Procedure For Performance Monitoring of Environmental Data Collection Agencies

Procedure FOR PERFORMANCE MONITORING OF ENVIRONMENTAL DATA COLLECTION AGENCIES Document No. 5-1741-0080 Rev. No. Page 1 of 5 PURPOSE SCOPE REFERENCES DEFINITIONS METHODOLOGY AND CONTROLS DOCUMENTATION AND RECORDS Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL - All rights reserved.

Uploaded by

kaandi
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
94 views5 pages

Procedure For Performance Monitoring of Environmental Data Collection Agencies

Procedure FOR PERFORMANCE MONITORING OF ENVIRONMENTAL DATA COLLECTION AGENCIES Document No. 5-1741-0080 Rev. No. Page 1 of 5 PURPOSE SCOPE REFERENCES DEFINITIONS METHODOLOGY AND CONTROLS DOCUMENTATION AND RECORDS Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL - All rights reserved.

Uploaded by

kaandi
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Procedure for Performance Document No.

Monitoring of Environmental Data 5-1741-0080


Collection Agencies Rev. No.1
Page 1 of 5

PROCEDURE FOR PERFORMANCE


MONITORING OF ENVIRONMENTAL DATA
COLLECTION AGENCIES

1 02.02.10 General Revision DDC DRC HOD


Issued for Implementation
0 29.07.02 DDC DRC HOD
(after revising to meet ISO-2000 version
Rev. No Date Purpose Prepared by Reviewed by Approved by

Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL – All rights reserved


Procedure for Performance Document No.
Monitoring of Environmental Data 5-1741-0080
Collection Agencies Rev. No.1
Page 2 of 5

Abbreviations:

DCA Data Collection Agency


EBR Environmental Baseline Report

Document Drafting Committee Members:

Mr.R.S.Prasad, Manager
Mr. P. K. Goel, Manager
Mr. Vikram Singh, Dy. Manager

Document Review Committee Members

Mr. B. B. Lal, AGM


Mr. V. S. Chhaya, AGM
Mr. Susheel Sadh, AGM
Mr. J.K.Joshi, AGM

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved


Procedure for Performance Document No.
Monitoring of Environmental Data 5-1741-0080
Collection Agencies Rev. No.1
Page 3 of 5

CONTENTS

CLAUSE TITLE PAGE NO.

1. PURPOSE 4

2. SCOPE 4

3. REFERENCES 4

4. DEFINITIONS 4

5. METHODOLOGY AND CONTROLS 4

6. DOCUMENTATION AND RECORDS 5

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved


Procedure for Performance Document No.
Monitoring of Environmental Data 5-1741-0080
Collection Agencies Rev. No.1
Page 4 of 5

1.0 PURPOSE

This document describes the procedure for performance monitoring of outside laboratory
which are enlisted as Data Collection Agencies with EIL.

2.0 SCOPE

This document is to be used as base document while preparing tender inputs for
preparation of tender for environmental baseline data collection.

3.0 REFERENCES

3.1 Environmental Baseline Reports prepared by DCAs.

4.0 DEFINITIONS

4.1 Environmental Baseline Report

The report which consists monitored environmental data in terms of quality of air, water,
noise, meteorology, flora and fauna, socio-economic prepared by the DCA.

5.0 METHODOLOGY AND CONTROLS

Based on approved EBRs and log reports, completion certificates shall be issued to the
DCA . These certificates govern the selection of vendor list for a particular work. The
procedure of assessment is described below:

Review filled-in log reports submitted by DCA.

Review the time schedule issued in the tender vis-as-vis actual time
taken by the DCA particularly for submission of EBR.

Fill the contents of completion certificate based on the assessment of


above steps.

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved


Procedure for Performance Document No.
Monitoring of Environmental Data 5-1741-0080
Collection Agencies Rev. No.1
Page 5 of 5
Concerned job engineer in consultation with lead engineer will do all the above activities.

Lead engineer will review all the above activities in parallel or as a whole.

Job engineer will incorporate all the comments as suggested by the lead engineer.

The approver will approve completion certificate. Job engineer will also incorporate
comments of the approver.

6.0 DOCUMENTATION AND RECORDS

Nil

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved