Chapter 5.3
Chapter 5.3
Chapter 5.3
Drainage below ground
5.3 Drainage below ground
CONTENTS SCOPE
Clause Page
DESIGN This Chapter gives guidance on meeting the Technical
Design standards D1 1 Requirements and recommendations for the design and the
Statutory requirements D2 1 construction of foul, surface water and ground water drainage
systems.
Drainage system design D3-D6 1-2
Design to avoid damage D7 2
Foul and surface water disposal D8 3
Ground water drainage D9 4
Provision of information D10-D11 4
MATERIALS
Materials standards M1 4
Drainage materials M2 4
SITEWORK
Sitework standards S1 5
Preliminary work S2 5
Excavation S3 5
Laying pipework S4 5
Protection of pipework S5 6
5.3
APPENDIX 5.3-A
Minimum dimensions for access fittings 9
and chambers
APPENDIX 5.3-B
Percolation test procedures for septic 10
tank installations
APPENDIX 5.3-C
Septic tank field drain design 11
APPENDIX 5.3-D
Cross section of typical underdrain 12
APPENDIX 5.3-E
Percolation test procedures for surface 12
water soakaways
INDEX 14
5.3
be installed on the surface water side of
as by the Local Authority, Building Control least 7m from a dwelling and within 30m of
the foul sewer junction, or trapped gullies
Authority and NHBC. a vehicular access to permit emptying. In
should be used.
Scotland they should be at least 5m from a
Sewers which are to be adopted under an surface water manhole
dwelling and a boundary.
agreement under Section 104 of the Water
Industry Act 1991 or Sewerage (Scotland) interceptor public (d) pumped systems
combined
Act 1968 are outside the scope of this sewer Where a gravity system is not possible,
foul
document. For information on standards pumps may have to be used. Pumped
required for adopted sewers, contact manhole systems should be designed in accordance
the local sewerage undertaker and other with BS EN 752 and BS 6297. The
relevant Authorities. installation should include:
Where ground water drains are connected • holding tank of sufficient volume to
Satisfactory outfall disposal is essential
to surface water drains, there should be a contain 24 hours domestic effluent
where a septic tank is installed. In England
silt trap on the ground water side of the based on 120L/150L per head per day
and Wales the Environment Agency
junction. • suitable warning system giving visual
consent may be needed to discharge
effluent from a septic tank. In Northern and/or audible signals to indicate system
(c) rights of connection to disposal
Ireland the Department of the Environment malfunction
systems
should approve proposals, in Scotland the • suitable equipment housing.
Ensure that a legal right exists when
Local Authority and, where appropriate, connecting drains to an outfall. 5.3 - D5 Drainage systems shall
the River Purification Authority should be designed to minimise the risk of
approve proposals. (d) capacity of private sewers blockage
Private drainage systems should be
Ground conditions may preclude the use sufficient to cope with the intended Items to be taken into account include:
of septic tanks in some locations. In all capacity. The design should be in (a) pipe sizes
cases NHBC will require evidence of a accordance with BS EN 752 or similar Pipe sizes should be designed for the
satisfactory percolation test where a septic authoritative document. maximum peak load, using BS EN 752 as
tank drainage system is being installed. the basis for calculations. Ground water
See Appendix 5.3-B. Where an existing private drainage system drains and soakaways should be designed
is to be extended, or where the capacity with sufficient capacity for normal weather
For surface water discharge into a is to be increased, sufficient investigation,
watercourse the permission of the conditions.
measurement and calculation should be
Environment Agency is required in England undertaken to ensure that all parts of the (b) gradients
and Wales. A “consent to discharge” is private system are of adequate capacity. Design gradients should be as even as
required from the DoE in Northern Ireland.
practicable, depending on the number
In Scotland the Local Authority and, 5.3 - D4 Drainage shall be designed to of WCs being served (minimum one for
where appropriate, the River Purification prevent health hazards 100mm pipes, five for 150mm pipes, with
Authorities should be consulted.
Items to be taken into account include: peak flows greater than 1 L/sec. at the
(a) ventilation of systems gradients shown below).
Ventilation of drains is normally achieved Where flows are 1.0 L/second or less,
by ventilating discharge stacks. For details, gradients for 100mm diameter pipes
reference should be made to Chapter 8.1 should not be flatter than 1:40.
‘Internal services’ (Design).
5.3
are not filled should be covered by a slab
(d) cesspools
(c) chemicals in ground and ground water incorporating an inspection cover.
A cesspool is a tank which stores effluent
If the ground or ground water contains
and has to be emptied periodically. The size of the soakaway should be
sulfates, concrete and masonry work
determined as described in Appendix
may require special precautions as Cesspools should be sited within 30m of
5.3-C, the area of the bottom of the
detailed in Chapters 2.1 ‘Concrete and its a vehicle access to permit emptying. They
soakaway should equal the area of trench
reinforcement’ (Design) and 6.1 ‘External should be at least 7m from a dwelling.
bottom in Chart 1.
masonry walls’ (Design).
Cesspools are required to be at least
Where the porous strata is overlaid by less
18m3 capacity. A 45 day holding capacity
FOUL AND SURFACE calculated at 150 litres/head/day should be
permeable sub soil a bore hole may be
permitted by the appropriate authority.
WATER DISPOSAL provided.
Proprietary septic tanks should be
5.3 - D8 Drainage systems shall be (e) septic tanks assessed in accordance with Technical
designed to connect to a suitable outfall A septic tank is a form of treatment plant Requirement R3.
Items to be taken into account include: and requires a suitable outfall (agreed by
the relevant authority) for treated effluent LESS POROUS SUBSOILS
(a) connection to a main foul sewer
discharge. Septic tank design is detailed in In less porous subsoils a sub surface
All connections to a public sewer will
BS 6297. irrigation system may be a possible
require the agreement of the responsible
authority. They should be consulted as to Septic tanks should be sited within 30m of alternative.
the type and position of the connection to a vehicle access to permit emptying. They Such an alternative will have to be
be made. should be at least 7m from a dwelling. In designed to determine the area of the sub
Scotland they should be at least 5m from a surface drainage trench from which the
All connections to a private sewer will
dwelling and a boundary. length of land drain can be found.
require the agreement of the owners of
the sewer. This should be obtained as part First a percolation test has to be carried
CAPACITY
of the design process. If the main private out to determine the percolation value (s)
The capacity of the septic tank should
sewer discharges into a public sewer the in seconds. Details of how to carry out the
be based on the number of people it will
local sewerage undertaker should be test are given in Appendix 5.3-B.
serve. This is determined by the formula:
notified of the proposal.
C = 180P + 2000 If the percolation value is less than 100s
(b) connection to a cesspool or a septic use Chart 1 to determine the field drain
tank where C = capacity of tank (in litres) min trench area and Chart 2 the pipe length to
The entry flow velocity should be 2700L provide this area. For percolation values
restricted to reduce disturbance in the and between 100s and 140s underdrains are
tank. For drains not exceeding 150mm necessary. For percolation values in excess
diameter a gradient not steeper than 1:50 P = design population/potential occupancy of 140s the soil is unsuitable for field
for a distance of at least 12m upstream of (min 4) drains.
the entry is required.
Appendix 5.3-C gives minimum capacities Design guidance for underdrains is given in
Rodding and cleaning facilities should be for septic tanks serving up to 10 persons. Appendix 5.3-D.
provided at the connection with the tank.
• depth of field drains. 437) and for cast iron soil, waste
than one dwelling should be designed in and ventilating pipes and fittings
accordance with BS 6297. The discharge Drains or sewers which are intended for (BS 416)
from the waste water treatment plant adoption should be clearly identified on
BS DD 76 Draft for Development, Precast
should be sited at least 10m away from relevant drawings. concrete pipes of composite
water courses and dwellings. The design construction
should be carried out by a suitably 5.3 - D11 All relevant information shall
BS EN 124 Gully tops and manhole tops for
qualified engineer. be distributed to appropriate personnel
vehicular and pedestrian areas
Ensure that design and specification BS EN 295 Vitrified clay pipes and fittings and
GROUND WATER DRAINAGE information is distributed to site pipe joints for drains and sewers
supervisors, relevant specialist BS EN 1401-1 Plastics piping systems for non-
5.3 - D9 Ground water drainage shall be subcontractors and/or suppliers. pressure underground drainage
designed to convey excess ground water and sewerage - Unplasticized poly
to a suitable outfall (vinyl chloride) (PVC-U)
MATERIALS STANDARDS
(a) layout of pipes
INSPECTION/MANHOLE COVERS AND
Depending on site contours and ground 5.3 - M1 All materials shall:
FRAMES
conditions, ground water drainage, where (a) meet the Technical Requirements
• Group 1 - Areas which can only be used
required, may be designed as a: (b) take account of the design
by pedestrians and pedal cyclists.
• natural system
Materials that comply with the design and • Group 2 - Footways, pedestrian areas
• herringbone system
the guidance below will be acceptable for and comparable areas, car parks or car
• grid system
drainage below ground. parking decks.
• fan-shaped system
• Group 3 - For gully tops installed in the
• moat system. Materials for drainage below ground
area of kerbside channels of roads which
(b) pipe construction should comply with relevant standards,
when measured from the kerb edge,
Pipe perforations should be holes or slots including those listed below. Where no
extend a maximum of 0.5m into the
to suit the nature of the ground. standard exits, materials should carry
carriageway and a maximum of 0.2m
a certificate of assessment from an
(c) outfall into the footway.
independent authority, acceptable to
Ground water drain systems connected • Group 4 - Carriageways of roads
NHBC. Materials of a higher standard are
to foul, surface water or combined drains (including pedestrian streets), hard
also acceptable.
should discharge into the drain through shoulders and parking areas, for all
a catchpit. Where available, ground water References to British Standards and Codes types of road vehicles.
drainage may discharge into a soakaway, of Practice include those made under the
Covers used for manholes within buildings
preferably through a catchpit or into a Construction Products Directive (89/106/
should be airtight and mechanically
watercourse. EEC) and, in particular, appropriate
secured.
European Technical Specifications
In England and Wales the National Rivers approved by a European Committee for Covers used for septic tanks, cesspits and
Authority consent may be needed for Standardisation (CEN). settlement tanks should be lockable.
discharge proposals. In Northern Ireland
the Department of Environment should
approve proposals; in Scotland the River
Purification Authority should approve
proposals.
5.3
should comply with the requirements of be re-filled to the designed level to allow
BS EN 13242, BS 5955 and BS EN 752, as for the bedding to be continuous. Fill
specified. material should be:
• granular material, or
Rigid pipes of nominal size 100mm and • concrete mix GEN 1 or ST 1/2 (not for
110mm nominal flexible pipes should have field drains).
pipe supported pipe supported on bed
granular material bedding to BS EN 13242 on trench bottom of granular material
of 4/10mm pipe bedding gravel. Rigid Hard spots should be undercut and
pipes of nominal size 150mm and 160mm removed, so that local stress points under
Nominal pipe size Granular material
nominal flexible pipes should have granular pipes are avoided. [mm] for bedding
material bedding to BS EN 13242 of Soft spots should be filled with suitable rigid flexible Material (complying
2/14mm pipe bedding gravel. See Sitework well-compacted material. pipes pipes with BS EN 13242)
clause S4 (a).
(c) width of trenches 100 110 4/10mm pipe bedding
Proprietary pipe systems should be Trenches should be as narrow as possible
gravel
supported and bedded in accordance with within working limits, allowing at least 150mm 150 160 2/14mm pipe bedding
the manufacturer’s recommendations. working space on each side of the pipe. gravel
or
(d) proximity of foundations 4/10mm pipe bedding
SITEWORK STANDARDS Foundation bottoms should be lower than gravel
material should be free from: located not more than 150mm from the
• boulders face of the wall. Flexible joints should
• building rubble be made in accordance with the pipe
• timber manufacturer’s recommendations. 100mm
150mm 150mm
max max
600mm 600mm
max max
pipe encased
flexible flexible in concrete at
joint joint least 100mm
thick all round
150mm
above
pipe ACCESS POINTS AND
GULLIES
PIPES BEDDED IN WALLS
5.3
In-situ concrete should be at least 150mm Septic tanks should be sited at least
thick. 7m from a dwelling, but within 30m of
a vehicle access to facilitate emptying.
(b) cover and ventilation In Scotland, they should be at least 5m
Cesspools should be covered and from a dwelling and a boundary. Septic
ventilated. tanks should be provided with access for
(c) siting, access and inspection emptying or de-sludging and cleaning. All
Cesspools should be sited at least 7m from such access points where entry is required
a dwelling, but within 30m of a vehicle should have no dimension less than
access to facilitate emptying. 600mm and be provided with lockable
(d) proprietary systems covers.
Proprietary systems should be installed Cesspools should be provided with access
for emptying or de-sludging and cleaning. The inlet and outlet of a septic tank should
strictly in accordance with manufacturers’
All such access points should have no be provided with access for inspection.
instructions. Adaptors, couplers and
sealing rings should be installed correctly dimension less than 600mm and be (e) velocity of flow
and only the lubricants and solvents provided with lockable covers. Provision should be made to limit the
specified by the manufacturer used. The inlet of a cesspool should be provided velocity of the flow to a septic tank. For
Proprietary manholes should not be used with access for inspection. drains up to 150mm diameter, the velocity
at a depth greater than that for which they may be limited by laying the last 12m of the
Cesspools should have no openings except incoming drain at a gradient not steeper
have been assessed as suitable. the inlet, the vent and the inspection than 1:50. A dip pipe should be provided,
(e) type of cover/grid access. with the top limb rising above scum level
Manhole covers and gully grids should and the bottom limb extending about
be of the correct type for the proposed SEPTIC TANKS 450mm below top water level.
location. Proprietary items (eg covers to 5.3 - S8 Septic tanks shall be sited and
plastic manholes) should be in accordance
constructed to prevent contamination of SURFACE WATER
with manufacturers’ recommendations.
water and health hazards SOAKAWAYS
INSPECTION/MANHOLE COVERS AND Items to be taken into account include: 5.3 - S9 Soakaways shall be sited
FRAMES (a) outfall disposal and constructed to provide adequate
• Group 1 - Areas which can only be used Satisfactory outfall disposal is essential short term storage for surface water
by pedestrians and pedal cyclists where septic tank sewage disposal is and adequate percolation into the
• Group 2 - Footways, pedestrian areas installed. Environment Agency consent surrounding ground
and comparable areas, car parks or car may be needed in England and Wales.
parking decks Items to be taken into account include:
In Northern Ireland the Environment
• Group 3 - For gully tops installed in the and Heritage Service should approve (a) location
area of kerbside channels of roads which proposals, in Scotland the Scottish Where possible soakaways should be built
when measured from the kerb edge, Environment Protection Agency should on land lower than, or sloping away from,
extend a maximum of 0.5m into the approve proposals. Check that this buildings. Soakaways should generally be
carriageway and a maximum of 0.2m approval has been obtained before starting sited at least 5m from the foundations of
into the footway drainage work. a building.
effective depth D
5.3
diameter D
TESTING
5.3 - S10 All foul and, where appropriate,
surface water drainage systems shall be
tested prior to handover
Inspection and testing should be arranged
when required by the Local Authority, the
sewerage undertaker and NHBC.
Before backfilling, visual inspections are
required and the Builder is advised to test.
When the dwelling is handed over, the
system must be in full working order and
free from obstruction.
Inspection chamber
shallow 0.6 or less 225 x 100 1902 - 1901
1.2 or less 450 x 450 450 Min 430 x 430 430
deep greater than 1.2 450 x 450 450 max 300 x 300 3
Access restricted
to max 3503
Notes
1 The clear opening may be reduced by 20mm in order to provide proper support for the cover
and frame.
2 Drains up to 150mm.
5.3
3 A larger clear opening cover may be used in conjunction with a restricted access. The size is
restricted for health and safety reasons to deter entry.
Notes
1 Larger sizes may be required for manholes on bends or where there are junctions.
2 May be reduced to 600 by 600 where required by highway loading considerations, subject to a
safe system of work being specified.
3 Not applicable due to working space needed.
4 Minimum height of chamber in shafted manhole 2m from benching to underside of reducing
slab.
5 Min clear space between ladder or steps and the opposite face of the shaft should be
approximately 900mm.
6 Winch only - no steps or ladders, permanent or removable.
7 The minimum size of any manhole serving a sewer (i.e any drain serving more than one
property) should be 1200mm x 675mm rectangular or 1200mm diameter.
Reproduced from Tables 11 and 12 of Approved Document H to the Building Regulations by
permission of HMSO.
Appendix 5.3-B
* Where underdrains are necessary, drainage trenches should be constructed not less than
600mm deeper than the pipe level specified in the design, and the lower part filled with pea
gravel (see Appendix 5.3-D)
5.3
A second system of drainage pipes should be laid on the bottom of the trenches to convey
surplus drainage to an outfall in a surface ditch or watercourse.
Underdrains are costly, and a secondary treatment system able to produce an effluent
suitable for surface discharge may be preferable.
240
230 9 persons
220
210
200 8 persons
190
180 7 persons
170
Field Drain Trench Area (m )
2
160
150 6 persons
140
130
120 5 persons
5.3
110
100 4 persons
90
80
70
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90 100
Percolation Value
700
650
600
550 450 wide
500
450
600 wide
400
350
300 750 wide
250 900 wide
200
150
100
50
0
0 20 40 60 80 100 120 140 160 180 200 220 240
2
Drain Trench Floor (m )
Appendix 5.3-D
Soil, gravel or
600mm
other topping
300 to
Tar paper
300mm
Invert of inlet pipe
600mm
Broken piece of tile
as cover to joint
Drain
5.3
600mm
Appendix 5.3-E
TEST PROCEDURE
A trial hole in a similar location and to the same depth as the proposed soakaway or septic
tank land drain will give a measured rate of percolation.
The procedure is as follows:
1 Bore a hole 150mm in diameter with an auger to a depth of one metre.
2 Fill with water to depth of 300mm above the bottom. As an aid, mark a stick 300mm from
one end, place in the hole and fill up to the mark on the stick (it takes approximately 5.5
litres to fill a 150mm diameter hole to a depth of 300mm).
3 Observe the time taken in minutes for the water to soak away (this may take several hours,
in some cases need to be left overnight).
4 If possible the test should be repeated and the average time used.
5 A second group of tests are carried out after the hole has been bored out to a depth of 2
metres, still using 300mm of water above the bottom of the hole.
6 If the soil appears to become more permeable with depth, it may be useful to deepen and
retest the bore in one metre stages.
400
300
=
D
200 3.5
m
D = 2.8 D
=
150 3.0
m
D=
100 2 .5
m
D= D=
2.0m
1.5
D= m
1 .0m
0
0 400 800 1200 1600 2000 2400 2800 3200 3600 4000 4400
5.3
EXAMPLE
Test time (t) = 900 minutes
Plan area to drain = 150m2
Therefore, using the graph, the diameter and effective depth of the soakaway (D) are both
2.8m.
Notes
• If the ground is of low permeability, dig separate soakaways to drain smaller but distinct
parts, for example:
- one side of a roof to one soakaway
- the other side to a second soakaway
- the driveway or yard to a third soakaway.
• Where the permeability of the ground increases with depth, tests in the deepened trial
holes will give shorter percolation times, so it may be cheaper to build a smaller soakaway
at a greater depth below the surface.
• Where possible, soakaways should be built on land lower than, or sloping away from,
buildings. They should also be kept a “safe” distance away from buildings. This should be
at least 5m from building foundations. In chalk and other soil and fill material subject to
modification or instability, the advice of a specialist geotechnologist should be sought
regarding the siting and advisability of soakaways.
INDEX
A G S
Access 2, 6, 9 Garden areas 6 Septic tanks 1, 3, 7, 10, 11
B Gradients 1 Sewage treatment works 4
Backfill 5, 6 Ground water 2, 3, 4 Soakaways 7, 12
Bedding 5 J Subsoils 3
Benching 7 Jointing 5 Surface water 3, 7
Blockage 1 L T
Bricks and blocks 5 Landfill gases 1 Testing 8, 10, 12
C Layout 4 U
Capacity 1, 3 M Underdrain 12
Cess pools 1, 3, 7 Manholes 4, 6, 7 V
Chambers 4 Movement joints 6 Ventilation 1, 7
Chemicals 3 O
Connections 3 Outfall 3, 4
Covers 4 P
D Pipes 1, 2, 4
Damage 2 Preliminary work 5
E Private sewers 1
Excavation 5 Protection 6, 8
5.3
F Pumped systems 1
Field drains 4, 11 R
Fittings 4 Radon 1
Flooding 2 Rendering 7
Foul sewer 3 Rights of connection 1
Foundations 5 Roads 6