Csicol Manual
Csicol Manual
Contractor
Consultant Representative
Report# Week Ending
Other Projects in same Contract - File
WEEKLY CONSTRUCTION REPORT
Date
THURS
EQUIPMENT SUN OP. MON TUES WED FRI SAT OP.
OP. TOTALS
HRS OP. HRS OP. HRS OP. HRS OP. HRS HRS
HRS
REMARKS ON CONRACTOR'S PROGRESS, SITE OCCUPANCY, LANE CLOSURE AND WEATHER TO BE
RECORDED ON FORM A.07 (SITE OCCUPANCY AND LANE RENTAL WEEKLY REPORT BRIDGES AND CONSTRUCTION)
CONTRACTOR COMMENTS
Consultant: Date:
AppendixA.06
Type of Work Grading, Bridges and Other Work
Contractor NAME
EQUIPMENT SUN OP. MON TUES WED THURS FRI SAT OP.
TOTALS
HRS OP. HRS OP. HRS OP. HRS OP. HRS OP. HRS HRS
621 Scraper 6.0 8.0 12.0 8.0 5.0 39.0
621 Scraper 8.0 8.0
621 Scraper 0.0
SAMP
621 Scraper 0.0
627 Scraper 12.0 12.0 12.0 12.0 8.0 5.0 61.0
400 Rock Truck 12.0 12.0 12.0 12.0 12.0 5.0 65.0
400 Rock Truck 6.0 6.0 12.0 12.0 5.0 5.0 46.0
400 Rock Truck 6.0 5.0 5.0 16.0
D7 Dozer 8.0 8.0
D6 Dozer 12.0 12.0 12.0 12.0 7.0 5.0 60.0
D5 Dozer 6.0 12.0 12.0 5.0 35.0
330 Hoe 12.0 12.0 12.0 12.0 12.0 2.0 62.0
270 Hoe 12.0 12.0 12.0 12.0 12.0 3.0 63.0
140H Grader 12.0 10.0 8.0 8.0 4.0 42.0
14G Grader 12.0 12.0 12.0 12.0 12.0 5.0 65.0
815 Packer 12.0 12.0 12.0 12.0 12.0 5.0 65.0
Protec Packer 12.0 6.0 6.0 12.0 36.0
JD and sheepsfoot packer 12.0 12.0 12.0 12.0 12.0 5.0 65.0
Water Truck 0.0
REMARKS ON CONRACTOR'S PROGRESS, SITE OCCUPANCY, LANE CLOSURE AND WEATHER TO BE
RECORDED ON FORM A.07 (SITE OCCUPANCY AND LANE RENTAL WEEKLY REPORT BRIDGES AND CONSTRUCTION)
CONTRACTOR COMMENTS:
Consultant: Date:
C.S. km To C.S. km
Total Length km
MPLE
Roadway
Common Excavation m3 233,100 233,100 5,000 18,000 35,000 12.9% 15.0%
Borrow Excavation m3 90,300 90,300 5,000 7,000 16,000 12.2% 17.7%
Culverts
600mm m 796 796 24 344 344 40.2% 43.2%
800 m 443 500 24 144 242 43.6% 48.4%
1200 m 49 98 0 98 98 100.0% 100.0%
AppendixA.06