100% found this document useful (2 votes)
669 views2 pages

Detailed Estimates For Main Materials

The document provides detailed estimates for materials needed for a pile cap including: - 185 cubic meters of cement, sand, gravel, and 237 pieces of 10.5m rebar - 591 pieces of 7.5m rebar and additional reinforcement bars - 20 kilograms of tie wire cut into 40cm lengths - 528 pieces of 0.5m weephole pipes totaling 264 meters - 2942 bags of cement, 197 cubic meters of sand, and 393 cubic meters of gravel for 392 cubic meters of rubble concrete

Uploaded by

Gama Liel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
669 views2 pages

Detailed Estimates For Main Materials

The document provides detailed estimates for materials needed for a pile cap including: - 185 cubic meters of cement, sand, gravel, and 237 pieces of 10.5m rebar - 591 pieces of 7.5m rebar and additional reinforcement bars - 20 kilograms of tie wire cut into 40cm lengths - 528 pieces of 0.5m weephole pipes totaling 264 meters - 2942 bags of cement, 197 cubic meters of sand, and 393 cubic meters of gravel for 392 cubic meters of rubble concrete

Uploaded by

Gama Liel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DETAILED ESTIMATES FOR MAJOR MATERIALS

PILE CAP
Cross-sectional Area: (actual calculation)
(0.50m x 0.6m) + (1.00m x 0.2m) + (0.5m x 0.2m x 0.2m) = 0.52 sq.m.
Total volume:
0.52m² x 354.0 m = 184.08m³, say 185 m³

Materials:
 Cement: Use 40kg. bag, class A (1:2:4)
185 cu. m. x 9.0 = 1665 bags
 Sand: 185 cu. m. x 0.5 = 92.5 cu. m.
 Gravel: 185 cu. m. x 1.0 = 185 cu. m.
 Ties:
 For 10mm diameter vertical bars:

2 x (364)

2 x (464)

464 mm 3 x (29) ------------- bending allowance

2 x (43) ------------- bending allowance

+ 2 x (100) ------------ hook allowance

2029mm, say 2.1 m

364 mm

Using 10.5m bar,


1pc. 10.5m bar= 5pcs. 2.1m
@ 354.0m total length with ties 0.3m spaced O.C.,
354.0m/ 0.3m= 1180pcs. + 1= 1181pcs.
1181pcs/ 5 = 236.2pcs = 237pcs 10.5m, 10mm dia. Bar

 For 12mm vertical bars

2 x 933
66
2 x 85
538
329
100
148
2 x 100
2 x (28) ------------- bending allowance
2 x (42) ------------- bending allowance
3557 mm, say 3.6 m
Using 7.5m bar,
1pc. 7.5m bar= 2pcs. 3.75m
@ 354.0m total length with ties 0.3m spaced O.C.,
354.0m/ 0.3m= 1180pcs. + 1= 1181pcs.
1181pcs/ 2 = 590.5pcs = 591pcs 7.5m, 12mm dia. Bar

 Reinforcement Bars (based on direct counting):

 Using 6m length for 16mm dia. rebars,


o No. of pcs. = 65 x 6 = 390pcs. 16mm dia., 6m bars
= 3693.3 kls. (based on standard weight of steel bars)
 Using 6m length for 10mm dia. Rebars,
o No. of pcs. = 65 x 10= 650pcs.,10mm dia.,6m bars
= 2405 kls.
 Total weight: 6098.3 kls.

 Tie wires:

 Cutting into 40cm length,


o No. of intersections (direct counting):
66 x (20 int., say 40) = 2640 intersections with allowance
2640 x 40cm = 1056m
= 19.92 kg, say 20 kg G.I. Wire
o Note:
1. One roll is equivalent to 45 kg or approximately 2385 meters at 53
meters per kilogram.
2. A 25 to 40cm long tie wire folded at the center is satisfactory.
WEEPHOLES

 354.00 ln.m. / 2.00m = 177pcs-1= 176


176 x 3pcs per cross section = 528pcs
Each weep hole= 0.50m length
Total length of pipe= 0.50m x 528pcs. =264m

RUBBLE CONCRETE (Class B mix),40kg

 Boulders = 784.29 cu.m.


 Concrete (estimated 50% of the total volume of the Rubble Concrete)
Volume: 0.5 x 784.29 cu.m. = 392.15 cu.m.

 Cement:
392.15 cu.m x 7.5 = 2941.125, say 2942 bags
 Sand:
392.15 cu.m x 0.5 = 196.07 cu.m., say 197 cu.m.
 Gravel:
392.15 cu.m x 1.0 = 392.15 cu.m, say 393 cu.m.