Burden, Spacing and Borehole Diameter at Rock Blasting
Burden, Spacing and Borehole Diameter at Rock Blasting
Environment
R. Agne Rustan
To cite this article: R. Agne Rustan (1992) Burden, spacing and borehole diameter at rock
blasting, International Journal o/Surface Mining, Reclamation and Environment, 6:3, 141-149, DOI:
10.1080/09208119208944329
ABSTRACT: Most text books on rock blasting claim that the relationship between burden and borehole diameter
is linear. The statistical calculation presented here with real values from one hundred open pit and
underground mines indicates that the relationship follows a power function. For underground mines the burdens
are consistently lower than those for open pit mines because of higher ore densities~ greater confinement
in blasting, and finally greater demand for well fragmented roc~. The results shown in this paper are
recommended to be considered in basic teaching of rock blasting technique. The formulas can be used for
a first rough estimation of practical burden and spacing. The formulas do not however give any information
about the fragmentation. For that purpose it is necessary to use other formulas not described in this paper.
• Charge diameter
den is linear.
- Dp.nsJty of explosive
- ne t cne t Ion heat
Langefors and Kihlstrom (1978) made a similar Taylor
- Detonation velocity (De~ends partly on borehole diameter)
- Decoupling ratio series development like Belidor,
Spec i f t c charge
Impedance ratio ot explosive to rock
(4)
• Delay time
• Scatter of delay in the detonator!"
• Number of delays used, and the use of deck charges initiated
Three more terms were used. The value of the constants
on d I fferent delays
• Sequence of initiation for Swedish hard rock are
RESULT PARAMETERS
Frngmenta t ion
leo = 0 k 1 =0.010 k 2 = 0.400
Throw
• DJgobJ lity
k 3 =0.004 and finally k j =0
for i:?: 4.
The most important parameter is the borehole diameter. The values for the differenttenns at Bel respectively 10
(We anticipate that the decoupling ratio of the charge is m will be the following
I throughout this paper).
The next most important parameter is the texture and Bclm BclOm
structure of the rock mass.
When the borehole diameter is known the charge can be
k1 om 0,1
k 2 0.40 4.0
calculated according to the following equation.
k3 0.004 0.04
reason for this, (Langefors-Kihlstrorn, 1978) is that the Co = c + 0.07/8 for B:s; 1.4 m
specific surface area is increased at small burdens. At c = blastability factor (kgim 3) (Necessary powder fac-
very large burdens the powder factor increases because the tor to break but not throw the rock).
volume increases rapidly and more and more energy is f = confinement of the borehole
needed for the throw of the fragmented material. Sd = drilled spacing (m)
Bd = drilled burden (m)
3 EMPIRICAL FORMULAS TO CALCULATE WE
MAXIMUM BURDEN RELATED TO 1HE BORE- The relation between burden and borehole diameter in
HOLE DIAMETER formula (6) is linear.
The maximum possible variation range of the maximum
First the formulas presented in basic literature on rock
burden can be calculated if the minimum and maximum
blasting will be presented. All these formulas illustrate a
values for the parameters within the square root symbol
linear relation between burden and borehole diameter.
are known.
Later on a new formula indicating a non linear relationship
Let us anticipate the following maximum values; Pc =
will be shown.
1600 kgim 3, s = 1.0, Co = 0.42 kgim 3, f = 1.0 and SdlBd =
3.1 Linear formulas 8 and the following minimum values; Pc = 800 kgim 3, s =
0.85, Co = 0.34 kgim 3, f= 0.75 and SdlBd = 0.1.
Langefors and Kihlstrom (1978) have developed an
Maximum values in the numerator are combined with
empirical formula to calculate the maximum burden. The
minimum values in the denominator and this gave the
constants ko, k\, k3, k4 were set to 0 in formula (4) and a
maximum value of 76 for the proportional constant in
correction factor for explosive properties, blastability and
formula (6). Minimum values in the nominator area were
geometric blast parameters were added.
then combined with maximum values in the denominator.
This gave the smallest value 14 for the proportional
Bm =0.958 d
~ Pe s
f S /B
I
(6) constant in formula (6).
Co (d d)
10
Powder factor (kg/m 3)
3,0
2,0
5
1,0
0,5
2 4 10 20 40 100
o 100 200 300 400
Borehole diameter (mm)
Burden (m) Fig 2. Relation between maximum burden (B m ) and bore-
Fig 1. Relation between burden and powder factor. hole diameter (d). Langefors and Kihlstrorn (1978), Ash
Langefors and Kihlstrom (1978). (1963), and Konya (1968).
144
The Langefors-Kihlstrom formula could therefore be Ash (1968) presented an emperical formula by Konya
written, see also Fig 2. where the maximum burden is proportional to the
diameter of the borehole.
Bm=(14t076) d (7)
Bm = 38 d~ (11)
An even more simplified version of the Langefors and
Kihlstrtim formula can be achieved if we anticipate that Bm = maximum burden (m)
the density of the explosive in the borehole Pe = 1.0, the d = borehole diameter (m)
weight strength s = 1.0, the corrected blastibility factor Co Pe = density of the explosive (kg/m3)
= 0.44 and finally Sd"Bd= 1.0. Pr = density of the rock (kg/m 3)
3.2 Maximum influence of explosive density and rock was not linear in open pit blasting. The following formula
density on the burden was derived by curve fitting.
Bm = (15 to 37) d (14) Usually the SIB ratio is equal to I for large borehole
diameters in open pit mines, but at borehole diameters less
than 100 mm, the SIB-ratio could vary between 1.5-2.0
This formula has been introduced into Fig 2 for and in extreme cases it could be as high as 8.
comparison with other linear relationships between burden
and borehole diameter.
If we anticipate common values for explosive density 4 POWER FORMULAS DERIVED BY STATISTICAL
and rock density, 1000 respectively 2800 kg/m 3, formula ANALYSIS
(II) can be simplified to
4.1 Underground magnetite mines in Sweden
(15)
To eleminate the influence of different rock densities,
values for borehole diameters and their respectively
3.3 Power formula developed for open pit mines
burdens were collected from magnetite orebodies at
Luossavaara-Kirunavaara AB (LKAB) and the Research
A diagram given in a brochure, from Atlas Copco showed
Mine at Luossavaara, see Table 2.
that the relation between burden and borehole diameter
The following formula was derived for the values given in
Burden (m) Table 2.
5
Table 2 Relation between practical burden and borehole
diameter when blasting in Swedish magnetite ore. Density
- 4800kg/m 3
fragmentation should be fine in underground blasting. This means that the best approximation of a Taylor
Another reason could be that the borehole length is series fit was
comparatively long compared to surface mines and hole
deviations have to be compensated by decreased practical (20)
burden.
Almgren and K1ippmark (1981) showed for example that However a power curve fit, see Fig 4, gave an even higher
drillhole deviations could cause additional costs for ore correlation coefficient and therefore the Taylor approxi-
losses and waste rock dilution when mining narrow mation formula 20 was not used.
orebodies. These costs might be as large as the operating
cost for sublevel stoping in large orebodies. B 1= 23.4 d O.855 +53 % Expected maximum (21)
Another reason is, that the boreholes can not be drilled p -33 % and minimum value
parallel underground, because the drilling drifts are too
narrow and the pillars between the drilling drifts too wide. Correlation coefficient R = 0.90
Only at the bottom of the borehole sufficient burden and
In Fig 4 each single value is evenly distributed above
spacings are achieved.
and below the power curve fit. Comparison is made to the
Langefors and Kihlstrom formula B m = 46 d.
4.2 Statistical derivation of formula for practical burden
Almost all values are below the Langefors and
(Bpi)
Kihlstriim curve for average Swedish rock. This means
that the Langefors and Kihlstrom curve is not valid for
The values used to derive formula (17) were very few,
large borehole diameters.
only three values and the zero point, and the basic values
From Fig 4 it can also be seen, that the values for
to derive formula (16) were also lacking. Therefore about
borehole diameters 165 mm underground are all below the
100 values for practical burdens and borehole diameters .
regression curve. This could imply that the burden and
were collected from different references. For example an
spacing used underground are too small. One explanation
extensive list from Canadian open pit mines by Dubnie
can be that this borehole diameter needs wider drifts and
(1972) was used. Other sources were Almgren (1988),
Nielsen (1986) and Bauer (1978). Together this represents
borehole diameters from 48 to 381 mm. Primary and
calculated data are shown in Table 3, see Appendix 1. Burden (m)
It is not sufficient to record the relation between burden
and borehole diameter because the powder factor is
determined by both the drilled burden (B d) and drilled
15
spacing (Sd)' In Appendix 1 the theoretical area per hole
has been determined, that means the product of BdSd' If •
the inclination of the bench face is 90 0 this product is the
same as Btl,Stl (practical burden x practical spacing).
The practical burden (Bpi) when spacing and burden are
10
equal was calculated according to the following definition.
•
B pl = ~ (18) •
A Taylor series fit was done for the relation between Bpi
and d according to the following equation
thinner pillars between the drifts to be able to give the 4.4 Statistical formula for underground mines (d = 48-165
boreholes a sufficient burden and spacing. Normally mm)
however it is not possible to increase the width of the drift
and decrease the width of the pillar due to the stability of The data from the 200 mm borehole diameter was
the drifts. neglected because they deviated very much from the gen-
There are however two underground mines, Mount Isa eral trend. It is also known that these large borehole
and Kidd Creek, using 90 m long and 700 mm diameter diameters can cause damage underground, and vibration
blastholes underground where the mean value for the restrictions on the surface might make it difficult to use
practical burden is very close to the regression line. This these borehole diameters in the future.
might imply a rational mining or the fragmentation may be
too large. The 200 mm boreholes were drilled with the rotary
crushing drilling technique. This method gives smaller
Fig 4 also shows that almost all underground values are borehole deviations. That could be one of the explana-
below the regression line. It was therefore necessary to tions why these borehole diameters can break a
separate data from underground mines from open pit data comparatively large area compared to the 165 mm
and make a regression analysis for each of them. boreholes. The latter borehole diameters are usually
drilled with the in the hole hammer technique.
4.3 Statistical formula for open pit mines (d = 89-381 mm) In Fig 5 the relation between practical burden and the
borehole diameter for underground mines is,
The following formula was derived for open pit mines.
BpI = 11.8 . dO. 630 +40 % Expected maximum (23)
-25 % and minimum value
B
pt
= 18.1 dO.689 +52 % Expected maximum (22)
-37 % and minimum value Correlation coefficient R =0.94
Valid for borehole diameters 89-381 mm The formula is valid for borehole diameters from 48 to
Correlation coefficient R =0.78 165mm.
~
formula, one for open pit mines (22), and one for
underground mines (23). Bpi = k2· dO.630 underground mines (25)
The basic formulas given in rock blasting text books are
recommended to be revised according to this information,
Other parameters like rock texture and structure are more
The reason why the underground formula is different
difficult to include in the formula, To include these
from the open pit formula might be
parameters it is necessary to undertake detailed structure
and strength analysis of the rock mass in many operations.
,.. Larger confinement of the boreholes underground.
,.. Cautious blasting has to be undertaken close to the
hanging- and footwall underground. 7 ACKNOWLEDGEMENTS
,.. The borehole length is larger underground and the
borehole deviations have to be compensated for a smaller Lulea University of Technology is thanked for its financial
burden and spacing. In open pit mines all boreholes can support of this study and Prof. G. Almgren and MSc M.
be drilled parallel to each other and the borehole deviation Kuchta for their good comments during the work. The
are small at large diameters. The bench height is generally doctorial students H. Wirstam and A. Mansson are also
only 15-20 m. thanked for their kind help in doing the statistical
computer analysis.
One reason that the relationship for open pit mines is not
linear is that when the borehole diameter is increased the
bench height is not scaled up, and for large drill hole REFERENCES
diameters only bottom charge is therefore used to break
the rock. It is however a well known fact that the rock Almgren, G. and Klippmark, K., 198 I. Economic aspects
will fragment better if the bench height is increased. on hole deviation in sublevel stoping, Internat. Conf, on
When the boreholes are gelling futher and futher apart it Caving and Sublevel Stoping, Nov 18-20, Denver,
is also necessary to use a higher powder factor to keep the Colorado, USA.
fragmentation below acceptable values. Almgren, G., 1988. Main Course in Mining, BT 203, Part
The Langefors and Kihlstromformula presented· in Fig 2. Lulea University of Technology, Lulea, Sweden. (In
I, is not correct in the burden range 1-10 m, because Swedish).
accordning to the diagram the powder factor should be Ash, R.L., 1968. The design of blasting rounds. Surface
almost constant, but the statistical analysis shows that the Mining, Chapter 7.3, AIME, New York.
powder factor (kglm 3) increases with burden according to Ash, R.L., 1963. The mechanics of rock breakage. Part I
Fig 5. Only at a linear relation between the burden and through IV, Pit and Quarry 56, 2 through 5 (August
borehole diameter the powder factor (kglm 3) will be through November, p 98,100,112,118-123,126-131,
constant. 109-11 1 and 114-118.
Probably the burden and spacings are too small when Ash, R.L. and Pearse, G.E., 1962. Velocity, hole depth
using 165 mm boreholes underground. If the boreholes related to blasting results. Min. Eng, No. 14, Sept. 9, pp,
can be arranged parallel and drilled with smaller borehole 71-76.
deviations it might be possible to increase the burden and Atchison, C., 1964. Comparative studies of explosives in
spacing from 3.8 x 3.8 m to 4.8 x 4.8 m. granite. Second series of test. USBM RI 6434.
Atchison, C., 1968. Fragmentation principles, Surface
Mining, (Editor Pfleider), pp. 335-372, (AIME, New
6 FUTURE WORK York).
Atlas Copco. Bench drilling catalogue. Know how and
This is the first step to create a more scientific rock equipment, p. 13.
blasting formula for calculation of the burden related to Bauer, A., 1978. Trend in drilling and blasting. CIM Bul-
the borehole diameter. It was found mathematically that letin, Sept, p. 81-90.
the power formulas presented in the paper might be Brannfors, S., 1973. Rock Blasting Technique. Norstedt
improved if the explosive density and rock density are in- och Stiner. (In Swedish).
troduced into the formulas like in formula (11). New Dubnie, A., 1972. Surface mining practise of Canada.
proportional constants have therefore to be derived. The Mines Branch Information Circular 292, Oct., p. 38-39.
influence of rock density and explosive density must Lama, R.D. and Vutukuri, V.S., 1972. Handbook of
however be examined by field tests to get the correct Mechanical Properties of Rock, Volume II. Trans. Tech.
values of the constants k t and k2 in formula (24) and (25). Publications.
Langefors, U. and Kihlstrom, B., 1978. Rock Blasting.
~
Almquist and Wiksell.
Bpi = k l . dO.689 open pit mining (24) Leins, W., Thurn, W. 1970. Ermittlung und Beurleitung
der Sprengarbeit von Gestein auf der Grundlage des
149
Steep Rock
5
5
5
Non 'e ore 219
Waste 2 J9
"9 .. ,
10.0
J1.3
10.0
11.3
~.5
100.00
J27.60
23.65
)0.00
) 1. 30
4.86
specific charge (powder factor), geometric scale and
physical properties of homogeneous rock on frag-
(Can)
CirJtfHh (CanJS
S
Waste
We.Urob (Can) S Waste
• 5 Ore
229
229
229
"9
..... ,
S.'
7.S
6.'
7.6
...9
4.3
40.96
57.76
21.07
18.49
6."0
1. 60
4.69
'.30
mentation by blasting. First Internat. Symp. on Rock Ca.alar teen} S
ClJnton (Canl S
Asbestos
Aabe.toa
279
220
S.l 6.1
5.5
37.21
30.25
6.10
5.50
'.S
Fragmentation by Blasting, Aug. 22-26, Lulea, Sweden. Savaoe RIver S Fe 220 8.0 8.0 4e.00 6.92
ITanlanlen)
Rustan, A., 1981. Factors influencing fragmentation at AnvU ICan) 5 Non Fe are 229 8.1 6.1 37.21 6.10
5 Waste 729 7.0 7.0 49.00 7.00
blasting, Literature review. Lulea University of BrunswJc1c 5 Non Fe 229 8.1 6, ) 31.2) 6.10
(Can)
Technology, Technical report No. 1981:38 T. (In
Swedish).
[eatell (Can) S
Pho~nllt ICan) S
Cranlale ICanlS
•
Cla.rabelle-
• S
S
Non Fe ore 229
Non r e ore 729
Non r. 229
s, ,
8.5
4.9
9.1
11.0
9.7
56.95
24.0)
.'.!o3
60.50
DO.'"
1. 55
".90
".89
1.78
1.10
(Can)
Enda1co (Canl
S
S Hon Fe
".
or. 229
8.1
S.l
6.1
6.7
37.21
"0,87
6.10
6. "
AHUt ISw) S Cu. Au 251 7.8 9.5 71.2& 8.44
GrUtHh ICan)S Ore 251 7.' 7.9 62,41 7.90
Appendix I. scnerreevrrre S Ore 251 8.' 8.2 67.24 8.20
(Can'
Canada 5 Hard • .10101'- 251 7.0 7.0 49.00 7.00
cant Fe
Carol (Can) 5 Ore :151 7.3 7.3 63.29 7.30
Table 3. Drilling dam used for determination of the relation 5 Waste 251 7.8 7.6 51.76 7.60
5 Ore 251 8.7 1.3 48.91 6.89
between burden, spacing and borehole diameter S Ore 251 7.0 7.6 53.20 7.29
5 Waste 251 S.7 7.3 48.91 6.89
5 Wast!!! 251 7.8 8.2 62.32 7 .119
Hooae MountainS Ore 251 8.1 8.1 65.61 8.10
type Ore-type Hol. Pract. Pract. Bro- Pract. (Can) 5 Waste 251 8.' 8.2 67.24 8.20
7.9 8.7&
dlame-
t.r
burden hole
dist.
k.n
area
burden
IS/B-l)
Wabuah (Can) 5
CJJnton (Can) 5 Waste '"
251 8.1
7.9
9.7
15.1
16.63
37.21 6 .10
9.02
e
("'1 ~g, ('~I ~gl Bethlehe. S Non Fe '"
251 S.l
10.3
6.1
81.37
37.21 6.10
Norway
)foTway
LKAB (Sw)
Ug
Up
U9 MagnetHe
.8
51
52
].1
1.8
1.8
1.5
2.0
2.5
2.55
3.60
... 50
1. 60
1. 90
2.12
ICen)
EcsulJ (Canl S
Ga.pe (Can)
Dibraltar
(Canl
S
S
Non Fe 251
'"
'"
...
S.7
S.7
.5
.7
7
56.95
.7.63
. . . 89
Norway Ug 62 2.0 2.4 LBO 2.19
Horway Ug 61 2.0 2.0 ".00 2.00 PJpe Lake S acn Fe 251 7.0 .0 49 00 1.00
vr ee er r e A8 Ug CU 10 1.8 1.8 3.2" 1. 80 (Can)
(Sw) Shdl1cameen S Non Pe 251 8.7 (,.7 ".99 e . 70
LKAB (Sw) Og Magnetite 76 2.6 2.1 5.2& 2.29 (Can)
SSAB/Grangea tJg MagnetS t e 76 2.1 L8 3.18 ].9 .. Brenda (Can) 5 251 7.9 9.7 76.63 8.7&
tSw) Toa Price (Au) 5 Fe 300 8.0 Il.O 64,00 8.00
vr ee er r e AS 09 Cu 89 2.3 2.3 5.29 2.30 Mount Iaa IAu)S 310 9.0 104 93.60 9.67
Canada S nard. 10101'- 311 7.9 7. g 62 • .fi1 7.90
IS"')
Tun08ten (CaniS Non Fe ore 89 2.1 2.1 4.41 2.10 cont Pe
Nordkalk "9 5 r.ree e rcne 96 2.5 ~.O 12.50 3.5 .. Sherman (Can) Fe-ore 311 8.' g.) 77.35 8.79
IS"'1 95 3.0 6.0 18.00 4.24 Wa.te 31J 8.' 9.1 77.35 8.79
Vhcar1a AS UQ Cu 104 3.0 3.0 9.00 3.00 Cartier (Can) Fe-ore 311 S •• 8.8 56.32 7.50
(SM) Waste 3)) 9. I 9.. 85.5. 0.26
LKAB (Sw) Ug- M39netHe 104 2.' 2.5 6.25 2.50 Toa Price IAulS ,. 360 8.0 8.0 64.00 8.00
B-C (Can) S Asbestoa 104 3.7 4.6 17.02 ... 13 Hount Wha]e- S Fe 380 10.0 11.0 170.00 13.04
It-B tcent S 104 e. 6 ".6 2L16 01.60 back (Au)
Jeffrey (Can) S 104 3.7 e.6 17.02 ... 13 Canada Hard. 10W'- 38) 9.1 9.1 02.0) 9.10
Carey tCan) S 104 4.0 ... 9 19.60 4.43 cant Pe
GullhOgen ISwjS LIDPstone 10~ 4.0 4.0 16.00 01.00
Mount r ee {Au)Ug Pb 11~ 3.0 4.5 13.~0 3.n Abbreviation. uaed:
Plnp Point S Non FI! ore 121 ... 6 ".6 21.16 '.60
fCan}
Reeves fCan) S aebe e t ce 127 4.3 5.~ 23.65 4.86
S - Surtace Au • Auetra11a H • Norway
U~ • Underground Can • Canada Sw Sweden
NaUonal (Can)S Asbe!ltos 127 01.3 4.9 21.07 4.59
Zink Corp (Au)Ug Pb. Zn 159 2.0 8.0 16.00 •. 00
B-C fCan) S Asbt-Sto5 159 5.5 6.7 36.85 6.07
NOTlftandh: S Asbestos 159 6.1 6.7 40.87 6.39
ICan)
t.ces eeveer-e Uc;;r Mac;;rn~tHe 165 .3 3. ) 2 . 21 3.49
Rl!searchmlne
15w)
Cobar (Au) Ug Cu. Pb . Zn 165 4.0 e .c 1': .00 •. oc
Copppr Cliff Og Nl. Cu 165 4.0 '.0 H.OO ".00
(Canl
Little StobIe Og Nl. Cu 165 3.7 3.7 13.69 3.70
ICan)
Lockprby ICanlUg Ni, Cu 16~ 3.3
Broken Hill
(Aul
tac Tl0 (Can)
Ug Pb.
Waste
Or.
Zn
'"
'"
JS,
.....,.,, •. 0
,.,
S.'
14.00
29.H
22.36
3.14
5.43
... 73