The procurement department of a company consists of many buyers who are responsible for
buying goods from the market. There is a hierarchy of people like the operator or the buyer
who creates the order and purchasing managers to supervise and control the procurement
process. Since purchase order is a legal document and it goes outside the company to the
vendor, it is very much important to control the process to avoid any errors or unauthorized
transaction. When the Purchase order is processed further for goods receipt and invoice
verifications, there will be accounting entries generate and it creates Accounts Payable entries
(AP).
Because of this reason and legal implications of Purchase orders, it is very much required to
control the procurement process by introducing approvals. For the same, SAP has provided a
concept of release strategy. In release strategy, there are different released codes which are
used for designated users. The release code is a two character ID allowing a person to release
(clear, or approve) a purchase requisition or an external purchasing document. The release
codes are basically controlled via a system of authorizations (authorization object M_EINK_FRG).
The user with specific release code assigned can perform a respective release in a purchase
order. For example, the user who creates the purchase order is assigned the lowest level release
code. When the purchase order is saved or checked, system will trigger the Release Strategy for
that document depending on the defined criteria. In the purchase order which is required to be
released by a higher level user, there will be a Release Strategy tab on header of the PO
document. In this tab, system shows all the levels of release codes who are involved in
approving the purchase order. Following practical example will demonstrate the purpose of
release strategy and its implementation in SAP.
If the value of Purchase order is less than 500.00 USD, it can be approved by a Purchase
Manager and then can be processed further.
When the Purchase order value exceeds 10000.00 USD, in addition to the purchase
manager, it requires an additional approval of Head of Department.
If the value of PO is more than 50000.00 USD, then it needs an approval of Vice
President once it is approved by the Manager and then by HoD.
To achieve this, there will be four release codes created in the system.
Now with this requirement, following release code will be attached to each document
depending on the value of the PO.
A Purchase order of value 12500.00 USD will have 10, 20 and 30 release codes. First
release will be user with release code 10; second release will be by user with release
code 20 and then final release by HoD who has release code 30.
Before we start configuring release strategy in SAP, we need to define the combination of
parameters to trigger the release. This triggering criterion can be a combination of Document
type and Purchasing organization along with value depending on which the number of release
codes are assigned when the document is created. In SAP we have a run time structure with
name CEKKO (Communication Release Strategy Determination Purch. Document) which
provides all the possible list of fields using which a release strategy can be configured. To view
all this fields of the structure you can use transaction code SE12. In SE12 screen, in the database
field provide the structure name CEKKO and click on Display button.
Let us assume that we want to configure the release strategy based on the combination of three
fields. These fields are Document Type (CEKKO- BSART), Purchasing Organization (CEKKO-
EKORG) and Purchase order total value (CEKKO- GNETW). We need to create individual
characteristic for each of this field and then group them into a release class. Please follow the
steps given below to create characteristics.
Provide the characteristic name and click on Create button to create the characteristic. Give
appropriate and meaningful name for each characteristic so that they become easy to identify in
further process.
In Basic Data of characteristic screen, provide appropriate description. If you want to configure
the release strategy for single document type, you need to select Single Values in Value
Assignment block and if it is required for multiple document type then select Multiple Values
radio button.
Now navigate to Values tab and provide the document types which are required in this release
strategy. For this example, we are taking document type NB which is Standard PO. Please see
below screen shot.
We need to make sure that these characteristics are used only in class which is made up for
Purchase order release. For this purpose we need to provide the restriction in characteristic.
Provide class type 032 in the restriction tab to achieve this.
If the system is used in multiple languages and if it is required to maintained the characteristic
description in multiple languages, then the same can be done from the description tab. Please
navigate to Description tab and for each language and save your characteristic.
Using the same method creates another characteristic BP_PURORG for Purchasing Organization.
For third characteristic which is Purchase order Net value, we need follow the same steps except
the below points:
When you mentioned the Structure name CEKKO and field GNETW for purchase order
net value, system will ask for the currency since this field is related to numbers and net
value of purchase order. Please mention USD as a currency for the characteristic.
If you have multiple criteria for different range of values, the same has to be provided in
Values tab with a Multiple Value radio button tick in Basic data.
Since there will be intervals in the purchase order values, you have to configure the
characteristic to allow the values in intervals. For the same please tick the check box
“Interval Vals allowed” in Value assignment block in Basic data tab.
BP_NETVAL for Net Value below 100.00 USD and above 100.00 USD
Once we have all the characteristics ready with us, we need to group them into a class. Please
see the below procedure to create the class.
SPRO Menu Path: SPRO: Material Management -> Purchasing -> Purchase Order -> Release
Procedure for Purchase Orders -> Edit Class
In main screen of CL02 transaction, provide appropriate Class Name and click on Create button.
Make sure that the class type must be 032.
In the detailed screen, provide appropriate description. In Same classification block please select
Do not Check radio button.
Now the next step is to assign the earlier characteristics to this class. Please note that those
characteristics are restricted to be used only in class type 032 which type this class is to be
created.
After the class is ready, the next is to configure the elements required in release strategy.
Following elements are required.
Release Groups
Release Codes
Release Indicator
Release Strategies
Workflow
Use following SPRO path for configuring these elements of release strategy.
SPRO: Materials Management -> Purchasing -> Purchase Order -> Release Procedure for
Purchase Orders -> Define Release Procedure for Purchase Orders.
When you click on this option, system will give sub options to proceed further. Please select
Release Group. Keep the cursor on Release Group and click on Choose button.
Use following SPRO path for configuring these elements of release strategy.
When you click on this option, system will give sub options to proceed further. Please select
Release Codes. Keep the cursor on Release Codes and click on Choose button.
Click on New Entries to create the Release codes for our release strategy. Number of release
codes depends on number of approval levels. Here only two release codes are created which are
10 and 20 for Buyer and Manager respectively. Please note that these release codes are to be
created under the same release group which we have configured in previous tab. Click on Save
to save your entries.
Use following SPRO path for configuring these elements of release strategy.
SPRO: Materials Management -> Purchasing -> Purchase Order -> Release Procedure for
Purchase Orders -> Define Release Procedure for Purchase Orders.
When you click on this option, system will give sub options to proceed further. Please select
Release Indicator. Keep the cursor on Release Indicator and click on Choose button.
This screen indicates release id for initial and released status. Release ID 0 indicates Blocked
status and with release ID 1 it is Released status. The field Changeable contains the parameter
which will define how the system reacts if a purchasing document is changed after the start of
the release procedure. Means once the order is released, we can still change the values in
purchase order which will trigger a new release status. If the field is allowed to change, we can
define the % of change allowed.
Use following SPRO path for configuring these elements of release strategy.
SPRO: Materials Management -> Purchasing -> Purchase Order -> Release Procedure for
Purchase Orders -> Define Release Procedure for Purchase Orders.
When you click on this option, system will give sub options to proceed further. Please select
Release Strategies. Keep the cursor on Release Strategies and click on Choose button.
Click on New Entries button and give your release group. After giving the release group, provide
appropriate Release strategy and description.
Now suppose you want to keep only one level of approval for all PO below 100.00 USD and 2
level of approvals for PO greater than or equal to 100. To achieve this we need to have two
release strategies. First release strategy will have only 1 release code and only value less than
100.00 USD is to be selected from characteristic BP_NETVAL. For the Purchase order having
value greater than or equal to 100.00 USD, we will create another release strategy which will
have both the release codes as we need two level approvals in this case. The following steps are
demonstration of second release strategy (with 2 approvals). The same steps needs to be
followed for another strategy.
Next step is to select the classification values for the selected characteristics in release class.
Click on Classification button to proceed.
Please note it is also possible to directly mention the values here provided Additional Values
option is enabled in your characteristic.
Configure Workflow
Use following SPRO path for configuring workflow for the above configured release strategy.
SPRO: Materials Management -> Purchasing -> Purchase Order -> Release Procedure for
Purchase Orders -> Define Release Procedure for Purchase Orders.
When you click on this option, system will give sub options to proceed further. Please select
Workflow. Keep the cursor on Workflow and click on Choose button.
This is the end of release strategy configuration. With this configuration, we are set to create a
purchase order to test our release strategy.
Please note that if the purchase order is not released, buyers will not be able to print the
Purchase Order. Also in Goods Receipts will be shown with Message no. ME 390 – Purchasing
document XXXXXXX not yet released
Purchase Order with Release Strategy has tabs at the end of the Header. This allowed the buyers
to check the release status of the Purchase Order.
The person with the release authorization has to use ME28 to release the Purchase Order.