1 Step - (Fill Days of Activity Duration) 1 Step (Assume Activity Start As Earley Days I.E ES - 01)

The document describes the critical path method for a project with 10 activities labeled A through J. The 4 main steps are: 1) Fill in the duration and predecessor for each activity 2) Calculate the early start and early finish for each activity 3) Calculate the late start and late finish for each activity 4) Calculate the float for each activity The critical path activities are found to be B, E, I, and K, with a total duration of 40 days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views

1 Step - (Fill Days of Activity Duration) 1 Step (Assume Activity Start As Earley Days I.E ES - 01)

The document describes the critical path method for a project with 10 activities labeled A through J. The 4 main steps are: 1) Fill in the duration and predecessor for each activity 2) Calculate the early start and early finish for each activity 3) Calculate the late start and late finish for each activity 4) Calculate the float for each activity The critical path activities are found to be B, E, I, and K, with a total duration of 40 days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

CRITICAL PATH METHOD 1ST Step- (Fill Days of Activity Duration) 1ST Step (Assume Activity Start as Earley

Activity Start as Earley Days i.e


Activity Duration Predcessor
A 3 -
4 10 ES + D -1 = EF(Earl
B 9 -
D D
C 11 -
D 7 A 7 7
E 9 B
1 3
F 5 B
A A
G 5 C
19
H 19 C 3 3
I 10 18 I
I 17 D,E
E E
J 5 F,G 17 17
1 9
K 3 I,J,K 9 9
B K B

9 3 9
F
ES EF
A 1 11 15
5
LS LF C J C 10 14 J
D
F F
11 5 11 5
5 5

5 5
12 16
G G

5 5

5 5
12 30
H H
19 19
Start as Earley Days i.e ES - 01) 3rd Step

ES + D -1 = EF(Early Finish) 4 10 ES + D -1 = EF(Early Finish)


D
EF + 1 = ES 14 20 EF + 1 = ES
7

1 3 1
A
35 11 13 19 35 LF - D + 1 = LS 11
3
10 18 I
E 21 37
17
36 38 1 9 12 20 36 38 1
9
K B K
3 11 38 40 3
3 9 3

19 1 11 15 19 1
C 10 14 J
8 18 F 33 37 8
11 5
28 32
5

12 16
G
F F F
ES EF 28 32 ES EF ES
5
A A A
LS LF LS LF LS
D D D
12 30
H
19 37
19 37
19
4th Step (Float)

10
4 10
D Float = LS-ES
14 20
7
10
3
A
2
13 19 35
3 2
10 18 I
E 21 37
2 17 2
9 12 20 36 38
9
B K
11 38 40
9 3

7 18
11 15 19
18
C 10 14 J
18 F 33 37
11 5
28 32
5

16
12 16
CONCLUSION
G
EF 28 32
5 Float is = 0(Zero), Means Critical
Path or Activity ie B,E,I & K is
LF Certical Path or Activity.If we
7 calculate Days of critical Path of
12 30
B,E,I & K = 11+9+17+3 = 40 Days
H
19 37
19 37
19