Systems-Engineering Management Plan
Systems-Engineering Management Plan
1.0 SCOPE
1.1 Purpose. This System Engineering Management Plan describes an internally developed
approach to a fully integrated engineering effort. It addresses how the typical contract
will be managed and conducted to ensure that program cost, schedules and technical
performance address the requirements for a SEMP in accordance with MIL-STD-499A.
(Note that –499B was never officially issued. Some concepts are from Defense System
Management College).
1.2 Application. This SEMP applies to the wide range of engineering efforts currently being
being pursued, especially those that involve the integration of systems. It is applicable to
programs that transcend the entire life cycle (Concept Exploration, Demonstration and
Validation, Full-Scale Development, Production and Operational Phases) or programs
that encompass a single phase. Additionally, the SEMP is applicable to those contract
that involve System Engineering and Technical Assistance (SETA) efforts in support of a
prime or Government Program Management Office.
1.3 Implementation. The SEMP approach adheres to the management approach directed by
the Office of the Secretary of Defense (OSD) and implemented through Directive 5000.1
and DoD Instruction (DoD) 5000.2 (both dated 23 February 1991, subsequent
instructions and updates). DoDI 5000.2 requires an effective systems engineering
program be implemented for each acquisition program in accordance with MIL-STD-
499. This SEMP addresses Systems Engineering in three parts as defined on paragraph
5.1 and amplified in sections 4, 6 and 10 of MIL-STD-499A. Technical Planning and
Control will be addressed in Paragraph 5.1 following as an integrated topic with the
Systems Engineering Management Section. System Engineering Process and Specialty
Engineering will be discussed as integrated efforts in paragraphs 5.2 and 5.3 respectfully.
This SEMP address the three management functions typical with a matrix-managed
organization. These include the Program Management Function (Overall program
authority, responsibility and control) and the two main support functions (1) Engineering
and Technical Control (2) Administrative including financial planning. Cost collection
and Cost Reporting functions are included in the Administrative responsibilities.
b) Engineering Staff. The Director of Engineering shall perform under the direction
of the Program Manager. The Director of Engineering shall establish and
maintain a Core Engineering Staff that is dedicated for each program. In
addition, the Director of Engineering shall maintain a cadre engineering staff to
assist the Core Engineering Staff on an as required basis. Typical the cadre staff
would include design engineers, specialty engineers and operational specialists.
1
c) Chief Engineer. The Chief Engineer and his staff will be responsible to the
Program Manager for technical program oversight. The Chief Engineer will be
responsible for tailoring all engineering processes to accommodate the needs of
the program and submit same to each designated PM for approval and
implementation. The Chief Engineer is responsible to the PM for defining and
conducting the technical review and audit process as defined in the Technical
Review and Audit Manual and for implementing and monitoring the Technical
Performance Measurement (TPM) program.
3.0 DEFINITIONS
3.1 Engineering Management. This office will conduct engineering management paralleling
the requirements invoked by DoDD 5000.1, DoDI 5000.2 and DoD 5000.2M for DoD
acquisition. The approach is based on the existence a flowdown of all these requirements
from acquisition managers either directly for contract execution or within the scope of a
SETA support requirement support to the acquisition manager.
3.2 Technical Program Planning and Control. The management of those design,
development, test and evaluation tasks required to progress from an operational need to
2
deployment and operation of an integrated system (to include contractual efforts
specifically directed to a portion of that defined task within that phase or in support the
operational phase of such a program). The technical program planning and control
process is based on a risk management strategy and include a comprehensive TPM
approach.
3.3 System Engineering Process. The structured sequence of activities and decisions that
transform an operational need into a description of system performance parameters and a
preferred system configuration. The process included rapid prototyping as a means of
demonstration systems capabilities. Rapid Prototyping focuses on correcting system
requirements misconceptions and reducing ambiguities is performance parameters early
in the engineering design phase as a cost risk mitigation effort.
3.4 Engineering Specialty Integration. The timely and appropriate interactive process that
ensures that engineering efforts and disciplines such as reliability, maintainability, human
factors, safety, quality assurance, TQM/CPI, etc., will effectively influence the system
design throughout the design process.
3.5 Other. The definitions included in the applicable documents and processes listed in
Section 2 shall apply.
Our engineering management process shall conform to item (a) through (k) specified
in paragraph 4 of MIL-STD-499A. The MIL-STD-499A requirements are stated here for
convenience:
f) Design Completeness. The design shall be complete from a total system element
viewpoint (hardware, facilities, personnel, computer programs, procedural data).
3
defined. Engineering data shall be the sole source of performance requirements
used in the design and production of the system.
i) Cost Estimates. Cost estimates shall include acquisition and ownership costs.
This shall include any established “design to” cost goals and a current estimate of
these costs.
4
identified shall be evaluated, for total program impact with respect to
performance, cost and schedules.
Under the charter to establish and maintain leadership in the development of systems and
in support of system acquisition managers, our management approach necessarily
parallels and supports the DoD acquisition policies set forth in DoDD 5000.1, DoDI
5000.2 and DoD 5000.2M. The fundamental philosophy is to allow engineering
directorates maximum flexibility and to eliminate over managing and its negative
attributes. The management philosophy is based on Risk Management strategies
followed by monitoring of cost, schedule and performance parameters. Comparison of
actual versus predicted, observing and evaluating trends, and using the latest management
analysis tools and techniques is the foundation of the management philosophy.
5.1 Technical Program Planning and Control. This System Engineering Management Plan
(SEMP) identifies organizational responsibilities and authority for systems engineering as
chartered by our corporation. This is illustrated in Figure 5-1 (put your org chart here).
Flexibility is provided by allowing administrative responsibilities at one level and
technical control at another, i.e., Director of Plans and Program can by under the
direction of Sr. VP MX operations for high risk programs of programs requiring high
corporate management visibility while still under SB administrative control.
5.1.1 Project Management. The program manager for each contractual effort is identified by
an officer of the company. He/she is be responsible to the Director of Plans and
Programs to perform business and program management efforts to accomplish overall
project objectives. These efforts include preparation, review, and revision/updating of
management documentation selecting and implementing the appropriate software
management tools for information management and performance analysis (including
requirement for upper management and customer review requirements) of overall
business, administration and engineering activities. Our organization will establish a
process for planning and controlling project, systems engineering and technical support to
acquisition mangers within this SEMP. Tailoring is the responsibility of the individual
PM. It is accomplished with concurrence by the acquisition manger.
5
the Technical Director or Engineering Manager responsible for executing the engineering
efforts. This is accomplished in accordance with the Task Authorization process;
Program Manager is individually accountable for the effort serves as a single point of
contract of technical monitoring and development progress within our company and is the
single point of contract for reporting status to the customer.
6
CEO Responsible for overall efforts and strategies and for corporate
performance
VP
xx Prime Responsibility for Program Execution
Systems Engineering
DIRECTOR
Responsible for Program Management including
of
sub-contracting
Plans of Program
DIRECTOR
Responsible for technical program execution including
of
technical planning and control
Engineering
7
CONCEPT DEMONSTRATION AND
DEFINITION VALIDATION PHASE FULL SCALE ENGINEERING PHASE
PHASE
A B B
SUBSITTED B D D D
WITH PROPOSAL
REVISIONS AND
PROGRAM SUBSYSTEM UPDATES AS REQUIRED INTERFACE SOFTWARE
DESIGN AND DESIGN AND DESIGN LISTINGS C5
SUPPORT SUPPORT DOCUMENT
PLANS PLANS SPEC
C C D
DATABASE
SEAR SEAR DESIGN
UPDATE DOCUMENT
5.1.3 System Test Planning. Figure 5-3 depicts the typical program test requirements.
Acquisition Managers and Prime Contractor Program managers have the same
responsibilities if the Government retains prime contract role and contracts for System
Engineering and Technical Assistance (SETA) efforts.
The system test planning necessarily includes risk mitigation efforts with
experiments to demonstrate risk reduction. The system planning also includes provisions
for performance measures development and reporting. These include intermediate
performance criteria and key engineering milestones and schedules to complement
engineering management with risk management strategies. Technical Performance
Measurement (TPM) techniques is developed, implemented and maintained as integral to
the system test planning process.
5.1.4 Risk Analysis. The PM is responsible for structuring technically sound programs that
assess risk at all levels and identify areas of high risk. High-risk areas are subject to
corrective actions or risk mitigation activities. Risk analysis techniques and the
characteristics of software tools necessary to support program risk analysis are identified
in the Risk Management Manual. PM, with acquisition manager’s concurrence, is
responsible for tailoring the manual to achieve adherence to overall technical, financial
and schedule program goals.
The risk manual is used in conjunction with DoD 4245-7M, which serves as a
guideline for identifying areas of risk and determination of risk drivers for establishing
the uncertainties inherent to risk analysis efforts. The risk manual includes using outlines
contained in DoD 4245.7M for reducing risk and implementing risk abatement programs.
Risk Analysis is a major function at each System Design Review (Ref. internal Technical
Review and Audit Process Manual).
5.1.5 Contract Work Breakdown Structure (CWBS). The program CWBS developed in
accordance with CWBS development guidelines. The guidelines are in accordance MIL-
STD-181 and Defense Systems Management (DMSC) Systems Engineering Management
Guide. The Program CWBS is identifying tasking development, tasking, authorization
and status monitoring activities. Each task in the CWBS tree is assigned a code that
preserves and communicates the CWBS subdivisional/summation requirements.
Standardization of CWBS nomenclature is inherent in the process to maintain traceability
for historical costs to fulfill compliance with DFARS 215.811.
5.1.6 Technical Performance Measurement (TPM). The program manager implements TPM in
accordance with the Technical Performance Measurement Manual. TPM implementation
follows MIL-STD-499A requirements and is tailored by the program manager (with
acquisition manger concurrence) to specific programs needs. The program complements
the System Management Philosophy being implemented.
9
CONCEPT DEMONSTRATION AND
EXPLORATION VALIDATION PHASE FULL SCALE ENGINEERING PHASE
PHASE
A C C C C C
B C C C B C C C C
SYSTEM
A CI – CONFIGURATION ITEM
ACQUISITION MANAGER/PM RESPONSIBILITY
B PM/TECHNICAL DIRECTOR RESPONSIBLE/ACQUISITION MANAGER/PM APPROVAL
HWCI – HARDWARE CONFIGURATION ITEM
C PM/TECHNICAL DIRECTOR RESPONSIBILITY
D PM/TECHNICAL DIRECTOR RESPONSIBIITY/ACQUISITION MANAGER/PM OBSERVER
LBEF – LAND BASED EVALUATION FACILITY
5.1.6.2 TPM Assessment Methods. There is a wide range of methods available for technical
performance. Test methods supported by comparative analysis between actual and
predicted results are preferred but these do not necessarily meet the criteria for early
prediction of problems. Forecasting methods such as math models and simulations which
have application in the concept definition and feasibility demonstration phase and which
phase appear to be best suited for our development or technical assistance efforts. Vitro
recognizes the need for early detection of problems to support management decisions
before irrevocable cost or schedule impact occurs. We are constantly developing or
evaluating Computer Aided System Engineering (CASE) tool sets with emphasis of
Systems Requirements definition. We have significant internal resources applied to
development of Rapid Prototyping Techniques (System Requirements and Man-Machine
Interface evaluation aids) to supplement our extensive systems simulation and computer
modeling development programs.
5.1.6.3 Report Frequency and Timing. The tailoring of reporting requirements is left to the
discretion of the individual PMs (or Acquisition Managers). TPM tracking results will be
reported at each Systems Design or System Progress Review. Formal TPM assessments
are be planned to coincide with planned completion of significant design and testing tasks
and will be significant inputs program decision milestone activities.
11
requirement in the Interface Control Documents (ICDs) or SIIs. These must be approved
by all parties to ensure agreement on the interface design details. Detail design engineers
must satisfy the requirement of these interface documents as they realize the design of
their piece of the system. In this way, the system is integrated so all the pieces work
together in an orchestrated whole. In this manner systems engineering will be concerned
with total systems architecture allowing design engineers the flexibility with their detail
design. Systems integration assembles the pieces and tests to ensure compliance with
systems requirements. The Chief Engineer, through the Technical Review and Audit
process, is responsible for auditing the design documentation and results of the tests to
ensure system interface complies with the requirement documentation.
5.1.8 Data Management. The PM will perform necessary activities in order to prepare, review,
and revise/update management data, as defined below, to reflect system design,
development, and installation requirements and status. As applicable, management data
will be inclusive of networks, cost estimates and models, cost performance reports, and
contractor funds status reports.
b) develops and maintains a Project Master Schedule (PMS), which will include
design documentation deliveries, program and design reviews, equipment
acquisition, and installation planning milestones
e) provides financial analysis and cost breakdown reports that cover each task
and subtask order in terms of both planned and actual expenditures
12
system. The program will provide toe establishing and maintaining systems
configuration identifications, and auditing SII Technical Data Packages (TDPs),
controlling changes to baselines of Configuration Items/Computer Software
Configuration Items (CIs/CSCIs), and control and status accounting for identification of
approval baselines and proposed or approved changes.
5.1.10 Technical Reviews and Audit. Program reviews and audits are outlined in the internal
Technical Review and Audit Manual. Technical reviews will be conducted in general
compliance with MIL-STD-1521 and DoD STD 2167A. Figure 5-4 summarizes review
requirements and responsibilities.
5.1.11 Formal Program Reviews. The PM conducts quarterly formal program reviews to
present complete contract status including performance cost and schedule. The technical
management program status, problems, and issues shall be presented from each Project
Leader.
5.1.12 Informal Reviews. PMs are encouraged to hold informal reviews, as necessary or as
requested by the Acquisition Manager to discuss and answer questions or action items,
resolve issues and problems, review and discuss hardware, software, and documentation,
and to present results of test or analysis.
5.1.13 Financial Management. PM maintains and management control system that includes
policies, procedures and methods that are designed to ensure that they are in concurrence
with the requirements of DoDI 5000.2, Part II, Section B, Attachment 1. Specific
processors and software management tool characteristics applicable to various efforts are
delineated in the internal Financial Management Planning, Reporting and Monitoring
Process Manual.
5.2 System Engineering Process and Planning. This section describes the system engineering
process to ensure a successful, cost-effective development program. It also provides the
guidelines for effective use of Computer Aided System Engineering (CASE) tools,
models, and simulation to aid the process.
5.2.1 System Engineering Process. The system engineering process recommended is depicted
in Figure 5-5. It is a flexible approach that is adaptable to typical system development
programs and to each component subsystem of these programs.
5.2.2 General Approach. The system engineering process utilities tried and proven techniques.
It is a top down design methodology characterized by an evolutionary iterative and
interactive process. Use of automated systems engineering tools is encouraged. The
emphasis is on commercially available tool sets with new development of models and
simulations only when necessary. New development is accomplished in a manner that
allows easy aggregation into an existing inventory to provide systems solutions. The
approach emphasizes rapid prototyping to allow earlier and more comprehensive design
reviews. The reviews will uncover specification errors and ambiguities in the
development phase where corrections are the least expensive. Finally, the process is
documented. PM requires the maintenance of a System Engineering Analysis Report
(SEAR). The SEAR has the same utility as the engineering notebook has for the
researcher. It provides the necessary engineering traceability. It provides the background
for follow-on investigations and Preplanned Product Improvement (P3I) programs. It can
13
CONCEPT DEMONSTRATION AND
EXPLORATION VALIDATION PHASE FULL SCALE ENGINEERING PHASE
PHASE
FUNCTIONAL FUNCTIONAL ALLOCATED
ANALYSIS & BASELINE BASELINE
SYSTEM ESTABLISHED ESTABLISHED
DEFINITION
COMPLETE
A A A A A
SYSTEM SYSTEM B B
REQUIREMENTS DESIGN PDR CDR HWCI
REVIEW REVIEW HWCI HWCI FCA
B B
HWCI SYSTEM
A B A A PCA FCA
B
* FORMAL SYSTEM
SYSTEM REQ’TS DRAFT PDR CDR QUALIFICATION PCA
RAPID HWCI CSCI CSCI REVIEW
PROTOTYPE B1 SPEC NO 1 NO 1 FORMAL
REVIEW REVIEW B QUALIFICATION
CSC1 CSCI REVIEW
A C B NO 2 NO 2
B
* CSC1 CSCI SOFTWARE A
NO ‘IV’ NO ‘IV’ FCA
MMI DRAFT DRAFT
RAPID SEGMENT SOFTWARE
PROTOTYPE SYSTEM SPEC SOFTWARE
PRODUCTION
REVIEW A SPEC REVIEW REVIEW PCA
READINESS
REVIEW
A CHIEF ENGINEERING RESPONSIBLE FOR INTERNAL REVIEW/PM FOR EXTERNAL REVIEW MMI – MAN-MACHINE INTERFACE
B PM RESPONSIBILITY HWCI – HARDWARE CONFIGURATION ITEM
C PM RESPONSIBILITY/ACQUISITION MANAGER REVIEW PDR – PRELIMINARY DESIGN REVIEW
CDR – CRITICAL DESIGN REVIEW
* RECOMMENDED ACTIVITIES FCA – FUNCTIONAL CONFIGURATION AUDIT
PCA – PHYSICAL CONFIGURATION AUDIT
CSCI – COMPUTER SOFTWARE CONFIGURATION ITEM
Figure 5-4
14
ENVIRONMENT
OPS
STEP 2
REQUIREMENTS
REQUIREMENTS/ SUBSYSTEM-A
OPS CONCEPT
EXISTING STEP 1 STEP 3
DEFINITION CSCI-1
MISSION MISSION ANALYSIS
ANALYSIS REVIEW CSCI-2
SUBSYSTEM-M
STEP 4
SCENARIOS
PARAMETRIC CSCI-1
REQUIREMENTS CSCI-2
MISSION ANALYSIS
EFFECTIVENESS MODELS
& SIMULATIONS FUNCTIONAL
IDENTIFICATION
FUNCTIONAL
FUNCTIONAL ALLOCATION
PERFORMANCE
REQUIREMENTS
STEP 3 ANALYSIS
TRADE SUBSYSTEM
STUDIES PERFORMANCE
SCHEDULE RISK
PERFORMANCE
SOFTWARE
HARDWARE
ARCHITECTURE EFFECTIVENESS
ARCHITECTURE
PHYSICAL CONTRAINTS STEP 7
DEFINE SYSTEM
COST ALTERNATIVES
TECHNICAL RISK
STEP 8
EVALUATION
SUBSYSTEM
CANDIDATES
RM&A
ANALYSIS RISK
EFFECTIVENESS ANALYSIS
RISK
LOGISTICS COST LIFE
ANALYSIS CYCLE COST
SUPPORTABILITY ANALYSIS
MANPOWER
MANPOWER GROWTH POTENTIAL
& SKILL LEVEL
ANALYSIS
STEP 8 STEP 9 STEP 10
EVALUATE REQ’TS & PROGRAM
SYSTEM MMI RAPID DEFINITION/
ALTERNATIVE PROTOTYPING SPECIFICATION
MAIN PROCESS FLOW DEVELOPMENT
ITERATIVE PROCESS
SECONDARY FLOW
15
be extremely useful and cost effective for program managers and system engineers
performing similar design initiative.
5.2.2.1 Step 1 – Mission Analysis Review. Review of Mission Analysis, as depicted in Figure 5-
5-5 is defined for a complete System front-end design application. Mission analysis can
be equally applicable to analyzing the requirements for component subsystems,
feasibility of modifying existing systems to meet operational requirements, or
modifications (reliability or performance enhancements) to exiting system. Tasks
associated with these subsets require similar reviews and continue along the same
process, differing only in scope and depth of the numerous supporting analyses. Results
of Step 1 will be documented in the SEAR and summaries will be available for PM
review.
5.2.2.3 Step 3 – Function Analysis and Allocation. Function analysis, as indicated, is composed
of two distinct process segments: (1) functional identification and, (2) functional
performance requirement analysis. The basic system engineering tool for functional
identification is the Functional Flow Diagram (FFD) that shows the logical sequences and
relationships between operational and supports functions at the system levels.
Commercially available tools, based on FFD techniques, aid and enhance the process.
Tool selection criteria should include ability to support the functional performance
requirement analysis. The output is then utilized for functional allocation processes.
5.2.2.4 Step 4 – Parametric Analysis. Parametric analysis that includes defining the
interrelationship between key subsystem performance requirements must be conducted
16
for all the system architectures defined in Step 3. This step evaluates the combinations of
subsystem performance capabilities that can achieve the total system performance. This
step identifies and quantifies all the major performance relationships of the key
subsystems. Data, data sets, and summary graphs for each alternative and concept shall
be documented in the SEAR.
5.2.2.5 Step 5 – Trade-Off Studies. Trade-Off Studies commence during the conduct of
parametric analysis. Subsystem trade-off results are developed for performance versus
design parameters, cost, weight, and other technical performance measures. Parametric
requirements are used to bound the performance range being explored. The emphasis
may be either or subsystem trade-offs, on key subsystem combinations that lead to
modification of older systems, or on new systems. Its goal is to achieve a synergistic
balance between architectures (software and hardware) and subsystem performance
allocations.
Steps 3, 4, and 5 are necessarily highly iterative and highly interactive. The
system engineer must assess the impact on system complexity, cost, physical constraints,
and overall mission effectiveness of the requirement. An awareness of the penalty for not
achieving a particular requirement must be continually present during the process.
Sufficient number of alternative approaches should be visible and documented in the
SEAR to ensure subsystem optimization.
5.2.2.7 Step 7 – Define System Alternatives. The system alternatives are the logical combination
of subsystem candidates from a consideration of the evaluation criteria and other relevant
factors, e.g., potential for evolutionary growth.
5.2.2.8 Step 8 – Evaluate System Alternatives. The different alternatives are examined. The
evaluation criteria include but are not limited to mission effectiveness, risk (technical,
costs, and schedule), life cycle cost, supportability (including RMA), manpower
requirements, and growth potential. The evaluation is supported by a series of
documented analyses in the SEAR that include mission effectiveness, risk, life cycle cost,
RM&A, logistics, and manpower (to include skills requirements). The results of steps 6,
7, and 8 are a study report that is documented separately or as an addendum to the SEAR.
5.2.2.9 Step 9 – Requirements and Man-Machine Interface (MMI) Rapid Prototyping. Rapid
Prototyping is a relatively ne but essential element in the system engineering process.
Commercially-available tools are available to use as kernels of an evaluation system that
17
achieves static and dynamic representations of the requirements. This allows customer
and the design staff to observe and interact with the systems concepts as modeled by the
analytical engineers. Moreover, the output of most models generates the detailed
requirements that become part of the specification. This eliminates the errors and
ambiguities that plague the translation of human ideas into specification language and
conveyance of those ideas to the design engineers.
5.2.2.10Step 10 – Program Definition and System Specification Development. The final step is
to select the preferred alternative(s) and to define the required development. Programs
that could be effectively evolved into the final system. The product of the process is a
system specification or a set of modifications to the existing system specification.
5.2.3 Decision and Control (D&C) Processing. The typical Project Decision and Control
process is depicted in Figure 5-6. The key characteristic of the process is the orderly
flow down of requirements and the flexibility of options in the implementation. It is
generally the acquisition responsibility to flow down requirements from newly defined or
changing mission and operational requirements to the system requirements. The PM is
responsible to the Acquisition Manager for ensuring that alternatives are identified and
appropriately evaluated during that process. The Acquisition Manager will involve the
appropriate working groups for assistance in the Centers of Excellence, and operations
groups for assistance in the identification and evaluation process. Once decided, the
requirements will be flowed down to the contractor for implementation.
5.2.5 Systems Modeling and Simulations. The PM shall develop and maintain a system
modeling and simulation capability that can be used to determine mission and system
performance effectiveness.
18
MISSION OPERATIONAL
REQ’TS REQ’TS
FUNCTIONAL
REQ’TS
OPERATIONAL
EXPERIMENTS
CRITICAL
PERFORMANCE REQ’TS
INTEROPERABILITY
TOP LEVEL
SUBPROCESS
SPEC
SYSTEM
CHARACTERISTIC WBS
PRODUCTION TAILORED
DECISION PROGRAM
TEST
PROGRAM
PRODUCTION
DECISION
19
• Engineering Trade Studies
• System Control Algorithm Development
• System Flight Analysis
• System Test Analysis
• L-C-C Estimating
• Reliability and Maintainability Analyses
• Spares Computational Analysis.
The PM shall make the models and simulations available (if requested) to the
Acquisition Manager or his designate agent to allow aggregation for total system
analysis.
5.3 Specialty Engineering Integration. This paragraph defines how the specialties
engineering of logistics, quality assurance, reliability, maintainability, human
engineering, system safety, and other areas are integrated into the mainstream design
effort. Figures 5-7 and 5-8 depict the processes for ensuring early influence of specialty
engineering on design process.
5.3.1 Logistics Engineering. Integrated Logistic Support (ILS) is the composite of all the
support considerations necessary to ensure the effective and economical support of a
system, subsystem or component over its life cycle. This includes the principle logistic
personnel, support and test equipment, facilities, transportation sand handling, and
technical data. This also includes the logistics management activities required to
implement the logistics engineering concepts, funding, policies, and procedures
formulated through logistics engineering efforts during the system design development
phase. Typical Table 5-1 summarizes the major ILS activities and delineates the division
of responsibilities between Acquisition Manager and the Program Manager. The
program manager’s responsibilities are subject to authorization (or delineating of
responsibility) by the acquisition manager.
5.3.2.1 Program Quality Assurance Requirements. The PM plans establish, implements and
maintains a Quality Assurance Program Plan. The Quality Assurance Program Plan
reflects the guidance of MIL-S-52779, MIL-Q-9858, and MIL-STD-2167. The plan
provides guidelines for PM Quality Assurance program and defines quality
responsibilities for participation in scheduled management and technical reviews, and in
support of the preparation of System test plans, test procedures, and specifications.
Details are provided in the SB Quality Assurance Process Manual.
5.3.2.2 System PM Quality Assurance Requirements. The System PM establishes and maintains
a comprehensive Quality Assurance Plan and documented Policy Papers. MIL-Q-9858 is
used for supplemental guidance. The PM implements Total Quality Management (TQM)
principles throughout the life of his cognizant program. Special care is taken to ensure
the use of TQM principles by contractors as described in the TQM principles by
20
MISSION FUNCTIONAL PARAMETRIC
ANALYSIS ANALYSIS REQUIREMENTS
REVIEWS AND ANALYSIS
ALLOCATION
SYSTEM
TRADE SUBSYSTEM
STUDIES PERFORMANCE
SUBSYSTEM
DESIGN
MISSION EFFECTIVENESS & SPECIALTY ENGINEERING INPUT
MODELS SIMULATIONS
SCHEDULE RISK RISK ANALYSTS/PRODUCIBILITY ANALYSTS/ACQUISITION MGMT
SYSTEMS ANALYSTS/OPERATIONAL SPECIALISTS/RM&A ANALYSTS
PERFORMANCE SYSTEMS ANALYSTS/OPERATIONAL SPECIALISTS/RM&A ANALYSTS
EFFECTIVENESS INSTALLATION SPEC/MARINE ENGRS/EMC ENGRS/SAFETY ENGRS
COST ANALYSTS
PHYSICAL CONTRAINTS
SYSTEMS ANALYSTS/RISK ANALYSTS/RMA ENGRS/LOGISTIC ENGR
COST
TECHNICAL RISK
EVALUATION
EQUIPMENT RM&A
DESIGN TECHNOLOGY RISK
APPROACHES
PRODUCIBILITY
COST SPECIALTY ENGINEERING INPUT
SUPPORTABILITY
RMA ENGR/LOGISTIC ENGR/SYSTEM ANALYSTS
EFFECTIVENESS SYSTEM ANALYSTS/RESEARCH ENGR/LOGISTICIANS
MANUFACTURING ENGR/LOGISTICIANS/SYSTEM ANALYSTS
PSI PLAN
COST ANALYSTS/ACQUISITION MGMT
LOGISTICS ANALYSTS/TRAINING SPEC/OPS SPEC
SYSTEM ANALYSTS/OPS SPECIALISTS
EVALUATE SYSTEMS ANALYST/LOGISTICIANS/ACQ MGMT
DESIGN
DETAILS
SYSTEM
DESIGN SPECIALTY ENGINEEERING INPUT
SYSTEM
TRADE SUBSYSTEM
STUDIES PERFORMANCE
SUBSYSTEM
DESIGN
MISSION EFFECTIVENESS & SPECIALTY ENGINEERING INPUTS
MODELS SIMULATIONS
SCHEDULE RISK RISK ANALYSTS/PRODUCIBILITY ANALYSTS/ACQUISITION MGMT
SYSTEMS ANALYSTS/OPERATIONAL SPECIALISTS/RM&A ANALYSTS
PERFORMANCE
SYSTEMS ANALYSTS/OPERATIONAL SPECIALISTS/RM&A ANALYSTS
EFFECTIVENESS INSTALLATION SPEC/MARINE ENGRS/EMC ENGRS/SAFETY ENGRS
COST ANALYSTS
PHYSICAL CONTRAINTS
SYSTEMS ANALYSTS/RISK ANALYSTS/RMA ENGRS/LOGISTIC ENGR
COST
TECHNICAL RISK
EVALUATE
SYSTEM
ALTERNATIVE
SYSTEM
DESIGN SPECIALTY ENGINEEERING INPUT
22
Table 5-1. Integrated Logistic Support
LS Planning Ensure establish ILS Directorate Designate ILS manager; ensure each
Responsibilities contractor has appointed ILS Manager with
sign-off authority equal to engineering and
production managers
Develop an Integrated Support Plan Develop and ILS Plan (ILSP) for
(ISP) to provide ILS Planning implementing Project Manager and
guidelines over the entire life cycle; subcontractor responsibilities
establish the ILS/System
Engineering Iterative, Interactions
Logistic Support Coordinate task ILS Directorate to Organizational and intermediate level LSA
Analysis (LSA) Requirements tasks
Maintenance Develop depot level maintenance Organizational and intermediate level tasks
Planning Program requirements from the LSA process using LSA/LORA process
• Identify miniature/microminiature
repair capability requirements
• Demonstrate (by analysis) fault
detection, fault isolation, and fault
localization capabilities
• Identify Maintenance Assist
Modules (MAMs)
23
Table 5-1. Integrated Logistic Support (Continued)
Training and Provide Training Plan guidelines Develop training plan using HARDMAN
Training Support analysis and LSA
Provide the Training/Systems
Engineering Linkages Develop training course in accordance with
MIL-STD-1379
contractors as described in the TQM (often considered CPI) and Subcontractor Control
Templates of DoD Manual 4245.7M.
5.3.3 System Safety. The PM develops and implements with Acquisition Manager approval
Safety Program Plan in general compliance with MIL-STD-882.
• PM maintains system safety data files available to and compatible with Acquisition
Manager’s requirements,
• Maintains a system safety report database available to and compatible with
Acquisition Manager’s requirement, Subsystem or Component Hazard Safety
Analysis responsibilities are included,
• System Hazard Analysis of Test Configuration is generally the responsibility of the
PM (Task 204) with Acquisition Managers assistance, if required,
24
• Operating and Support Hazard Analysis (O&SHA) is generally the responsibility of
System PM,
• Software Requirements Hazard Analysis, responsibility of the PM, to include Hazard
Analysis of (1) Top Level Design, (2) Detailed Design, (3) Code Level, (4) Software
Testing, (5) Software User Interface, and (6) Software Safety changes,
• A Fault Tree Analysis, to be conducted to identify all failure modes contributing to
an undesired event, is generally the responsibility of System PM
• Acquisition Manager generally establishes a System Safety Working Group as
detailed in MIL-STD-882 (task 104).
5.3.5.1 Failure Reporting, Analysis, Corrective – Action System (FRACAS) and Test Analysis
and Fix (TAAF) Program. PM establishes FRACAS and TAAF Programs. Failure
collection and recording commences with either first functional hardware test or first
formal software and continues through production. Data collection, analysis, and
correction requirements for Maintainability and Testability efforts are integrated with
FRACAS and reported at all Failure Review Board Meetings. All software and hardware
failures are used to determine the maturity of System Reliability and all test activities are
monitored and failures subjected to analysis to determine the effectiveness and adequacy
of BIT/BITE and to identify corrective actions in both design and production.
5.3.5.2 Models and Prediction. PM develops and maintains reliability (MIL-STD-756 Tasks 102
and 104 provide guidance) and maintainability (derived from the Reliability Model to
address Organizational Level maintenance) models. A method for allocating reliability
and maintainability to lower levels shall be evident in the processes. Reliability
predictions are accomplished in accordance with MIL-STD-756 and Maintainability in
accordance with MIL-HDBK-472. Predictions are continuously updated and integrated
into the LSA process.
25