Lean Manufacturing - TWI Case Study Model Answers PDF
Lean Manufacturing - TWI Case Study Model Answers PDF
Model Answer
TWI Current State Map
Order
60 days
Orders Production OE + after market
Rod + Forging
Control customers
suppliers Size adjust
2 weeks
Daily priorities
Shop order
2x Month
Daily
Weld area
Machining Supervisor
30 secs 30 secs 30 secs 30 secs 195 secs Value Add = 315 sec
The Eight Questions and Answers
1. What is the Takt Time?
We have 15 hours per day, and 20 days per
month.
= 300 hours per month
= 1080000 seconds per month
Demand = 24000 pieces per month
Therefore Takt = 1080000/24000
= 45 seconds per item
2. Should TWI build to a finished goods supermarket or
direct to shipping?
Finished product variety
= 20 lengths x 2 diameters x 3 types of end
fittings x 2 ends
= 20 x 2 x 3 x 2
= 240 product types (plus any colour variations)
This is a lot of variety to keep in a supermarket – we
would need 240 locations
Also, if we can reduce lead time to less than 2 weeks,
then we will be sure of the customer order.
So, we should aim to build direct to shipping.
3. Where can we introduce continuous flow production?
In Assembly, we have 195 seconds of work. This is split
between 6 workers. So, if we can get an even split of the
work elements, we can get a cycle time of 32.5 seconds.
If we are careful, we should be able to split the work
elements to give a cycle time of 39 seconds with 5
workers. This is within the Takt time. This will be cell 2
Weekly
Daily
Forgings Machined
Machining
forgings
<1 Day 1 Day <1 Day Same day Lead time = 10 days
6 Days 1 Day
30 secs 90 secs 195 secs Value Add = 315 sec