Carry-out pre-inspection of equipment /vehicle Operator/ Driver Daily In Progress
6. Scaffolding no inspection and  Develop/revise scaffolding procedure GM/PM/SM Within 2 weeks In Progress
tagging  Carry-out scaffolding and tagging PM/SM Before Use/ In Progress
Monthly
7. No SDS for site chemicals  Collect SDS from suppliers PM/SM Within 2 weeks In Progress
 Compiled and distribute across the site PM/SM Within 2 weeks In Progress
 Discuss in TBM PM/SM Before Use In Progress
Add more concerns….. --- --- --- ---
Notes: In your own re-entry plan, you may add more controls In your own re-entry In your own re-
plan, reflect the specific entry plan,
target time reflect the
reason of delay

5MCSS RE-ENTRY PLAN REV0